1-Project Appraisal Techniques
1-Project Appraisal Techniques
Appraisal Techniques
Prabina Chhetri
Visiting Faculty
Introduction
References
• Projects: Planning, Selection, Implementation and Review, Prasanna
Chandra (Tata McGraw Hill Publishing Company Limited)
• Construction Project Management, KK Chitkara
• Contemporary Engineering Economics by Chan S. Park
• Advance Engineering Economics by Chan S. Park and Gunter P. Sharp-
Bette
• Principles of Engineering Economics, Eugene L Grant, W Grant Ireson
and Richar S. Leavenworth
• Web Pages of ADB, WB and other online sources
Project Appraisal
What is Project Appraisal? (Consists of ‘Project’ and ‘Appraisal’)
When?
• After preparation and design of project
Internal Evaluation
• Attendance: 20%
• Assignments:20%
• Assessment: 40%
• Case study and presentation: 20%
Course Outline
1. Economic Concept
Cost concepts
Component of project cost
Assessment of benefits
Externalities
Course Outline (contd..)
3. Preparation of Project Cash Flow
Depreciation concepts
Effect of taxation
Incremental cash flow
Cash flow statement
Course Outline (contd..)
4. Project Evaluation Criteria
Method of financing
Cost of capital
Choice of minimum attractive rate of return
Capital budgeting
Course Outline (contd..)
6. Project Risk and Uncertainty
• Definition
• Planning
• Implementation
• Operation and Post Operation
Definition Phase
Definition is the earliest part of a project when the purpose and
requirements are clarified. To ensure the project’s value
• Start to implement
• Monitor the project
• Modify the project
• Closeout and evaluate
Implementation Phase
Start to implement:
• Ensure work begins on time with clear performance standards.
• Review project statement and objectives
• Set ground rules for working together.
• Review initial project assignments
• Confirm performance expectation
Implementation Phase
Monitor the project:
• Keep the project on track.
• These aspects can be monitored:
• Progress against objectives
• Progress against milestones.
• Resource use and cost
• Human performance
Implementation Phase
Modify the project:
• Respond to problems, opportunities or even changes in objectives
• Review and clarify threats and opportunities
• Locate the earliest point in process when each concern has impact.
• Use the Definition and planning Phase steps as required to revise the plan.
Implementation Phase
Closeout and Evaluate:
• Ensure all objectives were met and share lessons learned
• Review success against objectives
• Inform others that the project is finished
• Review lessons learned
• Document a project summary
Implementation Modalities
• Build –own- operate, BOO
• Build –own- operate-transfer, BOOT
• Build-operate-transfer, BOT
• Build-transfer, BT
• Lease-operate-transfer, LOT
Implementation Agencies
• Government
• Public utility
• NGO/INGO
• Development Board
• Private sector
• Public Private Partnership, PPP
Operation Phase
• Energizing
• Testing and commissioning
• Operation and Maintenance contract
• Preventive maintenance schedule and major maintenance fund
(overhauling, refurbishment etc.)
• Duration: 25-50 years as stated in the document
Post-Operation Phase
• Decommissioning
• Handing over
Thank you