Sample 1520 PDF
Sample 1520 PDF
O.R
-1-
Learning Curve Theory
Mathematical Perceptions
m x n = log m + log n
mn = n log m
m/n = log m – log n
Total Time
xy = axb+1
Question 1:
An electronics firm which has developed a new type of fire alarm system has been
asked to quote for a prospective contract. The customer require separate price
quotations for each of the following possibilities:
Order No. of fire alarm System
First 100
Second 60
Third 40
The firm estimates the following cost per unit for the first order:
Direct Materials Rs. 500
Direct Labour
Deptt: A (Highly automatic) 20 hours at Rs.10 per hour.
Deptt: B (Skilled Labour) 40 hours at Rs. 15 per hour.
Variable overhead 20% of direct labour
Fixed overhead absorbed
Deptt: A Rs. 8 per hour
Deptt: B Rs. 5 per hour
Determine a price per unit for each of the three orders, assuming the firm uses a
markup of 25 % on total cost and allow for an 80% learning curve. Extract from
80% learning curve table:
-2-
X represents the cumulative total volume produced to date expressed as a multiple
of the initial order.
Question 2:
A company has 10 direct workers, who work for 25 days a month of 8 hours per
day. The estimated down time is 25 % of the total available time. The company
received an order for a new product. The first unit of the new product requires 40
direct labours hours to manufacture the products. The company expects 80%
(index is -0.322) learning curve for this type of work. The company uses standard
absorption costing and the cost data are as under:
Required:
i. Calculate the cost per unit of the first order of 30 units.
ii. If the company receives a repeat order for 20 units, what price will be
quoted to yield a profit of 25% on selling price? (Nov. 2002)
Question 3:
An electronic firm has developed a new type of fire alarm system. A first unit
assembled had a material cost of Rs. 18000 and took 400 hours of direct labour to
assemble labour rate is Rs. 25 per hour. This type of assembly is known to
experience a learning curve effect of 80% (index of learning – 0.3219).
Demonstration of this unit to potential customers resulted in an order for 20 units
during the next quarter. The firm wishes to popularize this system and will
therefore pass on the benefit of cost savings due to learning effect to the customers
while setting the sale price.
i. Determine the price to be set for the first lot of 20 units to be sold. The
initial unit will not be sold as this is required for demonstration. The firm
follows a practice of inputting a fixed overhead at 125% of direct labour
cost and will set the selling price to earn a 20% gross margin on sale price.
ii. Assume that a further order for a lot of 60 units was received on a contract
basis from a single customer. The price was set on the basis of the
contracted total. However, after delivery of 30 units against the contract,
-3-
the contract was cancelled. Determine the deferred learning cost that may
have to be written – off consequent to the cancellation of contract for
balance not supplied.
Question 4:
Given that a = 10 hours and learning rate is 80%, you are required to calculate:-
Question 5:
Dynamo, a manufacturer of aircraft parts, has been asked to bid for 900 units of a
particular type of component. Four months ago the company had produced a first
lot of 400 units for another customer. The cost details of this first lot are given
below.
-4-
Question 6:
A customer has asked your company to prepare a bid on supplying 800 units of a
new product. Production will be in batches of 100 units. You estimate that labour
costs for the first batch of 100 units will average Rs. 100 a unit. You also expect
that a 90% learning curve will apply to the cumulative labour cost on this contract.
Required:
i. Prepare an estimate of the labour costs of fulfilling this contract.
ii. Estimate the incremental labour cost of extending the production run to
produce and additional 800 units.
iii. Estimate the incremental labour cost of extending the production run from
800 units to 900 units.
Question 7:
Question 8:
Direct labour cost is Rs. 4 per hour. Direct material needed for one equipment is
Rs. 10000. Fixed overheads are Rs. 32000.
Required
1. using the learning curve concept, calculate the expected average unit cost of
making
a. 4 equipments b. 8 equipments
-5-
2. After manufacturing 8 equipments, if a repeat order for manufacture of
another 8 equipments are received. What lowest price can be quoted for the
repeat order?
Question 9:
Illustrate the use of learning curves for calculating the expected average unit cost
of making-
(a) 4 machines
(b) 8 machines
Using the data given below:-
Data:
Direct labour needed to make first machine 1000 hours
Learning curve = 80%
Direct labour cost – Rs. 3/- per hour
Direct material cost – Rs. 1800 per machine
Fixed cost for either size orders – Rs. 8000
Question 10:
A company developing a new product makes a model for testing, and then a
demonstration model and then goes for regular production. The time taken to
make the model is 300 hours. And from past experience of similar models, it is
known that a 90% learning curve applies. The average time for each of the first
two production models will be:-
1. 270 hours
2. 243 hours
3. 216 hours
4. 219 hours
Support the correct figure with calculations.
Question 11:
-6-
SIMULATION
Although simulation can be of many types, our discussion will focus on the
probabilistic simulation using the Monte Carlo method. Also called Computer
Simulation, it can be described as a numerical technique that involves modeling a
stochastic system with the objective of predicting the systems behavior. The
chance element is a very significant feature of Monte Carlo Simulation and this
approach can be used when the given process has a random, a chance, and
component.
In using the Monte Carlo Method, a given problem is solved by simulating the
original data with random number generators. Basically, its use requires two
things. First, as mentioned earlier, we must have a model, that represents an image
of the reality of the situation. Here the model refers to the probability distribution
of the variable in question. What is significant here is that the variable may not be
known to explicitly follow any of the theoretical distribution like Poisson, normal,
and so on. The distribution may be obtained by direct observation or from past
record. To illustrate, suppose that a bakery keeps the record of the sale of number
of cake of a certain types. Information relating to 200 days’ sales is:
Thus, there is 0.02 or 2% chance that 5 cakes would be demanded on a day, 0.05
or 5% chance that the demand would be for 6 cakes, … and so on. This
distribution would serve as the model of the situation under consideration.
The second thing requires for simulation is a mechanism to simulate the model –
something to capture the random nature of the given system. Thus we should have
available a procedure that would help us to select, at random, values for the
variables which can be used to approximate the state of the system. Such a
mechanism can be any random number generator consisting of a device or a
procedure by which random number can be determined and / or selected.
-7-
There are various ways in which random numbers (or apparently random, but not
truly so) may be generated this could be result of some device, coin or die;
published table of random number, mid quare method, or some other sophisticated
method. It may be mentioned here that the ‘random’ numbers generated by some
method may not be really random in nature. In fact such numbers are called
pseudo – random numbers. There are some test with which numbers may be tested
for there randomness but we should not consider them here and consider only
briefly how the number may be obtained and used.
A more fast and convenient method is to make use of the published table of
random numbers, like the one published by the Rand Corporation (of U.S.A) : A
million random digits. A random number table is very efficient way to generate
random data in most situations. The numbers in this table are in random
arrangements. The underlying theory is that each number has an equal opportunity
of being selected.
Still on a more sophisticated level, computers are used for generating the random
numbers. With computers it is typically easier to generate random numbers by an
arithmetic process as needed rather than to read the number from stored table. An
early, probably the earliest method proposed for use on digital computer to
generate random number is a mid square. To illustrate these methods, suppose that
we wish to generate four – digits integers and the last number generated was 8937.
To obtain the next number, in the sequence, we square the last one and use the
middle four digits of the product. In this case the product is 79869969 so that the
next pseudo – number is 8699. The next few numbers in the sequence are 6726,
2390, 7121 and so on. Thus, using this method, having drawn up a suitable
computer program, a four digit number may be fed into the computer and a list of
pseudo random numbers obtained.
-8-
Question 1:
The director of finance for a farm cooperative is concerned about the yields per
acre she can expect from this year’s corn crop. The probability distribution of the
yields for the current weather conditions is given below:
120 0.18
140 0.26
160 0.44
180 0.12
She would like to see a simulation of the yields she might expect over the next 10
years for weather conditions similar to those she is now experiencing.
(i) Simulate the average yield she might expect per acre using the following
random numbers: 20, 72, 34, 54, 30, 22, 48, 74, 76, 02
Question 2:
The occurrence of rain in a city on a day is dependant upon whether or not it
Rained on the previous day.
-9-
Event Probability
No rain 0.50
1 cm rain 0.25
2 cm rain 0.15
3 cm rain 0.05
4 cm rain 0.03
5 cm rain 0.02
If it did not rain the previous day, the rain distribution is given by:
Event Probability
No rain 0.75
1 cm rain 0.15
2 cm rain 0.06
3 cm rain 0.04
Simulate the city ,s weather for 10 days and determine by simulation the total days
without rain as well as the total rainfall during the period . Use the following
random numbers:
67 63 39 55 29 78 70 06 78 76
for simulation . Assume that for the first day of the simulation it had not rained the
day before.
Question 3:
The output of a production line is checked by an inspector for one or more of three
different types of defects, called defects A, B and C. If defect A occurs, the item is
scrapped. If defect B or C occurs, the item must be reworked. The time require to
rework a B defect is 15 minutes and the time required to rework a C defect is 30
minutes. The probabilities of an A, B and C defects are 15, 20 and 10 respectively.
For ten items coming off the assembly line, determine the number of items without
any defects, the number scrapped and the total minutes of rework time: Use the
following random numbers:
RN for defect A
48 55 91 40 93 01 83 63 47 52
RN for defect B
47 36 57 04 79 55 10 13 57 09
RN for defect C
82 95 18 96 20 84 56 11 52 03
- 10 -
Question 4:
The management of ABC Company is considering the question of marketing a
new product. The fixed cost required in the project is Rs. 4,000. Three factors are
uncertain viz. the selling price, variable cost and the annual sales volume.
The product has a life of only one year. The management has the data on these
three factors as under:
Using the sequence (First 3 random numbers for the first trial etc.) simulate the
average profit for the above project on the basis of 10 trials.
Question 5:
Dr. STRONG is a dentist who schedules all her patients for 30 minutes
appointments. Some of the patients take more or less than 30 minutes depending
on the type of dental work to be done. The following summary shows the various
categories of work, their probabilities and the time actually needed to complete the
work:
Simulate the dentist’s clinic for four hours and determine the average waiting time
for the patients as well as the idleness of the doctor.
- 11 -
Assume that all the patients show up at the clinic at exactly their scheduled arrival
time starting at 8.00 a.m. Use the following random numbers for handling the
above problem:
40 82 11 34 25 66 17 79
Question 6:
A book- store wishes to carry systems Analysis and Design in stock. Demand is
probabilities and replenishment of stock takes 2 days (i.e. if an order is placed in
March 1, it will be delivered at the end of the day on March 3). The probabilities
of demand are given below:
Demand (daily) 0 1 2 3 4
Each time an order is placed, the store incurs an ordering cost of Rs. 10 per order.
The store also incurs a carrying cost of Rs. 0.50 per book per day.
The inventory carrying costs is calculated on the basis of stock at the end of each
day. The manager of the book-store wishes to compare two options for his
inventory decision:
A. Order 5 books, when the inventory at the beginning of the day plus orders
outstanding is less than 8 books.
B. Order 8 books, when the inventory at the beginning of the day plus orders
outstanding is less than 8 books.
Currently (beginning of the 1st day) the store has stock of 8 books plus 6 books
Ordered 2 days ago and expected to arrive next day.
Using Monte- Carlo simulation for 10 cycles recommends
Which option the manager should choose?
89 34 78 63 61 81 39 16 13 73
Question 7:
A company manufactures 30 items per day. The sale of these items depends upon
demand which has the following distribution:
- 12 -
Sales (Units) Probability
27 0.10
28 0.15
29 0.20
30 0.35
31 0.15
32 0.05
The production cost and sale price of each units are Rs. 40 and Rs.50 respectively.
Any unsold product is to be disposed at a loss of Rs.15 Per unit. There is a penalty
of Rs.5 per unit if the demand is not met.
Using the following random numbers estimates total profit / loss for the company
for the next 10 days:
10 99 64 99 95 01 79 11 16 20
If the company decides to produce 29 items per day, what is the advantage or
disadvantage to the company?
Question 8:
A bakery keeps stock of popular brand of bread. Previous experience indicates the
daily demand as given below:
Daily demand : 0 10 20 30 40 50
Probability : .01 .20 .15 .50 .12 .02
Using above sequences, simulate the demand for the next 10 days.
(i) Find out the stock situation if the owner of the bakery decides to make 30
Breads everyday
(ii) Estimate the daily average demand for the bread on the basis of simulated
Data.
- 13 -
Question 9:
A company manufactures around 200 mopeds. Depending upon the availability of
raw materials and other conditions, the daily production has been varying from
196 mopeds to 204 mopeds whose probability distribution is as given below:
Production per day Probability
196 0.05
197 0.09
198 0.12
199 0.14
200 0.20
201 0.15
202 0.11
203 0.08
204 0.06
The finished mopeds are transported in a specially designed three storey lorry
That can accommodate only 200 mopeds. Using the following 15 random numbers
82, 89, 78, 24, 53, 61, 18, 45, 04, 23, 50, 77, 27, 54, 10
Simulate process find out:
(i) What will be the average numbers of mopeds, waiting in the factory?
(ii) What will be the average number of empty spaces on the lorry?
Question 10:
A retailer deals in a perishable commodity. The daily demand and supply are
variables. The data for the past 500 days show the following demand and supply:
Supply Demand
Availability (kg) No. of days Demand (kg) No. of days
10 40 10 50
20 50 20 110
30 190 30 200
40 150 40 100
50 70 50 40
The retailer buys the commodity at Rs. 20 per kg and sells it at Rs. 30 per kg. Any
Commodity remains at the end of the day, has no saleable value. Moreover, the
loss (Unearned profit) on any unsatisfied demands Rs. 8 per kg. Given the
following pair of Random numbers simulate 6 days sales, demand and profit.
- 14 -
Advanced Accounting