PLTM Cileunca 660,5 Days Mon 23/12/19 Wed 13/10/21 40%

The document is a project schedule for a power plant construction project spanning from December 2019 to October 2021. It includes key milestones such as the project start, generator and turbine installation on site, construction start, and project completion. The schedule also outlines the engineering work from January 2020 to April 2021 including general engineering tasks, civil works, and mechanical, electrical and instrumentation drawings and designs.

Uploaded by

annisa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views6 pages

PLTM Cileunca 660,5 Days Mon 23/12/19 Wed 13/10/21 40%

The document is a project schedule for a power plant construction project spanning from December 2019 to October 2021. It includes key milestones such as the project start, generator and turbine installation on site, construction start, and project completion. The schedule also outlines the engineering work from January 2020 to April 2021 including general engineering tasks, civil works, and mechanical, electrical and instrumentation drawings and designs.

Uploaded by

annisa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

schedule 201224.

mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
0 PLTM CILEUNCA 660,5 days
Mon 23/12/19
Wed 13/10/21
40% 40%
1 1 MILESTONES 659,5 days
Mon 23/12/19 Tue 12/10/210% 0%
2 1.1 Project Start (NTP) 0 days Mon 23/12/19Mon 23/12/19100% 23/12
3 1.2 Generator Onsite 0 days Fri 28/05/21 Fri 28/05/21 0% 28/05
4 1.3 Turbine Onsite 0 days Mon 31/05/21Mon 31/05/210% 31/05
5 1.4 Construction Start 0 days Fri 17/01/20 Fri 17/01/20 100% 17/01
6 1.5 Project Complete 0 days Tue 12/10/21Tue 12/10/210% 12/10
7 2 ENGINEERING 456 daysFri 31/01/20 Fri 30/04/21 70% 70%
8 2.1 General 414 daysFri 13/03/20 Fri 30/04/21 70% 70%
9 2.1.1 Preparation Work / For Information 22 days Fri 10/04/20 Tue 13/04/2174% 74%
10 2.1.2 Technical Data List 45 days Fri 13/03/20 Sat 09/01/21 65% 65%
11 2.1.4 Technical Data Turbine 14,5 daysThu 19/03/20Thu 02/07/20100% 100%
12 2.1.5 Technical Data Generator 23,5 daysThu 19/03/20Thu 02/07/20100% 100%
13 2.1.3 Operation and Maintenance Instruction 15 days Fri 16/04/21 Fri 30/04/21 0% 0%
14 2.2 Civil 379 daysFri 31/01/20 Fri 12/02/21 80% 80%
15 2.2.1 Calculation 30 days Fri 31/01/20 Fri 01/01/21 75% 75%
16 2.2.2 Drawing 379 daysFri 31/01/20 Fri 12/02/21 81% 81%
17 2.2.2.1 Penstock Pipe and Structure 49 days Fri 07/02/20 Thu 26/03/20100% 100%
18 2.2.2.1.1 Penstock Piping 49 days Fri 07/02/20 Thu 26/03/20100% 100%
19 2.2.2.1.2 Saddle 35 days Fri 07/02/20 Thu 12/03/20100% 100%
20 2.2.2.1.3 Anchor Block 35 days Fri 07/02/20 Thu 12/03/20100% 100%
21 2.2.2.2 Penstock Bridge 22 days Fri 31/07/20 Mon 04/01/2151% 51%
22 2.2.2.3 Powerhouse Area 242 daysTue 16/06/20Fri 12/02/21 23% 23%
23 2.2.2.3.1 Powerhouse 50 days Tue 16/06/20Wed 20/01/2146% 46%
24 2.2.2.3.2 Tailrace 50 days Fri 25/12/20 Fri 12/02/21 0% 0%
25 2.2.2.4 Access Road and Bridge 134 daysFri 31/01/20 Fri 12/06/20 100% 100%
26 2.2.2.4.1 Access Road 25,6 daysFri 31/01/20 Fri 12/06/20 100% 100%
27 2.2.2.4.2 Access Bridge 29,34 days
Fri 31/01/20 Fri 12/06/20 100% 100%
28 2.2.2.5 Station Service (Gardu Hubung) 49 days Fri 20/03/20 Thu 07/05/20100% 100%
29 2.2.2.6 Guard Post 35 days Fri 13/03/20 Thu 16/04/20100% 100%
30 2.2.2.7 Temporary Facilities 77 days Fri 21/02/20 Thu 07/05/20100% 100%
31 2.3 Mechanical, Electrical & Instrument 368,2 days
Fri 07/02/20 Tue 09/02/2156% 56%
32 2.3.1 Calculation 91 days Fri 07/02/20 Thu 07/05/20100% 100%
33 2.3.2 Drawing 333,2 days
Fri 13/03/20 Tue 09/02/2143% 43%
34 2.3.2.1 Penstock Area 22 days Fri 13/11/20 Fri 08/01/21 33% 33%
35 2.3.2.2 Powerhouse Area 333,2 days
Fri 13/03/20 Tue 09/02/2144% 44%
36 2.3.2.2.1 Installation Plan 57 days Fri 13/03/20 Wed 20/01/2153% 53%
37 2.3.2.2.2 Turbine Drawing 29,2 daysTue 23/06/20Thu 27/08/20100% 100%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 1 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
38 2.3.2.2.3 Generator Drawing 47 days Fri 24/07/20 Sat 23/01/21 38% 38%
39 2.3.2.2.4 HPU and Valve Drawing 35 days Thu 16/07/20Thu 31/12/2082% 82%
40 2.3.2.2.5 Electrical Drawing 60 days Fri 13/03/20 Tue 09/02/2123% 23%
41 2.3.2.2.6 Main & Auxiliary Transformers Drawing
45 days Fri 25/12/20 Sun 07/02/210% 0%
42 3 PROCUREMENT 535 daysFri 28/02/20 Sun 15/08/2128% 28%
43 3.1 General 290 daysFri 03/07/20 Sun 18/04/2157% 57%
44 3.1.1 Purchasing Sparepart for Turbine and Accessories
273 days Fri 03/07/20 Sun 18/04/2158% 58%
45 3.1.2 General and Supporting Tools 21 days Wed 16/09/20Wed 06/01/2140% 40%
46 3.2 Civil 372,78 days
Fri 28/02/20 Sat 06/03/2125% 25%
47 3.2.1 Steel Structure 351,78 days
Fri 28/02/20 Sat 06/03/2125% 25%
48 3.2.1.1 Power House 29 days Fri 05/02/21 Sat 06/03/21 0% 0%
49 3.2.1.2 Pipe Bridge 1 (Tunnel) 29 days Mon 04/01/21Tue 02/02/210% 0%
50 3.2.1.3 Pipe Bridge 2 (Talang) 29 days Wed 20/01/21Thu 18/02/210% 0%
51 3.2.1.4 Jembatan Jalan Akses 29 days Fri 28/02/20 Fri 25/12/20 99% 99%
52 3.3 Piping 253,2 days
Fri 05/06/20 Sat 13/02/2113% 13%
53 3.3.1 Penstock Pipe 253,2 days
Fri 05/06/20 Sat 13/02/2115% 15%
54 3.3.1.1 Penstock Pipe Batch 1 (Morning Glory 34
- AB
days
1) Fri 25/12/20 Wed 27/01/210% 0%
55 3.3.1.2 Penstock Pipe Batch 2 (AB 1 - AB 5) 34 days Fri 05/06/20 Sat 13/02/21 20% 20%
56 3.3.1.3 Penstock Pipe Batch 3 (AB 5 - AB 11) 34 days Fri 05/06/20 Thu 21/01/2120% 20%
57 3.3.1.4 Penstock Pipe Batch 4 (AB 11 - AB 15) 34 days Fri 05/06/20 Thu 21/01/2120% 20%
58 3.3.2 Penstock Pipe Elbow 21 days Fri 05/06/20 Sun 10/01/2120% 20%
59 3.3.3 Inlet Pipe and accessories 21 days Fri 25/12/20 Thu 14/01/210% 0%
60 3.3.4 Penstock Pipe section Powerhouse 21 days Fri 05/06/20 Mon 11/01/2115% 15%
61 3.3.5 Penstock accessories 21 days Fri 05/06/20 Thu 28/01/217% 7%
62 3.4 Mechanical 358,2 days
Fri 03/07/20 Sat 26/06/2144% 44%
63 3.4.1 Generator - Fabrication and FAT 270 days Fri 03/07/20 Mon 29/03/2165% 65%
64 3.4.2 Generator - Transportation to site 46 days Tue 13/04/21Fri 28/05/21 0% 0%
65 3.4.3 Turbine - Fabrication and FAT 273 days Fri 03/07/20 Thu 01/04/2164% 64%
66 3.4.4 Turbine - Transportation to site 46 days Fri 16/04/21 Mon 31/05/210% 0%
67 3.4.5 HPU & Valve 214 days Tue 04/08/20Sat 26/06/21 17% 17%
68 3.4.6 Hoist Crane 21 days Fri 25/12/20 Thu 14/01/210% 0%
69 3.5 Electrical 234 daysFri 25/12/20 Sun 15/08/210% 0%
70 3.5.1 Electrical Components - Purchasing 188 days Fri 25/12/20 Wed 30/06/210% 0%
71 3.5.2 Electrical Components - Transportation to46site
days Thu 01/07/21Sun 15/08/210% 0%
72 3.5.3 Main and Auxiliary Transformer - Purchasing
116 days Mon 08/02/21Thu 03/06/210% 0%
73 3.5.4 Main and Auxiliary Transformer - Transportation
3 days toFrisite
04/06/21 Sun 06/06/210% 0%
74 3.5.5 Electrical MV - Purchasing 123 days Tue 09/02/21Sat 12/06/21 0% 0%
75 3.5.6 Electrical MV - Transportation 4 days Sat 12/06/21 Wed 16/06/210% 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 2 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
76 3.5.7 Electrical LV - Purchasing 127 days Tue 09/02/21Wed 16/06/210% 0%
77 3.5.8 Electrical LV - Transportation 4 days Wed 16/06/21Sun 20/06/210% 0%
78 3.5.9 Medium Voltage Cable and Accessories 14 days Fri 25/12/20 Thu 07/01/210% 0%
79 3.5.10 Grounding System 25 days Fri 25/12/20 Mon 18/01/210% 0%
80 3.5.11 Lighting System 25 days Fri 25/12/20 Mon 18/01/210% 0%
81 3.5.12 CCTV and Air Conditioning 25 days Fri 25/12/20 Mon 18/01/210% 0%
82 4 CONSTRUCTION 660,5 daysMon 23/12/19 Wed 13/10/2139% 39%
83 4.1 General Works 470 daysMon 23/12/19 Mon 05/04/2182% 82%
84 4.1.1 Temporary Facilities 470 daysMon 23/12/19 Mon 05/04/2182% 82%
85 4.1.1.1 Direction Keet (Owner) 36 days Fri 10/04/20 Wed 13/01/2147% 47%
86 4.1.1.2 Direction Keet (Contractor) 91 days Fri 17/01/20 Thu 16/04/20100% 100%
87 4.1.1.3 Temporary Warehouse 84 days Fri 17/01/20 Thu 09/04/20100% 100%
88 4.1.1.4 Project Safety Fence 34,55 daysFri 28/02/20 Thu 28/05/20100% 100%
89 4.1.1.5 Temporary Site Access 28 days Fri 17/04/20 Thu 14/05/20100% 100%
90 4.1.1.6 Temporary Warehouse 2 14 days Fri 27/03/20 Thu 09/04/20100% 100%
91 4.1.1.7 Mobilization and demobilization 80 wks Mon 23/12/19Mon 05/04/2175% 75%
92 4.1.2 Access Road Area 63 days Fri 28/02/20 Thu 30/04/20100% 100%
93 4.1.2.1 Site Preparations - Access Road Area 63 days Fri 28/02/20 Thu 30/04/20100% 100%
94 4.1.3 Pipe Penstock Area 77 days Fri 14/02/20 Thu 30/04/20100% 100%
95 4.1.3.1 Site Preparations - Pipe Penstock Area77 days Fri 14/02/20 Thu 30/04/20100% 100%
96 4.1.4 Powerhouse Area 7 days Fri 20/03/20 Thu 26/03/20100% 100%
97 4.1.4.1 Site Preparations - Powerhouse Area 7 days Fri 20/03/20 Thu 26/03/20100% 100%
98 4.1.5 Insurance (EAR, Tenaga Kerja) 30 days Fri 13/03/20 Wed 13/01/2134% 34%
99 4.1.6 Report and Documentation 80 wks Mon 23/12/19Tue 16/03/2180% 80%
100 4.2 Civil Works 390 daysFri 24/04/20 Tue 18/05/219% 9%
101 4.2.1 Access Road Area 390 daysFri 24/04/20 Tue 18/05/2129% 29%
102 4.2.1.1 Base + Sub Base 43 days Fri 24/04/20 Tue 20/04/2155% 55%
103 4.2.1.2 Paving + Drainage 36 days Thu 23/07/20Tue 18/05/2122% 22%
104 4.2.1.3 Access Bridge - Foundation 230,06 days
Thu 16/07/20Wed 03/03/21 21% 21%
105 4.2.1.3.1 Soil Work 23,74 daysThu 16/07/20Sat 09/01/21 35% 35%
106 4.2.1.3.2 Structure 82 days Fri 21/08/20 Wed 03/03/2117% 17%
107 4.2.2 Pipe Penstock Area 304 daysFri 01/05/20 Sun 28/02/2114% 14%
108 4.2.2.1 Pipe Penstock - Saddle Construction 304 daysFri 01/05/20 Sun 28/02/2120% 20%
109 4.2.2.1.1 Penstock Pipe Batch 1 (Morning Glory27 -days
AB 1)Fri 25/12/20 Wed 20/01/210% 0%
110 4.2.2.1.2 Penstock Pipe Batch 2 (AB 1 - AB 5) 27 days Fri 01/05/20 Fri 15/01/21 21% 21%
111 4.2.2.1.3 Penstock Pipe Batch 3 (AB 5 - AB 11)27 days Fri 15/05/20 Wed 20/01/2145% 45%
112 4.2.2.1.4 Penstock Pipe Batch 4 (AB 11 - AB 15)
27 days Fri 01/05/20 Sun 28/02/2114% 14%
113 4.2.2.2 Anchor Blok Construction 269 daysFri 05/06/20 Sun 28/02/2119% 19%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 3 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
114 4.2.2.2.1 Penstock Pipe Batch 2 (AB 1 - AB 5) 27 days Fri 05/06/20 Sun 17/01/2114% 14%
115 4.2.2.2.2 Penstock Pipe Batch 3 (AB 5 - AB 11)27 days Fri 05/06/20 Wed 20/01/2130% 30%
116 4.2.2.2.3 Penstock Pipe Batch 4 (AB 11 - AB 15)
27 days Fri 05/06/20 Sun 28/02/2113% 13%
117 4.2.2.3 Tunnel - Pipe Foundation 31 days Mon 05/10/20Wed 04/11/200% 0%
118 4.2.2.4 Penstock Bridge 1 (tunnel outlet) 27 days Fri 25/12/20 Wed 20/01/210% 0%
119 4.2.2.5 Penstock Bridge 2 27 days Fri 05/06/20 Tue 23/02/211% 1%
120 4.2.3 Powerhouse Area 247 daysThu 03/09/20Fri 07/05/21 0% 0%
121 4.2.3.1 Soil Work 28 days Thu 03/09/20Wed 30/09/200% 0%
122 4.2.3.2 Foundation 170,79 days
Thu 03/09/20Sat 20/02/210% 0%
123 4.2.3.2.1 Foundation for Equipment - Turbine28 1 days Thu 03/09/20Wed 30/09/200% 0%
124 4.2.3.2.2 Foundation for Equipment - Turbine31 2 days Wed 20/01/21Sat 20/02/21 0% 0%
125 4.2.3.2.3 Foundation for Powerhouse 27 days Fri 04/09/20 Wed 30/09/200% 0%
126 4.2.3.2.4 Foundation for Guard Post 24 days Mon 07/09/20Wed 30/09/200% 0%
127 4.2.3.3 Building 123 daysMon 05/10/20 Thu 04/02/210% 0%
128 4.2.3.3.1 Powerhouse - Construction 42 days Fri 25/12/20 Thu 04/02/210% 0%
129 4.2.3.3.2 Powerhouse - Architectural and Finishing
42 days Fri 25/12/20 Thu 04/02/210% 0%
130 4.2.3.3.3 Powerhouse - Installation Overhead12 Crane
days Fri 25/12/20 Tue 05/01/210% 0%
131 4.2.3.3.4 Guard Post - Construction 26 days Mon 05/10/20Fri 30/10/20 0% 0%
132 4.2.3.3.5 Guard Post - Arsitektural and Finishing
13 days Fri 25/12/20 Wed 06/01/210% 0%
133 4.2.3.4 Tailrace 84 days Sat 13/02/21Fri 07/05/21 0% 0%
134 4.2.3.4.1 Tailrace Works 84 days Sat 13/02/21 Fri 07/05/21 0% 0%
135 4.2.3.5 Access Road 36 days Sat 13/03/21Sat 17/04/210% 0%
136 4.2.3.5.1 Pavement access road and existing road
36 days
withSat
sirtu
13/03/21 Sat 17/04/21 0% 0%
137 4.2.3.6 Fence and Gate 41 days Fri 05/02/21 Wed 17/03/21 0% 0%
138 4.2.3.6.1 Gate and Fence Installation 36 days Fri 05/02/21 Fri 12/03/21 0% 0%
139 4.2.3.6.2 Drainage 36 days Wed 10/02/21Wed 17/03/210% 0%
140 4.2.4 Station Service (Gardu 7R2) 60 days Fri 25/12/20 Mon 22/02/210% 0%
141 4.3 Piping Works 136 daysThu 28/01/21Sun 13/06/210% 0%
142 4.3.1 Pipe Penstock Area 132 daysThu 28/01/21Wed 09/06/21 0% 0%
143 4.3.1.1 Penstock Pipe batch 1 (Morning Glory 38- AB
days
1) Thu 28/01/21Sun 07/03/210% 0%
144 4.3.1.2 Penstock Pipe Batch 2 (AB 1 - AB 5) 45 days Thu 04/03/21Sun 18/04/210% 0%
145 4.3.1.2.1 Pipe Stringing 24 days Thu 04/03/21Sun 28/03/210% 0%
146 4.3.1.2.2 Pipe Welding and NDT 17 days Thu 18/03/21Sun 04/04/210% 0%
147 4.3.1.2.3 Pipe Coating 21 days Sun 28/03/21Sun 18/04/210% 0%
148 4.3.1.3 Penstock Pipe Batch 3 (AB 5 - AB 11) 41 days Sun 28/03/21Sat 08/05/210% 0%
149 4.3.1.3.1 Pipe Stringing 39 days Sun 28/03/21Thu 06/05/210% 0%
150 4.3.1.3.2 Pipe Welding and NDT 18 days Sun 11/04/21Thu 29/04/210% 0%
151 4.3.1.3.3 Pipe Coating 17 days Wed 21/04/21Sat 08/05/21 0% 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 4 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
152 4.3.1.4 Penstock Pipe Batch 4 (AB 11 - AB 15)42 days Wed 28/04/21 Wed 09/06/210% 0%
153 4.3.1.4.1 Pipe Stringing 22 days Wed 28/04/21Thu 20/05/210% 0%
154 4.3.1.4.2 Pipe Welding and NDT 28 days Wed 05/05/21Wed 02/06/210% 0%
155 4.3.1.4.3 Pipe Coating 21 days Wed 19/05/21Wed 09/06/210% 0%
156 4.3.2 Powerhouse Area 22 days Mon 01/03/21 Mon 22/03/210% 0%
157 4.3.2.1 Pipe Installation 22 days Mon 01/03/21Mon 22/03/210% 0%
158 4.3.3 Hydrostatic Test 4 days Wed 09/06/21Sun 13/06/210% 0%
159 4.4 Mechanical Works 90,73 days
Sun 13/06/21Sat 11/09/210% 0%
160 4.4.1 Powerhouse Area 90,73 days
Sun 13/06/21Sat 11/09/210% 0%
161 4.4.1.1 Turbine Installation 47 days Sun 13/06/21Fri 30/07/21 0% 0%
162 4.4.1.1.1 Spiral Housing & Draftube (Unit 1 &92)days Sun 13/06/21Tue 22/06/210% 0%
163 4.4.1.1.5 Concrete Pouring 10 days Tue 22/06/21Fri 02/07/21 0% 0%
164 4.4.1.1.6 Concrete Drying 28 days Fri 02/07/21 Fri 30/07/21 0% 0%
165 4.4.1.1.2 Turbine Accessories 7 days Tue 22/06/21Tue 29/06/210% 0%
166 4.4.1.1.3 Power Cable & Control 19 days Tue 29/06/21Sun 18/07/210% 0%
167 4.4.1.1.4 Final Installation Turbine Accessories
9 days Sun 18/07/21Tue 27/07/210% 0%
168 4.4.1.2 Generator Installation 77,8 daysSat 26/06/21Sat 11/09/210% 0%
169 4.4.1.2.1 Generator & HPU 5 days Sat 26/06/21 Thu 01/07/210% 0%
170 4.4.1.2.5 Concrete Pouring 5 days Thu 01/07/21Tue 06/07/210% 0%
171 4.4.1.2.6 Concrete Drying 28 days Tue 06/07/21Tue 03/08/210% 0%
172 4.4.1.2.2 Generator Accessories 5 days Thu 01/07/21Tue 06/07/210% 0%
173 4.4.1.2.3 Electric & Instrument 24 days Mon 16/08/21Wed 08/09/210% 0%
174 4.4.1.2.4 Final Installation Generator & Electrical
4 days Wed 08/09/21Sat 11/09/21 0% 0%
175 4.5 Electrical, Instrument and Control Works 215,5 days Fri 05/02/21 Wed 08/09/210% 0%
176 4.5.1 Powerhouse Area 215,5 days
Fri 05/02/21 Wed 08/09/210% 0%
177 4.5.1.1 Cable Pulling 31,5 daysSun 30/05/21Wed 30/06/210% 0%
178 4.5.1.2 Switchgear Installation 10,5 daysThu 01/07/21Sun 11/07/210% 0%
179 4.5.1.3 Main Transformer Installation 10,5 daysTue 13/07/21Fri 23/07/21 0% 0%
180 4.5.1.4 Station Service Trafo Installation 10,5 daysTue 13/07/21Fri 23/07/21 0% 0%
181 4.5.1.5 SKTM Works 30 days Sat 10/07/21 Mon 09/08/210% 0%
182 4.5.1.6 Gardu Tembok Works 30 days Mon 09/08/21Wed 08/09/210% 0%
183 4.5.1.7 Grounding System 10 days Fri 05/02/21 Sun 14/02/210% 0%
184 4.5.1.8 Lighting System 10 days Fri 12/02/21 Sun 21/02/210% 0%
185 4.5.1.9 CCTV 10 days Fri 19/02/21 Sun 28/02/210% 0%
186 4.5.1.10 Air Conditioning 10 days Fri 26/02/21 Sun 07/03/210% 0%
187 4.6 COMMISSIONING and COMPLETION 35,5 daysWed 08/09/21 Wed 13/10/210% 0%
188 4.6.1 General 5 days Wed 08/09/21 Sun 12/09/210% 0%
189 4.6.1.1 Training (Class & Site) 5 days Wed 08/09/21Sun 12/09/210% 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Thu 24/12/20 Page 5 of 6


schedule 201224.mpp
ID WBS Task Name Duration Start Finish % Work
Half 2, 2019 Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021
Complete S N J M M J S N J M M J S N
190 4.6.1.2 Brosure, Catalog, Spare Parts 5 days Wed 08/09/21Sun 12/09/210% 0%
191 4.6.1.3 SOP & Maintenance Procedure 5 days Wed 08/09/21Sun 12/09/210% 0%
192 4.6.1.4 As Build Drawing & MDR 5 days Wed 08/09/21Sun 12/09/210% 0%
193 4.6.1.5 As Build Drawing & MDR (lokal) 5 days Wed 08/09/21Sun 12/09/210% 0%
194 4.6.2 Electrical 7 days Wed 08/09/21 Wed 15/09/21 0% 0%
195 4.6.2.1 Gardu Tembok Test 7 days Wed 08/09/21Wed 15/09/210% 0%
196 4.6.3 Commissioning 27 days Wed 15/09/21 Tue 12/10/210% 0%
197 4.6.3.1 Commissioning & Running Testing 7 days Wed 15/09/21 Wed 22/09/21 0% 0%
198 4.6.3.1.1 Preparation Test 1 day Wed 15/09/21Thu 16/09/210% 0%
199 4.6.3.1.2 No Load Test 1 day Thu 16/09/21Fri 17/09/21 0% 0%
200 4.6.3.1.3 Load Performance Test 40%, 60%, 80%
1 day
and 100%
Thu 16/09/21Fri 17/09/21 0% 0%
201 4.6.3.1.4 Emergency Overload Test 1 day Thu 16/09/21Fri 17/09/21 0% 0%
202 4.6.3.1.5 Stop Rejection Test 1 day Fri 17/09/21 Sat 18/09/21 0% 0%
203 4.6.3.1.6 Over Speed Test For Relay Over Speed
1 day Fri 17/09/21 Sat 18/09/21 0% 0%
204 4.6.3.1.7 Temperature Measurement On Load 1 Test
day Fri 17/09/21 Sat 18/09/21 0% 0%
205 4.6.3.1.8 Start and Automatic Stop Test 1 day Fri 17/09/21 Sat 18/09/21 0% 0%
206 4.6.3.1.9 Vibration And Noise Test 1 day Sat 18/09/21 Sun 19/09/210% 0%
207 4.6.3.1.10 Guide Vane And Generator Output Test
1 day Sat 18/09/21 Sun 19/09/210% 0%
208 4.6.3.1.11 Index Polarity Test 1 day Sat 18/09/21 Sun 19/09/210% 0%
209 4.6.3.1.12 Report 3 days Sun 19/09/21Wed 22/09/210% 0%
210 4.6.3.2 Test Run 21 days Tue 21/09/21Tue 12/10/210% 0%
211 4.6.3.2.1 Performance Test (Non-Stop) 21 days Tue 21/09/21Tue 12/10/210% 0%
212 4.6.4 Final Report & Handover 12 days Fri 01/10/21 Wed 13/10/21 0% 0%
213 4.6.4.1 Closed Out Report 11 days Fri 01/10/21 Tue 12/10/210% 0%
214 4.6.4.2 Hand Over Unit 1 & Unit 2 1 day Tue 12/10/21Wed 13/10/210% 0%

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone

Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline