Bs8485-2015+a1-2019 - (2019-02-20 - 01-27-50 PM) PDF
Bs8485-2015+a1-2019 - (2019-02-20 - 01-27-50 PM) PDF
Bs8485-2015+a1-2019 - (2019-02-20 - 01-27-50 PM) PDF
8485:2015+A1:2019
The BSI copyright notice displayed in this document indicates when the document was last issued.
Contents Page
Foreword iv
Introduction 1
1 Scope 2
2 Normative references 2
Figure 1 — BS 8485 document flow chart 3
3 Terms and definitions 3
4 Overview of ground gas protection 5
Figure 2 — Key ground gas ingress routes and accumulation areas within unprotected
conventional residential buildings 6
5 Site investigation for ground gases 7
5.1 General 7
5.2 Preliminary investigation 7
Figure 3 — Ground gas site characterization and assessment flow chart 8
Table 1 — Check list for assessing the adequacy of a site investigation 9
5.3 Field investigation and monitoring 10
5.4 Conceptual site model for design of gas protection system 10
Figure 4 — Example design conceptual site model cross sections 11
6 Process for ground gas characterization and hazard assessment 12
6.1 Risk assessment for ground gases 12
6.2 Methodologies for ground gas characterization 12
6.3 Characterization using conceptual site model and gas monitoring data 13
6.4 Quantitative assessment of gas risk to characterize a site 18
Table 2 — CS by site characteristic GSV 18
7 Solutions choice and detailed design 19
7.1 Approach 19
Figure 5 — Solutions choice flow chart 20
Table 3 — Building types 21
Table 4 — Gas protection score by CS and type of building 22
7.2 Selection of appropriate protection measures 22
Table 5 — Gas protection scores for the structural barrier 23
Table 6 — Gas protection scores for ventilation protection measures 24
Table 7 — Gas protection score for the gas resistant membrane 27
7.3 In‑ground pathway intervention 27
7.4 Detailed design 27
8 Implementation, verification and reporting 28
8.1 General 28
Figure 6 — Implementation stage 28
Table 8 — Information to be included in the design, installation and verification report 29
8.2 Site conditions and characterization of the ground gas regime 29
8.3 Design phase 29
8.4 Installation and verification phase 31
Annex A (informative) Floor slab and substructure design 33
Figure A.1 — Example of potential influence of vibro stone columns for gas migration 34
Table A.1 — Grades of waterproofing protection 36
Table A.2 — Risk rating summary 39
Annex B (normative) Applicability and design of ventilation protection measures 40
Figure B.1 — Typical passive ventilation arrangement with floor slab above ground level 41
Figure B.2 — Typical passive ventilation arrangement with floor slab below ground level and low
level vents 43
Figure B.3 — Typical passive ventilation arrangement with floor slab below ground level and
high level vents 43
Figure B.4 — Positive pressurization air blanket system 45
Figure B.5 — Typical active suction system with floor slab below ground level 45
Table B.1 — Gas regimes considered in the DETR/PiT Guide for Design [12] 47
Table B.2 — Gas regimes considered in the PiT Guide for Design [12] 47
Table B.3 — Variables in the DETR/PiT Guide for Design [12] 48
Figure B.6 — Performance criteria for methane 49
Figure B.7 — Performance criteria for carbon dioxide 50
Figure B.8 — CFD computed volume flow through rates vs wind speed for various media for
a 30 m wide foundation [12] 51
Figure B.9 — CFD computed volume flow through rates vs wind speed for various media for a 5 m
by 5 m wide foundation [12] 52
Table B.4 — Relative dispersal effectiveness of different gas dispersal layer media 53
Figure B.10 — Polystyrene void formers 54
Figure B.11 — Geocomposite void former 56
Figure B.12 — Idealized plan of granular gas dispersal layer with network of gas drains 58
Annex C (informative) Gas resistant membrane selection 60
Annex D (informative) Characterization without gas monitoring data 62
Table D.1 — Limiting values of thickness and organic content of made ground (after
RB17 [1], Table 1) 63
Annex E (informative) Sampling, examination and TOC testing of made ground for the
assessment of the potential for gas generation 65
Figure E.1 — Approach for detailed examination of made ground for the assessment of
the potential for gas generation 67
Annex F (informative) Worked examples 68
Table F.1 — Site A ground conditions 68
Table F.2 — Site A gas monitoring data 70
Table F.3 — Maximum implied CS derived by combining the maximum observed flow rate and
maximum observed concentrations from different boreholes during any monitoring event 71
Table F.4 — Site A subsequent additional gas monitoring measurements 72
Table F.5 — Implied maximum CS derived from consideration of the maximum hazardous
gas flow rate calculated from any single borehole standpipe during any of these subsequent
monitoring events 74
Table F.6 — Worst case implied CS derived by combining the maximum observed flow rate and
maximum observed concentrations from different boreholes during any of these subsequent
monitoring events 74
Table F.7 — Minimum gas protection score (points) for different types of building at Site A 74
Table F.8 — Combinations of measures to provide a gas protection solution for different types of
building at Site A 75
Table F.9 — Site B ground conditions 77
Table F.10 — Maximum implied CS derived from consideration of the maximum hazardous gas
flow rate calculated from any single borehole standpipe during any monitoring event 77
Table F.11 — Worst case implied CS derived by combining the maximum observed flow
rate and maximum observed concentrations from different borehole standpipes during any
monitoring event 77
Table F.12 — Minimum gas protection score (points) for different types of building at Site B 78
Table F.13 — Combinations of measuresA) to provide a gas protection solution for different types
of building at Site B 78
Annex G (informative) Radon 80
Annex H (informative) Volatile organic compounds (VOCs) 82
Bibliography 85
Summary of pages
This document comprises a front cover, and inside front cover, pages i to vi, pages 1 to 87, an inside back cover and
a back cover.
Foreword
Publishing information
This British Standard is published by BSI Standards Limited, under licence from The British
Standards Institution, and came into effect on 30 June 2015. It was prepared by Technical Committee
EH/4, Soil quality. A list of organizations represented on this committee can be obtained on request to
its secretary.
Supersession
BS 8485:2015 superseded BS 8485:2007, which has been withdrawn.
BS 8485:2015+A1:2019 supersedes BS 8485:2015, which is withdrawn.
It has been assumed in the preparation of this British Standard that the execution of its provisions
will be entrusted to appropriately qualified and experienced people, for whose use it has
been produced.
Presentational conventions
The provisions of this standard are presented in roman (i.e. upright) type. Its recommendations are
expressed in sentences in which the principal auxiliary verb is “should”.
Commentary, explanation and general informative material is presented in smaller italic type, and does
not constitute a normative element.
The word “should” is used to express recommendations of this standard. The word “may” is used in
the text to express permissibility, e.g. as an alternative to the primary recommendation of the Clause.
The word “can” is used to express possibility, e.g. a consequence of an action or an event.
Notes and commentaries are provided throughout the text of this standard. Notes give references
and additional information that are important but do not form part of the recommendations.
Commentaries give background information.
Introduction
Toxic, asphyxiating and flammable and potentially explosive ground gases can enter buildings and
other structures on and below the ground. They variously pose potential risks to occupants and
users, and to the structures themselves.
This British Standard is intended to be used by designers of gas protection measures and by
regulators involved in the assessment of design solutions. It recognizes that there are a number of
factors requiring consideration which affect the sensitivity of a development to the effects of ground
gas, and that there is a range of design solutions available for different situations. It is anticipated that
specialist advice is needed in the assessment of the ground gas data and in the risk assessment phase.
This British Standard provides a framework, in line with Model procedures for the management of
land contamination, CLR11 [2], which provides designers with information about what is needed for
an adequate ground gas site investigation. It also provides an approach to determine appropriate
ground gas parameters that can be used to identify a range of possible design solutions for protection
against the presence of methane and carbon dioxide on a development site. The framework is not
prescriptive and professional judgement may be made as to the acceptability of risk and whether
there might be benefit in undertaking more rigorous site assessment or adopting conservative
measures in design. Emphasis is placed on the justification and recording of risk assessments and
design decisions throughout the process.
A variety of gases might be present in the ground naturally, or be present as a result of contamination
of the ground, or arise from buried wastes. In addition to the main components found in air (nitrogen
and oxygen), ground gas can contain other gases (e.g. methane, carbon dioxide, carbon monoxide,
hydrogen sulfide, ammonia, helium, neon, argon, xenon, radon, etc.). It can also contain volatile
organic compounds (VOCs) or inorganic vapours (mercury).
Methane (which is flammable and an asphyxiant) and carbon dioxide (which is toxic and an
asphyxiant) can originate from a range of sources including:
• land‑filled wastes;
• degradable material present within the soil matrix of made ground;
• peat and organic matter within alluvial deposits;
• migrating landfill leachate;
• spilled or leaked petroleum hydrocarbons;
• silt formed in water bodies (e.g. ponds, docks and rivers);
• some natural deposits (e.g. chalk and coal measure strata); and
• leaks of mains gas (natural gas) and sewer gas.
Wherever biodegradable materials are present, microbial activity produces methane and/or carbon
dioxide depending on whether conditions are aerobic or anaerobic. A number of additional trace
gases can also be produced.
Permanent gases such as methane, carbon dioxide and carbon monoxide which might be present
in coal measure strata can also emanate from old mine workings (guidance is given in CIRIA
Report 130 [3]). Combusting coal measure strata, including waste in colliery spoil tips, can release
carbon monoxide, as can smouldering domestic waste. Under some circumstances, sulfur rich
deposits such as gypsum waste and some slags can release substantial quantities of hydrogen sulfide;
for example, when sulfur‑bearing wastes and domestic refuse are mixed.
1 Scope
This British Standard gives recommendations on ground gas site characterization and the choice
of solutions for the design of integral gas protective measures for new buildings to prevent entry of
carbon dioxide and methane, and provide a safe internal environment.
This British Standard gives a process that can be used to demonstrate that risks posed by the
potential or actual presence of carbon dioxide and methane have been addressed.
This British Standard does not cover protection of new buildings against other hazardous ground
gases. Nor does this British Standard cover protection of buildings into which methane and
carbon dioxide might be introduced by the activities for which they are used (for example, water
pumping stations).
The retrospective design of protection measures for completed buildings and the design of
retrospective protection measures after completion of building construction are not covered in this
British Standard.
NOTE 1 Guidance on radon and VOCs is given in Annex G and Annex H.
NOTE 2 This British Standard does not give recommendations on oxygen depletion.
NOTE 3 The assessment and decision making stages are presented in the form of process flow charts (Figure 3,
Figure 5 and Figure 6), accompanying information and explanatory guidance and, where appropriate, references
to other guidance and information. The contents of this British Standard are shown in the document flow chart
in Figure 1.
NOTE 4 Full protection of buildings might require a range of measures (for example, to control gas migration, to
protect car parking and garden areas, and to monitor gas concentrations) in addition to those incorporated into
the building. However, guidance on these is not provided and is available in the Ground Gas Handbook [4] and CIRIA
Report 149 [5].
2 Normative references
The following documents, in whole or in part, are normatively referenced in this document and are
indispensable for its application. For dated references, only the edition cited applies. For undated
references, the latest edition of the referenced document (including any amendments) applies.
BS 8576:2013, Guidance on investigations for ground gas — Permanent gases and Volatile Organic
Compounds (VOCs)
BS 10175:2011+A1:2013, Investigation of potentially contaminated sites — Code of practice
BS EN 13137, Characterisation of waste — Determination of total organic carbon (TOC) in waste,
sludges and sediments
Other publications
[N1] MALLETT. H., COX, L. (nee TAFFEL‑ANDUREAU), WILSON, S. and CORBAN, M. Good practice on
the testing and verification of protection systems for buildings against hazardous ground gases (C735).
CIRIA, London, 2014.
NOTE 3 The majority of borehole standpipes installed in contamination ground investigations are of 50 mm
internal diameter although other diameter pipes are also sometimes used.
NOTE 2 GSV is based on measured data but ultimately derived using professional judgement.
• site‑wide measures designed to reduce the gas hazard beneath the building.
Guidance on these additional measures is not provided in this British Standard but can be found in a number of
published guidance documents including Ground Gas Handbook [4] and CIRIA Report 149 [5].
Figure 2 — Key ground gas ingress routes and accumulation areas within unprotected conventional residential build‑
ings
Key
1 Through cracks and openings in solid A Roof voids
concrete ground slabs if present due to
shrinkage and curing
2 Through construction joints and B Beneath suspended floors
openings at wall‑foundation interface
with ground slab if not sealed
3 Through cracks in walls below C Within settlement voids below floor slab
ground level
4 Through numerous gaps and openings D Drains and soakaways (or similar voids)
in suspended block and beam floors or
timber floors
5 Through gaps around service pipes and
ducts or within the ducts
6 Through cavity walls
NOTE This figure is Figure 3 from CIRIA Report 149 [5] reproduced with the kind permission of CIRIA.
d) buildable: in that they can be built given an appropriate standard of workmanship, supervision
and verification.
Effectiveness should be assessed in terms of:
• the theoretical effectiveness assuming perfect installation; and
• the practical effectiveness (i.e. what it is reasonable to expect to achieve under normal
conditions); and
• likely long‑term effectiveness given the likely durability of materials, etc.
Extreme events (e.g. exceptional changes in atmospheric pressure, rapid groundwater rise and/
or flooding) should be taken into account when defining the CS (see 6.2.1) and when selecting the
protective measures.
Protective measures should include the use of materials that have a defined design life or no known
critical time deterioration properties, and should be placed where they might reasonably be expected
to continue to perform for the life of a building, that might be in excess of 100 years.
NOTE 4 Measures (especially ventilation) can be designed from first principles (see 6.2) or selected from “deemed
to satisfy” solutions following the recommendations in Clause 7.
Risk assessment and all design decisions should be documented and recorded in the design phase
report (see 8.1).
The evaluation of the adequacy of the site investigation should be carried out in accordance
with Table 1.
NOTE 2 Guidance on the sufficiency of gas monitoring data is provided in BS 8576:2013, Annex F.
All potential gas sources should be identified; these sources might include natural geological sources,
mine workings, waste materials, landfills and made ground. For each source an understanding of the
nature of the gas generation processes involved should be formulated.
NOTE 1 Some of the sources might be discounted as not being of concern during further investigation and
subsequent assessment.
The geology and hydrogeology of the site, and the presence of contamination, and how it might affect
gas sources and gas migration should be assessed; this includes assessing the effect of groundwater
level variations, including tidal variations (and how these can affect gas sources and gas migration).
All potential pathways should be identified, which includes natural geological pathways, services,
underground structures and mine workings. Pathways that are not credible should be discounted.
Potential receptors, both on- and off‑site, should be identified and their sensitivity assessed.
The desk study should be used to develop the preliminary conceptual site model that guides the
approach to assessing gas risk on a site and the requirements for field investigation, laboratory
testing and gas monitoring.
NOTE 2 Guidance on the development of the preliminary conceptual site model is given in BS 8576:2013, Clause 6.
Boreholes in the natural ground (external to the old wastes) should be located and designed to assess
the migration pathway.
NOTE 2 There might be a reduction in gas hazard with increasing distance from the source, if the site is
sufficiently large.
The design and implementation of field investigations for ground gases should be in accordance with
BS 8576:2013, Clause 7 to Clause 12.
The TOC of soils should be determined using the method in BS EN 13137.
NOTE 3 Different methods of determination of TOC give different results.
NOTE 2 Example cross‑section conceptual site models for design are given for gas sources below buildings and
off‑site from the building in question in Figure 4.
The conceptual site model should also include plans or other information that are required to
demonstrate an understanding of the ground and gas sources in and around the site.
Landfill
NOTE With nearby landfills, the potential for gas migration depends on a number of factors, including:
• design and operation of the landfill (presence of liners, permeability of capping layer, gas extraction
system in operation, whether it is continuous or not); and
NOTE 2 Use of fault tree analysis can help to identify critical states including what might go wrong. Guidance on
fault tree analysis is provided in CIRIA Report 152 [7] and the Ground Gas Handbook [4].
NOTE 3 Ground gas characterization and hazard assessment are the initial parts of the risk assessment process.
The subsequent stages are the analyses of source pathway receptor linkages.
NOTE 4 Risk assessment results are only reliable if data and other information available about the site are
sufficient in terms of quality, quantity and appropriateness (see 5.1).
Any uncertainty should be reflected in the design of the gas protection system.
NOTE 5 Information on the sources, properties and the hazards presented by carbon dioxide and methane is
provided in BS 8576:2013, Annex D. The information includes an indication of the magnitude of the hazards in
relation to concentrations and the control limits for various situations current at the time BS 8576:2013, Annex D
was prepared.
Risk assessment and all design decisions should be documented and reported (see Clause 8 for
further information and guidance on documenting and reporting).
6.3 Characterization using conceptual site model and gas monitoring data
COMMENTARY ON 6.3
This sub‑Clause sets out an empirical semi‑quantitative method of assessment of hazards from
permanent ground gases. It also sets out how the data collected during site monitoring visits that
measure hazardous gas emissions from specific monitoring points is assessed and used to designate
a GSV that represents the gas hazard present at the whole site (or GSVs for different zones of a
site if zoning is fully supported by a developed conceptual site model and is not just based on gas
monitoring data).
The process set out represents good practice and is based on CIRIA C665 [ 6 ], NHBC Guidance on
evaluation of development proposals on sites where methane and carbon dioxide are present [ 8 ] and
the Ground Gas Handbook [ 4 ]
6.3.1 General
COMMENTARY ON 6.3.1
The development of the GSV for the site or the zone follows a process in which:
• borehole hazardous gas flow rates are calculated for each borehole standpipe for each monitoring
event (see 6.3.3) and included in a database;
• the reliability of the measured gas flow rates and concentrations is assessed taking into account
borehole construction, etc (see 6.3.4 and 6.3.5);
• decisions are made as to whether to use peak gas flow rates or steady‑state rates in each
calculation (see 6.3.6);
• decisions are made about how to deal with any temporal or spatial shortages in the data
(see 6.3.7.3);
• a decision is made about whether the site might be zoned or not (see 6.3.7); and
• judgements are made about what GSV to use for design purposes taking all relevant information
into account.
The designation of GSV should be made after consideration of the available monitoring data
(6.3.5 and 6.3.6) and all other relevant aspects of an adequate conceptual site model and with
knowledge of the development’s sub‑structure and foundation arrangement.
The presence of significantly elevated concentrations of methane or carbon dioxide with zero flow
rates should be assessed and not dismissed. Even if all the monitoring indicates no gas emissions, an
assessment should be made about whether or not different atmospheric or groundwater conditions
might have led to measurable flows, whether any significant diffusive flow from the ground might
occur, or whether typically lower pressures within buildings might pose a risk to the building
development.
NOTE 1 Numerical modelling can be used to assess diffusive flows.
NOTE 2 Application of characterization using degradable organic fraction (see Annex D) might also help decision
making, where the source is a relatively thin layer of made ground.
The borehole Qhg (in L/h) should be calculated for each monitoring location and each monitoring
event using the following (for each hazardous gas):
Chg
Qhg = q (1)
100
where:
q is the measured flow rate (in litres per hour) of combined gases from the
monitoring standpipe.
Chg is the measured hazardous gas concentration (in percentage volume/volume).
NOTE 2 In equation (1), the measured hazardous gas concentration Chg is expressed as a percentage (%), i.e. as
parts per hundred.
NOTE 3 As an example, if a total borehole flow of 6 L/h is measured, and of that total flow (of mixed gases) 10%
is methane, then the flow of methane gas (i.e. the borehole Qhg for methane – QhgCH4) is 0.6 L/h (of methane),
calculated as:
10
Qhg CH 4 = 6 ×
100
= 0.6
i.e. 0.6 L/h of methane is being emitted, mixed with a flow of 5.4 litres of other gases.
If 25% of the total flow (of mixed gases) is carbon dioxide, then similarly the borehole Qhg for carbon dioxide
is 1.5L/h (of carbon dioxide) calculated as:
25
Qhg CO2 = 6 ×
100
= 1.5
i.e. 1.5 L/h of carbon dioxide being emitted from that borehole, on that monitoring event, mixed with the
other gases.
If a gas borehole flow is not detected, it should be assumed that it is at the detection limit of the
equipment used for the purpose of this calculation.
If a negative flow is recorded it should not automatically be discounted. Rather, an assessment of
whether, under different temporal conditions, a similar positive out‑flow of gas could occur should
be undertaken, consistent with development of the conceptual site model. Only when the reason for
the negative value is reasonably understood, and a positive flow can be credibly ruled out, should a
negative value be discounted.
The database should be designed to enable data representative of the source, and/or pathway and/or
receptor (as appropriate to each specific development) to be clearly identified and understood.
NOTE 2 Monitoring point specific Qhg can be usefully visualized on plan and section views. Colour coding can aid
such 3D spatial understanding of the gas regime, or regimes, that are present. Such presentation can be extended to
assess temporal variability.
If water is present above the top of the slotted section of the gas standpipe, any peak flow recorded
is likely to be due to a build‑up of pressure caused by rising water trapping the gas within the solid
section of pipe; in this case, the initial peak flow is not representative of the rate of gas generation
within the ground, and new, better designed standpipes should be installed and decisions made about
whether to carry out further monitoring from the existing installation.
6.3.7.1 General
The designation of GSV should be made by inspection of all the data based on the conceptual site
model for the situation with the development’s sub‑structure and foundations in place.
NOTE 1 Adopting a GSV based on Qhg calculated from peak flow measurements might result in a disproportionately
high gas hazard prediction, and assignment of an over‑precautionary CS.
NOTE 2 Examples of how monitoring data is considered to derive a GSV are given in Annex F.
Where a development is to be built directly on or very close to the source of gas, then the Qhg adopted
as the site or zone GSV should be based on gas measurements of the source. For a development off‑set
from a source, an assessment of the degree of hazard reduction afforded by the pathway between the
source and the receptor should be made.
NOTE 3 If the source has been monitored and is at some distance off‑set from the development, then selection of the
GSV based on an application of the Qhg obtained from the source is inappropriate.
A similar form of assessment of source hazard reduction should be made if the source is organic
degradable material (e.g. peat) within an alluvial sequence that is conceptualized as being capable
of supporting a reservoir of gas, but where the development above is protected to some degree by
a lower permeability strata. In this case the alteration to the pathway that the building’s foundation
solution might incur should also form a key part of the assessment.
The models in 6.2.2 are based on fluid flow through the ground by advection and diffusion and
should be compared to gas monitoring data wherever possible, with sensitivity analyses undertaken.
Table 2 — CS by site characteristic GSV
L/h
CS1 Very low <0.07 Typically <1% methane concentration and <5% carbon
dioxide concentration (otherwise consider an increase to
CS2)
CS2 Low 0.07 to <0.7 Typical measured flow rate <70 L/h (otherwise consider
an increase to CS3)
CS3 Moderate 0.7 to <3.5 –
CS4 Moderate to high 3.5 to <15 –
CS5 High 15 to <70 –
CS6 Very high >70 –
A)
The figures used in this column are empirical.
NOTE The CS is equivalent to the characteristic GSV in CIRIA C665 [6].
NOTE 2 The results from the models can be used to determine the scope of gas protection measures needed for a
building and to design any necessary underfloor ventilation.
NOTE 3 This approach is of particular use where gas migrates through the ground from a source adjacent to the
site (e.g. where landfill gas migration occurs).
NOTE 4 Further information on detailed quantitative risk assessment is provided in the Ground Gas Handbook [4].
The construction and use of the building, together with the control of future structural changes to
the building and its maintenance (the building’s management) should be assessed, since potential
risks posed by ground gases are strongly influenced by these factors. The assessment should lead to
the categorization of the building as a whole, or each different part of the building, into one of four
building types: Type A, Type B, Type C or Type D.
New buildings should be categorized in accordance with Table 3 and the descriptions that follow.
From the design CS and the type of building (A, B, C or D) the minimum level of gas protection (score)
in the range 0 to 6 should be determined in accordance with Table 4.
NOTE 3 The NHBC has published guidance [8] for use on residential developments, which utilizes an alternative
classification (“traffic light”) system. This guidance typically applies to Type A buildings utilizing beam and block
floor constructions with clear void ventilation. The design choice variables are limited to decisions relating to the
membrane specification and verification recommendations (see Table 7). Designers utilizing this system would
therefore need to refer to the NHBC [8] to assess compliance for specific recommendations.
When the minimum gas protection score has been determined for the building as a whole, or for each
part of the building, then a combination of two or more of the following three types of protection
measures should be used to achieve that score:
• the structural barrier of the floor slab, or of the basement slab and walls if a basement is present;
• ventilation measures; and
• gas resistant membrane.
NOTE 4 The method of selecting the combination of these types of protection measures for a particular building is
given in 7.2.
Once the types of protection measures have been decided, the detailed design and specification of the
measures should be undertaken (see 7.3).
NOTE 5 In some cases, the designer might be of the opinion at this stage that the extent of the protection
measures is potentially more than is needed, because of limitations in the scope of the site investigation
[these limitations having led to a more conservative GSV and CS than is likely from the conceptual site model
(see 6.3.7.2 and 6.3.7.3)]. In this case, further site investigation could be carried out to check the GSV. Only if there
is sufficient time to carry out additional site investigation and gas monitoring would this step be useful.
The detailed design and specification of the protection measures should be recorded in a design
report (see 8.3).
The gas protection system should consist of at least two different elements; for example, a barrier
element with either a membrane or a ventilation or dilution element (or both). The elements work
independently and collaboratively, and a single element should not be used because there would be
no redundancy to allow for defects in the component.
NOTE For low sensitivity buildings on low risk sites it might sometimes be possible to rely solely on a membrane
or slab; for example, where internal ventilation provides secondary protection.
The selection process should be transparent in that all interested parties can see the approach taken,
understand the various steps and decisions made, and be confident that a robust risk‑assessed
solution has been designed and installed commensurate with the construction and site constraints.
Where the CS is CS4 or higher, the site should have a comprehensive assessment done to support
the adequacy of the proposed protection measures. Reliance should not be placed solely on Table 5,
Table 6 and Table 7.
The common types of floor slab and substructure design and their relative performance as a
structural barrier to ground gas ingress are described in Annex A. The structural barrier score should
be assigned in accordance with Table 5; further guidance is given in Annex A.
Table 5 — Gas protection scores for the structural barrier
When practical, utilities should enter the building above floor level with any conduit or meter housing
being properly vented outside of the building.
The applicability and design of ventilation protection measures and selection of an appropriate score
should be carried out in accordance with Annex B.
A ventilation protection measure should have a design with a defined level of performance and
supporting dilution calculations. Recommendations on both design and performance criteria for
methane and carbon dioxide are provided in Annex B and should be followed.
NOTE 2 There are a wide range of different media used to form the gas dispersal layer for both passive and active
systems, and more are likely to be developed.
Designs should use a gas permeability value which is representative of the media in its as‑built
condition, taking into account the continuity of the media beneath the floor slab, loss of volume
due to compression, the pressure differences that apply across the media, and head losses in
the terminals.
NOTE 3 The types of media include expanded polystyrene void formers, geocomposite void formers, no (or low)
fines gravel, and drains formed by perforated pipes or geocomposite strips.
NOTE 4 The continuity of the media beneath the floor slab might be interrupted by ground beams, pile caps, edge
beams and other intrusions extending below the level of the media blanket, which might significantly reduce the
effectiveness of the dispersal layer.
NOTE 5 The effective volume of the gas dispersal layer might be reduced by its placement on a soft layer (for
example, sand blinding) which reduces its gas permeability and dispersal effectiveness. The effective volume would
also be reduced, or eliminated, if the media became flooded with groundwater or clay heave occurred.
NOTE 6 The performance of passive systems can be significantly affected by the number and type of side ventilation
terminals. Common side terminals are airbricks, low level vents and high level vent stacks. Guidance on side
ventilation is given in Annex B.
In certain circumstances passive ventilation is difficult to achieve, such as where there is a very large
building footprint, basement or complex ground beam arrangement. In such cases, a system might
be designed as “pressure relief” alone and this should be detailed accordingly in the design. As a bare
minimum all gas protection systems should include at least pressure relief (a preferential pathway to
atmosphere) for gases which might otherwise build up under the building footprint.
The gas protection scores applicable to different types of passive and active ventilation systems
are given in Table 6. The selected score should be assigned in accordance with Annex B and be
compatible with gas dispersal performance of the system.
Table 6 — Gas protection scores for ventilation protection measures
Table 6 (continued)
7.2.4 Membrane
Gas resistant membranes should be:
a) sufficiently impervious to methane and carbon dioxide;
b) capable after installation of providing a complete barrier to the entry of the relevant gas.
c) sufficiently durable to remain serviceable for the anticipated life of the building and duration of
gas emissions;
d) sufficiently strong to withstand in service stresses (e.g. due to ground settlement if placed below
a floor slab);
e) sufficiently strong to withstand the installation process and following construction activities
until covered (e.g. penetration from steel fibres in fibre reinforced concrete, penetration of
reinforcement ties, tearing due to working above it, and dropping tools); and
f) chemically resistant to degradation by other contaminants that might be present.
NOTE 1 A methane gas transmission rate of <40.0 ml/day/m2/atm (average) for sheet and joints (tested in
accordance with the manometric method in BS ISO 15105‑1:2007) is usually considered sufficient.
NOTE 2 Guidance on the durability and strength of plastic membranes used as VOC vapour barriers is
provided in CIRIA C748 [10].
There are many gas resistant membrane types available and membrane choice should be made
according to the resistance of the material to the passage of the challenge gas and the resistance
to site damage during and after installation in the designed position. The designer specifying the
membrane should consider the combination of a particular membrane’s properties to assess whether
it is suitable in any given situation. The specified membrane and the reasons for its selection should
be described in the design stage report (see 8.1).
NOTE 3 Advice on membrane selection is given in Annex C.
NOTE 4 The installation and subsequent protection of the membrane are key factors in its performance. A poorly
installed membrane cannot perform, however well detailed and irrespective of the performance of the material.
Historically, reference has been made to verification and integrity testing without having any referenced documents
against which to judge. The verification process is now described in CIRIA C735 [N1] and as such, confidence in the
installed solution can be measured. The process removes the uncertainty of unqualified or inexperienced installation
operatives by requiring a verification plan to be drawn up prior to the installation, with frequency and type of
verification being dependent upon the qualifications of the installation operatives, site risk and design criteria.
A verification plan for the installation of the membrane should be part of the detailed design
(see 8.3.2).
NOTE 5 Current guidance on verification recommendations takes into account the risk of the overall design and
confidence in its installation, and sets a frequency and level of verification appropriate.
A gas protection score (see Table 4) should only be assigned to a membrane which is formed of a
material with suitably low gas permeability and which has been installed so it completely seals the
foundation (including effective seals around all penetrations) and does not sustain damage from
in‑service stresses. The criteria which should be met to assign a gas protection score of two points is
set out in Table 7.
NOTE 2 For residential dwellings, management and maintenance is only acceptable where pathway intervention
measures (e.g. venting trenches) are beyond the extent of the building(s), on or close to the boundary of the property
in a position where access can be guaranteed.
The person who has selected the design measures and whoever is preparing the detailed design
should liaise during the development of the detailed design.
NOTE This consultation might result in a decision that the selected design measures cannot be implemented for
practical reasons and consequently a rethink might be needed about what design measures are to be employed.
The characterization of ground gas hazard at a site, the basis of the design of the gas protection
measures, the installation of the measures and the verification inspections, monitoring and testing of
the measures should be recorded in a report or series of reports, with design and as‑built drawings.
There can be substantial differences in report content depending upon the complexity of the ground
gas regime, the sensitivity of the development, the nature of the gas protection measures adopted
and the level of reassurance needed. However, the report should always adopt a formal structure and
state whether it covers design, installation and/or verification aspects and includes all the necessary
evidence to verify the adequacy and/or compliance of stated remedial objectives and design criteria.
To achieve this, the following given in Table 8 should typically be included within the design,
installation and verification report(s).
NOTE 1 The reports are likely to be produced as separate documents but may be combined in a single document on
completion of all relevant phases.
Reference should always be made to any specific requirements set by the regulator (e.g. via planning
conditions and/or building control conditional requirements). The design parameters, specifications,
justifications and method of verification should be approved in advance of works by the appropriate
regulatory authority and relevant correspondence should be referenced and, where appropriate,
included in an annex.
NOTE 2 Guidance on reporting and verification is set out in CLR11 [2], CIRIA C735 [N1] and Verification of
Remediation of Land Contamination [11].
• the existence of below ground basements, under crofts and/or mechanical ventilation features;
• wall construction;
• the complexity (stability) of the ground conditions and drainage characteristics; and
• existence and frequency of complex detailing (e.g. stepped foundations, complex building shapes, and lift pits).
NOTE 2 Energy efficiency and access considerations can significantly influence the design choice and ultimately the
approach needed at the construction phase. For example, the width of the cavity wall, to achieve thermal insulation
or level threshold access requirements under the building control regulations may require design of bespoke or
flexible air vents which can adapt to the increased cavity widths or reduced elevation positioning.
The designer should ensure that the report clearly details critical assumptions behind the design
philosophy and identifies crucial design elements. The report should make it explicit that where
construction proposals change, then the design should be re‑checked to ensure compliance with the
overall design objectives and, where appropriate, might need refinement.
To justify the venting design the designer/specifier should provide ventilation calculations to
show that the ventilation capability of the proposed system achieves the design specification. The
calculations and the justification for selected input parameters should be clearly reported.
NOTE 2 Recommendations to assist this process are given in Annex B.
NOTE 3 Venting calculations are particularly important for large span footprints, complex constructions, and/or
where a combination of proprietary products is used. For simple structures, such as structures comparative with the
NHBC “model house” (see [8]), or comparative with the design criteria as detailed in Passive Venting of Soil Gases
Beneath Building, Guide for Design [12], the venting capability is usually deemed to comply and venting calculations
may be unnecessary.
NOTE 4 Recommendations on ventilation modelling can be found in BS 5925. Useful advice is also provided in the
Ground Gas Handbook [4].
In specifying the barrier design, the designer should clearly define the characteristics for the gas
barrier and provide justifications; for example, a gas membrane barrier might need to achieve certain
puncture resistance, where reinforced slabs or screeds are being adopted and/or where protection
after the barrier’s installation might be delayed.
Other important information that should be contained in the report includes:
• the severity of the gas regime and sensitivity of the land use;
• component compatibility (particularly important for sealing components as some materials are
not compatible with others);
• need (or not) for preformed sections or fabricated units;
• expectation of installer (i.e. experience and knowledge, which is usually dependent on the
complexity of the detail, such as stepped foundations, complex building shapes and lift pits).
NOTE 7 The above list is not exhaustive or preclusive of the information to be included.
The designer needs to be aware of key considerations that are specific to the site requirements, and
should detail critical design criteria as appropriate within the main text of the report.
The proposed verification plan should be sufficiently detailed, within the main body of the report,
together with the rationale for the recommended approach. Where regulatory conditions relating to
the verification process have been applied, then the approach should be agreed in advance of works
to ensure that proposals are acceptable.
Information pertinent to the verification plan should include:
• how, when and by whom the verification task/s should be carried out;
• compliance criteria (i.e. what constitutes a pass/fail);
• frequency of verification task/s;
• methodology;
• QA/QC requirements;
• how and when information should be reported;
• regulatory requirements; and
• contingency plan (i.e. what needs to be done if results fail to meet compliance criteria).
Annex A (informative)
Floor slab and substructure design
A.1 General
Gas protection measures normally require a number of separate elements or components that
together create a composite and integrated system which adequately prevents ingress of ground
gases. The ground floor slab and/or basement floor slab is usually one of these elements; the others
are usually ventilation and/or a gas resistant membrane.
The design, form, construction and anticipated performance of a building’s substructure might
influence the physical characteristics and specification requirements for the impermeable/gas
resistant membrane, which in turn might be influenced by the proposals for ventilation. Each of these
elements contribute to the resistance to the passage of gas into the building so during the design
stage consideration is given to the appropriate combination of these elements. This is to maintain
their integrity during the construction stage and achieve satisfactory long term performance during
the design life of the building.
Building substructures provide varying degrees of resistance to the passage of gas depending on
their form but they are not sufficiently impervious to prevent complete gas ingress. For example,
segmental ground floor construction methods such as suspended beam and block floors contain
many joints and discontinuities. Such floor types provide significantly less resistance for ground gas
ingress than well‑constructed cast in‑situ reinforced concrete raft foundations, which are monolithic
with few joints. However, these are not completely impermeable and normally contain some
cracking at a microscopic level. For low sensitivity buildings on low risk sites it might sometimes
be possible to rely solely on a membrane or slab; for example, where internal ventilation provides
secondary protection.
The guidance in this British Standard on the selection of protection measures is based on
consideration of four typical classes of substructure:
• precast suspended segmental subfloors without and/or with bonded reinforced structural
concrete topping (e.g. beam and block);
• cast in‑situ ground bearing floor slab with mesh reinforcement for crack control constructed off
a sound sub‑base (e.g. traditional ground bearing floor slab);
• cast in‑situ monolithic reinforced concrete ground bearing raft or suspended/semi‑suspended
cast in‑situ reinforced concrete slab with minimal penetrations; and
• fully tanked basement (see BS 8102:2009, Grade 3 for further guidance).
To aid understanding and appreciation of the scoring in Table 5, and to assist in determining the
appropriate design of gas protection measures, background on some common forms of construction
and their associated influences in relation to ground gas protection is given in A.2, A.3 and A.4.
Key
1 Dwelling 5 Made ground
2 Gas pathways 6 Clay
3 Vibro stone column 7 Peat
4 Gas pocket 8 Bedrock
Ground bearing slabs are typically constructed from a minimum of 100 mm of cast in‑situ concrete
with a nominal mesh reinforcement or fibre reinforcement to control shrinkage. When concrete is
placed to form ground bearing slabs it is often tamped into position rather than vibrated and might
be less dense than purpose designed reinforced concrete.
Ground bearing slabs are used where the ground and/or any infill can safely support the weight of
the slab and the applied loads without undue settlement. A ground bearing slab is independent of the
foundations and normally abuts any loadbearing walls. Insulation to satisfy thermal requirements
might be incorporated above or below the concrete slab.
reinforcement to control shrinkage that is fully bonded to the top of the precast floor might
significantly reduce the overall permeability for a beam and block floor.
The issue of gaps at floor/wall junctions is obviated by the use of suspended floor since the floor
structure is built into the supporting structure. Service ducts and entries and other penetrations
through ground bearing structures can provide pathways for gas entry if not properly sealed and
need to be considered. Potential problems can sometimes be avoided by bringing services into the
building above floor level (the service runs and entry pods or meter housings need ventilation).
A.4 Basements
Basements can be shallow (one storey) or deep (two storeys or more) and can be full, occupying the
entire footprint of the building, or partial with only part of the structure below ground. Basement
slabs are normally constructed from in‑situ reinforced concrete and may be ground bearing slabs/
rafts or supported on piles.
Walls to shallow basements can be constructed from a wide range of materials including plain
masonry, reinforced masonry, mass concrete, reinforced concrete, precast concrete, various
proprietary insulated and non‑insulated formworks systems. For deep basements, walls are normally
constructed from reinforced concrete or embedded retaining wall solutions such as diaphragm walls,
contiguous pile walls, secant pile walls or interlocking driven sheet piling.
Every basement design takes into account the site‑specific conditions including the groundwater
regime. The two primary criteria for the design are normally:
• the structural design to support the vertical loads from the building superstructure and the
lateral loads from the retained ground and groundwater; and
• the waterproofing protection system to prevent or control ingress of groundwater.
Guidance on methods of dealing with and preventing the entry of groundwater into basements is
given in BS 8102:2009.
Table A.1 reproduces Table 2 from BS 8102:2009 which defines three grades of
waterproofing protection.
Table A.1 — Grades of waterproofing protection
Risks associated with the groundwater regime are taken into account when selecting a water proofing
system to achieve the required basement grade. The protection provided comprises one or more of
the following types:
• Type A: barrier protection including bonded sheet membranes, liquid applied membranes,
geosynthetic membranes, mastic asphalt membranes, cementitious multi‑coat renders
and slurries;
A.5 Influences of cracks and other pathways in concrete floor slabs and
basement walls
The ability of concrete to provide resistance to the passage of both moisture and ground gases is
strongly reliant upon the design and construction achieving defect free high quality dense concrete.
Cast in‑situ concrete can be affected by:
• plastic cracking after the initial placement of the concrete due to excessive bleeding/
evaporation rates;
• micro cracking occurring during the hydration process due to inadequate curing;
• shrinkage cracking due to thermal effects, segregation or honeycombing due to inadequate
compaction; and
• structural cracking acquired during the application of service loads (e.g. tension cracks).
For concrete substructures, any cracking that develops increases the permeability. Non‑structural
(limited depth) cracks have less influence on the gas permeability of the concrete slab or basement
wall than structural cracks going through the concrete. Adequately designed and detailed
reinforcement helps reduce susceptibility to cracking.
Joints in the construction, gaps between the floor and the walls and the number of openings within
the floor (e.g. service penetrations) might strongly influence the resistance to gas ingress.
Additionally, the thickness and areal extent of the slab (e.g. large industrial floor slabs) influences
the rate of diffusion through the concrete, if a concentration difference exists between opposite sides
of the concrete element. This is mainly a design consideration where substantial building footprints
are intended.
An important consideration is also the detail at junctions between the floor and wall or isolation
joints. In the case of ground bearing slabs the edge of the floor slab is not built in to the surrounding
walls. This can allow gaps to form along the slab perimeter due to settlement, movement and
shrinkage. These gaps create preferential pathways for gas ingress and can potentially cause damage
to membranes.
Raft foundations avoid such joints as the slab and stiffening ground beams are normally formed from
cast in‑situ concrete in one operation to form a monolithic substructure.
A.6 Overall risk rating for ground gas ingress for different types of building
floor slabs and for basements
Table A.2 provides a risk rating summary for ground gas ingress.
Table A.2 — Risk rating summary
Risk ratings
Substructure/ground floor Gaps Wall to floor Structural Micro Overall risk
type between crack cracking cracking rating
member
elements
Precast suspended segmental Moderate to Low Low Low to Very high
subfloors without and/or with high moderate
bonded reinforced structural
concrete topping (e.g. beam and
block)
Cast in‑situ ground bearing Low High Moderate Moderate to High
floor slab with mesh high
reinforcement for crack control
constructed off a sound sub
base (e.g. traditional ground
bearing floor slab)
Cast in situ monolithic Low Low Low Low to Medium
reinforced concrete ground moderate
bearing raft or suspended/
semi‑suspended cast in situ
reinforced concrete slab with
minimal penetrations
Cast in situ reinforced concrete Low Low Low Low Low
basement constructed
to provide Grade 2 or
Grade 3 (BS 8102:2009)
waterproofing
Annex B (normative)
Applicability and design of ventilation protection measures
B.1 General
COMMENTARY ON B.1
Ventilation protection measures typically take the form of a sub‑floor gas dispersal layer formed
directly beneath the ground floor slab, or beneath a gas membrane if one is placed beneath the
floor slab.
Ventilation protection measures should only be used with an overlying barrier formed by an
appropriately detailed and constructed slab and/or a gas membrane.
NOTE Passive dispersal layers cannot usually be designed to work effectively beneath basement slabs. However,
internal ventilation can be considered as part of the gas protection system for such areas of the building (see B.5 for
further information).
a) void space;
Figure B.1 — Typical passive ventilation arrangement with floor slab above ground level
Key
1 Floor construction including membrane
2 Fresh air in
3 Gas dispersal layer
Figure B.1 (continued)
Figure B.2 — Typical passive ventilation arrangement with floor slab below ground level and low level vents
Key
1 Floor construction including membrane
2 Fresh air in
3 Gas dispersal layer
4 Fresh air and ground gas out
5 Ground gases
6 Wind direction
Figure B.3 — Typical passive ventilation arrangement with floor slab below ground level and high level vents
Key
1 Floor construction including membrane
2 Fresh air in
3 Gas dispersal layer
4 Fresh air and ground gas out
5 Ground gases
6 Wind direction
Key
1 Floor construction including membrane
2 Air pump (fresh air in)
3 Clean air blanket
4 Fresh air and ground gas out
5 Ground gases
Figure B.5 — Typical active suction system with floor slab below ground level
Key
1 Floor construction including membrane
2 Fresh air in
Figure B.5 (continued)
Table B.1 — Gas regimes considered in the DETR/PiT Guide for Design [12]
Gas regime Hazardous gas Gas standpipe emission Equivalent total gas standpipe
concentration velocity volume emission flow
% v/v ms L/h A)
A 1 0.005 35
B 5 0.005 35
C 5 0.01 71
D 20 0.005 35
E 20 0.01 71
F 20 0.05 177
A)
Assumes a 50 mm diameter gas standpipe.
Table B.2 — Gas regimes considered in the PiT Guide for Design [12]
CIRIA C665 [ 6 ] PiT [ 12 ]
CS GSV Gas regime GSV Equivalent CS
L/h L/h
1 <0.07 A 0.35 2
2 0.07 to <0.7 B 1.77 3
3 0.7 to <3.5 C 3.53 4 (low)
4 3.5 to <15 D 7.07 4
5 15 to <70 E 14.14 4 (high)
6 >70 F 70.69 6
For each gas regime, a range of different pressure differences were applied to the opposite sides of
the idealized dispersal layers, to represent a range of different wind‑induced pressures that would
(principally) arise from wind speeds of 3 m/s, 1 m/s and 0.3 m/s. The steady state hazardous gas
concentration in the dispersal layer was then computed by CFD simulations and the results judged in a
scale from very good to unsuitable according to the steady state concentration achieved.
Underfloor passive ventilation systems should be designed to provide sufficient air flow to dilute
ground gases to acceptable concentrations within the dispersal layer beneath the floor slab for most
or all of the time.
NOTE 1 Since passive systems rely on wind to induce pressure driven flow, when there is negligible wind, there is
no flow‑through of clean external air and ground gas concentrations in the dispersal layer builds up. However, still
wind conditions principally occur when there is high atmospheric pressure, whereas ground gas emissions into the
dispersal layer are greatest when there is falling and low atmospheric pressures, which are always characterized by
windy conditions or when the surface of external areas to the building are temporarily frozen or saturated.
NOTE 2 Whereas simple calculations for the side ventilation of a clear air void space dispersal layer can be
undertaken (see BS 5925:1991), this approach cannot easily be applied to other dispersal media.
NOTE 3 The relationship between the hazardous gas flow rate from a standpipe (measured as flow or as
velocity from a 50 mm diameter standpipe) and the rate of gas emission from the ground beneath the idealized
dispersal layer (X in L/h.m2) was assumed using the following formula (see Methane and the development of
derelict land [14]):
GSV
X = (B.1)
10
This assumes that the gas emission from a borehole standpipe is representative of 10 m2 of ground, which is
considered an upper bound of the surface emission rate (see Gas protection – a common sense approach [15]).
The types of dispersal media considered and the variables in the computations are listed in
Table B.3 and the proposed performance assessment for methane and carbon dioxide are reproduced
in Figure B.6 and Figure B.7, respectively; these performance criteria should be used for design of
sub‑floor ventilation measures.
Table B.3 — Variables in the DETR/PiT Guide for Design [12]
200 and 400 2 652
4 420
Polystyrene shuttering Equivalent clear void 2 210 —
depth A):
2 652
22;
4 420
33;
60; and
100
Geocomposite drainage 40 cuspated 2 210 —
blanket
(36 equivalent clear void 2 652
depth)B)
4 420
No fines gravel blanket Thicknesses: 2 210 20 single size grading C)
200 and 400 2 652
No fines gravel blanket Drains at 2 000 524 to 3 140 200 blanket
with perforated pipe gas and 3 000 centres
(5 000 × 5 000)
drains
400 blanket
(30 000 wide)
A)
The equivalent clear void is the volume of the void around the legs of the void former, expressed as a
layer of clear space. The overall heights of the void formers modelled were: 80 mm (square leg); 100 mm
(square leg); 150 mm (round leg) and 200 mm (round leg). The 150 mm and 200 mm high void formers
were specifically designed as a gas dispersal layer void former.
B)
The equivalent clear void depth is the volume of the void around the cusps of the void former, expressed
as a layer of clear space.
C)
Modelling was also carried out on MOT Type 1 (well graded) gravel. However, this was shown to be a
completely unsuitable gravel for use in a gas dispersal layer.
Key
A Very good X Wind speed (m/s)
B Good Y Maximum hazardous gas concentration in ventilation layer (% v/v)
C Fair
D Poor
E Unsuitable
NOTE The information in this figure is based on Passive Venting of Soil Gases Beneath Buildings. Guide for
Design [12].
Key
A Very good X Wind speed (m/s)
B Good Y Maximum hazardous gas concentration in ventilation layer (% v/v)
C Fair
D Poor
E Unsuitable
NOTE The information in this figure is based on Passive Venting of Soil Gases Beneath Buildings. Guide for
Design [12].
NOTE 4 The DETR/PiT research - Passive Venting of Soil Gases Beneath Buildings. Guide for Design. [12] - and
subsequent additional CFD modelling results and interpretation published by two of the DETR/PiT research authors
provides the basis of the understanding of the effectiveness of alternative dispersal media and how passive systems
can be designed. An illustration of the relative performance of different media for a 30 m wide idealized dispersal
layer with no internal discontinuities and similar side ventilation provision is provided in Figure B.8 and for a 5 m
by 5 m wide idealized dispersal layer in Figure B.9.
Figure B.8 — CFD computed volume flow through rates vs wind speed for various media for a 30 m wide foundation
[12]
Key
1 Open void 200 mm deep (Model 2) X Wind speed (m/s)
2 Polystyrene shutter, 100 mm equivalent clear Y Volume flow rate of air through dispersal
space (Model 2) layer (m3/m width/h)
3 Polystyrene shutter, 22 mm equivalent clear
space (Model 2)
4 20 mm (no fines) gravel blanket 400 mm
thick with interleaved pipes at 3 m alternate
centres (Model 5)
5 20 mm (no fines) gravel blanket 400 mm thick with
pipes (not interleaved) at 2 m centres (Model 4)
6 40 mm thick cuspated geocomposite void former
blanket (Model 2)
7 20 mm (no fines) gravel blanket, 400 mm
thick (Model 2)
Figure B.9 — CFD computed volume flow through rates vs wind speed for various media for a 5 m by 5 m wide foun‑
dation [12]
Key
1 Open void 200 mm deep (Model 1) X Wind speed (m/s)
3 Polystyrene shutter, 22 mm equivalent clear Y Volume flow rate of air through dispersal
space (Model 1) layer (m3/m width/h)
6 40 mm thick cuspated geocomposite void former
blanket (Model 1)
7 20 mm (no fines) gravel blanket. 400 mm
thick (Model 1)
8 20 mm (no fines) gravel blanket. 200 mm thick with
pipes (not interleaved) at 2 m centres (Model 3)
9 20 mm (no fines) gravel blanket, 200 mm
thick (Model 3)
On the basis of the CFD modelling, the scale of potential dispersal effectiveness of different passive
gas dispersal media for different sizes of foundation is set out in Table B.4; the actual dispersal
effectiveness depends on adequate design, which should take into account the guidance given in
B.5 to B.10 and should include input from an appropriately qualified and experienced specialist.
NOTE 5 The relative dispersal effectiveness from Table B.4 reflects the results of modelling on products available in
the mid to late 1990s. Other cuspated geocomposites have been developed since that time which are likely to differ
in performance to those modelled.
NOTE 6 The CFD modelling in the mid to late 1990s assumed low level air brick side vents. The provision of high
level vents or fans would improve performance.
NOTE 2 Vents which are terminated several metres above ground level on one side of the building (for example
at building roof level) can usually provide a greater differential pressure across the dispersal layer than low level
vents on both sides of the building. The greater differential pressure causes a greater dilution of ground gases in the
dispersal layer. The suction effects of rotating cowls, or air flow across an open pipe, and thermal stack effects are
the reasons for increased pressure differential.
Regular inspections (and maintenance as necessary) should be made to check that side vents are not
blocked and elevated cowls are functioning correctly.
NOTE 3 Monitoring systems with alarms, such as those used for active venting systems (see B.11), are sometimes
installed to provide an indication of whether the venting system is working as planned. If the alarm sounds too
frequently consideration can be given as to why this is the case and whether the effectiveness of the system can be
improved, e.g. by installing spinning cowls on the exit vents or installing mechanically operated fans.
The volume flow‑through rate is governed by the size and number of side vents; for small
to medium width buildings (up to 15 m wide), the minimum area of side ventilation should
be 1 500 mm2/m run of wall on at least two opposite sides. For larger width buildings, the side
ventilation provisions should be at least 2 000 mm2/m run of wall for gas regimes up to and including
CS3 and 4 500 mm2/m run of wall for gas regime CS4. The minimum depth of the clear void space
should be 100 mm. Where there are multiple internal obstructions to air flow (caused by beams),
there should be four or five times the area of the side vents provided in the internal obstructions.
To assign a points score of 2.5 in Table 6, all of the recommendations in the paragraph above (in
B.6) should be met. If the amount of side ventilation, or internal cross openings, are less than the
above recommendations, then the score should be reduced to 2 or 1.5, depending on the additional
obstruction to air flow in the layer.
a) Round leg, high voidage void former (manufactured for gas dispersal layer)
b) Square leg, lower voidage void former (manufactured primarily as temporary formwork)
A dispersal layer formed of the thicker high voidage polystyrene void former, which has a high void
volume, compared to the volume of the legs, was shown by CFD modelling [12] to have a performance
almost as good as a clear void (see Figures B.8 and B.9). Thinner products with less depth of leg and less
void volume around the legs were shown to have less (but still very good) gas dispersal characteristics
(see Figures B.8 and B.9).
A passive gas dispersal layer formed of polystyrene shuttering is suitable for gas regimes up to and
including CS4. The volume flow‑through rate is governed by the size and number of side vents.
The side ventilation provisions and openings through internal obstructions (e.g. ground beams)
should be at least the same as those given in B.6 for a clear void dispersal layer.
The maximum points score of 2.5 points (in Table 6) for polystyrene shuttering should only be
assigned for the thicker products with an equivalent clear void depth of at least 60 mm, and comply
with the minimum side ventilation and internal cross openings given in B.6. For the thinner
polystyrene shuttering products, the maximum points score should be two points unless calculations
demonstrate that “very good performance” as defined by Figure B.6 and Figure B.7 will be achieved.
In assigning an appropriate score for a particular project, consideration should be made by the
designer of the gas protection measures to the as‑built void space that exists during the life of the
building. If the legs of the void former are seated on a soft layer (such as sand blinding) which fills
up part of the void space, this should be taken into account and the points score reduced accordingly.
Similarly, if clay heave is expected, which crushes the legs of the polystyrene void former over time, a
reduced points score should be assigned.
NOTE If the void space becomes flooded with groundwater, it is no longer effective as a passive gas
dispersal layer.
As a guide a points score of 1.5 in Table 6 can be applied for a 25 mm (or thicker) geocomposite
blanket for buildings up to 15 000 mm wide; for larger width buildings (or thinner geocomposite
blankets), the points score should be reduced to 1.0 or 0.5, depending on the width of the building.
Geocomposite blankets thinner than 25 mm should not be specified for CS3 (or above).
If calculations demonstrate that “very good performance” as defined by Figures B.6 and B.7 will be
achieved, a points score of 2.5 should be applied.
The layer should be a minimum of 300 mm in thickness and have a high porosity (greater than 40%);
the layer does not normally have any mechanical compaction.
NOTE 2 The gas dispersal characteristics of granular aggregate layers are similar to geocomposite blankets,
with the pressure head loss occurring within the aggregate layer and not at the side vent points. The gas dispersal
characteristics of granular aggregate layers have been found to be directly proportional to their thickness and a
methodology for their quantitative design is given in Gas protection measures for buildings, Methodology for the
quantitative design of gas dispersal layers [16].
The minimum side ventilation provision should be the same as for geocomposite blankets.
For small floor slab footprints, it might be possible to design a gravel dispersal layer to achieve “good
performance” or “very good performance” as defined by Figure B.6 and Figure B.7; if this can be
justified by calculation, a points score of 1.5 or 2.5, respectively, can be applied, but if only a fair or
poor performance is calculated, a reduced score of 1.0 or 0.5, respectively, should be applied.
For wide floor slab footprints,a gravel dispersal layer (provided it is comprised of a poorly graded, no
fines gravel) usually only really provides a pressure relief function, in which case the score (Table 6)
is 0.5 points; if the gravel contains a significant amount of fines (more than 10%) or is moderately to
well graded (such as MOT Type 1 or Type 2 gradings), then the layer does not even provide pressure
relief and zero points (see Table 6) should be assigned.
The gas dispersal performance of a granular blanket with gas drains is mainly determined by the
combination of (a) the thickness and porosity of the granular layer and (b) the spacing between the
drains, although the in‑line resistance to flow of a geocomposite strip and the resistance to flow of
the slots in pipes are also factors. The number and size of the side vents is less critical, however side
vents should normally be provided at no more than 10 000 mm centres and have an area equivalent
to 1 500 mm2/m run of wall on at least two opposite sides.
Figure B.12 — Idealized plan of granular gas dispersal layer with network of gas drains
Key
1 Header pipe
2 Gas drains
SV Side vent
If access to maintain the pellistors cannot be provided a system in which gas is drawn back through
narrow pipes to a central monitoring unit should be used; the unit typically draws gas from each pipe
in turn through a single sensor or group of sensors. The monitoring unit should preferably be fitted
with a chart or digital recorder, which if not always on, is turned on when the fans activate.
Two trigger levels should be set for the monitoring system for each gas or condition of concern (e.g.
different concentrations of methane).
NOTE 2 At the lower concentration, the extractor fans activate and an amber alarm is indicated on the control
box and in a repeater panel located somewhere that is clearly visible to those using the building (e.g. the building’s
central services monitoring area). The higher concentration represents a “red alert” situation because it can only
be reached if the fans have failed to actuate at the lower concentration (i.e. there is a fault in the system) or there is
too much gas for the fans to effectively remove it. Such an alert might trigger evacuation of the building or at least
formal consideration of whether this is necessary.
When an active system is installed, the building occupier should be provided with a manual
describing how the system is intended to work, what response there should be to “amber” and “red”
alerts, what maintenance is required of the fans and the monitoring system, and who to contact in the
event that either appears to be malfunctioning.
Ground gases might accumulate beneath and around basement structures and the measures to
protect such parts of the building should include a combination of barrier(s) to prevent ingress of
gases and adequate ventilation within the basement; barrier(s) are normally provided by the form of
construction of the basement and the inclusion of waterproofing or a combined waterproofing and
gas membrane, as necessary. There should be appropriate detailing of below ground service entries
into basements.
NOTE 2 It is often not practical to provide effective passive ground gas dispersal layers around and beneath
basements, although it is possible to provide preferential pathway media (such as a coarse granular curtain or a
geocomposite drainage sheet around the sides of basement wall.
Annex C (informative)
Gas resistant membrane selection
COMMENTARY ON Annex C
Annex C provides guidance on the choice and use of membranes to resist the passage of methane and
carbon dioxide.
The properties of a gas resistant membrane which can be assigned a gas protection score according to
the empirical methodology described in 7.2 are given in 7.2.4.
• the need for welded seams (this determines the minimum thickness of the membrane);
• what verification and integrity testing of the materials, seams and seals, etc. are needed.
NOTE Membranes are available in a variety of thicknesses and types. Each material has different characteristics
which affect installation procedures, durability, lifespan and resistance to damage and gas/vapour permeability
[10]. Membranes can be reinforced to improve the durability of the material and prevent over elongation.
Text deleted
Reinforced LDPE with an aluminium core offers high resistance to soil gases and is flexible with a
high tear resistance. Protection of the aluminium core is critical if contact with alkaline surfaces is
expected, and it has low ultraviolet (UV) light resistance (so needs to be covered). It also has low
elongation due to reinforcement and a foil layer. It is normally produced from high quality virgin
polymers as the film thickness and quality is critical for bonding. A minimum thickness of 0.4 mm
(equivalent to 370 g/m2 for polyethelene) is needed to provide sufficient protection and substrate for
welding. It can be joined using welding techniques or tapes.
HDPE reinforced FPP with aluminium core offers high tear resistance and high resistance to soil
gases but is relatively thin and difficult to join. FPP bonded to aluminium has poor adhesion unless an
interlayer is used.
An HDPE /EVOH/HDPE sandwich offers very high resistance to hydrocarbon vapours and good
resistance to other soil gases due to its construction. It also offers good elongation and puncture
resistance, has high costs and complex installation due to HDPE surfaces. It offers advantages when
high levels of resistance to vapours coupled with elongation are critical issues.
Spray on membranes can be applied to relatively uneven surfaces and areas with complicated
detailing. They need a substrate geotextile on large flat areas. However, it is difficult to maintain
constant thickness even if they are applied by experienced installation operatives.
NOTE 2 A protection layer is generally required above any membrane when it is placed directly under a
reinforced concrete slab, unless it can be robustly demonstrated this is not needed to protect the integrity of the
membrane after it is laid.
NOTE 3 Some membranes have a centre fold for packing which, in many cases, leads to large creases across
the full width of the sheet. It is not possible to adequately seal joints where creasing is present and consequently
creased membranes are only suitable for installation as a gas resistant membrane if the membrane is laid to ensure
that any folds or ripples are removed and the membrane lies smooth and flat over the prepared receiving surface
and provided that previous folds are kept away from all joints.
NOTE 4 Geosynthetic clay liners comprising a thin layer of dry clay powder sandwiched between two
geotextiles , sometimes used as waterproofing barriers, are not suitable as barriers to gas migration into
buildings. This is because the liner relies on the bentonite material becoming wet to form a barrier, which cannot be
guaranteed. Even if it is pre‑wetted during installation the clay can dry out in a building application where it is not
exposed to infiltrating rainfall and might crack, thus allowing vapour to migrate through it. Test results for water
vapour transmission on these types of barrier are not indicative of the likely rate of gas or vapour transmission.
NOTE 5 GCL products that are composite products incorporating a polyolyfin membrane may be viewed
differently to normal GCL products.
Annex D (informative)
Characterization without gas monitoring data
D.1 General
This annex provides guidance for an empirical approach to characterizing sites without gas
monitoring data where the source(s) of ground gas on the site is made ground with a low degradable
organic content. It is not intended to be exhaustive and its proper application requires an
understanding of the underlying scientific principles and technical issues.
NOTE 1 This approach is based on the method of characterizing a site without gas monitoring data described
in RB17 [1].
NOTE 2 RB17 [1] also advises that it is possible to characterize sites where the only sources of methane and carbon
dioxide are natural deposits, in the form of alluvium or carbonate strata (e.g. chalk) without gas monitoring data. In
the case of alluvium, including deposits with buried peat layers, RB17 advises that it can be assumed that the site is
CS2, due to the very low gas generation rates of such deposits. In the case of carbonate strata, RB17 [1] advises that
the gas risk is negligible and no gas monitoring or protection measures are usually necessary. Before applying this
empirical guidance, the conceptual site model is carefully assessed to check that there are not reservoirs of existing
methane and/or carbon dioxide gases that could have preferential pathways to the underside of the new building
development.
D.2 Principle
In this approach the representative gas regime (CS) is assigned based on:
• the conceptual site model, derived by updating the preliminary conceptual site model to
take into account geological, hydrogeological and geotechnical data of an adequate ground
investigation (BS 5930 and BS 10175) conducted to inform the design of the development;
• knowledge of the TOC content of potential ground gas generating made ground; and
• a detailed examination of the made ground soil material in accordance with Annex E.
D.3 Application
This approach may be adopted if:
• the preliminary conceptual site model has not identified any high gas generation sources; and
• the source is made ground that has less than 3 m average depth and 5 m maximum depth, and
with TOC less than the limit for CS3 in Table D.1.
Table D.1 — Limiting values of thickness and organic content of made ground (after RB17 [1], Table 1)
Thickness of made Maximum total organic carbon content of Site characteristic situation
ground made ground – TOC (CS) to be assumed
Made ground in place Made ground in place
for <20 years for >20 years
m % %
Maximum 5 m ≤1.0 ≤1.0 CS1
Average <3 m
Maximum 5 m ≤1.5 ≤3 CS2
Average <3 m
Maximum 5 m ≤4 ≤6 CS3
Average <3 m
NOTE Gas monitoring is required where TOC is greater than 4% (or 6% in old made ground). Gas monitoring
results show whether the high TOC is available or not and if existing conditions are generating ground gas.
The bounding values for TOC, the thickness of made ground and the age of the made ground in
Table D.1 are empirical and intended to be applied by taking into account all the available evidence,
i.e. they are for guidance only.
This approach may:
• not be applied on its own to assess off‑site sources or materials associated with waste
disposal; and
• only be used to define sites with very low to moderate hazard potential (CS1 to CS3).
NOTE 1 This approach is limited to a maximum of CS3.
The TOC data is collected during an adequate site investigation for the development.
The TOC of soils is determined in accordance with BS EN 13137:2001.
NOTE 2 TOC is an analytical determinand defined by the analytical method used. Different analytical methods give
different results. It is important therefore to only use the recommended method.
NOTE 3 Knowing the amount of degradable organic carbon that is present is important. However, there are no
standardized methods by which this might be readily estimated. Hence, TOC is used as the defining parameter as
this is a standard test for waste acceptance classification (WAC) testing carried out by commercial laboratories.
The applicable TOC value to be used in conjunction with Table D.1 is determined from the laboratory
TOC results. These results are obtained on the <10 mm soil fraction of the made ground and adjusted,
if necessary, to take into account the results of detailed examination of the materials present in the
ground (see Annex E).
Information on TOC and on the physical make‑up of the ground as determined by detailed
examination of the materials present in the ground is collected with the same attention to the need
for representative samples and adequate density of sampling as all other parameters that might be of
concern on a potentially contaminated site [see BS 10175 and BS ISO 18400‑104].
Care is needed where made ground includes organic materials that are not readily degradable.
For example, coal ash, clinker and coal can give high TOC results but the high TOC values do not
necessarily represent the risk of gas emissions from such materials, which have a low degradable
organic content (see Note 5). Such materials are generally not readily degradable so produce no
more than low volumes per unit time of methane or carbon dioxide. In such cases, the assessor
may estimate the degradable organic carbon content or the proportion of lignin, cellulose and hemi
cellulose in the sample by testing (e.g. Assessing MSW degradation by BMP and fibre analysis [17]).
Such an assessment is beyond the scope of this Annex.
NOTE 4 For example, coke breeze can contain up to 51% TOC but only 4% degradable organic carbon)
(see Fundamentals, Instrumentation and Techniques of Sum Parameter Analysis [18]).
NOTE 5 The TOC value is based on detailed examination and laboratory testing of the made ground deposit so
needs to take account of soil fractions that are fully representative of the deposit. For example, if made ground
contains 30% organic material at 20% TOC and the remaining 70% of the soil fraction has a TOC of 0.5%, the
overall TOC is 6.4%.
Discrete layers of highly degradable material are assessed separately from other made ground; for
example, a layer of rotting vegetation or highly organic sediment at the base of in‑filled ponds, as
these can support higher rates of gas generation, and thus represent a higher risk situation.
If these are present, then this method is best supplemented by targeted boreholes and
appropriate monitoring.
As with assessment using gas monitoring data, before assignment of a CS, careful consideration is
given to possible changes in ground conditions that might arise from foreseeable natural events (e.g.
changes in groundwater levels and sudden marked drops in atmospheric pressure), construction
activities or on completion of the planned development (e.g. disturbance of the ground admitting
water and air, inhibition of ground gas exchange with the atmosphere and creation of permanent
pathways by which water and/or air could enter the ground).
All assumptions made leading to an assignment of a CS, and the reasoning behind them are carefully
recorded and reported together with all relevant data and other information.
Annex E (informative)
Sampling, examination and TOC testing of made ground for
the assessment of the potential for gas generation
E.1 General
This annex provides guidance on a method for estimating the amount of degradable organic
material in a sample of made ground for the purpose of applying the approach of site
characterization in Annex E.
NOTE 1 This annex describes the detailed forensic examination referred to in Annex D.
NOTE 2 This annex does not provide guidance on how to take samples, where to take them from or the number of
samples required to provide an overall characterization of the ground in terms of the amount and type(s) of organic
materials present.
E.2 Application
COMMENTARY ON E.2
The most practical way to carry out the detailed forensic detailed examination in Annex E is to
complete it on‑site as samples are taken. This avoids having to transport and dispose of large volumes of
sample material. Alternatively it may be completed at a geotechnical or chemical test laboratory.
Detailed examination of samples is carried out with regard as appropriate to:
• guidance on the pretreatment of samples in the field in BS ISO 18400‑201;
• guidance on handling, preservation and transport of samples to laboratories in
BS ISO 18400‑105; and
• guidance on pretreatment of samples in the laboratory in BS ISO 23909.
The results of the examination are used in conjunction with a careful observation and description of
the ground from which the test sample has been taken.
E.3 Principle
A sample of made ground is taken and the main constituents divided into separate fractions. The
fractions are weighed to determine the proportion of each in the sample.
E.4 Apparatus
Weighing scales are used that have a maximum capacity of at least 15 000 g with a readability
of 0.02% of maximum capacity or 2 g, whichever is the lesser.
E.5 Sample
A sample of made ground with a weight of 10 000 g to 15 000 g is taken.
Larger samples (e.g. an excavator bucket‑load) are reduced in size following the guidance in
BS ISO 18400‑2012, as appropriate.
E.6 Procedure
The bulk sample is spread out on a suitable surface (e.g. plastic sheet).
The sample is divided into the following fractions following the procedures described in
BS ISO 18400‑2012 or BS ISO 23909 as appropriate (e.g. sieving, hand‑picking):
• fine soil materials including gravel less than 10 mm in size;
• coarse inert particles greater than 10 mm in size including clinker, gravel, concrete, brick, etc.;
• discrete fragments greater than 10 mm in size of, for example:
• woody material;
• vegetable matter;
• cloth, leather;
• metal, glass, ceramics and other inert materials;
• paper and card; and
• other degradable material.
The less than 10 mm fine soil might contain discrete particles of organic material (e.g. wood). A
decision might therefore need to be made as to whether or not to attempt to separate this by hand
picking. If this is done, the mass of the material removed is recorded.
Each fraction is then weighed and the result recorded.
The total organic carbon content of the fine soil fraction (i.e. <10 mm) is determined in accordance
with BS EN 13137.
E.7 Reporting
The test report includes the following information:
• site reference;
• sample reference;
• sample location and depth; and
• date of sampling.
It also includes the weight of each of the following fractions in the sample:
• fine soil including gravel less than 10 mm;
• organic fraction separated from the fine soil fraction if this has been done;
• coarse inert particles including gravel, concrete, brick, etc. greater than 10 mm;
• woody material, etc.;
• green vegetation, grass, food waste, etc.;
• cloth, leather;
• metal, glass, ceramics and other inert material;
• paper and card;
• other degradable material; and
• TOC content of fine soil fraction.
The approach used for detailed examination of made ground for the assessment of the potential for
gas generation is given in Figure E.1.
Figure E.1 — Approach for detailed examination of made ground for the assessment of the potential for gas genera‑
tion
Annex F (informative)
Worked examples
F.2 Site A
F.2.1 Site A ground conditions and available gas monitoring data
This is a typical estuarine site where there is a layer of made ground overlying alluvial deposits
comprising clay and peat, overlying river gravel. A relatively high groundwater Table is present
within the peat, but this is not as responsive as the underlying gravel aquifer, where the groundwater
response lags the tidal situation.
Based solely on knowledge of the potential gas sources (made ground and alluvium) an experienced
assessor is likely to anticipate that the site will be a very low or low hazard potential site
(CS1 or CS2).
A recent ground investigation, principally for geotechnical purposes, has already been carried out at
the site which included the installation of five combined gas and groundwater monitoring borehole
standpipes. Methane and carbon dioxide concentrations and standpipe emission flow rates were
measured on three occasions in these five standpipes.
Table F.1 summarizes Site A ground conditions.
Table F.1 — Site A ground conditions
Date BH ID Flow Concentration CH4 Concentration CO2 Qhg CH4 Qhg CO2 Stratum Flooded Barometric
A ) A ) screened response pressure
(peak) (peak)
zone (yes/no)
Peak Steady Peak Steady Peak Steady
BS 8485:2015+A1:2019
L/h L/h % % % %
10/06/2014 BH101 0.0 0.0 0.0 0.0 1.4 1.2 0.000 0.000 AL & S&G Y Rising
BH102 12.0 11.0 1.0 0.9 2.0 1.8 0.110 0.220 AL & S&G Y
BH103 2.0 0.0 0.1 0.0 1.3 1.2 0.000 0.000 AL & S&G Y
BH104 0.5 0.1 0.4 0.3 0.8 0.7 0.000 0.001 AL & S&G Y
BH105 20.0 16.0 0.3 0.2 9.0 8.5 0.048 1.440 AL & S&G Y
24/06/2014 BH101 0.1 0.0 0.0 0.0 1.1 1.1 0.000 0.000 AL & S&G Y Rising
BH102 9.0 8.0 0.1 0.1 2.5 2.3 0.008 0.200 AL & S&G Y
BH103 −40.0 ‑35.0 0.5 0.4 5.5 5.4 −0.175 −1.925 AL & S&G Y
BH104 0.6 0.6 2.1 2.1 0.2 0.2 0.013 0.001 AL & S&G Y
BH105 16.0 15.0 0.8 0.7 5.0 4.5 0.120 0.750 AL & S&G Y
08/07/2014 BH101 0.0 0.0 0.1 0.0 1.3 1.2 0.000 0.000 AL & S&G Y Falling
BH102 8.0 7.5 0.3 0.4 2.0 1.8 0.023 0.150 AL & S&G Y
NOTE Shaded cells are maximum steady state flow, positive and negative (all standpipes and measurements) and maximum concentrations for methane and carbon dioxide (all
Calculated using peak concentration and steady state flow (see 6.3.4).
NOTE 1 The standpipes had been installed principally for sampling groundwater in the sand/gravel layer and for
monitoring the presence of gas arising from peat layers in the alluvium; the screened section only extended in the
sand/gravel layer and the lower (saturated) part of the overlying alluvium layer.
The conclusion of the review is that this gas monitoring data is not reliable to characterize the ground
gas conditions.
NOTE 2 If the data had been used, the maximum implied CS derived by combining the maximum observed flow rate
and maximum observed concentrations from different boreholes during any monitoring event would have been as
in Table F.3.
Table F.3 — Maximum implied CS derived by combining the maximum observed flow rate and maximum observed
concentrations from different boreholes during any monitoring event
Flow rate Chg CH4 Chg CO2 Qhg CH4 Qhg CO2 Implied Implied
q (Chg × q) (Chg × q) CH4 CS CO2 CS
L/h % % L/h L/h
16 2.3 9 0.37 1.44 2 3
−35 2.3 9 0.81 3.15 3 3
NOTE Implied CS from Table 2 using Qhg flow rates, although Table 2 is for assigning site (or zone) CS based on
site characteristic GSV.
Date BH ID Flow Concentration CH4 Concentration CO2 Qhg CH4 Qhg CO2 Stratum Flooded Barometric
A ) A ) screened response pressure
(peak) (peak)
Zone (yes/no)
Peak Steady Peak Steady Peak Steady
BS 8485:2015+A1:2019
L/h L/h % % % %
05/08/2014 BH106 0.0 0.0 0.1 0.1 0.6 0.5 0.00 0.00 MG & AL N Rising
BH107 0.1 0.1 0.0 0.0 0.2 0.3 0.00 0.00 MG & AL N
BH108 0.5 0.4 0.3 0.3 9.0 8.5 0.00 0.04 MG & AL N
BH109 0.2 0.2 0.3 0.3 1.2 1.0 0.00 0.00 MG & AL N
BH110 0.0 0.0 0.1 0.0 0.1 0.0 0.00 0.00 MG & AL N
02/09/2014 BH106 0.0 0.0 0.1 0.0 0.4 0.2 0.00 0.00 MG & AL N Rising
BH107 0.2 0.2 0.5 0.4 4.0 3.2 0.00 0.01 MG & AL N
BH108 0.0 0.0 0.2 0.1 3.0 2.5 0.00 0.00 MG & AL N
BH109 −0.4 −0.3 0.5 0.4 5.5 5.2 0.00 0.02 MG & AL N
BH110 0.3 0.1 0.0 0.0 0.1 0.0 0.00 0.00 MG & AL N
16/09/2014 BH106 0.0 0.0 0.1 0.1 0.4 0.4 0.00 0.00 MG & AL N Rising
BH107 0.3 0.1 0.0 0.0 4.0 3.0 0.00 0.01 MG & AL N
BH107 0.3 0.2 0.2 0.2 1.5 1.4 0.00 0.00 MG & AL N
Table F.4 (continued)
Date BH ID Flow Concentration CH4 Concentration CO2 Qhg CH4 Qhg CO2 Stratum Flooded Barometric
A ) A ) screened response pressure
(peak) (peak)
Zone (yes/no)
Peak Steady Peak Steady Peak Steady
BRITISH STANDARD
L/h L/h % % % %
BH108 0.3 0.1 0.5 0.5 3.5 3.2 0.00 0.00 MG & AL N
BH109 0.2 0.1 0.9 0.6 5.0 4.8 0.00 0.01 MG & AL N
BH110 0.0 0.0 0.2 0.1 1.0 0.8 0.00 0.00 MG & AL N
A)
NOTE Shaded cells are maximum steady state flow and maximum concentrations for methane and carbon dioxide (for each standpipe).
Calculated using peak concentration and steady state flow (see 6.3.4).
BH ID Flow rate Chg CH4 Chg CO2 Qhg CH4 Qhg CO2 Implied Implied
The worst case CS is derived by combining the maximum observed flow rate and maximum observed
concentrations from different boreholes during any of these subsequent monitoring events, as shown
in Table F.6.
Table F.6 — Worst case implied CS derived by combining the maximum observed flow rate and maximum observed
concentrations from different boreholes during any of these subsequent monitoring events
Flow rate Chg CH4 Chg CO2 Qhg CH4 Qhg CO2 Implied Implied
q (Chg × q) (Chg × q) CH4 CS CO2 CS
L/h % % L/h L/h
1.1 1.0 9.0 0.01 0.10 1 2
NOTE Implied CS from Table 2 using Qhg flow rates, although Table 2 is for assigning site (or zone) CS based on
site characteristic GSV.
On the basis of the measurements in Table F.6, the site GSV is taken to be 0.10 L/h, which is the worst
case for methane and carbon dioxide. From Table 2, a GSV of 0.10 L/h lies within the range of GSV
values for CS2 (0.07 to <0.7), and is not near the upper end of this range. Therefore CS2 is taken as
the design gas regime for the site.
Table F.7 shows the Site A gas protection score needed for different building types.
Table F.7 — Minimum gas protection score (points) for different types of building at Site A
(2)
School and/or hospital, 3.5 (part) and Cast in‑situ Low fines gravel Gas resistant 3.5
(no basement) ground‑bearing slab blanket with gas membrane (in
2.5 (part)
drains into gravel accordance with all
(Partly Building Type B (1)
trench around the recommendations
and partly Building Type
building (preferential in Table 7)
C)
pathway only)
(2)
(0.5)
Managed apartments, (no 3.5 Cast in‑situ Low fines gravel Gas resistant 4
basement) suspended slab blanket into gravel membrane (in
trench around accordance with all
(Building Type B) (1.5)
building (preferential the recommendations
pathway only) in Table 7)
(0.5) (2)
Basement area of office 2.5 Cast in‑situ Part well ventilated DPM in car parking 5
building with basement ground‑bearing basement car park areas
car park and service/store basement slab
(4) (0)
rooms
(1)
(Building Type C)
part poorly Gas resistant 3
ventilated rooms/ membrane (in
spaces accordance with all
the recommendations
(0)
in Table 7) in service/
store room areas
(2)
Table F.8 (continued)
Type and use of building Minimum score Structural Barrier Ventilation/ Gas membrane Total achieved
dilution score
(score) (score)
(score)
Office building with 2.5 Grade2 waterproofed Low fines gravel DPM 2.5
basement plant rooms basement blanket beneath
(0)
basement slab and
(Building Type C) (2)
behind all walls
(pressure relief
pathway)
(0.5)
Large floor plan retail/ 1.5 Cast in‑situ 6F2 sub‑base + DPM 1.5
commercial/industrial ground‑bearing slab geocomposite
(0)
building (no basement) dispersal layer to
(1)
low level vents
(Building Type D)
(preferential
pathway only)
(0.5)
Suspended floor slab Well graded subbase DPM 1.5
(not pressure relief
(1.5) (0)
pathway)
(0)
F.3 Site B
F.3.1 Site B ground conditions and available gas monitoring data
This site includes an area of 1960s landfill within a former gravel pit, which is the area where the
buildings are proposed. Records of the types of wastes deposited are limited but indicate a greater
proportion of construction and demolition wastes with lesser proportion of household wastes.
Based solely on knowledge of the potential gas source (made ground deposited in 1960s landfill) an
experienced assessor is likely to anticipate that the site will be a “low or moderate hazard potential”
site (CS2 or CS3).
The ground conditions revealed by a site investigation carried out in accordance with the
recommendations in 5.0 are shown in Table F.9.
Table F.9 — Site B ground conditions
Standpipes have been installed with a response zone through the landfill and extending into the
underlying sand/gravel. There is a reasonable amount of gas monitoring data that is not presented in
detail in this example. The key measurements are given in F.3.2.
Flow rate Chg CH4 Chg CO2 Qhg CH4 Qhg CO2 Implied Implied
q (Chg × q) (Chg × q) CH4 CS CO2 CS
L/h % % L/h L/h
4.2 8.1 12.0 0.34 0.50 2 2
0.5 22.0 6.5 0.11 0.03 2 1
NOTE Implied CS from Table 2 using Qhg flow rates, although Table 2 is for assigning site (or zone) CS based on
site characteristic GSV.
The worst case implied CS is derived by combining the maximum observed flow rate and maximum
observed concentrations from different boreholes during any monitoring event, as shown
in Table F.11.
Table F.11 — Worst case implied CS derived by combining the maximum observed flow rate and maximum observed
concentrations from different borehole standpipes during any monitoring event
Flow rate Chg CH4 Chg CO2 Qhg CH4 Qhg CO2 Implied Implied
Q (Chg × q) (Chg × q) CH4 CS CO2 CS
L/h % % L/h L/h
4.2 22.0 12 0.92 0.50 3 2
NOTE Implied CS from Table 2 using Qhg flow rates, although Table 2 is for assigning site (or zone) CS based
on site characteristic GSV.
On the basis of the measurements, the site GSV is taken to be 0.92 L/h, which is the worst case for
methane and carbon dioxide. From Table 2, a GSV of 0.92 L/h lies within the range of GSV values for
CS3 (0.7 to <3.5), and is very close to the lower end of this range. Therefore CS3 is taken as the design
gas regime for the site but recognized that it is likely to be a conservative designation.
Table F.12 shows the minimum gas protection score for different building types at Site B.
Table F.12 — Minimum gas protection score (points) for different types of building at Site B
(0.5)
Office building with 3 Cast in‑situ Grade 1 Ventilated — 5
basement car park basement car park
ground‑bearing
(Building Type C) basement slab (4)
(1)
Table F.13 (continued)
Type and use of Minimum score Structural Barrier Ventilation/ Gas Membrane Total
building dilution achieved
(score) (score)
score
(score)
Basement plant 3 BS 8102 No external Internally applied 4
rooms of office ventilation asphalt‑latex
Grade 2
building measures gas resistant
waterproofed membrane
(Building Type C) (0)
basement
(2)
(2)
Large floor plan 2.5 Cast in‑situ No ventilation Gas resistant 3
retail /commercial / ground‑bearing slab measures membrane (in
industrial building, accordance
(1) (0)
at grade with all the
recommendations
(Building Type D)
in Table 7)
(2)
Suspended floor slab Low voidage Damp proof 3
polystyrene void membrane (DPM)
(1.5)
former dispersal
(0)
layer, low level
side vents (good
performance)
(1.5)
A)
The combinations of measures given in Table F.14 are examples of how the minimum required score could be
achieved. Other combinations of measures might be more appropriate for a particular building.
NOTE If the new building is not situated directly over the landfilled area an alternative approach is to delineate the extent
of the landfilled area and to introduce an in‑ground venting/barrier trench between the landfill and the building site.
Annex G (informative)
Radon
G.1 General
This British Standard does not consider the risks associated with radon gas, primarily as the methods
of measurement and risk assessment do not align with those for other ground gases. However, as
there are similarities in the methodology of mitigation of the effects of the gas Annex G is included to
give the reader a background to the subject and suggest further reading and research.
NOTE BS 8576:2013, Annex B also contains information on radon including suggestions as to how it could be
measured in the ground.
G.2 Background
Radon is a naturally occurring radioactive gas which decays into other radioactive species. It decays
to form a radioactive particle in the air which, when inhaled emits radiation that damages the lungs.
The main danger from high radon exposure is the increased risk of lung cancer. Estimates of radon
related deaths have been suggested based on epidemiological information to be up to 2 000 fatal
cancers per year.
Radon can move through cracks and fissures in the subsoil and eventually to the atmosphere. Most of
the radon disperses harmlessly into the air outside but some passes through the ground and collects
in spaces under or within buildings.
Radon is formed by the radioactive decay of the small amounts of uranium present in all rocks
and soils. It is commonly present in mine gas and can also be released from groundwater when it
is extracted from the ground. It can sometimes be found in significant quantities in private water
supplies in areas where there are high levels of radon gas. It can also arise from deposited wastes
such as those from the nuclear industry, phosphorus slags, and coal ash. There are published and
draft International Standards for investigation and determination of radon in soils (BS ISO 18589, all
parts) and in air (BS ISO 11665‑1). The latter provides guidance on analysis of historic records, site
reconnaissance, identifying preferential migration pathways and development of a sampling plan.
Information and guidance on radon in the environment is available on the Public Health England
(PHE) RadonUK website1. Also, the Health Protection Agency (now PHE) published advice on radon
in 2010 [19].
The Ionising Radiations Regulations 1999 [22] require action to protect employees if the average
radon gas concentration exceeds 400 Bq/m3 in air (see the Note to G.4). All below ground workplaces
require a risk assessment regardless of whether or not they are in an affected area and the HSE
recommend all occupied basements in workplaces are tested. The HSE and local authorities, as
appropriate, are responsible for ensuring and supporting compliance with this action including
installation of protective measures in existing properties when they are required. The Building
Research Establishment (BRE) has published guidance for building owners and managers [23].
Annex H (informative)
Volatile organic compounds (VOCs)
H.1 General
This British Standard does not consider the risks associated with VOC gases, primarily as the
methods of measurement and risk assessment do not fully align with those for other ground gases
(see BS 8576). However, as there are similarities in the methodology for mitigation of the effects of
VOCs entering indoor or ambient air spaces, this annex is included to give the reader a background to
the subject and to suggest further reading.
H.2 Background
VOCs are organic compounds that are volatile under normal environmental/atmospheric conditions,
although they can sometimes be found in the ground as solid, liquid and dissolved phases as well as
in the gaseous phase.
NOTE 1 A VOC can also be defined as an organic compound which is liquid at 20 °C and which generally has a
boiling point below 180 °C (see BS EN ISO 11074).
NOTE 2 Examples include single‑ring aromatic hydrocarbons and other low boiling halogenated hydrocarbons,
which are used as solvents or fuels, and some degradation products.
H.4 Protection
Protection of end users from VOCs can be achieved by treating the source of the VOCs, managing
the pathway between the VOC source and the receptor, by managing the receptor or a combination
of methods. CIRIA Report C716 [42] provides an overview of the techniques available for treating
or managing the risk presented by VOCs. The methods commonly used to mitigate the risks from
VOCs by managing the pathway(s) are similar to the mitigation methods used to manage the risks
presented by other gases including carbon dioxide and methane. Both in‑ground and in‑structure
pathway management techniques can be used. In addition within buildings and other structures, it
might also be possible to adjust pressure differences to reduce vapour intrusion.
As with other gases, common methods of in‑structure pathway management include the
incorporation of a membrane in the construction of the floor and a ventilated under‑floor void.
However, there are important differences between VOCs and other gases. These include:
• the number of different VOCs that might be present, singly or together, in ground gas;
• the fact that many VOCs undergo degradation during transport from the subsurface to the point
of exposure, which can be difficult to account for in modelling; and
• that risks can in some cases be presented by very low concentrations of VOCs (see CIRIA
Report C716 [42]).
Due to these differences, there is no easy way to determine the number of levels of in‑structure
protection that are needed to reduce the risk to an acceptable level. Instead the design needs to take
into consideration the effectiveness of the remediation solution (e.g. what has been done to remove
or control the source), the confidence in the site characterization and quantitative risk assessment,
and the number of lines of evidence for a risk being presented by the vapour intrusion pathway.
Gas resistant membranes are routinely used within the construction industry to reduce the ingress
of permanent gases into buildings. It seems reasonable, therefore, to ascertain whether gas resistant
membranes as defined in 3.3 provide protection against VOCs and whether, if protection measures
including a gas resistant membrane are to be installed, these also provide protection against VOCs.
There are no simple answers to these questions and decisions usually need to be made on a
site‑specific basis taking into account of, for example, the VOCs present, their concentrations, and
the nature of the membrane (e.g. material(s) from which it is manufactured, physical properties
thickness) and supplementary materials (e.g. adhesives and sealants).
Individual VOCs can variously permeate through, be absorbed by (sometimes causing swelling),
and degrade and change the physical properties of membrane materials. Consideration of whether
a membrane provides protection against VOCs is made more difficult because they are rarely
found in the sub‑surface as a single compound and are more typically found as a mixture of
different compounds.
The membrane has not only to prevent the entry of VOCs in the short‑term but to remain effective
for the design life of the building, i.e. remain durable. Degradation of the membrane can occur over a
prolonged period of exposure rather than in the short‑term.
Individual polymers permit particular VOCs to permeate them depending upon how chemically
similar they are to the challenge compound. For example, although HDPE does not permit the passage
of carbon dioxide and methane, VOCs can migrate through it at a rate that is quite high, taking into
account the allowable concentrations of those vapours inside buildings.
Specific chemical‑resistant membranes with a higher degree of resistance to either degradation or
corrosion are available. These types of membrane are specifically designed for use in‑ground where
the membrane may be in contact with chemicals at high concentrations (CIRIA Report C716 [42])
either as a separate phase liquid or dissolved in groundwater or a non‑aqueous phase liquid; for
example, VOCs can dissolve in non‑volatile hydrocarbons.
Specific chemical‑resistant membranes are not necessarily needed in all scenarios; for example,
where located above floor slab and ventilated sub‑floor void. Modelling demonstrates that the risks
can be appropriately managed with this construction. However, where high concentrations of VOCs
in gaseous form are anticipated, the suitability of any membrane that might be used needs careful
consideration.
As with permanent gases, the quality of installation of the membrane is a determining factor in how
well the installed membrane prevents VOC ingress into the building. Poor installation practices can
cause tears or punctures in the membrane. Tears and punctures can increase considerably the VOC
flow rate through the membrane as the VOC can move via a convective flow mechanism as well as the
normal diffusive flow mechanism. As noted above, VOCs can also degrade adhesives and sealants, and
particular care is needed if these are used.
Foamed polystyrene and HDPE geocomposite void formers are sometimes used to provide a sub‑floor
gas dispersal layer. If VOCs are present, it is important that the void former selected is not chemically
degraded by the VOC.
Bibliography
Standards publications
For dated references, only the edition cited applies. For undated references, the latest edition of the
referenced document (including any amendments) applies.
BS 5925, Code of practice for ventilation principles and designing for natural ventilation
BS 5930, Code of practice for site investigations
BS 8102:2009, Code of practice for protection of below ground structures against water
from the ground
BS EN 1992‑1‑1, Eurocode 2: Design of concrete structures — Part 1‑1: General rules and rules
for buildings
BS EN ISO 11074, Soil quality — Vocabulary
BS EN ISO 11665‑1, Measurement of radioactivity in the environment — Air: radon‑222 – Part 1:
Origins of radon and its short‑lived decay products and associated measurement methods
BS ISO 15105‑1:2007, Plastics — Film and sheeting — Determination of gas transmission rate —
Part 1:Differential‑pressure methods
BS ISO 18400‑104, Soil quality — Sampling — Part 104: Strategies (in preparation)
BS ISO 18400‑105,2) Soil quality — Sampling — Part 105: Packaging, transport, storage and
preservation of samples
BS ISO 18400-201, 2) Soil quality — Sampling — Part 201: Physical pretreatment in the field
BS ISO 18589 (all parts), Measurement of radioactivity in the environment — Soil
BS ISO 23909, Soil quality — Preparation of laboratory samples from large samples
ASTM D638, Standard Test Method for Determining Tensile Properties of Plastics
Other publications
[1] Contaminated Land: Applications in Real Environments. A Pragmatic Approach to Ground Gas
Risk Assessment. RB17. CL:AIRE, 2012.
[2] Department for Environment. Food and Rural Affairs. Model procedures for the management of
land contamination. CLR11. Environment Agency, Bristol, 2004.
[3] Construction Industry Research and Information Association. CIRIA Report 130 – Methane:its
occurrence and hazards in construction. CIRIA, 1993.
[4] WILSON. S., CARD, G. and HAINES, S. Ground Gas Handbook. Whittles Publishing,
Dunbeath, 2009.
[5] Construction Industry Research and Information Association. CIRIA Report 149 - Protecting
Development from Methane. CIRIA, 1995.
[6] Construction Industry Research and Information Association. WILSON, S., OLIVER, S., MALLETT,
H., HUTCHINGS H. and CARD, G. Assessing risks posed by hazardous ground gases to buildings
(C665). CIRIA, London, 2007.
[7] Construction Industry Research and Information Association. CIRIA Report 152 - Risk
Assessment for Methane and other Gases from the Ground. CIRIA, 1995.
2 BS ISO 18400‑105 and BS ISO 18400‑201 are in preparation and it is anticipated that they will be published in 2015.
[27] BUILDING RESEARCH ESTABLISHMENT. SCIVYER, C.R. Major Alterations and Conversions: A
BRE Guide to Radon Remedial Measures in Existing Dwellings. BR267. Garston. IHE BRE Press,
Watford, 1994.
[28] BUILDING RESEARCH ESTABLISHMENT. SCIVYER, C. R. and GREGORY, T.J. Radon in the
Workplace. BR293. Garston. BRE, Watford, 1995.
[29] BUILDING RESEARCH ESTABLISHMENT. SCIVYER, C.R., CRIPPS, A. and JAGGS, M.P.R. Radon
sump systems: a BRE guide to radon remedial measures in existing dwellings, 2nd edition.
BR227. Garston, Watford: BRE, 1998.
[30] BUILDING RESEARCH ESTABLISHMENT. Radon: Guidance on Protective Measures for New
Dwellings in Scotland. BR376. Garston. IHS BRE Press, Watford, 1999.
[31] BUILDING RESEARCH ESTABLISHMENT. Radon: Guidance on Protective Measures for New
Dwellings in Northern Ireland. BR413. Garston. IHS BRE Press, Watford, 2001.
[32] BUILDING RESEARCH ESTABLISHMENT. STEPHEN, R.K. Positive Pressurisation: A BRE Guide to
Radon Remedial Measures in Existing Dwellings. BR281. Garston. IHS BRE Press, Watford, 1995.
[33] BUILDING RESEARCH ESTABLISHMENT. Good Repair Guide GRG 37/1, Radon solutions in homes
– Improving underfloor ventilation. Garston. BRE, Watford, 2012.
[34] BUILDING RESEARCH ESTABLISHMENT. Good Repair Guide GRG 37/2, Radon solutions in homes
– Positive house ventilation. Garston. BRE, Watford, 2013.
[35] BUILDING RESEARCH ESTABLISHMENT. Good Repair Guide GRG 37/3, Radon solutions in homes
– Radon sump systems. Garston. BRE, Watford, 2013.
[36] BUILDING RESEARCH ESTABLISHMENT. Good Repair Guide GG 38, Radon solutions in older
homes. BRE, Watford, 2014.
[37] BUILDING RESEARCH ESTABLISHMENT. Good Building Guide GG 73, Radon protection for new
domestic extensions and conservatories with solid concrete ground floors. BRE, Watford, 2015.
[38] BUILDING RESEARCH ESTABLISHMENT. Good Building Guide GG 74, Radon protection for new
dwellings. BRE, Watford, 2015.
[39] BUILDING RESEARCH ESTABLISHMENT. Good Building Guide GG 75, Radon protection for new
large buildings. BRE, Watford, 2015.
[40] Construction Industry Research and Information Association. BAKER, K. et al. The VOCs
Handbook: Investigating, Assessing and Managing Risks from Inhalation of VOCs at Land Affected
by Contamination. C682. London: CIRIA, 2009.
[41] ENVIRONMENT AGENCY. JEFFRIES, J. and MARTIN, I. Updated Technical Background to the
CLEA Model. Science Report SC050021/SR3. Bristol: Environment Agency, 2009.
[42] WELBURN. P., BAKER, K., BORTHWICK, K. and MACLEOD, C. Remediating and mitigating risks
from volatile organic compound (VOC) vapours from land affected by contamination (C716).
London: CIRIA, 2012.
• The standard may be stored on more than 1 device provided that it is accessible Subscriptions
by the sole named user only and that only 1 copy is accessed at any one time. Tel: +44 345 086 9001
• A single paper copy may be printed for personal or internal company use only. Email: [email protected]