0% found this document useful (0 votes)
145 views62 pages

Nit 2187 3

Uploaded by

Imran Mulani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
145 views62 pages

Nit 2187 3

Uploaded by

Imran Mulani
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 62

Bharat Heavy Electricals Limited

(A Government of India Undertaking)


Power Sector – Eastern Region
Plot No. 9/1, Block-DJ, Salt Lake City,
Kolkata – 700 091 (INDIA)
Phone no. 033 - 2321 1691
Fax : 033 - 2321 1960
Web : www.jantermanter.com / www.bhel.com

TENDER CHANGE NOTE 01 (TCN – 01) DT: 04-12-2006


WITH REFERENCE TO THE NIT, PUBLISHED IN THE WEB SITES FOR THE WORK OF
INSTALLATION OF CAST-IN-SITU DRIVEN & BORED RCC PILE, TESTING, CIVIL FOUNDATION
WORKS AREA GRADING IN COMPLIANCE WITH STORM WATER DRAINAGE SYSTEM
INCLUDING DISMANTLING OF EXISTING STAIRS/ STEEL STRUCTURES ETC AND OTHER
MISCELLANEOUS CIVIL WORK FOR 1X250 MW UNIT #3 AT CESC-BUDGE BUDGE PROJECT
AGAINST TENDER DOCUMENT NO PSER:SCT:BDG-C 707:06, FOLLOWING CHANGES MAY
PLEASE BE NOTED AND COMPLIED.

01. Clarification on pre-bid discussion. (FILE 1)


02. Revised BOQ cum schedule of rates-Rev.01 (FILE 2)
03. Revised Technical requirements of BORED CAST-IN-SITU RCC PILES-SECTION-D21
(FILE 3). This supercedes earlier specification PART-III PILING – SPECIFIC
REQUIREMENTS of VOL-II.
04. Revised Technical specification of CONSTRUCTION AND INSTALLATION OF
DRIVEN CAST-IN-SITU PILES- PILING-PART VI (FILE 4). This supercedes earlier
specification CONSTRUCTION AND INSTALLATION OF DRIVEN CAST-IN-SITU
PILES- PILING-PART VI of VOL-II.
05. Introduction of Technical Specification for PILING PART-V - TESTING OF CONCRETE
PILES BY CONVENTIONAL LOADING SYSTEM. (FILE 5)
06. Layout showing Location of Bore holes of CESC Budge Budge generating Station
(File 6).
07. Introduction of Lab Test Reports

• BIDDERS ARE REQUESTED TO NOTE THAT THE REVISED BOQ CUM RATE SCHEDULE (REV-
01) SUPERSEDES ORIGINAL BOQ. BIDDERS SHALL SUBMIT THEIR OFFER ONLY AS PER
REVISED BOQ (REV-01). OFFER FROM BIDDER IN SUPERSEDED BOQ WILL NOT BE
CONSIDERED.

• BIDDERS ARE REQUIRED TO SUBMIT A DECLARATION IN TECHNO-COMMERCIAL OFFER


THAT THEY HAVE SUBITTED THEIR PRICE BID IN SEALED ENVELOP AS PER REVISED BOQ
(REV.-01) ONLY.

BIDDERS ARE REQUESTED TO SUBMIT OFFER BY THE DUE DATE OF SUBMISSION OF OFFER i.e. 13-12-06.

ALL OTHER TERMS & CONDITIONS OF THE TENDER REMAIN UNCHANGED.

SR MANAGER (SCT)

---------------------------------------------------------------------------------------------------------------
Regd. Office : BHEL House, Siri Fort, New Delhi- 110049
CLARIFICATIONS OF PRE-BID DISCUSSION ON 29/11/2006 AT PSER ,HQ, KOLKATA FOR THE WORK OF Installation of cast-
in-situ driven & bored RCC pile, testing, Civil foundation works area grading in compliance with storm water drainage system
including dismantling of existing stairs/ steel structures etc and other miscellaneous civil work for 1x250 MW unit # 3 at CESC-
Budge Budge Project.
(TENDER NO - PSER:SCT:BDG-C 707:06)

Sl no Description/ Tender clause / Clarifications asked


Clarifications by BHEL
tender clause no by bidder
A. NIT
A.1 PRE-QUALIFICATION DRIVEN PILING RIG (METCO) WITH Shall be read as :
CRITERIA (SL. NO. 8) 450 DIA & 550 DIA TUBE – 5 Nos. DRIVEN PILING RIG (METCO or Equivalent) WITH 450 DIA & 550 DIA TUBE – 5 Nos.

B. BOQ- ( VOL-III )
B.1 Sheet piling if required, please specify
St Nos. 101, 103, 105 Bidders to quote as per BOQ & Tender Specification
a separate BOQ Item
B.2 Please specify thickness of PVC Water
St. Nos. 1801 Refer BOQ & Rate Schedule (Rev-01) attached
Stop
B.3 St. Nos. 2501(A), 2501 Please clarify whether design part
Refer BOQ & Rate Schedule (Rev-01) attached
(B) included in these items
B.4 St. Nos. 2505 a (i), 2505 Please clarify dia of pile 600 mm. or
Refer BOQ & Rate Schedule (Rev-01) attached
b (i) 550 mm.
B.5 Please specify testing to be carried out
St. Nos. 2506 Refer BOQ & Rate Schedule (Rev-01) attached
only 550 mm / 450 mm dia or both
B.6 Please specify testing to be carried out
St. Nos. 2507(a) Refer BOQ & Rate Schedule (Rev-01) attached
only bored piles
B.7 Please specify testing to be carried out
St. Nos. 2507 (b) Refer BOQ & Rate Schedule (Rev-01) attached
only bored piles
B.8 St. Nos. 2401(A) Unit not specified Refer BOQ & Rate Schedule (Rev-01) attached
B.9 St. Nos. 2401(B) Unit not specified Refer BOQ & Rate Schedule (Rev-01) attached
B.10 In Description Column
St. Nos. 2409 “------- BHEL will provide one 20 T Refer BOQ & Rate Schedule (Rev-01) attached
capacity crane -------“
TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
EARTH WORK IN EXCAVATION, BACKFILLING AND DISPOSAL AS PER
100 SPECIFICATION, DRAWINGS AND AS DIRECTED BY ENGINEER FOR THE
FOLLOWING:-
Earth work in excavation upto 2m depth below ground level for
foundation, trenches, pipe lines, storm water drains etc including setting
out, clearing & grubbing, removal of debris, dewatering if required,
strutting, shoring/sheet piling if required, dressing the sides, levelling to
1 101 grade and ramming the bottom, stacking/disposal of surplus excavated CUM 33,300
material within a lead of 1.0 KM etc complete for all types of soils
including ash, laterite, morrum, weathered rock, decomposed rock, etc
which can be excavated by means of crow bar, pick axe, etc and does not
require chiselling or blasting.
Earth work in excavation for depth exceeding 2.0m but not exceeding
4.0m below ground level for foundation, trenches, pipe lines, storm water
drains etc including dewatering if required, strutting, shoring/sheet piling
if required, dressing the sides, levelling to grade and ramming the
2 103 bottom, stacking/disposal of surplus excavated material within a lead of CUM 27,700
1.0 KM etc complete for all types of soils including ash, laterite, morrum ,
weathered rock, decomposed rock, soft rock etc which can be excavated
by means of crow bar, pick axe, etc but does not require chiselling or
blasting.
Earth work in excavation for depth exceeding 4.0m but not exceeding
6.0m below ground level for foundation, trenches, pipe lines, storm water
drains etc including dewatering if required, strutting, shoring/sheet piling
if required, dressing the sides, levelling to grade and ramming the
3 105 bottom, stacking/disposal of surplus excavated material within a lead of CUM 1,500
1.0 KM etc complete for all types of soils including ash, laterite, morrum ,
weathered rock, decomposed rock, soft rock etc which can be excavated
by means of crow bar, pick axe, etc but does not require chiselling or
blasting.
Disposal of surplus excavated earth/rock beyond an initial lead of 1km
and upto a lead of 2 Km. dumping and levelling the dumped soil and
4 116 CUM 30,165
levelling the area from where the material is transported, complete with all
lifts as specified and directed by Engineer.
Disposal of surplus excavated earth/rock beyond an initial lead of 1km
and upto a lead of 3 Km. dumping and levelling the dumped soil and
5 116A CUM 26,000
levelling the area from where the material is transported, complete with all
lifts as specified and directed by Engineer.

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
Back filling around foundations in plinths etc.to proper grade and level
with selected materials within a lead beyond 1 Km but not exceeding 5
Kms.from available excavated soil including re-excavating loose
6 118 thickness, watering and ramming in layers of 25 cm. thickness to 90% CUM 45,500
Standard Procter denisty by manual / mechanical means, compaction with
mechanised compaction machine, dressing etc. complete including
transportation.
Back filling around foundations in plinths, trenches, drains etc.to proper
grade and level with selected good soil free from shingle, salts, organic
materials, roots, sod or any other foreign substance including re-
excavating loose thickness, watering and ramming in layers of 20 cm.
7 118b thickness compacted to 75% of relative density for non cohesive soil by CUM 5,000
manual/ mechanical means, dressing etc. complete as directed by the
engineer in charge including cost of material for all leads, loading,
unloading, royality and transportation. (payment for solid measure of the
consolidated filling)
Supply and filling sand (silver sand) under floors, in foundation and
plinths including cost of sand, transporting for all leads, loading,
8 119 unloading, spreading in layers in 25 cm loose thickness at all depths, CUM 220
watering, compaction with mechanised compaction machine or manually
to minimum 80% of relative density, dressing and levelling etc complete.
Providing and laying soling with brick jhama of sizes of 50mm to 100mm,
at all position and depths below or above finished ground floor level, below
foundations, below flooring,below erection common roads, providing hard
standing, and hard surfacing, etc in one or more layers each of
approximately 75mm thickness, hand packing, filling in interstices with
9 120 quarry spalls and providing a layer of moorum/sand over layer of soling CUM 5,450
to make the surface even including watering, thoroughly compacting
each layer with 10 tonne power roller with minimum 6 passes (or with
vibrating plate of approved capacity at places not approachable by
power roller) all as per the direction of the Engineer and as per
specification.

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words

PROVIDING AND PLACING CONCRETE WORK INCLUDING COST OF LABOUR,


MATERIALS AND EQUIPMENT FOR HANDLING, TRANSPORTATION, BATCHING,
MIXING, PLACING, VIBRATING AND CURING, (EXCLUDING COST OF
200 CENTERING, SHUTTERING AND REINFORCEMENT) COMPLETE AT ALL
ELEVATIONS AS PER DRAWING, SPECIFICATIONS UNLESS SPECIFIED
OTHERWISE AND AS DIRECTED BY ENGINEER FOR THE FOLLOWING: (CEMENT
FOR THIS PUPOSE SHALL BE ISSUED BY BHEL AS PER SCC.

Plain Cement Concrete of 1:4:8 for laying below below foundation,


10 201 CUM 165
trench, drain etc as levelling course, all complete.
Plain Cement Concrete of grade M10 as levelling course, under water
11 202 retaining structures, equipment foundations, under foundations/floors etc CUM 750
all complete.
Concrete of grade M-30 conforming to IS:456 with coarse sand and
graded hard stone aggregate 20mm nominal size for all major equipment
12 204 foundations at all heights/depths from finished ground floor level including CUM 500
addition of suitable plasticizer/ superplasticizer conforming to IS:9103
(latest) to achieve required slump in concrete all complete.

Concrete of grade M-25 conforming to IS:456 with coarse sand and


graded hard stone aggregate 20mm nominal size in foundations, under
floors etc at any level below finished floor level, any shape, position or
13 205 CUM 10,520
thickness etc complete including use of plasticizer/ superplasticizer
conforming to IS:9103 (latest) to achieve required slump in concrete all
complete.

Concrete of grade M-25 conforming to IS:456 with coarse sand and


graded hard stone aggregate 20mm nominal size in superstructure at all
14 207 heights from finished floor level at any level, shape, position or thickness CUM 200
complete including use of plasticizer/ superplasticizer conforming to
IS:9103 (latest) to achieve required slump in concrete all complete.

Concrete of grade M-20 conforming to IS:456 with coarse sand and


graded hard stone aggregate 20mm nominal size in superstructure at all
15 207A heights from finished floor level at any level, shape, position or thickness CUM 20
complete including use of plasticizer/ superplasticizer conforming to
IS:9103 (latest) to achieve required slump in concrete all complete.

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
Concrete of grade M-25 conforming to IS:456 with coarse sand and
graded hard stone aggregate 20mm nominal size in precast works like
16 211 trench covers, Rcc sleepers etc including formwork/moulds for CUM 80
thicknesses varying from 50mm to 250mm etc. all complete excluding
the cost of reinforcement as directed by BHEL .
Concrete of Grade M-20 conforming to IS:456 with coarse sand and
17 212 graded hard stone aggregate 20mm nominal size in foundation,grade CUM 20
slab, etc complete.
18 DELETED
Breaking existing concrete work at any level including cutting
reinforcements, removing the rubbish within a lead of 1Km., including
19 215 making good the broken edges/surface with cement mortar, painting, CUM 15
finishing to match with existing finishing, scaffolding/supporting at any
level, all complete and as directed by Engineer.
SUPPLYING, FIXING AND REMOVING FORMWORK AT ANY
ELEVATION INCLUDING ALL LABOUR, MATERIAL, SCAFFOLDING
300
COMPLETE INCLUDING POCKETS ETC. AS PER SPECIFICATIONS
AND AS DIRECTED BY ENGINEER FOR THE FOLLOWING:
Ordinary form work below finished ground floor level for foundations,
20 301 footings, bases of columns, walls, columns pilasters, beams, mass SQM 15,200
concrete, trenches etc.
Fairface form work below finished ground floor level for foundations,
21 302 footings, base of columns, walls, columns, pilasters, beams, mass SQM 6,500
concrete, trenches etc for exposed concrete works.
Ordinary form work above finished ground floor level for columns,
22 303 beams, suspended floors, roofs, lintels, cantilevers, staircases, landings, SQM 200
balconies, domes, arches etc for all heights.
Fairface form work above finished ground floor level for columns,
23 304 beams, suspended floors, roofs, lintels, cantilevers, staircases, SQM 550
landings, balconies, domes, arches etc for all heights.

24 307 Formwork in Pockets for foundation bolts, embedments, etc all complete. SQM 100

400 REINFORCEMENTS (Reinforcement rod will be supplied by BHEL as per SCC)

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
Providing, straightening, cutting, bending, placing in position at any level,
binding in position of mild steel reinforcements confirming to grade-1 of
25 401 IS:432 (part-I) including cost of binding wire, labour, transportation to & MT 5
from stores etc complete all as per specifications, drawings and as
directed by Engineer.
Providing, straightening, cutting, bending, placing in position at any level,
binding in position of tor steel reinforcements confirming of grade Fe-415
26 402 confirming to IS:1786 including cost of binding wire, labour, transportation MT 1,142
to & from stores etc complete all as per specifications, drawings and as
directed by Engineer.
Screed concrete 1:2:4 conforming to IS 456 with coarse sand and graded
27 508 hard stone aggregate 12.5mm/6 mm nominal size for drain to maintain the CUM 47
required slope etc.complete.

SUPPLYING & INSTALLATION OF PREMOULDED JOINT FILLER IN BETWEEN


EQUIPMENT FOUNDATIONS, MAT FOUNDATIONS, PILE CAPS, WALLS, BASEMENT
SLABS ETC. COMPLETE INCLUDING LABOUR, EQUIPMENT AND MATERIALS,
600
SEALING OF JOINTS INCLUDING COST OF SEALING COMPOUND (POLYSULFIDE
BASE SEALANT AS PER IS:12118) ETC. COMPLETE AS PER SPECIFICATIONS AND
DRAWINGS OR AS DIRECTED BY ENGINEER FOR THE FOLLOWING:

28 601 12mm thick joints. SQM 5

29 602 20mm thick joints. SQM 5

30 603 25mm thick joints. SQM 5


700 M.S.EMBEDMENTS
Receiving,loading, unloading,storing, welding, tacking, and fixing of
embedments, MS inserts, bolts, pipe sleeves, guide rails, angle pieces,
rungs of various diameters, plates of' dimensions as required
31 701 including cost of all labour, and equipment, transportation, handling, MT 15
welding,cutting, drilling, scaffolding and setting complete as per
specifications, drawings and as directed by Engineer (BHEL will supply
embedment parts).

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
Supply, fabricating and fixing of embedments, MS inserts, pipes, sleeves,
flats, guide rails, angle/beams pieces, rungs of various diameters,
plates of' dimensions as required including cost of all labour,
32 701A materials and equipment, transportation, loading, unloading, handling, MT 1
welding,cutting, drilling, scaffolding and setting complete as per
specifications, drawings and as directed by Engineer (all steel to be
supplied by contractor).
Supply, fabrication, transportation, delivery at site and erection, installation
and alignment of MS Foundation bolts ( Grade- 1 of IS: 432 & IS: 2062)
assembly in concrete along with nuts, locknuts ( IS: 1363, IS: 1364 & IS:
3138), washers, anchor plates, stiffener plates, protective tapes etc. upto
33 702 MT 18
& inclusive of 63mm diameter and upto 3000mm long, for columns
including pipe sleeves, templates wherever necessary etc. all complete as
per specifications and directed by the Engineer.(all steel to be supplied by
contractor).
BRICKWORK MASONRY INCLUDING SUPPLY OF MATERIAL, COST
OF LABOUR, SCAFFOLDING ETC. COMPLETE AS PER
1000 SPECIFICATIONS, DRAWING AND AS DIRECTED BY ENGINEER FOR
THE FOLLOWING:- (CEMENT FOR THIS PURPOSE SHALL BE
SUPPLIED BY BHEL AS PER SCC)
Providing brick work in cement mortar 1:6 (1 part cement: 6 parts
coarse sand) in walls, chambers etc. of 254mm & above in thickness at
all depths, places and positions below plinth including raking out joints,
34 1001 CUM 147
curing, scaffolding etc. all complete excluding plastering and paintng,
using bricks of class designation 7.5 or best locally available quality of
nominal dimensions as per specification.
Providing 254mm thick brick work in cement mortar 1:6 (1cement : 4
coarse sand) in walls, chambers etc. at all heights, places and position
above plinth including raking out joints, curing, scaffolding, etc complete
35 1002 CUM 25
but excluding plastering and painting, using bricks of class designation
7.5 or best locally available quality of nominal dimensions as per
specification.

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
Providing 127mm thick brick work in cement mortar 1:6 (1 cement : 6
coarse sand) for drain, road kerb , trench, drain pit/ chambers etc. at all
36 1003A places below plinth level including raking out joints, curing, etc. all SQM 5,720
complete using second class bricks of nominal dimensions excluding
plastering as per specification.
Providing 127mm thick brick work in cement mortar 1:6 (1 cement : 6
coarse sand) in partition walls, chambers etc. at all heights, places and
37 1003B position above plinth/graded level including raking out joints, curing, SQM 50
scaffolding etc. all complete using second class bricks of nominal
dimensions excluding plastering as per specification.
Dismantling existing brick work at all level including stacking and removing
38 1007 the debris within a lead of 1Km., including transportation, loading, CUM 10
unloading, etc all complete and as directed by Engineer.
39 1008 DELETED
CEMENT MORTAR PLASTER INCLUDING MAKING GROOVES WHEREVER REQUIRED, ALL
MATERIALS, SCAFFOLDING, CURING ETC. COMPLETE AS PER SPECIFICATION, DRAWING
1200 AND AS DIRECTED BY ENGINEER FOR THE FOLLOWING:- (CEMENT FOR THIS PURPOSE
SHALL BE PROVIDED BY BHEL AS PER SCC)

Providing 12mm thick plaster inside/outside of the building/boundary wall


40 1202 SQM 100
in cement mortar 1:6 at all height, smooth finish as per specification.

Providing 12 mm thick neat plaster in drains/culverts/manhole etc. as per


41 1204A SQM 200
specification.
Two or more coats of water proofing cement paint of approved brand and
42 1302 manufacture & of required shade to give an even shade on walls SQM 100
complete.
1800 MISCELLANEOUS
43 1801 Providing and fixing PVC water stops (6.0 MM THICK) - 225mm wide RM 40
44 1801A Providing and fixing PVC water stops (8.0 MM THICK) - 225mm wide RM 10
Laying of earthing mats/rods including transportation from yard stores,
45 1811 loading, unloading, cutting to length, welding etc complete as per MT 16
specification and as directed by Engineer.
2000 FENCING AND GATES.

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words

Providing and fixing Barbed wire (6- horizontal layers and cross
diagonals) fencing (9.38 Kg / 100 mtrs) fixed with GI staples etc, with
structural MS anglel (50mmx50mmx6mm) posts, 1200 mm high @ 1500
46 2001A mm c/c, above ground level, embeded in concrete(1:2:4) foundation SQM 1,500
250x250x500mm deep inside earth, including GI clips, two coats of
Bitumenous anti corrosive paint etc complete as per specification,
drawing and as directed by the Engineer.

Providing M.S gates 1500 x1200 size (made of MS angle 50x50x6 mm


frame work with 12 mm dia rod @ 200 mm c/c vertical & horizontal,
47 2002 securely welded with the frame, with m s sliding door bolt 300mm long, MT 8
incuding fixing welding, as per sketch /drawing with two coat of
anticorrosive bitumenous paintng etc complete.
2100 WATER SUPPLY

Providing and fixing GI pipes (zindal or equivalent quality) complete with


GI sockets, unions, elbows, tees, nipples etc and clamps including
cutting and making good the walls or below ground etc complete - 15 mm
48 2106A dia light quality. (Pipe line Payment will be made on the centre line RM 20
measurements of total pipe line including specials. No separate payment
will be made for accesories, specials. Payment for excavation and
backfilling will be paid separately as per respective items.).

Providing and fixing GI pipes (zindal or equivalent quality) complete with


GI sockets, unions, elbows, tees, nipples etc and clamps including
cutting and making good the walls or below ground etc complete - 20 mm
49 2106 dia light quality. (Pipe line Payment will be made on the centre line RM 30
measurements of total pipe line including specials. No separate payment
will be made for accesories, specials. Payment for excavation and
backfilling will be paid separately as per respective items.).

Providing and fixing GI pipes (zindal or equivalent quality) complete with


GI sockets, unions, elbows, tees, nipples etc and clamps including
cutting and making good the walls or below ground etc complete - 25 mm
50 2107 dia light quality. (Pipe line Payment will be made on the centre line RM 50
measurements of total pipe line including specials. No separate payment
will be made for accesories, specials. Payment for excavation and
backfilling will be paid separately as per respective items.).

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
Providing & fixing P.V.C. water tank of 2000 litres capacity (Syntex or
approved equivalent make) in position. The work to include making all
50 2117 NO. 4
necessary inlet & outlet pipes, fixture, ball cocks, valves etc all complete
as per specification and at all heights and levels.
2200 SANITARY WORKS
Supply and fixing white vitreous china Wash Basin size 550x450 with
R.S. or C.I. brackets painted white, 15mm chromium plated brass pillar
51 2201 cock, 32mm dia pvc waste pipe, 32mm dia chromium plated brass trap NO. 1
unions, cutting and making good the walls where required etc complete
as per specifications
Providing, laying below ground level light duty non pressure NP3 class
RCC pipes with collars jointed with cement mortar 1:4 etc complete -
52 2209 RM 25
300mm dia as per direction of BHEL.(Payment for excavation and
backfilling will be paid separately as per respective items).
Providing, laying below ground level light duty non pressure NP3 class
RCC pipes with collars jointed with cement mortar 1:4 etc complete -
53 2210 RM 25
450mm dia as per direction of BHEL.(Payment for excavation and
backfilling will be paid separately as per respective items).
2400 ERECTION ROADS
Preparation of sub grade by AVERAGE 300 MM DEPTH OF excavating
all types of soil, dressing to camber including Consolidation with power
54 2401 CUM. 5,700
road roller of 8 to 12 tonne capacity minimum 8 passes, and disposal of
surplus earth within plant boundary all complete as per specification.
Providing and transporting of cinder/ash from existing plant of
Budgebudge power generating to fabrication area/equipment storage area
55 2401A or main plant area etc by means of mechanically / manually upto a lead of CUM. 2,850
500 Mtr including spraeding, dressing, consolidation and maintaining level
as per BHEL sketc / drawingas per requirement.
Consolidation of sub grade with power road roller of 8 to 12 tonne capacity
56 2401B SQM 19,000
minimum 8 passes including rerolling etc complete.
Supplying and filling with river sand in compacted layers of 2x75mm
57 2402 including watering, consolidation to required camber including CUM. 5,250
transportation, royalities complete.

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words

Providing &Laying water bound macadam base / sub base course in


layers of required thickness with stone aggregate 63mm to 40mm size,
stone screening and blinding material including screening sorting,
58 2405 CUM. 600
spreading to template and consolidation with road roller including carriage,
spreading and consolidation of blinding material moorum etc Including
cost of material labour etc. all complete as per specification.

Carefully dismantling of existing fencing (made of wooden / balli post, CGI


sheeting and low height brick wall), shifting and re-erection of fencing
using same wooden post, CGI sheet with new low height brick wall with GI
59 2406 SQM 250
J-hooks & nuts etc complete as per direction of BHEL.(Payment for
excavation, backfilling, brickwork,plastering will be made separately as per
respective items).

Earth work in excavation upto minimum depth of 0.3m below natural


ground level for levelling and grading including dressing to specified levels
& grades and ramming of graded surface including removal of vegetation,
bushes, trees of girth measuring below 30 cms (measured at a height
60 2407 of 1.5 mtr above ground level), grass, etc, for all types of soils,ash SQM 44,000
including morrum etc. complete by dozing/mechanical means as per
specification, drawing and as directed by the Engineer. Surplus earth,
debris, vegetation, bushes, trees, etc unsuitable for filling shall be
transported to areas within a lead of 1.5 KM lead.

Cutting and felling trees of the girth measuring 30 cms and above
(measured at a height of 1.5 mtr above ground level), including cutting of
61 2408 Nos 150
trunks and branches, removing the roots and disposal of same within a
lead of 500 Mtr.
Dismantling of steel structure at any elevation, lowering of material and
carriage of the dismantled material up to a lead of one KM including
cutting, including scafolding, staging, tools & tackles, gas cutting, etc
62 2409 MT 150
complete as per instructions of the Engineer.(BHEL will provide one 40T
(OR ABOVE) capacity crane for ten days only based on advance intimation
by the contractor for existing stair case dismantling only).

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
Sprinkling of water by water tanker fitted with perforated GI pipe (portable
tanker minimum 3000 litre capacity) for roads and miscellanous area
within plant boundary, for dust supression and reduction of suspended
Tank-
63 2410 material at site for day to day work, as directed by BHEL Site Engineer 1,920
Hour
(water for this purpose shall be provided by BHEL free of cost and
utilisation of machine will be in terms of Tank hour put in actual use for
water sprinkling).
2500 PILING WORK

Installation of bored RCC cast in situ vertical pile as per IS 2911 (Part 1,
Section 2) with diameter and length as specified below (length to be measured
from pile cut-off level to the bottom of pile) using cement concrete M25 grade
conforming to IS 456 with 20 mm nominal size stone aggregates with cement
content of minimum 380 Kg per cum of concrete including all materials except
reinforcement, including boring/drilling in all types of strata from ground level to
termination depth of pile including providing bentonite slurry and/or casing for
stabilization of pile bore, flushing of pile bore, cleaning, providing plasticizer
wherever required, breaking pile head to cut off level and exposing pile
reinforcement for embedment in pile cap, empty boring if required from ground
level to pile cutoff level as per construction procedure etc all complete as per
specification, drawings and as directed by the engineer-in-charge.
2501
This should include mobilizing all necessary equipments, piling rigs/
materials, plant, labour, etc to the site of work, erecting all rigs, equipment
and plant and removal of same after completion of work complete with all
consumables, etc. This item doesnot include cost of reinforcement,
cutting, binding, welding, placement, etc. for which item 2509 will be paid
separately.

Note:-Soil investigation data is being supplied with the specification. Initial


load test of pile is being conducted separately at present and it will be
provided to bidder at the start of work. Structural design of piles will be
done by BHEL. Bidder has to install piles as per BOQ, specification &
drawing and ensure the rated capacity of pile and also conduct working
pile test as per item below.
Pile of 550 mm diameter and 26.5 m length below cut off level(Approx. at
64 a EL(-)3.5m below plant FGL), Safe load carrying capacity of pile in axial Each 200
compression=100MT, in tension=30MT, in latereral=5MT.

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words

Pile of 450 mm diameter and 30 m length below cut off level(Approx. at


65 b EL(-)3.5m below plant FGL), Safe load carrying capacity of pile in axial Each 50
compression=60MT, in tension=18MT, in latereral=3MT.

2502 Extra over following item for pile length more than the specified length.

66 a item no. 2501 a m 100

67 b item no. 2501 b m 10

2503 Rebate on the following item for pile length less than the specified length.

68 a item no. 2501 a m 100

69 b item no. 2501 b m 10

Installation and driving standard Driven RCC cast in situ vertical piles as per
IS 2911 part 1 section 1 with diameter and length as specified below (length to
be measured from pile cut-off level to the bottom of pile) using cement concrete
M25 grade conforming to IS 456 with 20 mm nominal size stone aggregates with
cement content of minimum 380 Kg per cum of concrete including all materials
except reinforcement, including driving the casings in all types of strata from
ground level to termination depth of pile including fixing the reinforcement cage in
the required alignment, extracting the casings, curing of exposed concrete,
providing plasticizer wherever required, breaking pile head to cut off level and
exposing pile reinforcement for embedment in pile cap, empty driving if required
from ground level to pile cutoff level as per construction procedure etc all
complete with all consumables as per specification, drawings and as directed
2504 by the engineer-in-charge.
This should include mobilizing all necessary equipments, piling rigs/
materials, plant, labour, etc to the site of work, erecting all rigs,
equipments, plant and removal of same after the completion of work. This
item doesnot include cost of reinforcement, cutting, binding, welding,
placement, etc. for which item 2509 will be paid separately.

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words
Note:-Soil investigation data is being supplied with the specification. Initial
load test of pile is being conducted separately at present and it will be
provided to bidder at the start of work. Structural design of piles will be
done by BHEL. Bidder has to install piles as per BOQ, Specification &
drawing and ensure the rated capacity of pile and also conduct working
pile test as per item below.
Pile of 550 mm diameter and 22m length below cut off level(Approx. at
70 a EL(-)3.5m below plant FGL), Safe load carrying capacity of pile in axial Each 1,660
compression=100MT, in tension=30MT, in latereral=5MT.
Pile of 450 mm diameter and 20m length below cut off level(Approx. at
71 b EL(-)3.5m below plant FGL), Safe load carrying capacity of pile in axial Each 410
compression=60MT, in tension=18MT, in latereral=3MT.

2505 Extra over following item for pile length more than the specified length.

72 a item no. 2504 a 800

73 b item no. 2504 b 250

2506 Rebate on the following item for pile length less than the specified length.

74 a item no. 2504 a 800

75 b item no. 2504 b 250

Conducting routine load test on job pile in accordance with IS 2911 (Part-
4) including necessary excavation, all arrangements of loading, unloading,
2507
test equipments, jacks, platforms, kentledge, dial gauges, recording of
results, all materials, labour, submission of test report etc but excluding
the cost of installation of job pile complete as per specification, drawing and
as directed by the engineer-in-charge for the following.

for lateral load test:

76 550 mm diameter pile-5 MT safe load capacity Each 10


a

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words

77 450 mm diameter pile-3 MT safe load capacity Each 4

for vertical compression test by Cyclic loading:

78 b 550 mm diameter pile-100 MT safe load capacity Each 12

79 450 mm diameter pile-60 MT safe load capacity Each 8


for uplift test:
80 550 mm diameter pile-30 MT safe load capacity Each 4
c

81 450 mm diameter pile-18 MT safe load capacity Each 2

Carrying out pile integrity test on job pile including all arrangements for
test, equipments, materials, labour, submission of test report etc but
82 2508 Each 25
excluding the cost of installation of job pile complete as per specification and
as directed by the engineer-in-charge.
Providing, straightening, cutting, bending, welding, lapping, placing in
position at any level, binding in position of HYSD steel reinforcements -
83 2509 MT 1,100
TMT bars confirming of grade Fe-415 as per IS:1786 including cost of
binding wire, labour, transportation etc.
Carrying out `Integrity Testing' PULSE ECHO TEST of concrete in the
84 2510 installed pile including necessary excavation, all arrangementfor testing, Each 20
recording of results, all materials, labour etc. complete.
Carrying out Cross hole test on installed pile including all arrangement for
2511
testing, recording of results, all materials, labour etc. complete.

85 For bore pile 550 dia Each 30

86 for bore pile 450 dia Each 30

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TENDER NO. PSER:SCT:BDG:C 707:06 VOL-III - REV.01
BOQ CUM RATE SCHEDULE FOR PILING CIVIL FOUNDATION WORKS FOR 1 X 250 MW BUDGE BUDGE EXTENSION UNIT - 3 (CESC)
SL. ST. DESCRIPTION QUANTITY RATE
UNIT TOTAL
AMOUNT IN RS.
NO. NO PILE, PILE CAPS AND OTHER MISC. CIVIL WORKS In Figures In Words

Conduct High Strain Dynamic Pile Testing on R C bored piles using Pile
Driving Analyzer. The equipment shall have ability to record both force and
velocity. Both strain and acceleration sensors shall be used to collect data
87 2512 & atleast 2 pairs shall be connected at diametrically opposite sides of the Each 15
pile. The test and equipment shall conform to ASTM D4945-96 & include
CAPWAP analysis. The test shall be conducted by an experienced
independent test agency with atleast five years experience.

TOTAL

For item not covered above, quote % above or below the CPWD schedule
(DSR-2002)
88 (i) Rate for complete %

89 (ii) Rate for supply only %

90 (iii) Rate for item excluding supply of materials %

BIDDERS PARTICULARS NAME/DESIGNATION DATE/SIGN/CO.SEAL


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 1 OF 25

VOLUME: II B

SECTION - D
SUB-SECTION – D21

BORED CAST-IN-SITU RCC PILES

SPECIFICATION NO. PE-TS-999-600-C001

Bharat Heavy Electricals Limited


Project Engineering Management
Power Sector, BHEL House
Asian Games Village Complex
Siri Fort, New Delhi-110049

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 2 OF 25

CONTENTS

CLAUSE NO. DESCRIPTION

1.00.00 SCOPE

2.00.00 GENERAL REQUIREMENTS

3.00.00 MATERIALS

4.00.00 PILE INSTALLATION

5.00.0 SAMPLING, TESTING, AND QUALITY ASSURANCE

6.00.00 PILE TESTING

7.00.00 CODES AND STANDARDS

8.00.00 RATES AND MEASUREMENT

ANNEXURE-A

ANNEXURE-B

ANNEXURE-C

ANNEXURE-D

TABLE - 1

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 3 OF 25

TECHNICAL SPECIFICATION FOR INSTALLATION OF BORED


CAST-IN-SITU PILES

1.00.00 SCOPE

This specification covers the installation of bored cast-in-situ reinforced


concrete vertical piles of specified load carrying capacity and diameter for
various structures. This specification also covers carrying out initial and routine
load tests on piles to assess their vertical, horizontal and pull out load carrying
capacities.

2.00.00 GENERAL REQUIREMENT

2.01.00 This specification along with specific requirements under Annexure-A covers the
technical requirements for piling work.

2.02.00 The work shall include supplying and providing necessary materials, mobilization
of all necessary equipments (Annexure-B), providing necessary engineering
supervision through qualified and technical personnel, skilled and unskilled
labour, etc. as required to carryout the complete piling work, and submission of
records as per schedule.

2.03.00 The Contractor shall carryout all works as mentioned in Scope above. All works
shall be executed to the satisfaction of the Engineer.

2.04.00 Pile capacities in vertical compression, horizontal, pullout loads for various pile
diameters are given in Annexure-A.

2.05.00 The Contractor shall confirm and guarantee the "Safe Load" capacities by
conducting both initial and working load test on piles as mentioned in the specific
requirements.

2.06.00 The Contractor shall submit along with tender documents his tender design of
piles based on soil data furnished by the Owner along with this specification. The
ultimate load capacity of a pile may be estimated using suitable static formula and
the minimum factor of safety shall be 2.5. However, safe load carrying capacity
shall be conformed and guaranteed by conducting initial and routine load tests.

2.07.00 In case of initial or routine load test piles, if the Contractor fails to establish the
safe load capacity as per his design, the Owner has the right to either derate the pile
capacity on prorata basis or insist the Contractor to modify the pile design, to
achieve the desired safe load capacity at no extra cost to the Owner.

2.08.00 Derating is acceptable up to 90 percent. In such case, additional piles shall be


installed as per the design requirements.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 4 OF 25
2.09.00 The Owner shall decide whether to derate or modify the design based on the
design considerations such as providing additional piles in the designed pile cap,
provision for extending the pile cap size, etc.

2.10.00 In case the Owner decides to modify the design instead of derating the pile,
the contractor shall carry out the same and install separate test piles and test the
same to guarantee the safe load at no extra cost to the Owner. However no extra
shall be charged for the additional test piles as well as testing of these piles as per
agreed contract conditions.

2.11.00 In case of working piles, if the pile does not meet the guaranteed capacity or
rejected due to any other reason, the Contractor shall install extra piles at no
extra cost to the Owner. Further, the extra cost, due to the increase in the pile cap
size if any, on account of extra piles, shall be borne by the Contractor.

2.12.00 It is essential that all equipment and instruments are properly calibrated both at
commencement and immediately after the completion of tests so that they
represent true values. Certificates to this effect from an approved institution shall
be furnished to the Engineer. If the Engineer so desires the Contractor shall
arrange for having the instruments tested at an approved laboratory at no extra cost
to the Owner and the test report shall be submitted to the Engineer. If the
Engineer desires to witness such tests Contractor shall arrange to conduct the
test in his presence.

2.13.00 The Contractor shall make his own arrangements for locating the coordinates and
position of piles as per drawings supplied to him and for determining the
Reduced Levels (RL) of these locations with respect to the benchmark
indicated by the Engineer. Two established reference lines in mutually
perpendicular direction shall be indicated to the Contractor. The Contractor shall
provide at site all the required survey instruments to the satisfaction of the
Engineer so that the work can be carried out accurately according to
specifications and drawings.

2.14.00 The contractor shall assure the quality of piling work including cleaning of pile
bore, quality of concrete, integrity of piles, etc.

2.15.00 AVAILABLE SUB-SOIL DATA


An abstract of the sub soil data is furnished in the tender document. However, the
detailed soil investigation report shall be made available for reference of the
bidder, if so required, at the office of the Owner. The soil data furnished is in
good faith and only for the guidance of the Bidder, to arrive at design
parameters and construction methods.

3.00.00 MATERIALS

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 5 OF 25

3.01.00 General

All materials viz cement, steel, aggregates, water, etc. which are to be used for pile
construction shall conform to relevant IS codes for properties, storage and
handling of common building materials. However, aggregates more than 20 mm
size shall not be used.

3.02.00 CONCRETE

Concrete shall be manufactured either by central batching plant or Ready Mix


concrete. However, for initial test piles suitable method as approved by the
Engineer may be used. Concrete shall conform to IS: 10262 & IS: 456.

3.02.01 Technical Specification for Cement Concrete (Plain and Reinforced) works
along with IS: 2911 Part I/Sec 2 shall be followed for concrete works of piles. Use
of plasticiser to control the water cement ratio shall be permitted on specific
approval from the Engineer. Water cement ratio shall not be greater than 0.5.

3.02.02 Grade and minimum cement content


Minimum grade of concrete shall be as per Annexure-A conforming to IS:
456. Minimum cement content of 400 Kg/M³ of concrete shall be used for M-20
grade concrete.

3.02.03 Slump of concrete


The slump of concrete shall vary between 150 to 180 mm.

3.03.00 REINFORCEMENT

3.03.01 Longitudinal reinforcement in pile shall be high strength deformed steel bars
conforming to IS: 1786 unless specified otherwise. Lateral reinforcement in pile
shall be of mild steel conforming to IS: 432 Part-1 or HYSD bars as per IS:
1786.

3.03.02 The longitudinal reinforcement shall be provided considering the combination of


vertical (compression and tension) and horizontal loads. However, the
minimum longitudinal reinforcement shall be 0.4 percent of the sectional area
calculated on the basis of nominal pile diameter. Minimum six numbers of bars
shall be provided for longitudinal reinforcement. The diameter of longitudinal
reinforcement bars shall not be less than 12mm. The stipulated minimum
reinforcement shall be provided for the full length of pile.

3.03.03 The longitudinal reinforcement shall project 50 times its diameter above cut off
level unless otherwise indicated.

3.03.04 The laterals shall be tied to the longitudinal reinforcement to maintain its shape
and spacing. The laterals may in the form of links or spirals. The minimum diameter

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 6 OF 25
of the links or spirals shall be 6 mm and the spacing of the links or spiral shall not
be less than 150 mm and in no case more than 250 mm.

3.03.05 Reinforcement cage shall be sufficiently rigid to withstand handling and


installation without any deformation and damage. As far as possible number of
joints (laps) in longitudinal reinforcement shall be minimum. In case the
reinforcement cage is made up of more than one segment, these shall
preferably be assembled before lowering into casing tube/pilebore by providing
necessary laps as per IS: 456.

3.03.06 The minimum clear distance between the two adjacent main reinforcement bars
shall normally be 100 mm for the full depth of cage.

3.03.07 The laps in the reinforcement shall be such that the full strength of the bar is
effective across the joint and the reinforcement cage is of sound construction.

3.03.08 Laps shall be staggered as far as practicable and not more than 50% bars shall be
lapped at a 'particular section. Lap joints shall be staggered by at least 1.3 times
the lapped length (Centre to Centre).

3.03.09 Proper cover and central placement of the reinforcement cage in the pile bore
shall be ensured by use of suitable concrete spacers or rollers, cast specifically for
the purpose.

3.03.10 Minimum clear cover to the longitudinal reinforcement shall be 50 mm, unless
otherwise mentioned.

3.03.11 Bundling of bars is not permitted.

4.00.00 PILE INSTALLATION

Installation of piles shall be carried out as per pile layout drawings, installation
criteria, and the direction of the Engineer.

4.01.00 Equipment and Accessories

4.01.01 The equipment and accessories for installation of bored cast-in-situ piles shall be
selected giving due consideration to the sub soil conditions, ground water
conditions and the method of casting, etc. These shall be of standard type and
shall have the approval of the Engineer.

4.01.02 List and details of equipment and accessories proposed to be used for the job shall
be submitted along with the bid.

4.01.03 The capacity of the rig shall be adequate so as to reach the specified founding
level.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 7 OF 25
4.01.04 Provision shall be kept for chiselling within the pilebore, as specified
elsewhere in this specification. Chiselling shall be carried out only with the
approval of Engineer.

4.02.00 Installation Criteria

4.02.01 For determining the founding level of piles in soil as specified elsewhere, the
Contractor shall have to perform Standard penetration test (SPT) as per IS:
2131 in a separate bore hole. The SPT shall be conducted at 1.0 m interval
between the depths covering 5 metres each above and below the specified
founding level. The bore shall be 100 mm diameter and method of boring shall
conform to IS: 1892.

4.02.02 For determining founding level of piles in rock, as specified elsewhere


socketing horizon shall be established by the Contractor by collecting rock
cores of NX size in a separate borehole, and testing the same for uniaxial
compressive strength (UCS). Cores shall be collected by double tube core
barrel attached with diamond bit. Coring shall be done upto a depth as indicated
in the "specific requirements." Coring in rock shall conform to IS: 6926.

4.02.03 In case it is not possible to test the cores so obtained for uniaxial compressive
strength, cores shall be tested for point load strength index and correlated to
obtain uniaxial compressive strength.

4.02.04 Number of boreholes for carrying out SPT in soil or uniaxial compressive
strength in rock, shall vary from one in 100 to 150 piles or pile group of 150
Sqm depending on the site condition and as decided by the Engineer.
However, at the location of initial load test piles, one such borehole shall be
done.

4.02.05 A protocol between contractor and BHEL site shall be maintained regarding the
strata at founding level. SPT value and UCS from the nearest borehole shall be
indicated therein.

4.02.06 The founding level of the pile shall be decided based on the criteria elaborated in
the specific requirements under Annexure-A. Concreting shall not be done until
the above conditions for founding level are satisfied.

4.02.07 Approval of founding level by the Engineer shall in no way absolve the
Contractor of his responsibility to guarantee the Safe load capacity of the piles as
indicated in this document.

4.03.00 Control of position and alignment

4.03.01 Piles shall be installed as accurately vertical as possible. The permissible limits
for deviation with respect to position and (inclination) alignment shall conform
to IS: 2911 Part I/Sec. 2, which is reproduced below for ready reference.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 8 OF 25

a) The maximum deviation of vertical piles shall not exceed 1.5 per cent in
alignment.

b) Piles shall not deviate more than 75 mm or D/4 whichever is less (75mm
or D/10 whichever is more in case of piles having diameter more then
750mm) from their designed position at the working level.

4.04.00 Boring

4.04.01 Boring operations shall be done by rotary or percussion type drilling rigs using
reverse mud circulation (RMC) method. Rotary hydraulic pulley shall be
preferred.

4.04.02 The Contractor shall satisfy himself about the suitability of the method to be
adopted for site. If DMC (direct mud circulation) or RMC is used Bentonite slurry
shall be pumped through drill rods by means of high-pressure pumps. The
cutting tool shall have suitable ports for the bentonite slurry to flow out at high
pressure. If on mobilisation, the Contractor fails to make a proper bore for any
reason, the Contractor has to switchover to other boring methods as approved by
the Engineer at no extra cost to the Owner.

4.04.03 Working level shall be above the cut off level. After the initial boring of about
1.0m a temporary guide casing of suitable length shall be lowered in the pile bore.
The diameter of guide casing shall be of such diameter, so as to give the
necessary finished diameter of the concrete pile. The centre line of guide casing
shall be checked before continuing further boring. Guide casing shall be
minimum of 1.0m length. Additional length of casing may be used depending
on the condition of the strata, ground water level etc.

4.04.04 Use of drilling mud (bentonite slurry) for stabilizing the sides of the pile bore is
necessary wherever subsoil is likely to collapse in the pile bore. Drilling mud to
be used shall meet the requirement as given in Annexure-C.

4.04.05 The bentonite slurry and the cuttings, which are carried to the surface by the
rising flow of the slurry, shall pass through settling tanks of adequate size to
remove the sand and spoils from the slurry before the slurry is recirculated to the
boring. The bentonite slurry mixing and recirculation plant shall be suitably
designed and installed.

4.04.06 The bentonite slurry shall be maintained at 1.5m above the ground water level
during boring operations and till the pile is concreted. When DMC or RMC
method is used the bentonite slurry shall be under constant circulation till start of
concreting.

4.04.07 The size of cutting tools shall not be less than the diameter of the pile by more than
75mm. However, the pile bore shall be of the specified size.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 9 OF 25

4.05.00 Chiselling

4.05.01 Chiselling may be resorted to with the permission of the Engineer below the
socketing horizon. The chiselling tool or bit shall be of adequate size and
weight so as to reach the desired depth.

4.06.00 Cleaning of Pile bore

4.06.01 On completion of the pile bore upto the required depth, the bottom of the hole
shall be cleaned very carefully before concreting work is taken up. Cleaning shall
ensure that the pile bore is completely free from sludge/bored materials, debris
of rock/boulder etc. Necessary checks shall be made as given in clause 5.0 to
confirm the thorough cleaning of the pile bore.

4.06.02 Pile bore shall be cleaned by fresh drilling mud through tremie pipe after
placing reinforcement and just before start of concreting.

4.06.03 Pile bore spoil along with used drilling mud shall be disposed off from site as
directed by the Engineer.

4.06.04 Pile bore bottom shall be thoroughly cleaned to make it free from sludge or any
foreign matter before and after placing the reinforcement cage.

4.07.00Adjacent Structures

4.07.01 When working near existing structures care shall be taken to avoid any damage
to such structures.

4.08.00 Concreting

4.08.01 The Contractor shall carry out concrete mix design in accordance with IS:
10262 and submit mix design calculations and get them approved from the
Engineer well in advance for installation of piles. Adequate number of tests on
cubes, etc. shall be carried out as mentioned in clause 5.0 to ensure concrete of the
minimum specified strength in accordance with IS: 456 at requisite workability
(slump).

4.08.02 Concreting shall not be done until the Engineer is satisfied that the bearing
strata (soil/rock) met with at the termination level of pile.

4.08.03 The time interval between the completion of boring and placing of concrete
shall not exceed 6 hrs. In case the time interval exceeds 6 hrs the pilebore shall
be abandoned. However, the Engineer may allow concreting provided the
Contractor extends the pile bore by 0.5 m beyond the proposed depth, and clean
the pilebore. The entire cost of all operation and materials for this extra length
shall be borne by the Contractor.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 10 OF 25
4.08.04 Proper placement of the reinforcement cage to its full length shall be ensured
before concreting.

4.08.05 Concreting shall be done by tremie method as specified by IS: 2911 (Part I
/Sec.2). The level of drilling mud shall be maintained sufficiently above the
ground water level.

4.08.06 The concreting operations shall not be taken up when the specific gravity of bottom
slurry is more than 1.2 and sand content more than 7%. The drilling mud sample
shall be collected from the bottom of pilebore as mentioned in clause 5.

4.08.07 Consistency of the drilling mud suspension shall be controlled throughout the
concreting operations in order to keep the bore stabilized as well as to prevent
concrete getting mixed up with the thicker suspension of the mud.

4.08.08 It shall be ensured that volume of concrete poured is at least equal to the
theoretically computed volume of pile shaft being cast.

4.08.09 The temporary guide casing shall be withdrawn cautiously, after concreting is done
upto the required level. While withdrawing the casing concrete shall not be
disturbed.

4.09.00 Cut off level (COL)

4.09.01 Cut off level of piles shall be as indicated in drawings released for construction
or as indicated by the Engineer.

4.09.02 The top of concrete in pile shall be brought above the COL to remove all
laitance and weak concrete and to ensure good concrete at COL for proper
embedment in to pile cap.

4.09.03 When the pile cut off level is less than 1.0 metre below the working level,
concrete shall be cast to the piling platform level to permit overflow of
concrete for visual inspection. In case COL of pile is more than 1.0 metre
below working level then concrete shall be cast to a minimum of one metre
above COL.

4.10.00 Sequence of Piling

4.10.01 Each pile shall be identified with a reference number.

4.10.02 The convenience of installation may be taken into account while scheduling the
sequence of piling in a group. This scheduling shall avoid piles being bored
close to other recently constructed piles.

4.11.00 Building up of Piles

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 11 OF 25
4.11.01 If any pile, already cast as per construction drawing, requires any extra casting due
to any change in cut off level or the cast pile top level is less than the specified
level or for any other reason, then the pile shall be built-up by using atleast one
grade higher concrete than that used for concreting of the same pile, ensuring
proper continuity with the existing concrete and to the satisfaction of the
Engineer. Necessary reinforcement as per design requirement and suitable
shuttering shall be provided before casting the concrete. Surrounding soil shall
also be built up to the required level by proper compaction to ensure lateral
capacity of the pile.

4.12.00 Breaking off of Piles

4.12.01 If any pile already cast, requires breaking due to lowering in cut off level or for
any other reason, then the same shall be carried out, not before seven days of
casting without affecting the quality of existing pile such as loosening,
cracking etc. and to the satisfaction of the Engineer.

4.13.00 Preparation of Pile head

4.13.01 The soil surrounding the piles shall be excavated upto the bottom of the lean
concrete below the pile cap, with provision for working space, sufficient enough to
place shuttering, reinforcement, concreting and any other related operations.

4.13.02 The exposed part of concrete above the COL shall be removed/chipped off and
made to a uniform level at COL, but not before seven days of casting of pile.

4.13.03 The projected reinforcement above COL shall be properly cleaned and bent to the
required shape and level to be anchored into the pile cap.

4.13.04 The pile top shall be embedded into the pile cap by 50mm or clear cover to
reinforcement, whichever is higher.

4.13.05 All loose material, like debris due to chipping/breaking of pile head to the
desired level, shall be removed and disposed off as directed by the Engineer.

4.14.00 Rejection and Replacement of Defective Piles

4.14.01 The Engineer reserves the right to reject any pile which in his opinion is
defective on account of load capacity, structural integrity, position, alignment,
concrete quality etc. Piles that are defective shall be pulled out or left in place as
judged convenient by the Engineer, without affecting the performance of
adjacent piles. The Contractor shall install additional piles to substitute the
defective piles as per the directions of the Engineer, at no extra cost to the
Owner.

4.15.00 Recording of Piling Data

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 12 OF 25
4.15.01 The Contractor shall record all the information during installation of piles.
Typical data sheet for recording pile data shall be as shown in Appendix D of IS:
2911 Part I/Sec.2. The pile data shall also include all the details as in
Annexure-D. On completion of each pile installation, pile record in triplicate shall
be submitted to Engineer within two days of completion of concreting of the pile.

5.00.00 SAMPLING, TESTING AND QUALITY ASSURANCE

5.01.00 Facilities required for sampling and testing of materials, concrete, etc. in field
and in laboratory should be provided by the Contractor. The Contractor shall
carry out all sampling and testing in accordance with the relevant Indian
Standards and this Specification. Where no specific testing procedure is
mentioned the tests shall be carried out as per the prevalent accepted
engineering practice and as per the directions of the Engineer. Tests shall be
done in the presence of the Engineer or his authorized representative. In case the
Engineer requires additional tests, the Contractor shall arrange to get these tests
done and submit to the Engineer the test results in triplicate within three days
after completion of any test.

5.02.00 The Contractor shall maintain records of all inspection and testing, which shall be
made available to the Engineer. The Engineer at his discretion may waive some of
the stipulations for small and unimportant concreting operations and other works.

5.03.00 Materials found unsuitable for acceptance shall be removed and replaced by the
Contractor. The work done by this unsuitable material shell be redone as per
specification requirements & and to the satisfaction of the Engineer at no extra cost
to the Owner.

5.04.00 Quality Assurance Programme

a) The Contractor shall submit and finalize a detailed Field Quality Assurance
Programme within 30 days from the date of award of the contract,
according to the requirements of this specification. This shall include setting
up of a testing laboratory, arrangement of testing apparatus/equipment,
deployment of qualified/experienced manpower, preparation of field quality
plan, etc. On finalized field quality plan, the Owner shall identify, customer
hold points, beyond which work shall not proceed without written approval
from the Engineer. The testing apparatus/equipment installed in the field
laboratory shall be calibrated/ corrected by the qualified persons as
frequently as possible to give accurate testing results.
b) Frequency of sampling and testing, etc. and Acceptance Criteria are given in
Table - 1. The testing shall be done at field laboratory or any other
laboratory approved by the Engineer. However, the testing frequencies set
forth are the desirable minimum and the Engineer shall have the full
authority to call for tests as frequently as he may deem necessary to satisfy
himself that the materials and works comply with the appropriate
specifications. The materials shall be tested to meet all the specified
requirements before acceptance at manufacturers premises or at independent

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 13 OF 25
government approved laboratory. Tests indicated in the table are for cross
checking at site the conformity of the materials to some of the specifications.

5.05.00 Testing of Concrete

5.05.01 Concrete and other materials shall be tested for quality, strength and other
properties. Details of testing shall be as specified under technical specification
for Cement concrete (Plain and Reinforced).

5.05.02 One sample consisting of six test cubes shall be made from the concrete used in
each test pile, three to be tested after 7 days and three after 28 days.

5.05.03 For working piles, minimum one sample consisting of six test cubes shall be
made from the concrete for the first ten piles, three to be tested after 7 days and
three after 28 days. Thereafter, minimum one sample consisting of three test cubes
for every 10 piles shall be tested for the 7-days & 28-days cube strength.

5.05.04 In preparation of test cubes or specimens vibrators shall not be used.

5.05.05 Concrete shall be tested for slump at every 1-hour interval during concreting of
piles.

5.05.06 The frequency of sampling and testing of concrete and materials shall be done
as per technical specification for cement concrete (Plain & Reinforced).

5.05.07 The acceptance criteria shall be as mentioned in Table-1.

5.06.00 Testing for position and alignment

5.06.01 Each pile shall be checked for its position with respect to specified location. Each
pile bore shall be checked for its alignment.

5.06.02 Permissible limits for deviation shall be as specified under clause no. 4.03.

5.07.00 Properties of Drilling mud

5.07.01 Properties of drilling mud shall be checked as per requirement under Annexure C.
Prior to the commencement of piling work and thereafter minimum once in a week
or as found necessary by the Engineer, one sample consisting of 3 specimens shall
be tested. Acceptance criteria applicable are as specified else where with 5%
variation. This relaxation is not applicable for properties of drilling mud before
concreting.

5.07.02 Density of the drilling mud shall be checked in each pile before concreting.

5.08.00 Check for Pile bore

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 14 OF 25
5.08.01 On completion of boring and cleaning the bottom of each pilebore shall be
checked from the sample collected from near the bottom of pile bore or by any
other methods as approved by the Engineer, to ensure that it is free from
pilebore spoil/debris and any other loose material, before concreting. Concreting
shall be done only after the approval of the Engineer.

5.08.02 For sampling of drilling mud from the pilebore the following method or any
other suitable method shall be adopted.

a) A solid cone shall be lowered by a string to the bottom of pilebore. A


sampler tube closed at top with a central hole (hollow cylinder) is lowered
over the cone, and then a top cover shall be lowered over the cylinder.
Care shall be taken for proper fittings of assembly to minimize the leakage
while lifting the cone assembly to the ground surface. The slurry collected in
the sampler tube shall be tested for density and sand content.

b) Use of borehole camera for checking the pile bore spoil and strata is
acceptable on approval of the Engineer.

5.09.00 Pile Integrity test

5.09.01 Low strain integrity test shall be conducted on 50% of the jobs piles and on all test
piles or as directed by Engineer. The system shall have the computer readout
facility and report on the findings of this shall be furnished to the Owner. This test
shall be used to identify the job piles for routine load test.

Piles shall be trimmed to cut off level or sound concrete level. No pile cap
blindage work should be undertaken prior to this test. The cast in-situ piles
should not be tested before 14 days of casting.

5.09.02 The test shall be undertaken by persons trained and experienced and capable of
interpreting the results with specific regard to piling. This test is limited to
testing the integrity of the shaft and is not intended to replace the use of static
load testing.

5.09.03 Low Strain Integrity Test Methodology:

a) In this test, a low stress wave is set up in the pile shaft and is also known as
Sonic Integrity or Sonic Echo test.

b) A small metal/hard rubber hammer is used to produce a light blow on top of


the pile. The shock wave travelling down the length of the pile is reflected
back from the toe of the pile and recorded through a suitable transducer/
accelerometer in a computer for subsequent analysis.

c) The primary shockwave, which travels down the length of the shaft, is
reflected from the toe by the change in density between the concrete and sub
strata. However, if the pile has any imperfections or discontinuities within

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 15 OF 25
its length these will set up secondary reflections, which will be added to the
return signal.

d) By analysis of the captured signal and knowledge of the conditions of the


ground, age of concrete, etc. a picture of the locations of pile shaft defects
can be built up. The observed signals are amplified into digital display as
velocity versus length records providing information on structural integrity of
piles.

e) The stress wave velocity and approximate pile lengths are provided as
input for the integrity testing. The stress wave velocity is dependent on the
Young's Modulus and mass density of pile concrete.

f) More than one recording of signals shall be done until repeatability of


signals is achieved on the same pile.

g) The tests shall be conducted at 3-6 locations to cover the entire cross
section of the pile.

6.00.00 PILE TESTING

Pile load test shall be carried out as per IS:2911 Part-4 (latest edition) or as
directed by Engineer.

6.01.00 INITIAL LOAD TEST

Initial load test shall be carried out on separately cast piles for confirmation of
estimated pile capacities and to fix a more accurate driving criteria viz.
set/bow, total number of blows and approximate depth etc. of founding level.
At least 2 nos. of tests shall be conducted for each mode (vertical
compression, pull out and lateral). The maximum test load shall be as
mentioned in bill of quantities.

6.02.00 ROUTINE LOAD TEST

Routine load tests shall be carried out on job (working) piles for 0.5% of total
no. of piles (for each mode and type). Maximum test load shall be 1.5 times
the design safe load capacity. Piles showing unsatisfactory results as per load
test results shall be treated as defective piles. Defective piles shall be removed
or left in place and replaced by additional piles as directed by Engineer at no
extra cost to the owner. Any additional cost towards design implications, if
any, due to above shall be born by the contractor.

7.00.00 CODES AND STANDARDS

All work shall be carried out as per this specification and shall conform to the
latest revision and/or replacements of the following or any other Indian
Standard (IS) Codes, unless specified otherwise. In case any particular aspect

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 16 OF 25
of work is not specifically covered by Indian Standard Codes, any other
standard practice, as may be specified by the Engineer, shall be followed.

IS: 432 - Specification for mild steel and medium tensile steel bars
(Part 1 & 11) and hard drawn steel wire for concrete reinforcement.

IS: 456 - Code of practice for plain and reinforced concrete.

IS: 1200 - Measurement of Building and Civil Engineering works


(Part 23) Piling.
IS: 1786 - Code of practice for twisted steel high strength
deformed bars for concrete reinforcement.

IS: 1892 - Code of practice for Subsurface Investigation for


foundation.

IS: 2131 - Method of Standard Penetration Test for Soils

IS: 2911 - Code of practice for design and construction of pile


Part I/Sec 2 foundations - Bored cast-in-situ concrete piles.

IS: 2911 - Code of practice for design and construction of pile


Part IV foundation - Load test on piles.

IS: 6926 - Code of practice for Diamond core Drilling for Site
Investigation for River Valley Projects.

IS: 10262 - Recommended guidelines for concrete mix design.

8.00.00 RATES AND MEASUREMENTS

The clauses below shall apply for item rate contracts only. They shall not be
applicable to turnkey/lump sum Contracts.

8.01.00 Rates

8.01.01 The items of work in the schedule of items, describe the work in brief. The
various items in schedule of items shall be read in conjunction with the
corresponding sections in the Technical Specifications, including amendments,
and additions, if any. For each item in schedule of items, the unit rate shall
include for the activities covered in the description of the item as well as for all
necessary operations described in the specification and specific requirements.

8.01.02 The unit rates shall include for minor details which are obviously and fairly
intended, and which may not have been included in the description in these
documents, but are essential for the satisfactory completion of the work. Unit
rates shall also include for all safety measures as required by codal provisions,

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 17 OF 25
local regulations, acts, bye-laws, etc. and for execution of work to the
satisfaction of the Engineer.

8.01.03 The quoted rate for each item shall be inclusive of mobilization of all plant,
equipment, scaffolding, labour, materials, skilled and unskilled labour, and
demobilization after completion of work, supervision, establishing the level and
coordinates at each work.

8.01.04 The quoted rate for piling for a particular diameter and capacity of pile shall
remain valid for the actual lengths provided /to be provided irrespective of the
minimum length specified elsewhere in this specification.

8.01.05 The quoted rate for piling as per description of item works shall be inclusive of
providing all plant equipment, labour, materials, skilled and unskilled labour,
making observations, establishing the ground level and coordinates at each
location of pile by carrying levels from one established bench mark and
distances from one set of grid lines furnished by the owner.

8.01.06 The quoted rate for piling shall be inclusive of bailing out all the pile bore spoil
from the pilebore, keeping the borehole free from bored material/debris etc.
and disposing the bored/chiselled material along with the drilling mud upto 2 Km.
beyond plant boundary or as directed by Engineer, flushing the pile bore by
fresh bentonite before concreting, collection of samples from bottom of
pilebore, transporting to laboratory, testing and reporting of results.

8.01.07 The quoted rate for piling shall include shifting of plant and equipment from one
pile location to another pile locations, providing temporary casing pipe and
removal of the same after completing, concreting, supply of necessary materials,
equipment and manpower, cost of boring by approved method as specified,
circulation of bentonite slurry and cleaning of borehole free from sludge, as
specified, etc.

8.01.08 The quoted rate for piling shall also include chiselling, if any, required for
socketing the pile in rock.

8.01.09 The quoted rate for the piling shall include concreting by termite method,
length of pile above COL, withdrawal of guide casing, cost for preparation of
pile head and disposal of debris etc., resulting from breaking off of pile upto
COL, upto a distance of 2 Km from the plant boundary or as directed by
Engineer.

8.01.10 The quoted rate for piling shall also include providing reinforcement and its
cleaning, straightening, cutting, bending, binding with annealed wire, welding,
tackwelding, providing concrete cover blocks, spacers, placing the reinforcement
cage in pile casing/bore and other cost of tools and plants, materials, labours,
carting the steel from store to piling site and return of unused steel to the
Owners storage point, etc.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 18 OF 25
8.02.11 Plasticiser/Admixture when used as directed by the Engineer shall be included
in piling rates.

8.01.12 The quoted rate for piling shall include for all quality assurance requirements, but
not limited to providing for technical inspection, transportation of samples to
laboratory, testing samples, maintaining and submitting all test records, etc.

8.01.13 The quoted rate for boring in separate borehole shall be inclusive of
performing of SPT at regular intervals as specified and collecting rock cores
from boreholes, upto the depth as specified shall be inclusive of transporting to
laboratory, testing and reporting of the results.

8.01.14 Unit rate for low integrity test shall be inclusive of mobilization of the entire set
of equipment, computer readout, printer, and equipment which may not lave
been included in the description but are essential for the satisfactory
completion of the work as per internationally accepted practice. The rate
quoted shall be inclusive of repeatability of test, preparation of pile top surface etc.

8.02.00 Measurement

8.02.01 Piling length shall be measurement by linear measurement from pile cut-off
level to the tip of pile in meters upto second place of decimal separately for
each diameter and capacity of pile. The length of pile to be cast above cut off
level, as per specification, and as approved by Engineer, shall be considered
for cement reconciliation only. Theoretical diameter of piles shall be
considered for reconciliation of cement consumption. No extra payment shall be
made for the length from existing ground to cut-off level.

8.02.02 Reinforcement steel shall be measured for reconciliation purpose only and the
measurement shall be done for providing and placing reinforcement in piles,
by weight in tones, up to third place of decimal in the following manner:

i) The weight shall be arrived at by multiplying the actual length measured


alongwith standard hooks, rings or spirals, spacers, cranks, bends, authorized
laps, etc. by sectional weight. These shall be submitted with supporting
documents giving the schedule of bars with sketches. The sectional weight
to be adopted shall be IS code’s sectional weight. Nothing extra shall be
payable to the contractor on account of difference in weight, if any, due to
different methods adopted for issue and measurement.

ii) Standard hooks, cranks, bend, authorized laps, supports, hangers and
chairs which are covered in approved bar bending schedule shall be
measured in tones.

iii) Dowels, neither shown on the drawings nor instructed by the Engineer, but
required for construction facilities shall not be measured.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 19 OF 25
8.02.03 Breaking off of piles, due to subsequent change in design cut off level, shall be
measured separately. This shall be measured in cubic metres upto second place
of decimal. This will be payable only when the pile is cast and on the basis of
written instruction of the Engineer for lowering of COL.

8.02.04 Measurements for the item of boring in a separate borehole shall be measured in
metres from ground level upto the depth as specified, upto second place of
decimal. Item of work of boring in soil and coring in rock shall be measured
separately for the actual length of boring in soil and coring in rock.

8.02.05 The item for pile integrity test shall be measured in terms of no. of piles tested.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 20 OF 25
ANNEXURE-A

Specific Requirements for Bored Cast-in-situ RCC Piles


Al.0 Minimum cement concrete grade M-25

Minimum cement content 400 Kg/M³

A1.1 Safe load

Diameter of Pile

Diameter of Pile Vertical/ Horizontal/ Lateral Pullout/Tension


(mm) Compression (MX) (MT)
(MT)
550 100 5 30
450 60 3 18

A2. Installation criteria

The installed pile(s) shall satisfy the following criteria.

A2.1 In Soil

a) Minimum length of the pile shall be 26.5 m below COL for 550mm
diameter and 30m below COL for 450mm diameter.

A3. Average cut-off level for tender design and initial load test can be assumed as
(-)3.5m below finished ground level.

A4. A protocol shall be signed between BHEL site and contractor regarding,

Strata at the founding depth

Installation criteria

Socketing depth

Density of bentonite before concreting

Slump of concrete.

Time interval between end of boring and start of concreting,

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 21 OF 25
ANNEXURE-B

List of Equipments
SI.No Description Capacity No.

1. Piling Rigs

2. Chisel 3 T min
6 T max

3. High pressure Mud Pumps 10 HP min


25 HP max

4. Bentonite mixing plants

5. Concrete batching plant

6. Soil testing equipments

Note:

1. The no. and capacity of the piling equipment varies for each work.

2. Additional equipments shall be mobilized if required as per the


directions of the Engineer to match the work schedule at no extra cost to
the Owner.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 22 OF 25
ANNEXURE-C

Bentonite suspension used for piling work shall satisfy the following requirements

a) Liquid limit of bentonite when tested in accordance with IS: 2720(Part V) shall
be more than 300 percent and less than 450 percent.

b) Sand content of the bentonite powder shall not be greater than 7 percent.

c) Bentonite solution should be made by mixing it with fresh water using


pump for circulation. The density of the freshly prepared bentonite
suspension shall be between 1.034 and 1.10 gm/ml depending upon the pile
dimensions and type of soil in which the pile is to be installed. However,
the density of bentonite suspension after mixing with deleterious materials in
the pilebore may be upto 1.25 gm/ml.

d) The Marsh viscosity when tested by a Marsh cone shall be between 30 to 60


seconds.

e) The differential free swell shall be more than 540 percent.

f) The pH value of the bentonite suspension shall be between 9 and 11.5.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 23 OF 25
ANNEXURE-D
PILE DATA
1. Reference No. Location (Co-ordinates) __________________area.

2. Sequence of Piling

3. Pile diameter & Type

4. Working level (Platform level)

5. Cut off level (COL)

6. Actual length below COL

7. Pile termination level

8. Top of finished concrete level

9. Date and time of start and completion of boring.

10. Depth of Ground water table in the vicinity.

11. Type of soil at pile tip

12. Method of boring operation

13. Details of drilling mud as used:

i) Freshly supplied mud


Liquid limit -

Sand content -

Density -

Marsh viscosity -

Swelling index -

pH value -

ii) Contaminated mud


Density -

Sand content -

14. SPT* N values in soil (from the nearest bore hole).

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 24 OF 25
+UCS** value in rock (from the nearest bore hole).

* Standard penetration Test


** Unconfined compression strength

15. Chiseling if any, from..….. m to …... m

16. Date and time of start and completion of concreting.

17. Method of placing concrete

18. Concrete quantity


Actual

Theoretical

19. Ref. Number of test cubes

20. Grade and slump of concrete

21. Results of test cubes

22. Reinforcement details:


Main Reinforcement Stirrups: Type
No.__________ No.__________
Dia. __________ Dia.__________
Depth _________ Spacing _________

23. Any other information regarding obstructions, delay and other interruption to the
sequence of work.

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TITLE: SPECIFICATION NO. PE-TS-999-600-C001
VOLUME - II B
TECHNICAL SPECIFICATION FOR
SECTION - D | SUB-SECTION – D21
INSTALLATION & TESTING OF
REV.NO. 01 DATE 19/08/2002
BORED CAST-IN-SITU RCC PILES
SHEET 25 OF 25
TABLE -1
FREQUENCY OF SAMPLING AND TESTING

SI. Type of material Nature of Test/ Method of Test No. of test Acceptance
No work characteristics & frequency Criteria
1. Pilebore size
a) diameter Physical each pile as per
b) length measurement specification
2. Founding level to establish in separate 1 borehole Annexure - B
socketing horizon/ borehole meant for 100-
and or founding for the purpose 150 piles
level & upto depth a) SPT in soils/ or group
5m below founding weathered rock of 150
level. b) Core & UCS Sqm
value of rock
3. Bentonite (Mud) Liquid Limit, Marsh
properties. Viscosity, Specific
a) Basic proper- gravity, sand in lab As per Cl. As per
ties of bentonite content, swelling 5.7 Annexure C
before use. index, pH value.
b) Contaminated Density, sand content in lab Each Pile As per annexure
mud from pile bore C
bottom before
concreting
4. Position and - Physical or any Each Pile As per Cl. 4.3
Alignment Approved method
5. Cleaning of - As per Cl. 5.8 Each Pile Pilebore be free
pilebore from bored
materialcuttings
debris/sludge
6. Reinforcement Physical each cage As per
(R/F) Spacing of inspection and approved
longitudinal R/F measurement design
cover laps bind-
ing of laterals
7. Concrete
a) Workability Slump cone test Each pile As per Cl. As per
5.5 specification.
b) Cubes Compressive As per spec. As per Cl. As per IS: 456
Strength test 5.5
8. Materials like
aggregate, sand As per technical specification for concrete and relevant IS codes
etc.
9. Pile head Physical each pile

C:\Documents and Settings\ssen\Desktop\LAB-TEST-CESC\FILE-3-D21-FINAL-PILING(2).doc


TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_1 OF__7__

PILING-PART VI

CONSTRUCTION AND INSTALLATION OF


DRIVEN CAST-IN-SITU PILES

REV. NO. DATE APPROVED

Issued RAV. DATE:


COPYRIGHT AND CONFIDENTAL PEM
The information on this document is the property
of BHARAT HEVY ELECTRICAL LTD. Prepared: Approved: Date:
It must not be used directly or indirectly in any
way detrimental to the interest of the Company.
TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_2 OF__7__

CONTENTS :

SECTION DESCRIPTION

1.0 SCOPE

2.0 CODES

3.0 MATERIALS

4.0 DESIGN CONSIDERATIONS

5.0 EQUIPMENT AND ACCESSORIES

6.0 CONTROL OF PILE DRIVING


TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_3 OF__7__

1.0 SCOPE :

1.1 This standard specificationh covers the construction and installation of driven
cast-in-situ load bearing concrete piles.

1.2 For specific work requirements concerning construction or otherwise modifying


or supplementing the provisions of this specifications, reference may be made to
‘Specific Requirements’ In the case of may conflict between the requirements set
forth in specific Requirements and the provisions of this specification, the
‘Specific Requirements’ shall govern.

2 CODES :

2.1 IS :2911 (PartI/SecI). Indian Standard code of practice for Design and
Construction of pile foundations : Part I Concrete Piles, section 1 Driven Cast –
In- Situ load bearing concrete piles, shall be referred to in conjunction with these
specifications during the entire design, construction and installation work.

2.2 Reference to any code shall always mean reference to the latest revised edition of
the code including all its amendements upto date, unless otherwise specified. In
the event of any conflict between the requirements of this specification and those
of the refered codes, the former shall govern.

3 MATERIALS :

3.1 All materials, viz, cement, steel, aggregates, water etc, which are to be used in the
construction work, shall conform to BHEL, Standard Specification for Material
for Reinforced concrete Piles.

3.2 CONCRETE :

Concrete shall be manufactured either by central batching plant or Ready Mix


concrete. Concrete shall conform to IS: 10262 & IS: 456.

3.2.1 Technical Specification for Cement Concrete (Plain and Reinforced) works along
with IS: 2911 Part I/Sec 2 shall be followed for concrete works of piles. Use of
plasticiser to control the water cement ratio shall be permitted on specific approval
from the Engineer. Water cement ratio shall not be greater than 0.5.

3.2.2 Consistence of concrete shall be suitable to the method of installation of piles.

3.2.3 The minimum slump shall be 100mm when concrete in the pile is not compacted.
It shall not exceed 175mm in any case.

The grade of concrete to be used for pilling shall be M-25. Minimum cement
content in concrete shall be 380 kg/m3. When concreting under water or
drilling mud, 10% additional cement over that required for the design mix of
concrete for the required slump shall be used subject to a min. of 400 kg/m3.
TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_4 OF__7__

3.2.4 The average compressive stress under working load shall not exceed 25% of the
specified works cube strenth at 28 days calculated on the total cross sectional area
of pile. Where the casing of pile is a) Permanent, b) of adequate strenth and c) of
suitable shape, the allowable compressive stress may be increased.

4 DESIGN CONSIDERATIONS :

4.1 Pile shall be designed in such a way that the load from the structure or supports
should be transmitted to the soil without causing any soil failure and without
causing such settlement under permanent/transient loading which may result in
structural damage and /or functional distress. The pile shaft have adequate
structural capacity to withstand all loads and moments which are to be transmitted
to the subsoil.

4.2 The soil report data consisting of borelog datas, laboratory test results and pile
recommendations is attached alongwith for bidders. Safe pile load capacity to be
adopted for working loads as below. Initial load test of pile is being conducted
separately and the result/recommendations will be provided to bidder at the start
of work at site.

4.3 Bidder has to conduct working load test of pile as per IS :2911 Part-IV and ensure
the safe rated load capacities of pile. Structural design of pile will be done by
BHEL. For driven cast in situ piles, bidder has to provide the set criteria for
approval of BHEL/CESC/TCE as per the equipments mobilised for driving casing
of driven piles to ensure end bearing strength of soil strata. The hammer weight of
pile rigs for driving pile shall be preferably 5MT.

4.4 The construction of extension unit#3 is in continuation to existing unit#1&2. As


the construction work for Unit#3 including driving of pile casing is to be done
adjacent to existing unit#2, care has to be taken that no damage occurs to existing
structure and functioning of sensitive instruments in existing unit. A vibration
measurement exercise was done by BHEL/CESC/TCE while driving pile casing
of 550mm diameter during initial pile load test and based on that extent of
bored/driven pile is decided adjacent to eisting structures.
Bidders has to follow the driving procedure as approved by BHEL. Progressive
increase in blow height is to be adopted for driving pile casing in viscinity of
existing structures with limited nos. of rigs operating at a time near existing
structure in each zone.

Safe load capacity of pile

Diameter of Pile Vertical/ Horizontal/ Lateral Pullout/Tension


(mm) Compression (MX) (MT)
(MT)
550 100 5 30
450 60 3 18

a) Minimum length of the pile shall be 22 m below COL for 550mm


diameter and 20m below COL for 450mm diameter.
TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_5 OF__7__

Average cut-off level for tender design and initial load test can be assumed as
(-)3.5m below finished ground level.

4.5 REINFORCEMENT :

4.5.1 The design of reinforcement cage and the minimum reinforcement shall be in
accordance with is :2911 (Part I Sec. I)
4.5.2 The reinforcement shall be normally provided upto the full depth of pile and the
designed quantity of reinforcement will be curtailed at appropriate level as per
designn requirements in case of piles subject to compressive load only provided it
could be ensured that there shall be no danger to green concrete due to driving of
adjacent piles.
4.5.3 The minimum clear cover to reinforcement shall be 50mm . The lateral spacing of
the reinforcement cage in spacing shall be chosen so as to impart adequate rigidity
of the reinforcing cage during handling and installations. For aggresive soil
conditions, the clear cover shall be suitably increased in case special cement is not
used.
4.5.4 The longitudinal reinforcement shall be provided considering the combination of
vertical (compression and tension) and horizontal loads. Minimum six numbers of
bars shall be provided for longitudinal reinforcement. The diameter of
longitudinal reinforcement bars shall not be less than 12mm. The stipulated
minimum reinforcement shall be provided for the full length of pile.
4.5.5 The longitudinal reinforcement shall project 50 times its diameter above cut off
level unless otherwise indicated.
4.5.6 The laterals shall be tied to the longitudinal reinforcement to maintain its shape
and spacing. The laterals may in the form of links or spirals. The minimum
diameter of the links or spirals shall be 6 mm and the spacing of the links or spiral
shall not be less than 150 mm and in no case more than 300 mm.
4.5.7 As far as possible number of joints (laps) in longitudinal reinforcement shall be
minimum. In case the reinforcement cage is made up of more than one segment,
these shall preferably be assembled before lowering into casing tube/pilebore by
providing necessary laps as per IS: 456.
4.5.8 The minimum clear distance between the two adjacent main reinforcement bars
shall normally be 100 mm for the full depth of cage.
4.5.9 The laps in the reinforcement shall be such that the full strength of the bar is
effective across the joint and the reinforcement cage is of sound construction.
4.5.10 Laps shall be staggered as far as practicable and not more than 50% bars shall be
lapped at a 'particular section. Lap joints shall be staggered by at least 1.3 times
the lapped length (Centre to Centre).
4.5.11 Proper cover and central placement of the reinforcement cage in the pile bore
shall be ensured by use of suitable concrete spacers or rollers, cast specifically for
the purpose.
4.5.12 Bundling of bars is not permitted.

5 EQUIPMENT AND ACCESSORIES :

5.1 Equipment and accessories shall in general confirm to requirements but not
limited to that, stated in the relevant clause of IS :2911 (Part I/Sec I).
TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_6 OF__7__

5.2 List of equipments and accessories to be used for a specific project shall be
submitted along with the bids ; demonstrating that the piles would be installed to
the design penetration. The equipment and accessories shall also be approved by
Engineer-in-Charge at the time of mobilisation.
5.3 Based on the site investigation data, contractor should also submit list of
anticipated problems and remedial actions proposed by him to overcome these
anticipated problems including requirement of mobilization and use of necessary
equipments for the purpose.

6. CONTROL OF PILE INSTALLATION

6.1 CONTROL OF ALIGNMENT :

Pile shall be installed as accurately as possible either vertical or to the specified


inclination. As a guide for vertical pileds, a deviation of 1.5% and for raker a
deviation of 4% shall be normally permitted. Piles shall not be out of position by
more than 75 mm from the designed location at the working level of piling rig. In
case of a single pile in a column, positional tolerance shall not exceed 50 mm. In
cae of piles deviating beyond these limits and to such an extent that the resulting
eccentricity cannot be taken care of by a redesign of the pile cap or pile tiles, piles
shall be replaced or supplemented by one or more additional piles.

6.2 WITHDRAWAL OF CASING :

6.2.1 It shall be ensured that volume of concrete poured in at at least equal the volume
of pile shaft being concreted and the rate of concreting should match with the rate
of withdrawal of casings. It should be ensured that minimum 1 m height of
concrete should always be maintained in the casing.

6.2.2 When withdrawing the casing, the head of concrete in the hole shall always be
more than the head of ground water table outside the casing to prevent inflow of
water inside.

6.3 ADJACENT STRUCTERES :

6.3.1 When Working near existing structures care shall be taken to aviod any damage to
such structure. Fig 1 of IS :2974 (Part I) may be folowed a a guide.

6.3.2 In case of deep excavation adjacent to piles, proper shoring or other suitable
arrangement shall be made to guard against the lateral movement of soil stratum
or releasing the confining soil stress.

6.4 SEQUENCE OF PILING

6.4.1 In a pile group, the sequence of installation of piles shall normally be from the
centre to the periphery of the group or from one side to the other.
TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_7 OF__7__

6.4.2 In case of compact soil specially, the consideration shall be given to the
possibility of doing harm to a pile recently formed by driving the tube nearby
before the concrete has sufficiently set.

6.4.3 Driving piles in loose sand tends to compact the sand which in turn increases the
skin friction. Therefore, the order of installing such a pile in a group shall avoid
creating a compacting block of ground into which further piles cannot be driven.
In case where stiff clay or compact sand layer have to be penetrated, similar
precautions need to be taken. This may be overcome by driving the piles from the
centre outwards or by beginning at a selected edge or working across a group.
However, in case of soft soils, the driving may have to proceed from outside to
inside so that the soils is restrained from flowing out during operations.

6.5 JETTING

Jetting of casings by means of water shall not normally be permitted. In every


special circumstances however, it may be carried out only with the express
permision of the Engineer-in-Charge without impairing the bearing capacity of
piles already in place, the stability of soil, or the safety of any adjoining building.

6.6 The top of concrete in a pile shall be brought above the cut-off level to remove all
laitance and weak concrete before caping and to ensure good concrete at the cut-
off level. The reinforcing cage shall be left with adequate protuding length above
the cut off level for embedment into the pile cap.

6.7.1 As a general guide line for cut-off level upto 1.5m below working level, the
concrete shall be cast to a min. of 300mm above cut off level. For each additional
0.3m increase in cut-off level below working level, an additional coverage of
50mm shall be allowed.

6.8 DEFECTIVE PILE

Defective pile shall be removed or left in place without affecting the performance
of the adjacent piles or the cap as a whole. Additional piles shall be provided to
replace them when required. Various pile testing items are provided in the BOQ
and it is necessary that the installed pile shall pass the tests specified, failing
which it will be treated as defective pile.

6.9.1 Any deviation from designed location alignment or load capacity of any pile shall
be noted and adequate measures taken well before concreting of the pile cap and
plinth beam.

6.9.2 During chipping of the pile cap, manual chipping may be permitted after three
days of pile casting while pneumatic tool for chipping shall not be used before
seven days after pile casting.

6.10 RECORDING OF DATA


TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_8 OF__7__

Typical data sheets for recording piling data shall be as shown in IS :2911,
(PartI/Sec I).

7.01.00 Rates

7.01.01 The items of work in the schedule of items, describe the work in brief. The
various items in schedule of items shall be read in conjunction with the
corresponding sections in the Technical Specifications, including amendments,
and additions, if any. For each item in schedule of items, the unit rate shall
include for the activities covered in the description of the item as well as for all
necessary operations described in the specification and specific requirements.

7.01.02 The unit rates shall include for minor details which are obviously and fairly
intended, and which may not have been included in the description in these
documents, but are essential for the satisfactory completion of the work. Unit
rates shall also include for all safety measures as required by codal provisions,
local regulations, acts, bye-laws, etc. and for execution of work to the satisfaction
of the Engineer.

7.01.03 The quoted rate for each item shall be inclusive of mobilization of all plant,
equipment, scaffolding, labour, materials, skilled and unskilled labour, and
demobilization after completion of work, supervision, establishing the level and
coordinates at each work.

7.01.04 The quoted rate for piling for a particular diameter and capacity of pile shall
remain valid for the actual lengths provided /to be provided irrespective of the
minimum length specified elsewhere in this specification.

7.01.05 The quoted rate for piling as per description of item works shall be inclusive of
providing all plant equipment, labour, materials, skilled and unskilled labour,
making observations, establishing the ground level and coordinates at each
location of pile by carrying levels from one established bench mark and distances
from one set of grid lines furnished by the owner.

7.01.07 The quoted rate for piling shall include shifting of plant and equipment from one
pile location to another pile locations, providing temporary casing pipe and
removal of the same after completing, concreting, supply of necessary materials,
equipment and manpower, cost of boring by approved method as specified,
circulation of bentonite slurry and cleaning of borehole free from sludge, as
specified, etc.

7.01.08 The quoted rate for the piling shall include concreting by tremie method, length
of pile above COL, withdrawal of guide casing, cost for preparation of pile head
and disposal of debris etc., resulting from breaking off of pile upto COL, upto a
distance of 2 Km from the plant boundary or as directed by Engineer.

7.01.09 The quoted rate for piling shall also include providing reinforcement and its
cleaning, straightening, cutting, bending, binding with annealed wire, welding,
tackwelding, providing concrete cover blocks, spacers, placing the reinforcement
TECHNICAL SPECIFICATION
FOR MISCELLANEOUS STEEL
WORKS
PEM-CIVIL PAGE_9 OF__7__

cage in pile casing/bore and other cost of tools and plants, materials, labours,
carting the steel from store to piling site and return of unused steel to the Owners
storage point, etc.

7.01.10 Plasticiser/Admixture when used as directed by the Engineer shall be included in


piling rates.

7.01.11 The quoted rate for piling shall include for all quality assurance requirements,
but not limited to providing for technical inspection, transportation of samples to
laboratory, testing samples, maintaining and submitting all test records, etc.

8.01.00 Measurement

8.01.01 Piling length shall be measurement by linear measurement from pile cut-off level
to the tip of pile in meters upto second place of decimal separately for each
diameter and capacity of pile. The length of pile to be cast above cut off level, as
per specification, and as approved by Engineer, shall be considered for cement
reconciliation only. Theoretical diameter of piles shall be considered for
reconciliation of cement consumption. No extra payment shall be made for the
length from existing ground to cut-off level.

8.01.02 Reinforcement steel shall be measured for reconciliation purpose only and the
measurement shall be done for providing and placing reinforcement in piles, by
weight in tones, up to third place of decimal in the following manner:

i) The weight shall be arrived at by multiplying the actual length measured


alongwith standard hooks, rings or spirals, spacers, cranks, bends, authorized
laps, etc. by sectional weight. These shall be submitted with supporting
documents giving the schedule of bars with sketches. The sectional weight to be
adopted shall be IS code’s sectional weight. Nothing extra shall be payable to the
contractor on account of difference in weight, if any, due to different methods
adopted for issue and measurement.

ii) Standard hooks, cranks, bend, authorized laps, supports, hangers and chairs
which are covered in approved bar bending schedule shall be measured in tones.

iii) Dowels, neither shown on the drawings nor instructed by the Engineer, but
required for construction facilities shall not be measured.

8.01.03 Breaking off of piles, due to subsequent change in design cut off level, shall be
measured separately. This shall be measured in cubic metres upto second place
of decimal. This will be payable only when the pile is cast and on the basis of
written instruction of the Engineer for lowering of COL.
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__1__OF__7__

PILING PART-V
TESTING OF CONCRETE PILES
BY CONVENTIONAL LOADING SYSTEM

REV. NO. DATE APPROVED

COPYRIGHT AND CONFIDENTAL Issued RAV. DATE:


The information on this document is the PED
property of BHARAT HEVY ELECTRICAL HYD
LTD. It must not be used directly or indirectly Prepared: Approved: Date:
in any way detrimental to the interest of the 1
Company.
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__2__OF__7__

CONTENTS

1. GENERAL

2. VERTICAL LOADING TESTS

3. LATERAL LOADING TEST

4. PULL OUT CAPACITY OF PILES

5. COMBINED VERTICAL AND LATERAL LOADING

6. SPECIAL TYPE OF LOADING

APPENDIX 1 – PILE LOADING TEST RECORD

2
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__3__OF__7__

1. GENERAL

1.1 Scope

1.1.1 This specification covers the requirements and methods of testing of a single
pile for evaluating its safe capacity in :

a) Vertical Loading (compression )

b) Lateral loading

c) Pull out.

d) Combined vertical and lateral loading.

e) Special type of loading such as vibratory loadings.

1.1.2 These specifications shall be applicable for all types of piles in general
excepting sheet piles.

1.1.3 For specific work requirements or otherwise modifying or supplementing the


provisions of this specification, refer to specific requirements. In case of
conflict between requirements set forth in the specific requirements and the
provisions of this specification, the specific requirements and the provisions of
this specification, the specific requirements shall govern.

1.2 Definitions

1.2.1 Reference to Indian Standard codes shall always mean reference to the latest
issue of the relevant standards, including all the amendments up to date.

1.3 Codes

1.3.1 All testing shall be performed in accordance with the following codes and the
provisions of these specifications:

IS : 2911 – (part-IV ) – Codes of practice for design and Construction of pile


Foundations – load test on piles .

1.4 Requirements

1.4.1 The load test shall be required to provide data regarding the load – deformation
characteristics of the pile up to failure or otherwise specified and the safe design
capacity.

1.4.2 Full details of the equipment proposed to be used and the test set up shall be
submitted to the Engineer-in-Charge with detailed sketches for approval.

3
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__4__OF__7__

Approval of the Engineer-in-Charge shall be also be obtained after the test set
up is complete, prior to commencement of loading.

1.4.3 All measuring devices shall be tested satisfactory performance and accuracy at
an approved institution and certificate to that effect obtained and submitted to
the Engineer –in-charge, prior to use.

1.4.4 The test pile shall be constructed using the same equipment and technique as for
the job piles.

1.4.5 A minimum time period of one week shall be allowed between the time of
installation and testing in case of a precast pile and less than four weeks from
the time of vesting in case of a cast-in situ pile.

1.4.6 Recodes

A full record giving all details of the test in the Performa in appendix-1 shall be
submitted in TRIPLICATE to the Engineer-in-Charge immediately on
COMPLETION of each test. The record shall also include the plot of load- time
settlement characteristics of the piles.

2 VERTICAL LOADING TEST:

2.1 Equipment and test Set-up

2.1.1 Test pile

2.1.1.1 The test pile shall be decided by the Engineer-in-Charge. It may be one of the
working piles or separate test pile.

2.1.1.2 The head of the test pile shall be brought to the proper level and provided with a
pile cap with a moral and plane surface and with adequate space for proper
seating of a jack and dial gauges.

2.1.1.3 Test pile surface shall be prepared for testing purposes on the expiry of one
week after casting the pile.

2.1.2 Loading Systems

2.1.2.1 Loading shall be applied by the reaction method consisting of an hydraulic jack
reacting centrally against a loaded platform. Supports of the platforms shall be
adequately designed. Special anchor piles or any other suitable type of
anchorage system may also be used. However, use of the uplift supply of neigh
boring piles for providing the reaction shall normally not be permitted.

2.1.2.2 The loading system shall be adequate to ensure that the test can be carried up to
the specified limit. The reaction to be made available for the test shall be at least
25% greater than the maximum jacking force required.

2.1.3 Measuring System


4
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__5__OF__7__

2.1.3.1 Loading on piles

The load applied on the pile shall be recorded on a calibrated pressure gauge
mounted on the jack.

2.1.3.2 Settlement of pile

a) Settlement of pile shall be recorded by dial gauges suspended from datum


bars.

b) The datum bars shall have rigid supports preferably of concrete pillars or
steel section, embedded well into the ground. The supports shall be locked
more then three times the piles diameter, subject to a minimum of 1.5 M,
clear away from the pile face and also sufficiently away from the supports
of the loaded plat from to avoid any disturbance on these accounts.
Movements near the supports of the datum bar shall be avoided while the
test is in progress.

2.2 Method of conducting Test

The test shall be carried out by the direct method of loading in successive
increments or by the cyclic loading method as specified and as directed by the
engineer-in-charge.

2.2.1 Direct Method of Loading in Successive Increments

The test shall be carried out as per the procedure outlined.

a) The load shall be applied to the pile top in increments of about one fifth
the rated capacity of the pile or as specified. Settlement readings shall be
taken before and after the application of cash new load increment and at
2,4,8,15,30,60 minutes and at every two hours until application of the next
load increment.

b) Each stage of loading shall be maintained till the rate of movement of the
pile top is not more than, 0.1 mm in first 30minutes, 0.2 mm per hours or
until two labours have elapsed, which is later.

c) (I) Yield of soil-pile system occurs causing progressive settlement of the


pile exceeding a value of one tenth of the pile diameter.

(II) The loading on the pile top equals twice the rated capacity or as
specified in the case of a separate test pile and 1.5 times the rated capacity
of the pile in case of a working pile.

d) Where yielding of the soil does not occur, the full test load shall be
maintained on the pile head for 24 hours or more if necessary and
settlement reading shall be taken at 6hours interval during the period.

5
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__6__OF__7__

e) Unloading shall be carried out in the same steps as loading. A minimum


period of ½ hour shall be allowed to elapse between two successive stages
of load decrement. The final rebound shall be recorded 6 hours after the
entire test load has been removed.

f) If so directed by the Engineer-in- charge, loading and unloading cycles


shall be carried out for all load stages within the assumed working load.

g) Assessment of Safe Load:

The safe of the pile shall be the least of following values:

i) 2/3 of final load at which the total displacement attains a value of


12mm. Unless otherwise required, in given case on the basis of
nature and type structure in which case, the safe load should be
corresponding to the stated total displacement permissible.

ii) 50 percent of final load at which the total settlement equate the
10% of pile diameter in case of bored piles and 7.5 percent of bulb
diameter in case of under – reamed piles.

2.2.2 Cycle Loading Test

The test shall be carried out as per the procedure outlined by IS : 2911 – (part –
IV) and as described below:

a. The load shall be supplied to the pile top in increments of about one fifth
the estimated safe capacity of the pile or as specified. Settlement readings
shall be taken before and the application of each new load increment and
at 2,4,8,15,30,60 minutes and at every two hours until application of the
next load increment.

b. Alternate loading and unloading shall be carried out at each stage and the
total and net settlements recorded as specified. If so directed by the
Engineer-in-charge, more then one cycle of loading and unloading shall be
carried out at any or all of the stages.

c. Each stage of loading or unloading shall be maintained till the rate of


movement of the pile top is not more then 0.2 mm per hour provided that
the minimum period is two hours for loading and one hour for unloading.
The following lod stages shall however be maintained for longer periods
as given below:

i) At 1. 5 times assumed safe - 24 hours.


Capacity ( for routine test only )

ii) At load of twice assumed safe - 24 hours


capacity ( for initial test only )

6
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__7__OF__7__

This loading shall be continued till one of the following occurs:

i) Yield of the soil pile system occurs causing progressive settlement


exceeding one tenth of the pile diameter.
ii) The loading on the pile top equals twice the estimated safe load in
case of a separate test pile and 1.5 times the rated capacity of the
pile in case of working pile.

d) Assessment of Safe Load :

The safe capacity of the pile shall be the lest of the following :

i) The thirds of the final load at which the total settlement attains a
value of 6 mm.

ii) Two thirds of the final load at which the total settlement attains a
value of 6 mm.

iii) Half of the final load at which the total settlement equals one tenth
of the pile.

3. LATERAL LOADING TEST :

3.1. Equipment and test set-up

3.1.1 Test Pile

The test pile shall be decided by the Engineer-in-Charge. It may be one of the
working piles or a separate test pile.

The test pile shall be cut off at the proper level and provided with a cap with
vertical plane sides having an adequate area for proper seating of the jack and dial
gauges.

3.1.2 Loading System

Loading shall be applied by an hydraulic jack of adequate capacity, abutting the


pile horizontally and reacting against a suitable system. The reaction may be
provided by the wall of the excavated-pit when the test is being conducted below
ground level or by a neighbouring pile in which case thrust pieces shall be
inserted on either end of the jack to make up the gap.

3.1.3 Measuring System

3.1.3.1 Lateral load applied on the pile shall be measured by a calibrated pressure gauge
mounted on the jack, having a least count of 500 Kg.

3.1.3.2 Deflection of the pile hand shall be measured by dial gauges, fixed to datum bars
and having a least count of 0.01 mm. The datum bars shall be provided with rigid
supports as described in Clause 2.1.3.2 (b) above.
7
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__8__OF__7__

3.2 Method of Conducting Test :

The test shall be carried out in accordance with the provisions of IS :2911– (part-
I)and as detailed below :

3.2.1 Loading shall be applied in increments of 500 kgs. Or as specified.

3.2.2 Each stages shall be maintained for a period till the rate of movement of the pile
head is not more then 0.1 mm / 30 min. or 1 hr. whichever is greater.

3.2.3 Loading shall be continued till one of the following occurs:

a) Deflection of the pile head exceeds 12 mm.

b) The applied load on the pile is twice the assumed lateral load capacity of
the pile in case of a separate test pile and 1 ⅓ Times the rates capacity in
the cast of a working pile.

3.2.4 Assessments of Safe Load :

The safe load shall be the smaller of the following :

i) Half the final lod for which the total deflection is 12 mm.

ii) Loading corresponding to 5 mm total defection.

NOTE: The deflection is at the cut off level of the pile.

4. PULL OUT CAPACITY OF PILES

4.1 Equipment and test Set up

4.1.1 Test pile

The test pile shall be decided by the Engineer-in-Charge. The test shall be
conducted on a separate pile installed separate pile installed specifically for this
purpose.

4.1.1.2 the test pile shall be built upto the proper length and the proper length and the
head provided with suitable arrangements for anchoring the load applying system.

4.1.2 Loading System

4.1.2.1 Load shall be applied using an approved reaction system uplift force on the pile
may be applied directly to the test pile or through a lever system. The reaction
may be provided by neighbouring piles or blocks may be constructed for the
purposes. A hydraulic jack shall be used for load application.

4.1.3 Measuring System


8
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__9__OF__7__

4.1.3.1 Load applied by jack shall be measured by a calibrated pressure gauge with a least
count of 1000 kgs.

4.1.3.2 Movement of the pile shall be measured by dial gauges, fixed to datum bar and
having a least count of 0.01 mm. A minimum of two dial gauges, placed
diametrically opposite shall be used. Datum bars shall be provided with rigid
supports as described in 2.1.3.2 (b) above.

4.2 Method of Conducting Test

The test shall be conducted as outlined below:

4.2.1 Loading shall be applied to the pile top increments of one fifth rated capacity of
pile.

4.2.2 Each stage shall be maintained for a period till the rate of movement of the pile
head is not more then 0.1 mm / 30 min. or one hour, whichever is greater.

4.2.3 Loading shall be continued till one of the following occurs:

a) Yield of soil pile system occurs causing progressive movement of the pile
exceeding 12 mm.

b) The loading on the pile top equals twice the estimated safe load or as
specified.

4.3 Assessment of Safe Load

The safe capacity of the pile shall be the smaller of the following:

a) Two-thirds of the load at which the total displacement is 12 mm or the


load corresponding to a specified permissible up lift, and

b) Half of the load at which the load-displacement curve show as a clear


break (downward trend).

5. COMBINED VERTICAL AND LATERAL LOADING :

5.1 Equipment and Test Set-up

5.1.1 The equipment and test set up shall be same described in Clause 3. in addition a
platform shall be constructed on the pile top, and loaded to 1.0 times the pile
capacity in vertical loading.

The pile shall be first subjected to the full vertical load. The lateral load shall
commence after all settlements due to the vertical load have ceased and while the
full vertical load is in position.

9
TECHNICAL SPECIFICATION
HYDERABA FOR PILING.
D PAGE__10__OF__7__

5.1.2 The loading system, measuring system and recording of results shall be the same
as described in Clause – 3.
5.2 Method of Conducting Test and Assessment of Safe Load

This shall be in accordance with the provision of Clause 3.2 above.

6. SPECIAL TYPE OF LOADING

This shall include evaluating the pile response to vibratory loads, both horizontal
and vertical in nature. The test set up and method of conducting the test shall be
covered under specific requirements.

APPENDIX

FILE NO………………………..DATE OF ……………………….WT. OF HAMMER……………………

TYPE…………………………..DRIVING ……………………….AVR. DROP OF HAMMER…………..

DLAMETER (CM)……………..CASTING……………………..TOTAL NO. OF BOWS………………..

LENGTH BELOW COMMENCEMENT OF TEST… SUM OF TEMPORARY

G.L.(M)…………………….. ……………………………………COMPRESSION IN CMS……………

LOCATION ………………… COMPLETION OF TEST………. GROUND LEVEL ………………….

TYPE OF TEST : DIRECT/CYCLE LOADING

______________________________________________________________________
SETTLEMENT AVRSETTLEMENT
DATE TIME TOTAL LOAD LOAD TOTAL (DEFLECTION) (DEFLECTION)
TIME ON OFF LOAD GAUGE
________________________

SOUND REMARKS
I II TOTAL NETT
_________________________

HR.MINS TONNES TONNES MM MM MM MM M


_______________________________________________________________________

10

You might also like