Bim For Construction Clients
Bim For Construction Clients
sci1
On
31/03/2020
BIM
Building Information Modelling, otherwise known as ϐ Richard writes from a position of great personal
Acting as an authorative guide to Clients, this book: We commend this book to clients of all shapes and
• provides understanding of the strategic client sizes: those with large repeat programmes as well
value of BIM and how it changes the client role as those considering the need for a one-off
• shows via case studies how typical clients are construction project, and all those in industry
experiencing using BIM supply chains – particularly those directly able to
• includes guidance on setting up a project on a influence clients’ decisions. Its lessons will enable
BIM-using basis the industry to deliver better value for money for its
• demonstrates how structured information clients by finally delivering on integration and
enhances the briefing, design, construction and collaboration.
operation stages, supporting better decisions Don Ward, Chief Executive, Constructing Excellence
• contains guidance on where BIM is going next. (incorporating the Construction Clients’ Group)
Richard Saxon
clients to make successful use of BIM. balanced approach on the effort required and the
benefits that are achievable.
BIM for
Construction
Clients
Driving strategic value through
digital information management
Contents
About the author iv
Acknowledgements v
Introduction 1 1
iii
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
iv
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Acknowledgements
This book is the result of a push by the RIBA to increase the architectural profession’s service
levels to clients. I thank Steven Cross, Sarah Busby and Elizabeth Webster of RIBA Publishing
for their guidance throughout the project and also thank Terry Stocks for his supportive
foreword. Mark Bew, chair of the BIM Task Group, gave advice freely, as did Nick Nisbet
of AEC3, Kathryn Bourke of Whole Life and David Churcher of Hitherwood Consulting.
Stephen Hamil at NBS helped me to understand the BIM Toolkit as it emerged. Dale Sinclair
of AECOM, author of the RIBA Plan of Work 2013, has been a key contributor of ideas. Paul
Fletcher of Through helped to frame the forward view beyond BIM Level 2. Alistair Kell of
BDP was a ready source of experience and criticism. Kester Robinson of Deploi BIM Strategies
offered useful comment. Don Ward of Constructing Excellence has been very supportive,
together with his Construction Clients’ Group leaders Gren Tipper and Gary O’Brien, and
group member Karen Allford of the Environment Agency. Constructing Excellence co-badges
the book.
My client story sources, James Pellatt of Great Portland Estates, John Lorimer, formerly of
Manchester City Council, Michael Lytrides and Richard Garfield of Imperial College London
and Brian Spencer, Chloe Obi and Sara Chapman of Bouygues, were all vital contributors.
David Miller of David Miller Architects provided both insight and case study material. Ben
Derbyshire of HTA provided his practice’s BIM Execution Plan model. buildingSMART allowed
reproduction of their Employer’s Information Requirements template. The RIBA Client
Adviser working group, chaired by Tom Jacques, provided a context for the book, developing
approaches to advising clients of their whole-life interests in what they undertake. This book
is a companion volume to client adviser group member Peter Ullathorne’s book, Being an
Effective Construction Client, which covers the full spectrum of client concerns.
Photography credits and thanks go to Dave Parker, Morley von Sternberg, Tim Soar,
Hufton+Crow, Martine Hamilton Knight and David Barbour. BIM image credits and thanks are
owed to AHMM, Rob Charlton and Olly Thomas of BIM Technologies, Ryder Architecture, Billy
Choi of Allies and Morrison, Boswell Mitchell Johnson and MG Partnership, David Miller of
David Miller Architects, Plowman Craven, and Alistair Kell and Martin Davies of BDP. Diagrams
were reproduced with permission from the RIBA, the NBS, Constructing Excellence, Mervyn
Richards, AEC3 and the British Standards Institute. Others were adapted by the author from
sources named.
This book could not have been written without the support and patience of my wife, Anne.
v
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
vi
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
vii
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
16
Fig 1.01:
See Chapter 5.
Manchester Central Library
Introduction
Chapter 1
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
1
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
2
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 1 Introduction
What is BIM?
Instead of clients and members of their team exchanging drawings and reports
which are inevitably prone to ambiguity, incompleteness and error, they can now
share a totally trustworthy, multi-dimensional model of the evolving project in a
‘Common Data Environment (CDE)’, a server which manages access, contributions
and changes, and also supports all communications. The structured, shareable
information in BIM allows contributions to be coordinated easily, greatly reducing
the risk of error and defect. The early design process is accelerated, with potential
for better stakeholder engagement through 3D representation and the simulation
of operation. Technical design is supported far better, with suppliers’ contributions
filling in the model’s detail, element by element. Cost management can get closer
to the design process and avoid late ‘value engineering’. Construction sequences
can be rehearsed, logistics optimised and site communications improved, taking
out risk and time. Finally, the as-built version of the model can provide vastly
superior support to occupiers and facility managers, pulling down the cost of
Operation & Maintenance (O&M) whilst raising the performance of the occupier
and the asset.
3
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
4
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 1 Introduction
place so that there need be no change there at this stage. Draft standards are in
circulation to define best practice.
BIM Level 2 further improves its life-cycle support by including a tool called ‘Soft
Landings’. This was developed for the University of Cambridge in 2004 and adds
consideration of operation and facility management to the initial brief, carrying
this through design, construction and commissioning to early-occupation ‘sea
trials’ to ensure that performance is as intended. A completed ‘Asset Information
Model’ (AIM) will be part of this handover support, converting the project BIM into
O&M terms.
5
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
see fit. There is a learning curve to being an ‘active’ user, as business change
is required in the client’s approach and methodology. The facilities and asset
management functions need to become better connected to project leadership.
The effort required is minor compared to that facing the supply team, but it is
significant. This book is written to assist clients in taking up BIM, or in moving on
from passive to active engagement. It also steers clients towards procuring more
collaborative teams.
Chapter 1 Introduction
Notes
1
The buildingSMART story. The International Alliance for Interoperability (IAI) was formed
in 1994. This society of BIM enthusiasts began creating the Industrial Foundation Classes
(IFC) format, a way in which the elements of buildings can be described in software so that
otherwise incompatible computing platforms can recognise each other’s content. The society
was renamed buildingSMART International in 2005 and continues to develop IFC and related
concepts. Open BIM is defined as IFC based. buildingSMART International is regarded as the
owner of the modern BIM concept and has member chapters in most advanced countries.
2
Government Construction Strategy 2011 and Construction Industry Strategy 2013. The UK
government published its strategy for construction in 2011, following a report called the
Low Carbon Study, which aimed to show what was needed to achieve public policy goals.
Amongst other policies set out was the goal of buying all government projects on a BIM basis
by 2016. In 2013 the government approach was widened into a shared Construction Industry
Strategy, which set targets for performance improvement by 2025, relying significantly on
BIM for achieving them.
3
BIM Task Group www.bimtaskgroup.org. The full set of coordinated BIM Level 2 documents
can be accessed at www.bimlevel2.org
4
Latham, Egan and Wolstenholme Reports. The Latham Report of 1994 came at a time of
deep recession in construction and was commissioned by the Conservative government to
address the major dysfunctions of the industry. It called for a collaborative approach, better
payment practices and better dispute resolution. The 1997 Construction Act introduced many
of the recommendations as law. The Labour government revisited the issues in the Egan
Report of 1998. It put clients in the driving seat to achieve project success and introduced the
concept of ‘lean thinking’, drawn from the motor industry. Use of contractor-led integrated
teams became public policy. The Wolstenholme Report came after renewed recession in 2009
and asked the industry not to waste a good crisis. Implementation of cultural change called
for by Latham and Egan needed to be accelerated.
5
The RIBA Plan of Work 2013 (see Chapter 8).
6
The UK BIM Toolkit 2015 (see Chapter 10) and http://www.thenbs.com/bimtoolkit/
7
Digital Built Britain 2015 (see Chapter 15) and www.digital-built-britain.com
7
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 2
Why clients
should be
using BIM
Fig 2.01:
Mayfield School, Redbridge
See Chapter 7.
8
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
9
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
There are many reasons why clients are – or are not – taking up BIM.
Some have been instructed to do so: central government spending
departments were given five years’ notice of a deadline to put all their
projects on a BIM basis by April 2016. As of mid-2015, several local
governments have taken up the idea in order to be early adopters. Some
universities have done the same. A handful of commercial developers are
actively using BIM to some degree. There are also many contractors using
BIM without client requirement to do so, instructing consultants they hire
to do the same. Similarly, there are many consultants using BIM for their
own advantage; their clients may even be unaware that it is being used
on their work. Over 2,000 BIM projects were thought to be in progress in
2015, valued at over £10bn, excluding the giant Crossrail and HS2 schemes
which are BIM flagships.
The client case for using BIM is that it can create more value. It can
improve the product and service purchased, and it can decrease its cost,
improving client competitiveness. There is as yet no benchmarked list of
benefits and costs: it is too early to identify all the effects, and commercial
confidentiality cloaks the numbers. The business case has to be outlined
qualitatively. It is clearly still persuasive to some leading clients:
10
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
100
90
80
70
60
50
40
30
20
10
0
93% said that BIM
improved quality and
functionality of the design.
Fig 2.02: Client survey shows payback from BIM surveys of US and UK owners (clients) by Dodge Data
and Analytics in 2014 and 20151
11
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
12
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
– to judge the suitability of options offered; early cost and time estimates can
be made with greater accuracy; client decisions will be supported with the
fuller data requested to suit internal needs so that a firm concept choice can
be made.
• At Design Development stage, the buildability of the proposal can be
demonstrated, the cost and carbon content optimised, and a fully coordinated
design can emerge without any risk of clashes between professional
contributions and with less duplicated effort. Efficient use of volume can result
in better net-to-gross numbers. Cost fixed at ‘Decision to Build’ will have
less contingency in it to cover risk. Detailed information to support the client
decision will be automatically validated for consistency and completeness.
The chance of later client mind-changes will have been minimised.
• At Technical Design stage, when the specialist suppliers do their detailed
designs for fabrication, clashes will again be eliminated and off-site
manufacture promoted by the availability of data to drive machine tools.
Selected products will add all their performance data to the model.
• At Site Assembly stage, speed and safety will be enhanced by the
constructors’ use of field BIM tools to rehearse work sequences, brief workers
and answer their request for information; requests back to the professional
team will be minimised. Delivery logistics will be smoother and waste will be
reduced as all delivered components will fit. Use of robots to do dangerous
and intricate work will be encouraged by the data available. Commissioning
will be facilitated by the wealth of information to hand about every element.
• At Handover stage, the absence of defects will be a major by-product of
using BIM; as-built documents will be immediately available in the form of a
model including images of hidden volumes. All the associated O&M data will
be presented in a format which will load easily into facilities management
(FM) software, saving months of toil. Clients will be able to hold a digital
model of the as-built facility as the basis for managed O&M. Claims from
the constructors for extra costs are not to be expected as clients will be far
less likely to have had late changes of mind, nor will teams have suffered
information problems.
13
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
• At Occupation stage the constructors and designers will stay on the job until
the building is through its ‘sea trials’ and delivering the intended performance.
FM costs will show a marked fall as information is immediately to hand to
support planned and reactive maintenance. Finishes, systems and equipment
will last longer. Space planning and other asset management functions will
benefit from the database which can be in the same terms as your corporate
performance and asset data, allowing useful analytics. Feedback will be more
easily captured for use in future projects.
This picture may sound utopian but it is not. The BIM process, fully implemented,
produces complete and trustworthy information – a single source of truth. The
ambiguity, inconsistency and incompleteness of conventional information is what
produced the adversarial work style that we have all suffered so far. ‘Perfect’
information can generate better collaboration across the team, changing the
culture of the industry. It also facilitates better client practice by seeking clear and
more detailed instructions early, and supporting internal decisions better. Projects
speed up and time is money.
14
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
policies which call for low carbon, low waste or more socially conscious working
conditions will be better supported by BIM. The decision support information
which can be provided is beyond previous levels required but pays back fast in
avoided iteration. In general, modern product manufacture is seeing a swing of
costs from making into research and design. Overall costs fall while perceived
value rises. Design and management costs for creating buildings and infrastructure
will not fall as fast as construction and operation costs, as service content will
deepen if value is to be maximised.
Whilst Active BIM clients can expect the full scope of BIM performance returns,
Passive BIM clients will still get some of them. If the lead consultant or contractor
sets information management standards to suit the supply team, then trustworthy
information will result and site efficiency will increase. Some capital cost and time
is likely to be saved and build quality will rise. There will not, however, be much
more support for client decisions nor will there be digital O&M information.
The small or occasional client is the least likely to be convinced to use Active
BIM. But some of these have good reason to make the effort. The Royal Opera
House redevelopment was in the occasional category and would have greatly
benefitted during its life cycle. Museums are in this category too. Work to existing
infrastructure or buildings, including historic ones, is just as viable. BIM tools can
capture the asset into a digital model economically and in accurate detail by using
laser scanning or computerised photography. Every item along a road or railway
track can be scanned rapidly into an inventory.
An Active BIM client will face start-up costs. These are likely to be:
• Setting up of internal systems, including training staff. Clients do not need to
be able to ‘author’ BIM models but they do need to read them with one of
the available softwares and to use the BIM standard for data exchange known
as COBie.2 Internal project processes will probably need reviews to optimise
them for BIM use (see Chapter 3).
• Cost of additional advice at business case and preparation stages, to define
and prepare the project to use BIM, and to appoint a competent team.
15
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
16
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Notes
1
Dodge Data and Analytics: Smart Market Report 2014
and Business Value of BIM Report 2015.
2
COBie. BS 1192-4. 2015 (see Chapter 14).
3
Integrated Project Insurance (see Chapter 15).
4
CIC Protocol (see Chapter 12).
5
PAS 1192-5. 2015, Security-minded BIM.
17
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 3
How BIM
changes the
client role
Fig 3.01:
The Leadenhall Building, City of London, 2014.
85% offsite fabricated, thanks to BIM.
Client, British Land; Architect, RSHP;
Contractor, Laing O’Rourke.
18
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
19
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
When clients use the full BIM Toolkit they will be getting two buildings
for the price (or less) of one: the real building and its digital doppelganger.
The two are important acquisitions and clients need to ask what they want
from each of them. Clients are also potentially shifting their stance from
concentrating on the capital project alone to considering the whole-life
value of the built asset. These changes in approach require readiness in the
client organisation. Readiness comprises having a strategy for using BIM,
a process modified to support it and people trained to work the revised
process. This book will discuss the BIM readiness strategy as if clients
were planning to use Active BIM where they play their full role. Any less
advanced target can be approached by choosing from the actions below.
20
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
AS
SE
TI
E
NF
OR CLIENT D CISIONS
M
MO ATIO AT I O N E X C H A N
DE N ORM GE
L INF
HAN
DOV END S
ER A TAG 11
CCE E 6 AGE
PTE
D 0 S T
END F SET
7 BRIE
1
6 COMMON DATA
ENVIRONMENT 2
5 3
GE 5 END
ND STA 4 CON STAGE
E CEP
T CH 21
OSE
N
E4
END DY TO
TAG
REA
DS
STA BUIL
EN
GE
31
D
Fig 3.02: The BIM process can be plotted against the RIBA Plan of Work 2013 (see Chapter 8)
21
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
22
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Process remodelling
Use of the BIM Toolkit should provide support information at each decision point
in the process. If you build regularly you will have a process in place to progress
each project through gateways. BIM has a recommended process map too,
calling for client go/no-go decisions at four key stages (fig 3.02). The learning
coming from UK government pilot projects is that many clients’ internal processes
do not easily interface with project processes. The client also cannot easily take
the project decisions, as the design team does not necessarily provide ‘decision
support’ information suited to the internal client process: design information is
not all that is needed. The results of both misalignments are costly changes of
mind as the internal process catches up with the project. It is useful to map the
internal process, superimpose the model BIM project process and align the two.
This reveals how internal processes may need to adjust to be ready to take timely
project decisions. UK BIM also incorporates the concept of Soft Landings, adding
facility management needs into the brief and keeping contractor and consultants
on site for a period after occupation to ensure that the building is running as
specified. That process needs to be incorporated as well. A new British Standard,
BS 8536, now defines best practice.2
Process alignment also reveals what information is needed from the team to
support each decision point, the answers to the so-called PLQs. The team will use
that knowledge to structure the data available at each stage. The ideal source of
final handover requirements is the information that is needed to manage property
assets. A fundamental need for the team is to understand how assets perform
for the client organisation. What is the future asset management strategy? What
are the whole-life value and cost profiles? These underlie a credible business case.
The AIM3 should be the eventual target for project information, and the source of
feedback and wisdom about what proves useful to feed into the next project.
23
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Technology infrastructure
As for the technological infrastructure which may be needed to run projects on
BIM, this is evolving fast. The client’s office probably has networked computers
suitable for administrative work and good broadband connections. It will need
software to read the information sent and to add management functions. But
now that organisations can run many applications online without owning the
software, and link to all the players through a Common Data Environment (CDE)
leased for the project, the office may be as well equipped as it needs to be.
Conferencing tools and projection of simulated designs for group experience may
require specially equipped rooms. The supply team, consultants and contractors
have much more taxing hardware needs but these too are reducing as online
services improve.
Investing in people
Readying the client team to use BIM is a major issue, however. There is probably
an enthusiast for BIM in the office and clients do need a BIM champion to focus
the management of change. The design–build team will have an information
manager running the information interaction between the client internal team
and the supply side, as well as coordinating all suppliers’ information flows. But
clients will need an opposite number to them and a management-level sponsor
for the changes needed in project processes and decision-making. Financial
support will be needed in the transition to an operation which can then fund itself
from savings. The internal project management team will also need to document
and validate the processes deemed suitable. The team, including facility and
asset managers, will need educating in the relevant body of knowledge, and
training in use of particular processes. Some clients are employing BIM consultants
to act as mentors through the transition. Just remember that clients do not need
to be able to author BIM documents, only to read the outputs and process them
for internal needs.
24
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Updating procurement
The procurement process will have to evolve to include the BIM factor. Unless it
is planned to use Passive BIM, clients should not begin buying projects with BIM
services until internal changes are in place. That internal work will have produced
an updated Project Execution Plan including:
• Team selection documentation
• Contract requirements
• BIM deliverables required, including the model Employer’s Information
Requirements and the questions (PLQs) which need answering at each stage.
In addition to the normal criteria that the organisation uses to shortlist
consultants and contractors, it will be seeking evidence of collaborative working
and competence in BIM use. It will set minimum requirements for proposed
personnel and their experience and the organisation’s use of aspects of BIM. A
scoring approach has been developed by the Construction Project Information
Committee.4 The quality of the proposed BIM Information Manager, from either
the lead consultant or the contractor, will be particularly important. One vital new
factor is how well the members of the team can work together in a collaborative
BIM environment. Not everyone can collaborate well with others and ‘plug-and-
play’ technically. Does the team come as a ready-made, experienced group?
Just choosing the best of each profession does not guarantee success as a team.
At this stage in the progress of BIM it is recommended to seek the professional
team as a group put forward by the architect, or for design–build procurement to
choose a contractor with their own established design team.
The preferred form of professional appointments and building contract can stay as
they usually are for the use of BIM Level 2. Government users are moving towards
more collaborative forms of contract but this is not essential to success. The CIC
BIM Protocol5 is the straightforward way to add BIM requirements to a standard
contract. Tasks for allocation to all can be derived from the Digital Plan of Work6
which has comprehensive listings of deliverables from each player, including the
Level of Definition7 of the information required at each stage. Fuller detail on all
these follows in Chapters 9, 10 and 11 on Stage 1 of the project process.
25
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Seeking support
Clients should seek to learn from each other as far as possible. Groups such as the
Constructing Excellence Construction Clients’ Group8, the Construction Industry
Council’s BIM Regions9, and the BIM4Clients Network10 are very useful. Sector
groups like AUDE (university clients), BCO and BCSC for commercial clients and
Infrastructure UK for infrastructure clients may have BIM groups within them.
A tailored task
There is no single approach that will suit all clients. A specific plan will be needed
to meet the organisation’s needs, in consultation with advisers. Clients may
not feel ready for all the aspects of good practice at the start of a project but
remember that buildings take a good amount of time to complete and that
ambitions and ability may grow during the work. It is possible to retrofit some
requirements to the plan at handover, by adding more data to the deliverables. It
is not as economic as asking for everything at the start but it is perfectly possible.
All this paints a picture of major effort by the client who wants the best from
BIM. It is modest compared to that required by consultants, contractors and
product makers but it is a one-off effort. It is a shift from an analogue process
to a digital one, bringing more precision and rigour, and lower total costs in the
outcome. Those who have a BIM project under their belt find the next one simpler.
Designers, who have much more to change, report investment recovery after
three projects, with major savings after that point. ¢
26
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Notes
1
Employer’s Information Requirements (EIRs) (see Chapter 9).
2
Soft Landings and BS 8536: 2015 (see Chapter 14).
3
Asset Information Model (AIM) (see Chapter 14).
4
Construction Project Information Committee (CPIC) (see Chapter 11).
5
Construction Industry Council (CIC) Protocol (see Chapter 11).
6
Digital Plan of Work (see Chapter 10).
7
Level of Definition (see Chapter 10).
8
Constructing Excellence Constructing Clients Group www.ccg.constructingexcellence.org.uk
9
BIM Regions www.bimtaskgroup.org/bim-regions-champions/
10
BIM4Clients and other BIM4 communities www.bimtaskgroup.org
27
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 4
The
developer’s
story
Fig 4.01:
240 Blackfriars Road, London,
from across the Thames.
28
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
29
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
One of the first commercial buildings in London to have used BIM was
240 Blackfriars Road, developed by Great Portland Estates (GPE). This
reflective, faceted tower by architects Allford Hall Monahan Morris was
completed in 2014 and much discussed, both as a piece of architecture and
for its novel process. Its client, GPE’s Head of Projects, was James Pellatt,
who first saw BIM being used in 2004 by a Mechanical and Electrical
(M&E) specialist contractor to model an installation at the More London
development, but as ‘lonely BIM’, unconnected to the rest of the team.
In 2006 he was in New York and saw the construction of the new Yankee
Stadium, managed by his then company, Tishman Speyer, which was a
member of buildingSMART and a pioneer of BIM. He was convinced to try
it in the UK, having long experience of the difficulty of coordinating the
designs of the various professions. The catalyst to making the effort was
the 2011 Government Construction Strategy from Paul Morrell, its Chief
Construction Adviser. The government mandate made it likely that BIM
would be taken up widely and GPE was convinced to try it.
In 2011 the state of the depressed UK construction industry was a race to the
bottom. Some clients were seeking lowest possible price and total risk transfer by
single-stage tendering. This drove out innovation and collaboration. GPE wanted
a quality product and knew that collaboration was needed to harness consultants
and trade contractors together. Neither can now fully design a building alone, in
their view. Speed to market also favours early contractor involvement and two-
stage contracting or construction management. GPE began the use of BIM during
what is now RIBA Stage 3, after planning permission and ‘when the jelly had
stopped wobbling’.
There was initial reluctance from the professions to commit to BIM at 240
Blackfriars Road. A parallel working approach was therefore taken, with 2D CAD
drawings as the contractual vehicle but with a model alongside. Extra effort was
required but was funded in the budget by expecting savings in contingencies
and builders’ work detailing. A BIM consultant, BIM Technologies, was hired to
act as Information Manager and coach. The trade contractors were also paid
to model to the standards of the moment (this was before the publication of
30
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Fig 4.02: Geometry of glazed skin Fig 4.04: Precise skin panels
31
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
PAS 1192-2). GPE has been able to confirm that it saved £2.00 for every £1.00
invested, as risk allowances were negotiated out of the contract and savings
were made during the project. In addition, the client estimates that perhaps three
months were saved in avoiding potential delays on site. The building was also
geometrically challenging and the act of modelling meant that the complex crown
of the building could efficiently hold both plant and a stunning occupied space.
Coordination meetings became collaborative as trade contractors could see the
clash problems on screen and solve them without confrontation. The chillers were
installed early as a result of 4D construction study, saving temporary steelwork.
The advantage from planning work better was avoided delay. Time is money in
the hand for a developer.
Quick letting is also crucial to viability. A building with strong visual appeal lets
faster and BIM ensures quality in the fit and finish of elements, plus supporting
unusual geometry. The quality argument helped to convince the architects to
make the effort to use BIM. Quality also extends into the tenant experience. Once
the initial pleasure of occupying a striking building fades, the potential irritations
of living in a sub-optimal place can undermine the developer’s reputation. BIM’s
ability to support better facility management is important here. Whilst COBie was
asked for in the 240 Blackfriars Road brief, it was not used. GPE’s approach to FM
as a landlord needed to develop further to take full advantage.
240 Blackfriars Road finished on time and budget at the start of the economic
recovery, was let before completion and was chosen by one of the main publishers
to the construction industry as its base. They now use the unique volume in the
building crown as their signature space (see cover image).
GPE began with those parts of BIM that it could master. It did not try to
undertake full BIM Level 2 as the government describes it. The response of
the professionals used has been instructive. The M&E engineers now become
more significant and the structural engineers have to satisfy them as well as the
architect. The quantity surveyors were initially aghast at the idea of tendering
on the basis of the federated model, feeling that it would expose all the areas
of incompleteness where claims could arise. This is now the opposite of the
profession’s view, as the model helps to avoid claimable inconsistencies.
32
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
33
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
GPE has gone on to develop all six of its current London projects in BIM. On
one of them it was decided to model all the apartments in the development to
a high level of geometric definition, as the demands of the local authority and
market combined to produce a very complex mix of layouts. In many apartments
it became clear that the ceiling voids would not accommodate one of the
air-conditioning units required, a discovery that would have been disastrously
expensive to solve if it had happened on site.
The lessons from 240 Blackfriars Road have been learned to some degree but
it is clear that the learning curve is long and slow. GPE still does not start using
BIM before Stage 3 and it uses a BIM facilitator firm to support the team rather
than hoping that the architect or contractor can act as Information Manager.
In Pellatt’s view, too much is at stake to have people learn such crucial skills on
the project. GPE does use established BIM players again, but would rather teach
chosen designers to use it than go to process-led firms for design. It has found
it very useful to brief site teams on the next work to be done by using YouTube
videos where the 4D model and video of the site are intercut to show the build
process intended. GPE is confident of on-time completion of complex work and
of avoiding surprises. Its FM approach has developed, with plant and equipment
asset registers produced a year before completion to allow tendering for the
building management FM role and to support commissioning and Soft Landings.
Tenants have been offered FM content to support their role as occupiers but none
have so far shown interest.
One of the six second-generation GPE projects is a refurbishment in London’s
Tech City. Scanning has been used to create the BIM and the vogue for exposed
surfaces means that understanding the bare structural surface is worthwhile.
Scanning will continue to be used to monitor the work.
James Pellatt is pleased that the government will persist with BIM Level 2 and
will march onwards to Level 3. This will keep up the pressure on everyone in the
industry and enable clients like GPE to ask for more. ¢
34
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
35
Chapter 4 The developer’s story
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 5
The local
authority’s
story
Fig 5.01:
Manchester Central Library
36reconstruction, 2014.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
37
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Key to the project was the City of Manchester’s Capital Programme Director, John
Lorimer. A visiting professor at BIM-focused Salford University, Lorimer was awake
to the potential of BIM in 2004. When the head of Ryder – the competition-
winning architect for the library part of the project – asked Lorimer whether they
could use BIM, he immediately said yes. That was in 2010. Ryder comes from
Tyneside, another hub of BIM pioneering, with Northumberland University and the
practice together running the BIM Academy. Newcastle is also the home of the
RIBA’s commercial arm NBS, later to write the BIM Toolkit (see Chapter 10).
Manchester prides itself on its innovative and public-spirited approach. As a
construction client, the city wants to understand and manage risk, rather than
avoiding doing so, as is the practice of so many others. Their ‘Building Schools for
the Future’ (BSF) programme was undertaken with the city retaining construction
risk. Far more risk lies in the delivery of services to the citizens, and in managing
the reputation of Manchester internationally, in their view.
The BIM appointment was ‘on a handshake’, with no formal agreement as
would now be recommended. Manchester City Council and Ryder were keen
to involve the whole professional team. The key to making this exercise work
38
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Original
1 Great Hall
2 Archive
3 Librarian’s Office
4 Open Library
5 Portico
6 Shakespeare Hall
7 Plant Room
8 Theatre Reception/Cafe
9 Theatre
10 Stage
11 Green Room
12 Book Stacks
13 Store
14 Main Office
15 Meeting Room
16 Van Dock
17 Public Lift
18 Goods/Staff Lift
New
1 Great Hall
2 Open Library
3 Meeting Room
4 Retained Book Stacks
5 Portico
6 Shakespeare Hall
7 Plant Room
8 Interpretation/Exhibition Space
9 Exhibition Space
10 Archive Open Access Space
11 Archive Storage
12 Conservation Studio
13 Plant Room
14 Van Dock
15 Riser Shaft
16 Goods/Staff Lift
39
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
before all the current guidance existed was the keenness of the staff of all the
firms involved to make BIM effective. Everyone worked 100%. The team for the
Town Hall part of the project, led by Ian Simpson Architects (as it then was), also
adopted BIM when it saw the progress on the Library.
The first hurdle was to demonstrate to Historic England (as it then was) that
the remodelling could be done sympathetically. A laser survey of the building
produced the initial model and allowed proposals to be shown in 3D (fig. 5.01).
The insertion of a new core on the perimeter was the largest challenge. English
Heritage was persuaded by the manner in which all angles could be studied
and all options compared. The programme was planned to allow an unhurried
consideration of historic issues, accelerating once they were cleared.
The BIM-minded contractor Laing O’Rourke was brought in early on an NEC3
contract and a single project office set up for all contributors. Up to 120 people
were housed together in council space. This approach had worked well for
Manchester’s BSF programme. The City of Manchester and Salford University set
up a jointly funded research programme to study the project in progress and to
capture learning. The government’s BIM Task Group, on which John Lorimer sat,
took advantage of the learning to frame its new tools. The concept of Employer’s
Information Requirements did not properly exist, nor the full allocation of back-to-
back tasks across the team which is now supported by the BIM Toolkit Plan
of Work.
Time and cost savings were substantial as the project progressed. Clash
detection, the most basic advantage of BIM, paid off in the complex geometry
of the Library. 4D studies allowed some temporary works to be avoided and the
contractor believes that nine months was taken out of the project by the ability
to rehearse work sequences. Savings found were shared between the client and
the team on a ‘pain-gain’ basis and this allowed £1.2m to be ploughed back into
quality enhancements by the client; £200k more was retained as savings
on completion.
40
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Fig 5.03: Conserved reading room Fig 5.04: Oculus provides view from new hall to reading room
41
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Construction News recognised that the Manchester City Council and Laing
O’Rourke team achieved the result due to strong vision from the city and close
collaboration and transparent partnership from the range of organisations
involved. Manchester Chamber of Commerce describes the project as helping
to ‘establish Manchester as one of the global leaders in the application of this
technology’.
John Lorimer’s learning from the project, carried forward into his current role at
the BIM Academy, has several messages for clients:
• Are there age or generation barriers to converting people into BIM users?
Some older people are eager but many are unable to rethink their way of
working. Younger people need to be promoted to leadership in BIM projects.
• Clients should not think of every project as a stand-alone issue. Teams need
continuity and supply chains have to mature in order to take full advantage
of BIM.
• FM needs to be brought together with the design and build processes much
earlier so that the FM data requirements can be surfaced and influence the
model content.
• Clients need to be prepared to pitch in and help sort out issues arising from
the team’s attempts to use BIM. There is reduced risk in the project as a
whole, but in these early days the learning curve is there and collective.
• Clients should encourage their professional teams to educate them about
BIM. Contractors and consultants can be too deferential to have a robust
conversation. Equally, projects are not about BIM, they are about client need.
Dialogue needs to be open. ¢
42
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
43
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 6
The
university’s
story
Fig 6.01:
Imperial College London,
Biomedical Engineering Hub
44on the White City Campus.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
45
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
46
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Imperial College
Imperial College London (ICL), a science-based, world-leading institution, is a
good example of an early adopter of the current BIM tools. It started its journey
into BIM use in 2014 and has two projects in progress as learning experiences.
One is a relocation of laboratory facilities within an existing building to be
refurbished, whilst the other is a new Biomedical Engineering building, a major
new-build project at the university’s new 25-acre campus in White City. The
Estates Leadership is determined to base the Imperial approach on the proper
organisation of Estates Management information, and thus of well-considered
Employer’s Information Requirements. The university has established procedures
for project delivery and decided to review these with consultancy help in order to
establish requirements. BIM Technologies was appointed after a selection process
based on terms of reference devised by ICL’s BIM Strategy Group. The Group
attended seminars and liaised with fellow clients in Constructing Excellence, the
best practice organisation.
47
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
48
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
49
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
ICL intends to standardise the softwares used on its projects, for ease of
interoperability between professions and for desired features. A viewing
software is used to allow ICL officers to see the several profession models alone
and together. COBie will be used for data transfer to FM software, rather than
proprietary Autodesk methods.
ICL has an Approved Suppliers List for delivery of its capital projects (up to £10m
in value). The firms involved have been briefed on the planned uptake of BIM Level
2, as they have on all the other plans for updating its estate’s project management
approach and delivery procedures. It is expected that the adoption of a BIM
Level 2 approach will form part of the estate’s team project management policy
framework, which includes:
• stakeholder-focused briefing
• whole-life-based value decisions
• emphasis on thorough feasibility studies
• use of single- or two-stage contract procurement with novation of design
teams to the contractor
• use of the NEC3 form of contract
• risk management processes as part of each contract
• assurance of compliance with ICL standards
• handover of completed assets with detailed record documentation to ensure
the efficient operation and maintenance of assets.
Client responsibilities under the 2015 Construction (Design and Management)
Regulations (CDM) are also currently under review, to ensure that ICL is taking a
leadership role in driving the highest standards of health and safety on its projects.
Following stress-testing on the trial projects and the further development of
its project processes, ICL expects to roll out BIM Level 2 on all its capital projects,
integrated with its FM practices and procedures. The Ministry of Justice concept of
briefing for standard spaces by using a library of room data models also appeals
to ICL. This could support the use of preferred laboratory layouts, model staff
and student accommodation and common rooms. ICL does not seek a standard
50
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
look but wants to meet performance standards. The estate’s team sees itself as
providing the college with world-class assets and facilities to enable it to further
enhance its status as a world-class university.
The laboratory relocation project is based on a laser-scanned surface survey of
both internal and external areas, with additional laser scanning of the services void
where this was possible, backed up with invasive checks on concealed services in
the space intended. Superficial survey is insufficient for this project, where there is
a highly complex services installation.
The design team members for the new Biomedical Engineering building led by
architects Allies and Morrison are all experienced users of BIM, and their skills
and knowledge will ensure the learning goals of the project are well covered.
The project is a 13-storey block plus one basement with a triangular plan to fit
the site geometry. Laboratories lie either side of a spinal corridor with plant in
the point of the triangle and the core in the widest part. Solar shading forms the
elevation’s character, with irregular vertical fins. The rational structure, services
and cladding concepts will be amenable to off-site fabrication facilitated by BIM.
The construction phase will start in 2016. ¢
Notes
1
BIM Planning Guide for Facility Owners, Version 2, June 2013
BIM Project Execution Planning Guide, Version 2, July 2010
Both downloadable at www.bim.psu.edu
51
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 7
The contractor–
client’s story
Fig 7.01:
Mayfield School, Redbridge: briefed,
52designed and built in 17 months.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
53
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
54
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Fig 7.02: The school is built from timber panels, insulated and clad in a rainscreen
55
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Bouygues UK was one of five contractors asked to bid for new buildings to be
added to an existing campus, including changes to several existing buildings
to take it from an 8- to a 12-form entry secondary school. The timetable was
very tight to meet the start of the academic year 2014–15 but the bid process
became protracted, leaving only 17 months to design and build. Use of an existing
planning permission for location and massing was presumed essential to meet the
programme but had many limitations.
Once Bouygues UK had been awarded the project, a new strategy emerged
to use BIM to meet the many challenges. David Miller Architects, experienced
BIM practitioners, were brought in. Laser scanning was used to capture into BIM
the site survey and the details of the retained buildings, including those to be
integrated with the new stock. It was decided to construct the new buildings
in cross-laminated timber (CLT) panels, a lightweight, low-carbon technology
which would avoid piling in the soft ground. With BIM, CLT can be quickly
ordered, fabricated and delivered and the saved time was used to reopen the
school’s brief and revise the planning permission. The original brief had involved
limited engagement with the school staff and was inhibited by expected budget
limitations. Better 3D spatial arrangements were rapidly trialled with the school,
resulting in new preferences for location and layout and a new gym building to
unlock the centre of the site. Revised planning permission was duly obtained in
only seven weeks by a team working in parallel with the production information
team. Procurement of the building began immediately after financial close
was achieved.
The building was laid out to use the panel module of the chosen CLT
manufacturer and the model was used to define each panel, complete with
services’ openings. The structural and services consultants and contractors needed
to meet the production programme to avoid later site alterations. The CLT panels
were cut by numerically controlled tools instructed to follow the architect’s digital
model. They were ‘right first time’. The panels were then delivered in order of
erection so that they could be handled just once, a logistics feat modelled with the
BIM. The superstructure took only 12 weeks to be erected (fig. 7.05).
56
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
57
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Fit-out of the interior began on the lower floors before enclosure of the top.
The furniture, fixtures and equipment requirement have been developed with the
school’s staff, using simulations of views, layouts, materials and colours, creating a
strong sense of ownership of the finished buildings.
The Mayfield School has won several awards as a piece of architecture and for its
exploitation of BIM capabilities. Key points are:
• BIM allowed the user client to understand and contribute to the proposals
and to make confident decisions.
• Laser survey captured existing conditions rapidly and accurately into BIM.
• BIM supported off-site construction of the CLT structure, a safer and greener
choice. BREEAM Excellent status was achieved, with the sequestered carbon
in the structure equivalent to ten years’ operating emissions.
• Nine months were saved from the programme that would have been needed
with conventional design and construction, three before construction and six
on site.
• An as-built model of the building was offered to the school, along with O&M
data arising from the model. Neither were required by the user but showed
the local authority what it could have in future.
58
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
59
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 8
Stage 0:
First steps
Fig 8.01:
Victoria Station, Manchester,
remodelled under a sweeping roof
using BIM, 2015.
60Client, Network Rail; Architect, BDP.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
61
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapters 8 to 14 walk the client through the actions necessary to gain full
advantage from the use of BIM Level 2. If any of these steps seem out of
reach now that is not a reason to hold back. Benefits will still be gained by
partial BIM usage, but less than all those available.
62
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
77 0
0
Handover and close-out 66 1 Preparation and brief
1
8 STAGES
0 1 2 3 4 5 6 7
Key support tasks Including use of BIM, sustainability, health & safety
63
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
64
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
DESIGN
CONSTRUCTION OUTCOMES
PROCESS PUSH
USER PULL
Fig 8.03: Understanding value: The ratios between capital and whole-life costs, and between
design investment and outcome value, are instructive. © Constructing Excellence.
Whole-life considerations
BIM reduces the management gap between capital projects and operational
assets. Conventional practice separates the accounts of those who develop
from those who occupy or operate a facility. Capital targets are often achieved
by pushing costs forward into the operational stage, without much awareness
of the impact. Performance is often degraded below the specified level by
substituting chosen products with poorer ones without that impact being noticed.
BIM supports the integration of life-cycle information in several ways. Cost and
performance data are attached to each element of the design, allowing the impact
of proposed substitutions to be identified and managed. Facility management
needs are identified in the brief and design and delivered by a process called Soft
Landings. This ensures that specification is not dumbed-down unknowingly and
that the building is commissioned and de-bugged fully, with operators trained
to use the building and the immediately available O&M information base which
comes from fully implemented BIM.
65
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
The costs and benefits of considering whole-life value are becoming easier to
study. Cost consultants now have a BIM-compatible suite of guidance documents3
which structure information across the life cycle and which can enable ‘what-if’
exercises for a variety of scenarios. Optimising a proposed asset can be done by
looking at a four-sided process:
1 Optimise the performance of the asset to deliver required outcomes.
2 Minimise the operating cost consistent with 1.
3 Minimise the capital cost to deliver 1 and 2.
4 Consider the best way to hold the asset.4
Procurement paths
The decision to require BIM use as part of the business case implies an outline
decision on how the project will be procured from the construction industry.
Whilst BIM Level 2 does not need an unconventional procurement approach,
experience suggests that the traditional pattern of ‘design–bid–build’ does not
exploit the BIM method fully. The traditional procurement path is that where the
client employs a design team and cost advisers to take the project to a detailed
stage, seeks competitive tenders from contractors on firm information and then
appoints the winner to build the design. BIM benefits from an ‘integrated team’,
where client, consultants and constructors work together from an early stage. This
is so that the design can take advantage of input from constructors and that the
managed information flow can be fully used by all.
Advisers will help the client to decide which variant of procurement to use to
meet project goals. Choices beyond the ‘traditional’ range through forms of
two-stage procurement where the contractor joins the client’s design team after
concept design but earlier than would be traditional, taking the lead once design
and cost are final, to design–build where a contractor is appointed to form and
lead the team from the start. There is also what the USA calls ‘Integrated Project
Delivery’, where the client leads a single team of consultants and a construction
manager from the start. This is quite common practice in the USA but rarely used
yet in the UK.5 Each variant has different attributes from the point of view of client
66
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
risk exposure and design control. All variants can be operated under standard
forms of contract and insurance.
The close of Stage 0 is an information exchange between the Business Case
team and the decision-makers within the client body. In a pattern which will
recur at the end of each stage of the Plan of Work, the information ‘deliverables’
provide the basis for the client’s decision to move on or not. If the decision is
positive, it is to proceed with a project as defined by the Strategic Brief, using BIM
in principle, and on a preferred procurement path. ¢
Notes
1
The concept of the Client Adviser has been defined progressively more clearly since 1994 when it
appeared in the Latham Review (see Chapter 1, Note 4). Advisers are non-executive consultants,
probably on briefing, cost and programme aspects, who help the client to make their business
case for a project, to determine the procurement path and then support the setting up of the
project team. Depending on the procurement path, they may continue to support the client
through the project. The RIBA runs a directory of accredited Client Advisers.
2
PAS 1192-3. See Chapter 14.
3
The RICS has published revised guidance to its members on costing new building projects,
refurbishments and whole-life operation and maintenance. Known as New Rules of
Measurement (NRM) 1, 2 and 3, the guides open up whole-life costing as an everyday technique.
The database to support whole-life cost benchmarking is advancing as a result. NRM’s element
classification structure is now reconciled with architectural classification through Uniclass 2015,
supporting automated costing applications, the ‘fifth dimension’ of BIM.
4
This formula for optimising investment in a project is one devised by EC Harris (now Arcadis),
the built asset consultants. The final point, considering how best to hold the asset, covers the
options to own, rent, build, sell and leaseback or to obtain the facility as a service including
finance and operational management. The choice will be driven by the client’s resources and
financial structure.
5
Integrated Project Delivery (IPD) was defined for use with BIM by the American Institute of
Architects (AIA) in 2008. It is essentially the US ‘Construction Manager’ or ‘Owner Builder’
procurement path where the client retains the project risk and appoints design consultants and
a fee-based construction manager at Stage 1. Specialist contractors can be called in to work with
the consultants earlier than in two-stage forms of procurement and the collaboration workstyle
is supported. It has the advantages of greater speed and flexibility for the client, but requires a
confident client to lead it. IPD does not have a tailored insurance product to suit it in the UK,
nor is there a standard form of agreement to structure a collaborative team.
Both are in development for future forms of BIM working (see Chapter 15). Nevertheless, it has
been used in the UK, notably by Heathrow Airport from Terminal 5 onwards. T5 was one of the
first projects to use BIM at what became defined as Level 2 in 2008.
67
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 9
Stage 1:
Setting out client
requirements
Fig 9.01:
St John Bosco Arts College, Liverpool, 2014.
BIM helped to bring cost per square metre 15%
below benchmark allowing more space.
Client, Liverpool City Council / Neptune / Sigma
68Inpartnerships; Architect, BDP.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
69
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Stage 1 is where most of the new client activities are needed to set up a
project on a BIM basis. This stage essentially consists of appointing the
appropriate team and forming the initial project brief so that concept
design work can begin. Depending on the procurement path selected, the
client can either develop the brief with advisers and then use it to select
the team, or appoint the team to help develop the brief. This account will
be based on developing the brief before team selection.
The term ‘brief’ used to mean the Employer’s Requirements for the function, form,
economy and timescale of the project. Now that requirements for information
structure and management have become a major part of the brief, the term used
is Employer’s Information Requirements (EIRs). These can either stand separately
from the design brief or be combined. Combination is more logical and will be
normal once the BIM process is fully integrated with typical procedure.
Three chapters in this book are devoted to Stage 1. After the preparation of
the Employer’s Information Requirements comes the planning and allocation of
tasks, followed by team appointments. In normal practice these steps are taken
in parallel, ending with the appointment of the team and the development and
agreement of the initial brief.
70
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
PRODUCT PROCESS
ORGANISATION
BRIEF FOR THE NON-DESIGN DECISION
INFORMATION REQUIREMENTS
REQUIRED FACILITY REQUIREMENTS
(OIR)
ASSET INFORMATION
FM BRIEF TO BS 8536 REQUIREMENTS (AIR) PAS 1192-3 GUIDANCE
PROJECT EXECUTION
PLAIN LANGUAGE EMPLOYERS PLAN, PROGRAMME,
QUESTIONS INFORMATION SECURITY POLICY,
REQUIREMENTS TRAINING POLICY, ETC.
(EIR) To PAS 1192-2,3 & 5.
to receive the necessary support information at each decision point and to make
timely decisions that stuck.
The next layer of development is formation of the Asset Information
Requirements (AIRs). If the asset is to be retained and managed, the occupiers,
facility managers and asset managers will need relevant information which can be
loaded into their management systems. On the Product side, they will need the
as-built description of the asset and support in picking up the responsibility for
operation. On the Process side, they will want structured information to enable
analysis and decision support. The Product requirements are met by requesting
facility information to meet BS 8536: 2015, the new standard on defining Facility
Management requirements and Soft Landings service to deliver quality assurance,
support and training. On the Process side, the asset information needs structure,
which can be based on PAS 1192-3 on Asset Information Modelling. This standard
71
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
is the sibling of the core BIM standard, PAS 1192-2, and shows how asset
information can be structured and managed to provide a continuously up-to-date
resource for the owner.
Then we come to the project’s Employer’s Information Requirements. These
combine the relevant requirements from the OIRs and AIRs with further inputs.
On the Product side comes the brief for the physical building, whilst on the Process
side come the requirements for information management. The information
management needs will cover:
• Collaborative working requirements, setting out how team members are
expected to interact.
• Information Exchange points in the project plan and the maturity at which
information should be at each exchange to answer the client’s questions.
• Model management processes and the role of the Information Manager.
• Software formats required (if any), exchange formats and file size limits.
• Training and health and safety needs.
• Security requirements for information.
• Guidance documents which are to be used.
• How team selection will be made, tenders assessed and competencies judged.
The buildingSMART template for Employer’s Information Requirements creation is
provided as Appendix A.
This is a formidable and novel set of statements for a client to prepare and
will almost certainly involve advisers. The client has the choice of retaining the
advisers who supported Stage 0, appointing Stage 1 advisers with BIM expertise
or appointing key members of the project team to prepare their own instructions.
This last approach is perfectly reasonable but precludes the client from selecting
the team based on response to the Employer’s Information Requirements. In a
two-stage approach clients can appoint, say, the architect, information manager,
project manager and cost consultant on a time basis to develop the Employer’s
Information Requirements and their BIM Execution Plan in response, then
negotiate their full appointments based on the defined task (see also Chapter 11).
72
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
73
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
APPROVED
NON-VERIFIED DESIGN
verified design
DATA used in-house
shared with
only professional
project team
teams
INFORMATION
EXCHANGES AUTHORISED
1,2,3,6
Project history
VERIFIED
COORDINATED &
for regulatory
validated output
requirements
for tender or
and knowledge
construction
management
Fig 9.03: Assuring information quality involves moving it from place to place through a controlled process to
BS1192: 2007
74
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Data Environment’ (CDE). This is a server or web-based site that holds all the
project material and allows sharing and authorship in a controlled way. There
are several competing proprietary services which can act as the Common Data
Environment for the project.
Other requirements
The Employer’s Information Requirements will set out client requirements for
health and safety practice, training of staff, use of local labour or any other aspect
where suppliers will be expected to comply. The guidance documents which the
client will expect suppliers to use will also be set out. The whole BIM Toolkit will be
on this list, along with other relevant codes. Finally, if the Employer’s Information
Requirements are produced before the team – or some of its members – is
selected, they will contain the proposed method of selection and of tender
assessment. How supplier BIM competencies will be judged should be set down
(see Chapter 12).
With the Employer’s Information Requirements drafted, the client can move on
to planning the project and allocating roles, and then call for supplier proposals
or formalise appointments already started. ¢
75
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Fig 10.01:
Stage 1:
Planning
the work
77
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
78
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
The NBS BIM Toolkit starts by asking the client to record the facts of the project
and then offers a stage-by-stage format to record the roles to be played, the tasks
to be undertaken and the deliverables expected. Prompts are given, with 21 tasks
suggested for Stage 0, 49 for Stage 1 and 50 for Stage 2. Additional roles, tasks
and deliverables can be entered as necessary for the nature of the project. Only
a few of the tasks are labelled for the client to undertake. The rest are for the
appointed consultants, or before them, the advisers supporting Stages 0 and 1.
The novel thing about describing deliverables in BIM is that they have to be
annotated with the ‘Level of Definition’ expected. This concept has two aspects,
Level of Detail (LOD) and Level of Information (LOI). The LOD is the level of
geometric development, equivalent to the old drawing scale conventions. As
project stages previously advanced, the scale of drawings increased, enabling and
requiring a greater level of detail to be shown. In BIM all models are effectively ‘full
size’ and there needs to be a convention as to what level of detail is appropriate
to support the client’s decisions at each end-of-stage information exchange.
This new convention also tackles a former problem where designers often
overdesigned for a stage and had to rework drawings as later inputs rendered
them outdated. The LOD convention stops that overdesign by describing how
far the model should go at each stage. For example, at Stage 2 a door will only
be shown as a generic object, an opening in a wall with a swing radius. The door
will become a doorset – frame and door together – gradually being modelled
in more detail and then at Stage 5 will become a specified product with all its
manufactured geometry shown.
The LOI concept is similar but relates to the associated data attached to an object
in the model. For a doorset, this will build up stage by stage with performance
specification (e.g. fire performance or acoustic performance) being succeeded by
the data attached to the selected manufacturer’s product. That data eventually
transfers, at Stage 6, into the Facility Management database to help the building
owner operate and maintain the doorset.
79
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
The two aspects of Level of Definition march forward roughly in step. But
separating the two allows for those situations where one goes ahead of the
other. For example, the client may have a list of preferred products or a library of
standard spaces already modelled. These will be imported into the project model
at a level of detail or information ahead of the rest of the model. Also, some
workflow patterns require different levels of definition between professions at a
particular stage.
One feature of the Toolkit is that elements of the design can all be allocated
a classification number which is standard for that element, e.g. the doorset
in question (Sc_25_30_20_25). This is ‘Uniclass 2015’, a reconciliation of the
different codes used across the professions. This reconciled classification concept
allows machines to read the data, permits scheduling of like parts and supports
benchmarking between projects. Costing can operate more rapidly and accurately
than before.
Depending on the procurement path selected, the responsibility matrix for
information production will be planned only as far ahead as practicable. Where
the contractor is not joining the team until or after Stage 3, for example, plans for
Stages 2 and 3 will be made but later stages will await the contractor’s input as
they may wish to use specialist contractor design services differently to the initial
view of the consultants.
80
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
81
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
• The information delivery plans of each specialist in the supply chain, dubbed
their Task Information Delivery Plans.
• Plans for the use of COBie, which can be deployed from the start to carry
briefing information and then accumulate the asset information required.
• The methods and procedures proposed including any volume strategy (where
disciplines are allocated horizontal and vertical volumes in the emerging
design to accommodate their elements, thereby simplifying clash-avoidance),
the geometric origin point for all models, the file and layer naming
conventions and metadata requirements, annotations and attribute data
required, the software and exchange formats proposed.
The BEP will be useful not only to those involved at the start but for those who
enter the project later, typically the main contractor, specialist contractors and
product suppliers. They will need to agree with the BEP or modify it if that is
acceptable. The consultants’ models created in Stages 2 and 3 are progressively
replaced by specialists’ models of their contribution and by product makers’ object
models to form the Stage 5 construction model. Each contributor needs to follow
the BEP precisely, under the guidance of the Information Manager, with the client
agreeing to any digression from the performance and information requirements,
say in order to stay within the capital budget. ¢
82
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Note
1
The NBS BIM Toolkit is available via the NBS website: http://www.thenbs.com/bimtoolkit/
83
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 11
Stage 1:
Appointing
the team and
completing the
initial brief
Fig 11.01:
Point-cloud from scanned survey
of Copperas Hill former Sorting
84Office, Liverpool.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
85
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
There are many variants on these options and choices of contractual form, but
all can deliver BIM-based projects at Level 2. The option to use Integrated Project
Delivery (IPD), the preferred approach for BIM use in the USA, is unlikely to be
selected in the UK at its present level of maturity (see Chapter 8, Note 5).
Depending on the choice of procurement path and the sophistication of the
project, the client can also choose to form the team in one of two ways:
1 From the start: the client chooses professionals to support Stage 0 and Stage 1,
where they help write the terms for their later appointment for the project
as a whole and for the expansion of the team. This approach is suitable for
Traditional and Novation options.
2 Stage-by-stage: the client selects advisers for Stage 0 and for preparing the
Stage 1 Initial Brief, the Project Execution Plan and the Employer’s Information
Requirements. These advisers support the selection of the team to deliver
the project from Stage 2 onwards. This approach suits Design–Build or more
ambitious concepts such as Design–Build–Operate or Design–Build–Finance–
Operate (also known as the Private Finance Initiative, PFI or PF2). It is also
suitable for Traditional or Novation routes where the project requires
design competition.
86
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 11 Stage 1: Appointing the team and completing the initial brief
87
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
the same as being able to use BIM. Facility in BIM develops over several projects
anyway, with at least three projects needed to become familiar with the methods
required and to reap productivity gains.
To help with finding credible partners to form a BIM-using team, it is worth
taking two approaches.
1 Firstly, the project leader could use the questionnaires developed by CPIC,
the Construction Project Information Committee run by the construction
professions. These pro formas2 put rigorous questions to prospective designers
and suppliers to identify the ones who are established users from those with
limited capability. The sort of questions put include:
• Ability to collaborate electronically.
• Understanding of 12 areas of BIM advantage to practice, with evidence of
their use.
• Project experience, with three examples.
• Capability questions to identify needs for training and support. Training
plans may well be necessary to raise capabilities to the required level.
IT capability is also assessed, with subjects covered including:
• Policies on information production and distribution, including formats used
and limits on reuse by others in the team.
• Drawing and CAD management practice, including the proportion of work
in the firm done in BIM.
• Document numbering systems used.
• Experience with web-based collaboration tools.
• Professional Indemnity Insurance limitations on collaboration, if any.
• Policies on project email distribution.
• Policies on staff use of the internet.
• IT infrastructure description.
88
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 11 Stage 1: Appointing the team and completing the initial brief
89
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
90
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 11 Stage 1: Appointing the team and completing the initial brief
91
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
The CIC Protocol also provides clients with confidence that the professional
indemnity insurance market is content to cover firms acting in a BIM Level 2
context as if they were practising in the pre-BIM way, subject only to the provisions
in the CIC Protocol defining liabilities.
Fee agreements
As noted in Chapter 2, the fees required to deliver BIM Level 2 need not be higher
than those for conventional practice where experienced firms are employed and
no external BIM consultant is added. Additional services may be required, for
example Soft Landings. The shape of the fee flow may differ however, with Stages
2 and 3 more intensive than before and Stages 4 and 5 less so. Lower construction
and operating costs should follow from a well-resourced planning and design
period.
92
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 11 Stage 1: Appointing the team and completing the initial brief
Notes
1
NBS National BIM Report.
2
www.cpic.co.uk
3
www.cic.org.uk
4
See Chapter 7 of The BIM Management Handbook, published by RIBA Publishing 2015.
Written by Professor David Mosey, it covers the contractual implications of BIM.
93
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 12
Stages 2 and 3:
Concept
and design
development
Fig 12.01:
Liverpool John Moores University
will occupy the remodelled
Copperas Hill Sorting Office.
94BIM visualisation by Architect BDP.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
95
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
The Concept and Design Development stages cover the period during which the
agreed client brief is turned into an accepted design committed to be built. It is a
hands-on period for the client when the ‘value proposition’ for the project is created.
Where ‘value’ is defined as ‘benefit minus cost’, the design defines both sides of the
equation. Early contractor input to ensure buildability is advisable to minimise risk
and optimise economy. It is also when public approval for the project is obtained,
involving any compromises required for permission to be granted. BIM can play a
powerful role in these stages.
96
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
97
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
until there is general approval. These early renderings are often requested by
clients to communicate with users, funders and planners but should not be
confused with the underlying technical BIM model. The skill of the architect will
make these impressions consonant with the facts of the underlying BIM, but all
remains to be proved in the rest of Stages 2 and 3.
98
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
BENEFIT OF COST OF
CHANGES CHANGES
0 1 2 3 4 5 6
Project strategies
The client brief for the building should contain goals for performance in areas such
as sustainability and operation and maintenance. The design team will need to
offer strategies for meeting these goals, along with other strategies for technical
requirements like fire safety and acoustics. As part of the production of options,
the team will want to illustrate the effects of taking alternative project strategies.
One of the good uses of BIM is to be able to analyse strategies for their virtues
and constraints. For example, some options may use deep-plan approaches to
minimise external wall area and outside noise effects and maximise net-to-gross
floor area. Others may use shallow planforms to gather daylight and fresh air.
Quick analysis is possible with computing tools to show the performance of
options against the goals of the brief and the project strategies.
Satisfying stakeholders
Good BIM practice is to front-load consideration of stakeholder needs so that
changes after the end of Stage 3 can be eliminated if possible. The graph (fig.
12.02) shows the benefits of making changes to improve the scheme decrease
99
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
whilst the costs of change increase as a project progresses. After a certain point
changes cannot be cost-justified. Changes from the client side tend to flow from
late awareness amongst one or more stakeholders of the implications of what is
being offered by the design. This late awareness can be the result of personnel
changes amongst user groups, say the arrival of a new professor in an academic
department. This is a recognised risk in university projects. More usually, the
call for change can arise because stakeholders have not really understood the
design or how it works for them. With the ability of BIM-powered presentation
and simulation of performance, it is easier to be sure that needs are being met
and incorporated in design. One example is the use of room data. In hospitals
it is normal for the complex user brief to be partly expressed in terms of what
is expected in each of the often thousands of rooms required. Room data was
previously logged on drawing sheets with elevations of each wall of a room
indicating the equipment expected and the space around it. With BIM those data
sheets become models, volumes of served space with their furniture, fixtures and
equipment. This principle can be used anywhere. The Ministry of Justice is briefing
for court complexes now with a series of ‘pre-design’ room models of the courts
required with all their contents and performances tagged on. Users can ‘visit’
and approve these room models as a summation of their brief for that space. The
whole building design becomes more legible to them and later change is less likely.
Standardisation
The room model is one example of useful standardisation. Many clients have
standard requirements, for example those of a supermarket chain in laying out a
store. These standards can be stored as BIM element models ready to be imported
into the Stage 2 work. Schools and universities are less likely to use standard
solutions but do have largely standard needs. Element models could be created for
a series of projects using preferred dimensions, layouts and specifications.
A project strategy to use standardisation can be a great economy of effort and time
over a programme of buildings. The final buildings need not look identical or even
have similar massing: that can be site-specific. But procurement and construction
100
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
can be speeded up and economised. This can also extend to using off-site
constructed elements: student housing has greatly exploited off-site construction
of room units for some time. Powered by BIM, this approach is made more rapid
and flexible. Machines to manufacture the modules can be driven by the BIM data.
Contractor involvement
The principle of completing a design that will not be changed after Stage 3
requires that buildability is considered before the end of the Design stage.
The rise of two-stage contracting reflects increasing interest in the practice of
early involvement of the contractor. In the current heated market (2015–16),
contractors prefer not to bid on a lump-sum basis where they cannot optimise
the design to their abilities. Specialist constructors are equally hard to interest
in the riskier single-stage market. This suits BIM users who need constructor
input to confirm and improve the design before handing it over for technical
development and construction. Leading practice is to seek a contractor using the
Stage 2 material so that they can play a consultant role in Stage 3. The contractor
receives a fee for Stage 3 input and develops the cost and time proposal during
the Stage 3 work so that the client can simultaneously sign off the design and
the contract sum at the close of the stage. Contractor input needs to be before
a planning application to have the ability to make significant suggestions to the
team. For example, contractors will often show the high cost of basements and
challenge the team to do without them. They may also propose significant off-site
construction and suggest that the detailed design is for manufacture and assembly
rather than site-based trades. That will affect the character at a detailed level.
The parallel working of designer and contractor teams during Stage 3 gives
a good indication of how well they will work together from Stage 4, whether
novated together or not. Clients can reject the contractor if they do not gel and
seek another. But the collaborative workstyle needed by BIM favours contractors
who can work that way.
101
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
102
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Note
1
BREEAM: the Building Research Establishment Energy Assessment Method. This standard way
of scoring the environmental performance of a design is often used by planning authorities
to call for a performance level above the legal level set by Building Regulations. Clients
often include their required BREEAM level in the brief (e.g. Good, Very Good, Excellent or
Outstanding). Simulations run on the BIM can supplement scores based on identified design
features. In practice, buildings do not often perform fully to their design criteria, for a variety
of reasons (see Chapter 14).
103
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 13
Stages 4, 5 and 6:
Technical design,
construction and
handover
Fig 13.01:
Furniture, fixtures and equipment
104
content of a BIM, visualised in 3D.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
105
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
During its progress through the work stages, BIM’s content changes to suit
the needs of the participants in the stage. Stages 2 and 3 are focused on
the client and consultants, developing the functionality and arrangement
of the building (its geometry) and the specification of performance (data
to be satisfied). Once we move into Stages 4 and 5, the emphasis shifts
to the interests of the contractor and their specialist suppliers. The design
is articulated into packages of work for the different specialists and
those packages are developed into detail for fabrication. The Stage 3 BIM
has most of its detail changed from generic ‘placeholders’ for intended
products to the actual chosen product detail. The consultants, either
novated to the contractor or chosen by them, work with the specialists
to coordinate the packages. This avoids clashes between elements and
maintains the approved design intent. The flow of information from
which to build is complex because of the increased number of players:
cladding specialists, structural frame makers, suppliers of many kinds of
engineering services, etc. The contractor reviews and adjusts the tasks,
and the timing of them, which is allocated to all players in the digital plan
of work. They plan sequences of sitework on the model and manage each
subcontract to keep within the contract sum allocated. The skill mainly
used is called ‘design management’. Clients should be clear that the last
thing that this process needs is interruption from changes caused by client
requests. Change management processes should have been set up but will
ideally remain unused after Stage 3.
106
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Indeed, the best role for the occupier–client during Stages 4 and 5 is to think
about the move into the completed building and all the facility management
and internal change management that will be required. For a property developer
client, the emphasis should move to the letting or selling of the property once
completed. The client team will need to receive regular reports and spring into
action should a problem arise that requires a client response, such as delays or
change to specified material for non-availability. Experience with BIM projects
suggest, however, that the previously typical flow of requests for information from
contractor to consultants falls away almost entirely. The model contains answers
to the coordination questions that typically arise and new drawings are not
requested as they can be taken from the model.
Stages 4 and 5 will usually be run concurrently by the contractor with a flow
of package designs moving in sequence through detail and fabrication onto site
assembly. Building regulations will be processed at Stage 4 and if a contract has
been tendered traditionally it will be during Stage 4.
107
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
108
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
FACILITY
subject of exchange
SPACE COMPONENT
spatial LOCATION EQUIPMENT OCCURRENCES
Since 2011 there have been many further thoughts on the format of handover
data. These cover both the geometric information and the associated data
for operation and maintenance. Clients should discuss with their advisers or
appointed teams at Stage 1 what approach to take. Options include:
• Setting the geometric BIM at a simpler Level of Definition than the Stage
5 fabrication model level used to build, so that facility managers are not
overwhelmed by irrelevant detail.
• Substituting for the ‘drawn’ model one based on scanning2 the finished
building, including inside now-concealed volumes. This shows what was
actually built. All associated data can still be tagged on.
• Using proprietary tablet applications to enable Facility Managers to ‘look
through’ surfaces to see installations and read off required O&M data.
• Loading the chosen CAFM system directly from the BIM using an application
to translate from proprietary platform to proprietary platform.
109
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
The government COBie approach took into consideration the need to avoid
being limited to a proprietary approach such as occurred when office IT became
predominantly Microsoft based. For BIM, the public-sector ideal is to use open
standards allowing all suppliers to compete. These open standards are based on
the IFC concept3 which allows softwares to interoperate. COBie uses the IFC data
structure. The UK BIM market for buildings is however dominated by one supplier,
Autodesk, although other platforms compete for the infrastructure market.
The threat of proprietary lock-in is therefore substantial and many clients are
pragmatically using that approach to obtaining their data transfer to CAFM.
COBie as verifier
COBie can, however, do much more than act as a data transfer medium. Because
it is a digital repository of shareable, structured information it can be used to
check the completeness and accuracy of the data within it. It has always been
laborious and unreliable to check documents manually to see that the required
information is present in the handover material. COBie allows automatic checking.
It will flag missing, inaccurate or incomplete fields in its matrix and help ensure
completeness. COBie and IFC data structure allows checking in other contexts
too. For over a decade Singapore has processed planning and building regulations
submissions made in IFC BIM format on a computer-to-computer basis. Work has
started on a UK building regulations checking system on a similar basis.
Specific handover requirements can be met precisely with tailored COBie
processing – for example, the balance of content in geometry and data shifts
through the levels of definition until data dominates at handover. The geometric
information can be edited down at handover to that relevant to O&M. The
database of O&M information can also be edited, to be in full or limited to links
to the databases and websites of the suppliers of each item. The ‘link’ approach
lightens the storage and processing load and also avoids obsolescence of
information. But link addresses can shift over time and must be scanned regularly
to keep them live.
COBie checks can be run at each information exchange as the data build up
through required levels of definition. The key check however is the final Stage 6
110
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
handover package. Successful COBie compilation and transfer into the client
CAFM system saves months or even years of post-handover work by client facility
managers to transfer all the information required to operate and maintain the
building successfully. Roomfuls of ring-binders from the contractor are replaced by
a laptop interface. The Soft Landings team is also able to use and prove the CAFM
system to support its ‘sea trials’ and to sort out any issues that arise in use.
The project data has up to this point been held in the Common Data Environment
(CDE) provided by the appointed Information Manager. At handover of the
deliverables it may be sensible to take the data into client keeping. As several
parties may need access for FM, Asset Management or remodelling work, it may be
sensible to set up another Common Data Environment under client control.
Completing Stage 6
The Soft Landings process, including commissioning the CAFM system, runs from
Stage 6 into Stage 7. Close out of Stage 6 is the settling of the final account of the
capital project. Forms of contract best suited to BIM support a rapid resolution of
all issues which can affect the final account. They should have been surfaced and
settled as they arose. ¢
Notes
1
COBie is a compression of ‘from Construction into Operation of Buildings: information exchange’.
The standard was devised by the US Army to meet its need to digitise facility information and is
used across the US Government estate. UK COBie was formalised in BS1192-4:2014 to work with
the UK BIM Toolkit. A version for infrastructure use has also been created.
2
Scanning: two technologies have emerged for capturing existing assets into digital form. Laser
scanning uses light like a radar beam to identify a ‘point cloud’ of millions of measurements which
can then be drawn up as a BIM. Computerised photography uses digital camera images integrated
to form a 3D view of reality. This is both a model and a picture. These methods have transformed
surveying and allow completed work to be checked against the design BIM as well as recorded for
O&M purposes.
3
IFC stands for ‘Industrial Foundation Classes’. This term covers the common description of building
elements in design software platforms so that elements are recognised when read by another IFC-
using software platform. So a door remains a door with all its characteristics when two otherwise
incompatible platforms are exchanging information. Platform-neutral operation is very helpful to
supply chains as they have invested in a variety of trade-specific softwares to support their work.
Transferring from one to another before IFC meant re-entering information, with all the cost and
risk of error involved. The IFC vocabulary is still being extended to meet all requirements, together
with its associated dictionary of terms. Full interoperability of IFC-based softwares is one of the
requirements of moving to the next level of BIM (see Chapter 15).
111
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 14
Stage 7:
Living and
learning
Fig 14.01:
Alder Hey Children’s Hospital, Liverpool,
2015, used BIM for design, build and
operational support.
Client, Alder Hey Children’s NHS
112
Foundation Trust; Architect, BDP.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
113
Chapter 2 Why Clients should be using BIM
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Stage 7 was added to the RIBA Plan of Work in 2013 to recognise a major
change in the concept of asset creation, facilitated by the arrival of BIM.
Previously, clients had treated the operational life of the building as a
separate matter from the capital construction. The design and build team
was retired after handover and completion of the defects liability period.
Information on paper about the built artefact was requested but was
frequently slow to arrive and expensive to use. Facility managers had their
own tools to help them operate and maintain the asset. They were not
often asked to report on actual performance against planned performance
and hardly ever on the effectiveness of the asset in comparison to the
business case that justified the project. Objective in-use assessment (or
Post-Occupancy Evaluation) was rare.
The new model changes the linear model of a project into the circular form
of an asset life cycle. Stage 7 represents the in-use period which is likely to be
many times the length of the capital phase and to cost more. Costs arise from
consumables, utilities, operational staffing and maintenance and replacement of
elements. Within the life cycle are several sub-cycles of renewal:
114
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
O&M information
in BIM connects
Cost reduction System integration
designer, builder,
• O&M information ready at building owner • BIM data integrated with
handover and occupier Computer-Aided Facility
• lower FM set-up costs Management
• speedier data retrieval • BIM data integrated with
Building Management
• reduced visits to address System
issues.
Performance enhancement • BIM data integrated with
Enterprise Resource
Accessible O&M data supports: Planning
• better preventive maintenance • continuously updated
• fewer breakdowns database.
• faster problem resolution
• longer system life
• more satisfied customers.
Considerable benefits can be gained from the use of the AIM, the post-handover
description of BIM, in facility and asset management (fig. 14.02):
• The O&M information arrives complete and available, cutting the time and
cost of setting up CAFM (Computer Aided Facility Management) and CMM
(Computerised Maintenance Management) systems.
• The information can be integrated with the Building Management System
(BMS), increasing control and improving reporting.
• The enhanced ability to manage and maintain the asset preventatively increases
user satisfaction through improved environment and avoided breakdowns,
reduces utility consumption and carbon emission and prolongs the life of
equipment and systems by up to 50%. The sustainability score is high.
• Finally, all the data can be integrated with the client’s Enterprise Resource
Planning (ERP) process, allowing business management to oversee the use and
costs of the facility.
115
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
116
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
those who created the model (see Chapter 12) allow the client to use the data for
normal purposes but exclude liability on the original team for any changes made
after handover. Good practice in managing the AIM is set out in PAS 1192-3.
Core requirements are:
• An authorised person to approve all information issued and received.
• Currency of all information to be maintained, either by automatic
synchronisation or periodic review.
• Appropriate roles to be allocated for all information handling.
• Removal and archiving of all obsolete information.
• Provision of full security, including back-up and recovery.
Performance reporting
This should be a normal part of the duties given to the Facility Managers.
Operating costs, emissions and utility usage should be tracked closely, with
departures from predicted levels investigated to reveal why. It may be that the
building’s use is not in accordance with the design assumptions: more hours
of use may be accruing and plug loads for IT and research tools may be higher
than expected. Some of the outlier results will point to issues to be addressed,
such as air leakage beyond tolerance, water wastage, over-lighting at night for
cleaners, under-utilisation of space and poor security practice. Reports should
enable continuous improvement in performance and the setting of higher targets.
They should also be a source of learning for future buildings or improvement
to the building in question and to the behaviour of occupiers. Is there over- or
under-design, over- or under-use, excessive maintenance cost due to incorrect or
reduced specification, unreliability? A recent university building proved to have
an inadequate front door design for the exposure on site: the disabled-friendly
double-door lobby was too often wide open to the elements as student groups
came and went, with resulting waste and discomfort. Replacement with a
revolving door proved essential and will be the expected solution in future projects
on such sites.
117
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Space management
Conventionally, space management is achieved by loading 2D plans of the
building into a free-standing programme for allocating and recording use of
space. With AIM such a function can be achieved running as an application on the
AIM. Floor space geometry is available, of course, but so are all other attributes
which affect the capacity and capability of the spaces. Integrated with the Building
Management System (BMS), the space-planning function can be used to allocate
rooms and ensure that relevant services are available to users.
In multi-tenanted commercial space, the marketing of space to tenants is like
the briefing and design stages of new building creation. Illustrative occupational
patterns may be needed to show tenants how a space could serve their needs.
The ability to generate 3D imagery, walk-throughs and virtual reality experiences
is a prime virtue of the AIM. Structural and servicing capabilities can also be
displayed and modified if necessary.
Asset management
Integration of the AIM into client organisational management systems is
possible and desirable. Figure 14.03 shows how the AIM can relate to other
asset management processes. A facility is there to support an activity. It is also a
financial asset with exchange value and liability attached. In both these senses it
is an asset to be managed. Corporate real estate functions in major companies
consider all stock available and work to make best use of it. They acquire when
new locations or space is needed, move occupants when sensible and dispose of
when space is no longer necessary, appropriate or economic. Data from buildings
in use is essential to knowing how well assets are performing. It also supports
valuation if selling an asset or receiving offers for it. A combination of the AIM
and the BMS will provide the necessary data. The feedback of performance data
is thus equally useful to an owner–occupier and an investor in revealing what
works and what does not and how business cases are fulfilled or not. The Asset
Information Requirements identified will form the basis of Employer’s Information
Requirements in any future project.
118
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
EXTERNAL PIMs
New asset
acquisition,
major works
LINKED ENTERPRISE
OUTSOURCED SYSTEMS
ASSET ASSET INFO ASSET
INFORMATION Maintenance INFORMATION Finance.
REQUIREMENTS management MODEL
Property database.
(AIR) systems (AIM)
supervisory control
& data acquisition
DIRECT INPUT e.g. BMS
Minor works,
surveys,
performance
evaluation
. 1: The Asset Management Policy, Strategy and Plan should comply with the requirements of PAS 55-1
Note
(update to ISO 55000 when published).
Note 2: The Asset Management Plan should define the event triggers that lead to local supplier direct input to
the AIM.
Note 3: The Asset Management Plan, with references to the Asset Management Strategy, should define the event
triggers that lead to external PIMs arising from new asset acquisition or major works on an existing project.
Note 4: Activities such as governance, data quality, monitoring of provision and usage of asset information are
implied in Figure 14.03 but not shown in detail.
Note 5: Where the OIR results in a new project within the scope of PAS 1192-2 then the relevant AIR shown here
becomes part of the Employer’s Information Requirements for that project.
Fig 14.03: High-level asset information process map: PAS 1192-3 2014
119
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
In-Use Evaluation
Often called Post-Occupancy Evaluation, because if carried out after occupants
had left, the concept of evaluating the success of a new building is more talked
about than carried out. Officially it is government policy to close the file on a
project by comparing its original business plan to the outcome after two years.
Occupants are rarely those who made the plan. Those involved in the project,
both client and design/build team, tend to ignore the need for evaluation in case
it shows them in a bad light. This is a well-founded concern, as the majority of
buildings do not deliver as much as they were planned to deliver. The concept
of ‘Display Energy Certificates’ in the lobby to show what a building is using
compared to its designed performance was dropped by the government in 2014,
as likely to be embarrassing rather than motivating. Awards may have been won
and testimonials may glow but environmental performance and operating costs
are rarely on target and often widely out. The comfort and usefulness of the
space for its purpose may also be compromised in some way. One of the reasons
for underperformance is the lack of learning from in-use evaluation. Projects
are briefed, designed, built, commissioned and operated without sufficient
understanding of how performance is actually delivered and why potential is often
lost at each step as the project progresses. Teams may normally be evaluated on
their success in meeting budget and time goals at project handover but the in-use
evaluation, done at least two years into the occupancy period, needs to become
normal too, probably by making it ‘no-blame’2.
Good practice is to have the evaluation done by a team not involved in the
delivery. This ensures objectivity. The evaluators need access to the business case
as well as to operational records and occupiers’ opinions. Their report, a formal
Information Exchange, needs to be in the public domain in some way so that all
can learn. Anonymised reporting, such as that by the CarbonBuzz programme3 is a
step in the right direction. Periodic evaluations are expected over the building’s life
cycle. One aim is to collect data on the out-turn whole-life cost of specifications
used. Was good value achieved? Did replacement come when expected?
120
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
The hope of the BIM ‘movement’ is that tomorrow’s buildings will be better
because they will be based on better data, designed more economically for
‘whole-life’, built to higher standards and well operated with the support of
the information model. ¢
Notes
1
BIM for Facilities Managers, edited by Paul Teicholz for the International Facility Management
Association, published by Wiley, 2013.
2
No-blame feedback processes are used, for example, by the British Army to ensure full and frank
disclosure of all outcomes and actions, without which vital lessons will not be learned. No record
of individual contributions is made.
3
CarbonBuzz is a programme at University College London (UCL) to capture actual performance
data from buildings in use, holding it without attribution so that contributions are encouraged
and benchmarking is supported (www.carbonbuzz.org).
121
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Chapter 15
What comes
next for BIM?
Fig 15.01:
Fulton Center metro station, NYC, 2015
Client, New York City Transit and Arup.
Architect: Grimshaw and James Carpenter
Design. The project used many advanced IT
122
applications.
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
123
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
124
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
INTERNET
OF
THINGS
SMART
GRID DECARB
‘power by GRID
the hour’ DIGITAL smart
(servitisation) BUILT buildings
BRITAIN and cities
FABRIC ALL
ELECTRIC
RENEWABLES
whole-life
value incl.
well-being Value SUST
circular NEW
economy MATERIALS
social
insured
media BEHAVIOURAL
outcomes SOFT ICT
&A ECONOMICS
LANDINGS
3d
dPOW printing
collaboration
tools and
contracts
125
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
There is a national strategy for construction, agreed between the industry and
government in 20131 and with a target for transformation by 2025. Amongst many
issues tackled, the strategy aims to raise headline performance:
• 33% reduction in capital and operating cost.
• 50% reduction in project timescales.
• 50% reduction in carbon emissions.
• A switch from expecting ‘outputs’ toward ‘outcomes’, the resultant impact on
stakeholders.
This ‘Better, Faster, Cheaper’ mantra contrasts with the long-term trend of rising
costs, timescales and energy use. The strategy recognises that the use of digital tools
will be one of the main ways in which its goals will be met. These tools include BIM,
at progressively higher levels, but also many other technologies.
126
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
The interaction of these innovations is explored in a 2015 paper from the BIM
Task Group, ‘Digital Built Britain’.3 It sets down the likely next phases of evolution
of digital built environment and plans made to achieve them in the UK. It sees a
series of steps forward:
• Incremental improvements to BIM Level 2 use, towards Level 3.
• Maturation of related digital technologies, complementary to and competing
with BIM.
• Emergence of new business models for the supply of built environment.
Improving BIM
By early 2015 BIM had most of its Toolkit for Level 2 working but lacked the
important Digital Plan of Work (see Chapter 10) and an all-through classification
system for machine-reading of elements in models. Those tools arrived in
mid-2015 but will take time to bed down and affect practice. There is also a
continuous stream of improvements offered by the software industry to make
BIM Level 2 flow more easily. Common Data Environment tools will offer more
support to work flow. Decision support tools will help clients take better stage-end
decisions. Good practice in BIM will become widely shared as client and supplier
experience is gained, succeeding to the somewhat academic initial codes
of practice.
E-Briefing is a new concept, where clients for buildings to house high-technology
processes are able to populate their brief to suppliers with ‘chips’ of data about
elements to be incorporated from the start, to form a basis for testable solutions
and provision of automatically validated data.4 E-Regulation is being developed
for the UK, on the model long used in Singapore. This will allow designers to
test their models against building regulations, health and safety rules, licensing
requirements and potentially even town planning regulations where these are
based on pre-planned or permitted development. Automated checking and
approval would result, freeing inspectors to concentrate on site-based checking
that permitted design is actually executed.
127
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Changes to contractual practice are in the pipeline. The major trial in progress
is of procurement based on Integrated Project Insurance (IPI).5 Current practice
dictates that all parties to a client’s contracts are separately insured against claims
of error. This creates a situation where, when a problem arises, all team members
are forced to retreat to their corners to protect their position and where four-fifths
of insurance premiums are spent to defend claims, with only a fifth going to solve
the client’s problem. Clients also have to prove professionals have been negligent
to succeed in a claim – a major hurdle. With IPI, the client takes out a single policy
to ensure that the project will be finished on time and budget and remain defect-
free for 12 years. No negligence need be proved. The team members are at risk for
the first increment of any claim, but collectively. They have an agreement between
them on how they will share risk, and reward if they outperform. Collaboration is
rewarded and more stable design-build teams are likely to form.
The IPI concept, when proven, should allow risk-averse clients to get the
collaborative benefits previously only available to confident, risk-retaining clients.
It will also allow future forms of BIM to be used, where the team shares a common
model and individual liability cannot be easily identified.
The concept of BIM Level 3 will arrive once the set of tools to enable full
interoperability across diverse platforms is mature. Several years of work lie
ahead to write all the elements still required, given the levels of funding available.
When mature, BIM Level 3 will allow a shared, multi-user project or asset model
with continuous synchronisation of worldwide inputs, held in the Cloud for ease
of access.
Smart technologies
While BIM is over 20 years old and developed slowly at first, smart technologies
are more recent but developing rapidly. ‘Smart’ in this context means technologies
based on sensors, analytics and actuators to provide a level of artificial intelligence.
Internet and mobile phone technologies have empowered this approach and
reduced its cost dramatically. Telemetry, which could only be afforded to monitor
128
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
jet engines, is now able to be included in a fitness wristband. Data pouring from
the accelerometers in mobile phones can reveal the location of potholes in roads.
We are looking at buildings becoming ‘connected’ as people now seek to be.
Sensors are becoming small and cheap, communicating via the internet and
often powered by ambient movements. The performance of all systems and the
occupancy and comfort of occupants can now be captured as streaming data.
Big Data analytics in the Cloud can derive correlations which can inform facility
management and future design and installation. Self-operating building systems
are nearer than the self-driving car, raising the potential smartness of building
management systems from ‘not very’ to ‘extremely’. A lot of this technology can
be retrofitted so that it is not just for new buildings.
Social media has a role to play. Building occupants interact with the building in
currently unrecorded ways and their habits in energy use are a factor in the gap
observed between planned and actual performance. Social Physics6, recording
the group dynamics of occupants, could nudge them towards better behaviours
but also provide insight into Behavioural Economics and how design influences
people.
The motive power for buildings is likely to become solely electric with many
buildings connected to a smart grid which can use surplus renewables and supply
decarbonised grid power. Much less heat will be needed and carbon emissions
from remaining fuel-burning will be better captured at power-station level. Local
renewables are naturally lower voltage and direct current so buildings may well
store and use such power for building systems and plug loads.
High-performance computing is the mainstay of industrial design. Prototypes
are created virtually and tested in ways that previously required real-world
prototyping. Many options can be created to find optimum characteristics, far
more than human patience could explore. This capability will migrate into building
design. There will also be applications (apps) in abundance to handle design
issues such as behaviour in fire, disabled access, search for ideal products or value
engineering to find potential savings.
129
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
130
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
down to what it should be seeing. ‘It helps when you see a red light to know that
you are approaching a stop light,’ said a Google engineer to the New York Times.
BIM will play the role of the map in the digital built environment. Sensor-based
data will interact with the BIM data to provide comprehensive diagnostic and
control responses. BIM will be driving the design and fabrication of buildings and
infrastructure but sharing their operation with other technologies.
Clients should look forward to a construction industry that really does become
client-focused, and can deliver value to increasingly demanding organisations.
Clients can also expect the whole-life cost of building to fall, in line with costs in all
other industries. Quality of life will increase as the built environment actively cares
for its users and produces a superior outcome, surprising on the upside rather
than disappointing. As the world’s urban population stands to double in the next
35 years, it will be a matter of survival for the built environment to be made and
run far better. Thanks to BIM and related technologies, this is looking possible. ¢
Notes
1
Construction Industry Strategy (see link in Note 2, Chapter 1).
2
www.nationalplatform.org.uk
3
www.digital-built-britain.com
4
E-briefing (see www.brydenwood.co.uk)
5
IPI: www.griffithsandarmour.com/Integrated-Project-Insurance.aspx
6
Social Physics, by Alex Pentland, published by Scribe 2014.
131
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
132
APPENDIX A
Employer’s Information
Requirements Template
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
Employer’s
Design/Construction/Operation and Supply Team
Information Requirements
Template
EIR Template by buildingSMART UKI is licensed under a
Creative Commons Attribution‐NoDerivatives 4.0 International License.
This template is intended to aid the documentation of the “Information Requirements” for the
Employer and others acting as information customers in a design and supply team. An Information
Requirements document can help inform the design and supply team as to what information is
required, together with its format and extents, along with sufficient context to support their
professional judgment and assessment.
The twin objectives of an EIR are to support the acquisition of asset and product information by client
and customer and to support the supply chain to respond with advice, execution plans and delivery.
An EIR is (as defined in BS PAS 1192 part 2) a “pre‐tender document setting out the information to be
delivered [to the customer], and the standards and processes to be adopted by the supplier as part of
the project delivery process”. It offers “document setting out the information to be delivered by the
supplier as part of the project delivery process to the employer.” It may be referenced in the Contract
through directly or through a ‘BIM Protocol’
This template does not proscribe the supplier’s internal arrangements or responsibilities in the supply
team, nor proscribe training and competence assessments that the supplier may wish to offer in
support of the BEP supplied.
Some organisations may have a standing Organisational or Asset Information Requirement (as
defined in BS PAS 1192 part 3) which may follow this template, so that only the specifics in Section1
vary across projects. Section 2 may implement ISO 55000, SFG20 and BS8536.
An EIR should:
cascade down the supply chain so as to be effective
be generic, concise, clear and unambiguous
provide for common naming and classification of documents and assets to aid searches
document the customers and any received policies s as to achieve consistency
clarify customer involvement and checks that are required
indicate the customers purposes for the information so as engage with the supply chain
indicate acceptable formats to reduce data loss
should help define completeness by discipline and stage and purpose
© 2015 buildingSMART UKI Page 1 .
133
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Guidance
In many of the topics below, the Employer is asked to choose between using named industry
standards, taking other advice from their design and supply team or providing their own policy. The
Employer should expect to receive back a detailed response showing how the requirements are met
in the suppliers BIM Execution Plan (BEP). The outline strategy as to how these will be delivered
should be within the Pre‐Contract BEP and further clarity in the post contract BEP. Wherever possible
International, European and UK standards should be chosen in preference to the advice of the design
and supply team, or specific requirements.
Adopting named industry standards: The nominated standard or policy is to be used. These
standards are intended to be familiar and efficient. The first (unstared) option encapsulates
the requirements for the delivery of UK Governments Level 2 BIM.
* As advised by the design and supply team in their Execution Plan provided in response to
this Information Requirement. The employer/customer has no opinion, but the design and
supply team choice should be explained and documented in the Execution Plan.
** As listed/described/referenced: The employer/customer has a specific view on this which
is then described or listed. Using the employers own custom lists or policies may incur
additional costs, delay and risks in the information delivery over and above industry best
practice.
Requested names and codes should be concise, contain no punctuation or spaces, and kept short as
they may be used in file names.
Requested descriptions can be longer but should not contain abbreviations, commas, or colons or
special characters.
© 2015 buildingSMART UKI Page 2 .
134
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
Section 1: Facility/product, site and project information : Is there any specific information?
Specific information and requirements that are specified by the Employer and primarily affect the
next tier of the design and supply team.
Identification: What is the facility/product, site and project?
The preferred names for the facility/product, site and project will be used to ensure that all
documents and information carry the expected identifying names, typically a code or number. There
can also be a longer description for each. For the site, this longer description should be the address.
Otherwise the design and supply team will choose these.
The facility (either a building or piece of infrastructure) or product that is, or will become, your asset.
Facility: Name, Description
The site gives the relevant surrounding context, and is usually of limited extent.
Site: Name, Address and postcode
The project defines the commercial context, and is usually of limited duration.
Project: Name, Description
Pre‐Existing Strategies: Are there any already known volume, phasing or discipline strategies?
You may already have some knowledge of how the project, site or facility is to be broken down. Are
there any known volumetric divisions of the site, or any known setting out requirements? This could
be in the south west corner of the site and may be related to the Ordnance Survey Grid, or another
other geospatial system in use. Otherwise a common site datum setting out point benchmark for the
site will be defined and used consistently by the design and supply team.
Volume strategy: As advised* / As listed**:
Employer’s volumes list: name, description, (extents or disciplines)
Common building origin and orientation: grid point, grid line
Common site origin and orientation: named point and north direction
Geospatial : OS / geospatial reference / as advised
Are there any known names of required phasing divisions of the project, or any known working
calendar information? An example might be a regeneration project needing ‘decant’, ‘demolish’,
‘build’. Otherwise the team will use best practice.
Phasing strategy: As advised* / As listed**:
Employer’s list of name, description, (dates/months/weeks)
© 2015 buildingSMART UKI Page 3 .
135
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Common calendar and week numbering : ISO 8601 /As advised/As listed:
Employer’s calendar pattern
Are there any known named project work‐package or discipline divisions of the project? An example
might be the distinction between contractor‐supplied and employer supplied equipment. Otherwise
the design and supply team will use best practice.
Discipline strategy. As advised*/As listed**;
Employer’s list of work‐package name, description, (content)
Collaboration and Involvement: Are there any information sharing or security protocols to be
used?
Do you expect to be involved in the specification and use of the means used to deliver your
information requirements? What is the expectation for the security and accessibility of the processes
and data locations? Advice is that neither ‘dropbox’, ‘sharepoint ‘nor ‘ftp’ are adequate, so
preference is for professional environments that support compliance to BS1192. Otherwise the design
and supply team will follow best practice.
Collaboration process: BS1192 with PAS1192 part2 and part 3 / As advised* / As
described**:
Description of specified collaboration process
Common Document/Data Environment tool: As advised* / As nominated**:
Employer’s nominated CDE tool
Security: PAS 1192 part 5: S/A/3/2/1/ CESG: IL1/IL2/IL3/IL4/ As advised*/As
nominated**:
Employer’s list of nominated security standards
Information and Security management role
Employer’s nominated person with these responsibilities
© 2015 buildingSMART UKI Page 4 .
136
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
Section 2: General: Are there any general information requirements?
General information requirements additionally affect subsequent tiers of the design and supply
teams.
Aims and Purposes – What is the overall aim of these information requirements?
As a guide to the design and supply team, what use for the information, beyond matters of record, is
intended? The information is to be provided with the appropriate licence to be used for the purposes
identified. An example might be “Information is required for record purposes, statutory compliance,
coordination and approvals, construction, handover and use of the facility including end‐of‐life”.
Otherwise the design and supply team will use best practice.
Aims:
Employer’s description of the aims of this information requirement
Purposes intended and full licence required for :
Matters of record: As BS1192 part4 /As advised*/No
Statutory compliance: As BS1192 part4 5.2.2/ As advised*/Yes
Capacity and utilization As BS1192 part4 5.3.2/ As advised*/No
Security and surveillance As BS1192 part4 5.3.3/ As advised*/Yes
Project Information Model: Yes/ As advised*/No
Asset Information Model: Yes/ As advised*/No
H&S/CDM: Yes/ As advised*/No
Construction procurement: Yes/ As advised*/No
Asset register: As BS1192part4 5.2.2/ As advised*/No
Operational management: As BS1192 part 4 5.4.3/ As advised*/No
Maintenance management: As BS1192 part 4 5.4.4/ As advised*/Yes
Repurposing As BS1192 part 4 5.3.4/ As advised*/Yes
Decommission and disposal As BS1192 part 4 5.4.6/ As advised*/Yes
Replacement planning and whole life: As BS1192 part 4 5.4.5/ As
advised*/No
© 2015 buildingSMART UKI Page 5 .
137
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Predicted and actual cost and environmental impacts: As BS1192
part 4 5.4.2/ As advised*/Yes
Environmental compliance: Yes/ As advised*/No
As‐built: Yes/ As advised*/No
Others No / As advised* / As listed**
o Employer’s list of other information purposes
© 2015 buildingSMART UKI Page 6 .
138
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
Classification : Are there preferred classification tables for information about the project?
Otherwise the design and supply team will use facility industry best practice classification tables.
The project stages have been standardised in order to help you and the design and supply team
follow a common project plan.
Stages: CIC stages/As advised*/ As listed**:
Employer’s list of code, description of stage classification entry
Roles have been standardised so that there is less ambiguity as to who is doing what.
Roles: PAS1192 part 2 section 9.2.3/Uniclass C/As advised*/ As listed**:
Employer’s list of code, description of role classification entry
Suitability codes have been standardised so that there is less ambiguity as to what information is
suitable and licenced for.
Suitability and licence: PAS1192 part 2 section 9.2.3/As advised*/As listed**:
Employer’s list of code, description of suitability classification entry
Facility classification codes have been standardised within the construction sector. (Other codes may
be used for taxation, land use planning and so on).
Facility: Uniclass table D/ Uniclass 2 En /As advised*/ As listed**:
Employer’s list of code, description of facility classification entry
Zones and floors/regions are used to organise spaces within the facility.
Zones: Uniclass D&F/ Uniclass2 SP /As advised*/ As listed**:
Employer’s list of code, description of zone classification entry
Floor/regions: COBie FloorType/As advised*/ As listed**:
Employer’s list of code, description of floor/region classification entry
Systems and Types are used to organise components within the facility.
Systems: Uniclass table G&H/NRM/Uniclass2 SS /As advised*/ As listed**:
Employer’s list of code, description of classification entries
Types: Uniclass L/ Uniclass2 Pr /As advised*/ As listed**:
Employer’s list of code, description of classification entry
© 2015 buildingSMART UKI Page 7 .
139
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Naming policies – Are there naming policies for aspects of the project?
Naming policies in use for Spaces/locations and Components in older FM application may be more
prescriptive than in more modern design authoring tools, where the facility, floor or region should
not be included. Floors/regions and Types may be named after their filenames, rather than explicitly.
Systems and Zones may be named through the use of layering, rather than explicitly. Layer names
may include other information such as classification and graphic styles.
Zones and floors/regions organise the spaces/locations in the facility.
Zones (layers for spaces and locations) BS EN ISO 4157‐1 1999 /As advised*/ As
listed**:
Employer’s description of naming policy for zones
Floors and regions : BS EN ISO 4157‐1 1999 /As advised*/ As listed**:
Employer’s description of naming policy for floors and regions
Spaces and Locations : BS EN ISO 4157‐2&3 1999 /As advised*/ As listed**:
Employer’s description of naming policy for spaces and locations
Systems and Types organise the components in the facility.
Systems (layers for components) : PAS 1192 Part 2 section 9.3/As advised*/ As
listed**:
Employer’s description of naming policy for systems
Types and assemblies: BS8541 Part 1 section 4.3 / As advised* / As listed**:
Employer’s description of naming policy for types
Components and equipment (items): BS EN ISO 4157‐3 1999 /As advised*/ As
listed**:
Employer’s description of naming policy for components and equipment
© 2015 buildingSMART UKI Page 8 .
140
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
Checks ‐ Are there any specific tests of the information deliverables intended?
Note: some tests may be dependent on the use of specific classification tables.
Compliance and continuity are technical expectations relating to the use of the standards,
Continuity tests: Automated comparisons between information issues/As
advised*/ As listed**:
Employer’s list of name, description of continuity test(s)
Compliance tests: Automated checks of information against schema/As
advised*/ As listed**:
Employer’s list of name, description of compliance test(s)
Completeness and coherence tests relate to the provision of full data and the absence of clashes. The
recommendation is to use a published list to test completeness, called a digital Plan of Work (dPoW).
A dPoW typically covers the level of information on attributes (LoI) expected and the level of Detail
on shapes (LoD) expected for specific types of asset.
Coherence (clash and interference) tests: Automated checks/As advised*/ As
listed**:
Employer’s list of name and description of coherence test(s)
Completeness tests: dPOW (2015) / UK BTG Labs dPoW / No, as advised*/ As
listed**:
Employer’s list of stage, object, property (LoI) or shape (LoD) test(s)
Veracity relates the final as‐built facility/product to the information provided. Consistency is expected
between the information delivered and any other documents.
Veracity tests: Inspection checks/As advised*/ As listed**:
Employer’s list of name, description of veracity test(s)
Consistency tests: Inspection checks/As advised*/ As listed**:
Employer’s list of name, description of consistency test(s)
© 2015 buildingSMART UKI Page 9 .
141
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Information and documents – in what form should the information and documents be delivered?
The advice is to use IFC and COBie for information, and to use PDF for supplementary documents.
Information schemas: ISO 16739 IFC2x3 and BS1192 part 4 COBie2.4/As
advised*/ As listed**:
Employer’s choice of structured asset information format
Document formats: PDF/As advised*/ As listed**:
Employer’s list of file format extension and description
Document and information deliverable naming: PAS 1192 Part 2 section 9.3/ As
advised*/ As described**:
Employer’s description of file naming policy
© 2015 buildingSMART UKI Page 10 .
142
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
Annexes provide some guidance on the standards mentioned. Wherever possible these standards
should be chosen in preference to special requirements.
Annex A: standards relevant to the Information requirements
o BS1192:2007, PAS1192:2, PAS1192:3, BS1192 part 45
o BS8541 part 1‐6
o BS EN ISO 4157‐1:1998, Construction drawings. Designation systems. Buildings and parts
of buildings
o BS EN ISO 4157‐2:1998, Construction drawings. Designation systems. Room names and
numbers
o BS EN ISO 4157‐3:1998: Construction drawings. Designation systems. Room identifiers
o ISO 8601: Dates and calendars
o CIC stages: (see PAS1192 part 2 section 9.9.* or CIC BIM Protocol Appendix 1)
o ISO 16739:2005 & 2013 IFC
o PAS 1192 part 5
S Protect any commercially &/or personally (PII) sensitive data
A Additionally incl. adjacent site(s)
3 Additionally protect security sensitive data from CIC 3 onwards
2 Additionally protect security sensitive data from CIC 2 onwards
1 Additionally protect security sensitive data from CIC 1 onwards
© 2015 buildingSMART UKI Page 11 .
143
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Annex: Requirable content in COBie
If COBie is required in the absence of a formal dPoW, the minimum specification is to identify the
required fields (columns) from the requirable fields (columns) in COBie. Requirable fields (columns)
are coloured green. A COBie deliverable is made up of the tabs described in A.1 to A.20 : Refer to
BS1192 part 4 for lists of all the fields (columns)
Instruction
There are no requirable columns in this sheet
Contact
Contact Example Required?
© 2015 buildingSMART UKI Page 12 .
144
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
Facility
no/as
advised*/y
Description Single storey secondary school es**
no/as
advised*/y
ProjectDescription New build secondary school. es**
no/as
St Joseph’s Secondary School, Garston, advised*/y
SiteDescription Herts, WD25 9XX es**
Floor (region)
Floor Example Required?
no/as
Description Entrance level advised*/yes**
no/as
Elevation 0.0 advised*/yes**
no/as
Height 4000.0 advised*/yes**
Space (location)
Space Example Required?
no/as
RoomTag CL 101 advised*/yes**
no/as
UsableHeight 2955.0 advised*/yes**
no/as
GrossArea 24.837 advised*/yes**
no/as
NetArea 24.837 advised*/yes**
© 2015 buildingSMART UKI Page 13 .
145
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Zone
Zone Example Required?
no/as
Description Basic teaching spaces advised*/yes**
Type
Required?
On site warranty and
advanced replacement
WarrantyDescription warranty no/as advised*/yes**
© 2015 buildingSMART UKI Page 14 .
146
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
© 2015 buildingSMART UKI Page 15 .
147
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Component
Component Example Required?Notes
System
System Example Required?
Connection (optional)
Whiteboards to education resource no/as advised*/yes**
Description server 1
© 2015 buildingSMART UKI Page 16 .
148
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix A
buildingSMART UKI
Employer’s Information Requirements 2015
Duration 0 no/as advised*/yes**
LeadOutTime 0 no/as advised*/yes**
© 2015 buildingSMART UKI Page 17 .
149
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
buildingSMART UKI
Employer’s Information Requirements 2015
Document
Document Example Required?
Attribute
Attribute Example Required?
AllowedValues no/as advised*/yes**
There are no requirable columns in this sheet
© 2015 buildingSMART UKI Page 18 .
150
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
151
Appendix A
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
152
example
BIM Execution Plan
APPENDIX B
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix B
HTA Design LLP, 106-110 Kentish Town Road London NW1 9PX, Tel: 020 7485 8555
153
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
01
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
HTA DESIGN issued for the Project outlined as part of the Building Information Modelling process. Modification not
permitted without obtained permission of the author.
154
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix B
02
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
Introduction
HTA Design LLP intends this BIM Execution Plan to be used to accurately catalogue and record the
Client/ Employer’s requirements as it relates to the Asset Information Model. Specifically to the model’s
anticipated use, analysis and level of detail expected at each stage of the development and design
process through to construction. This document represents the agreed input and output content,
standard, format and schedule from all consultants for use to achieve the required objective which is the
timely delivery, exchange, reuse and final handover of the Asset Information Model to the client.
· To have the architect maintain a schedule of accommodation which illustrates drawn area against client
room area requirements
· To improve safety
· To review the scheme at regular intervals, to feedback lessons learnt and to feedback learning
outcomes and successes
The BIM Model will be used to provide the project team with live information to update and make timely
design decisions and create design alternatives whilst being aware of consequences and real time
impacts on the GFA, façade design, mechanical electrical, structural and other engineering and security
issues. It is intended that the model will also aid in producing cost-estimation, material quantification and
selection. As well as opportunities for fully investigating life cycle maintenance issues, energy efficiency,
solar impact and project scheduling.
155
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
03
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
156
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix B
04
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
Content
1. Project Information
6. BIM Coordination
6.2 Meetings
7. Responsibility Matrix
8. Change Management
157
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
05
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
Category Information
Project Owner
Project Name
Project Address
Contract Type/Delivery
Project Lead
BIM Coordinator
BIM Manager
BIM Modeller
BIM Modeller
Landscape
Project Director
158
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix B
06
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
5
5
6
5.0 Owner required level of BIM and Employers Information Requirements (EIR)
159
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
07
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
No party is authorized to alter the platform or version without prior consent from the BIM
manager. Changes to the platform or version will have consequences to the way project
information / data is collaborated. No software shall be upgraded without being communicated too
all relevant parties for discussion.
160
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix B
08
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
6.3 Meetings
Throughout the project the BIM Leader from each company is required to attend regular Virtual Design
and Construction (VDC) coordination meetings. During design, this meeting will be led by____
______________, as part of the Design Team Meetings (DTM). This meeting will review model and
documentation progress, highlight clashes that have developed in the model, and coordinate BIM usage
(model structure, linking of models, collaboration views, work set and naming generally etc.).
Each party’s models will contain a set of views specifically constructed for use by other members of the
team when they reference the model. Once established, do not change the names of these views as
others may be linking them.
161
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
09
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
File Naming
File names will follow the naming convention outlined in guidance document BS 1192 . Do not add a date,
version or any other modifier that changes over time.
Job code Organisation Discipline Zone (Module) Level File Type Description
xxx-xxx Xxx X Xx Xx Xx Xxxxxxxxxxxx
2. Coordinates – For each distinct building the origin will be set at the intersection of grid, A/1.
Global coordinates will be published to each building file through a process of acquiring
coordinates from the site file via shared coordinates.
162
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix B
10
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
7 Responsibility Matrix
TBC - Hill to review with HTA the authorship strategy, on the basis of the following suggestion.
Structural
Architect - M&E Services
Engineer -
HTA Engineer - TBC
Gemma Design
163
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
11
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
HVAC Risers
HVAC Major Runs (above 50mm)
HVAC Minor Runs (below 50mm)
Plumbing Risers
Plumbing Major Runs (above 50mm)
Plumbing Minor Runs (below 50mm)
Plumbing Fixtures
Roads
Roofs
Security Devices
Rooms
Shaft Openings
Site
Sprinklers
Stairs
Structural Reinforcing, Area, Path and Rebar
Structural Framing and Beam Systems
Structural Columns
Structural Connections
Structural Foundations
Structural Trusses
Telephone Devices
Topography
Walls
External - Structural - performance wall
External - Architectural - finishes
Internal - Smart wall
Windows
Changes that occur in the model once it has been issued need to be recorded in the tracking document in
excel as outlined below. This document needs to be issued with each exchange and updated by the
consultants before issue. The document should be archived after every exchange? Different strategy for
discussion.
164
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Appendix B
12
HTA BIM Execution Plan – 00.07.15. Rev_00
Project:
Client:
Job Code:
Modelling methodology to obtain required BIM level to enable the model to be used for:
165
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Image credits
Cover image UBM offices, 240 Blackfriars Road, London © Dave Parker
Page iv, 1, 41 (all), 43 © Morley von Sternberg
Page vii © Terry Stocks
Page 77 © NBS
Page 115 After diagram by Paul Tiecholz in ‘BIM for Facility Managers’
Page 119 Permission to reproduce extracts from BSI publications is granted by BSI
Standards Ltd (BSI). No other material use is permitted. British Standards
can be obtained in PDF or hard copy from the BSI online shop (http://shop.
bsigroup.com)
166
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled
Licensed copy from CIS: sci1, Steel Construction Institute, 31/03/2020, Uncontrolled Copy.
BIM
Building Information Modelling, otherwise known as ϐ Richard writes from a position of great personal
Acting as an authorative guide to Clients, this book: We commend this book to clients of all shapes and
• provides understanding of the strategic client sizes: those with large repeat programmes as well
value of BIM and how it changes the client role as those considering the need for a one-off
• shows via case studies how typical clients are construction project, and all those in industry
experiencing using BIM supply chains – particularly those directly able to
• includes guidance on setting up a project on a influence clients’ decisions. Its lessons will enable
BIM-using basis the industry to deliver better value for money for its
• demonstrates how structured information clients by finally delivering on integration and
enhances the briefing, design, construction and collaboration.
operation stages, supporting better decisions Don Ward, Chief Executive, Constructing Excellence
• contains guidance on where BIM is going next. (incorporating the Construction Clients’ Group)
Richard Saxon
clients to make successful use of BIM. balanced approach on the effort required and the
benefits that are achievable.