Question #1: Final Exam REVIEW

Mark decided to improve the project's completion date by doing activities in parallel that were originally scheduled sequentially, which is an example of fast tracking (A). Crashing a schedule means doing activities that were sequenced in parallel to shorten the project duration (C). Resource leveling will generally reduce the overutilization of resources (C). The critical path is Start – A – B – J - Finish (D). The float for activity F is 8 days (B). If the project is crashed by 4 days, the total additional cost will be $21,000. The cost performance index is 1.33 if the task was originally scheduled to take 2 people but after 2 weeks was only 75% complete with 1 person (C).

Uploaded by

Chahat Jaura
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
245 views2 pages

Question #1: Final Exam REVIEW

Mark decided to improve the project's completion date by doing activities in parallel that were originally scheduled sequentially, which is an example of fast tracking (A). Crashing a schedule means doing activities that were sequenced in parallel to shorten the project duration (C). Resource leveling will generally reduce the overutilization of resources (C). The critical path is Start – A – B – J - Finish (D). The float for activity F is 8 days (B). If the project is crashed by 4 days, the total additional cost will be $21,000. The cost performance index is 1.33 if the task was originally scheduled to take 2 people but after 2 weeks was only 75% complete with 1 person (C).

Uploaded by

Chahat Jaura
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Final Exam REVIEW

Question #1
Mark is a Senior Project Manager in the construction industry and currently working on a
large hi-way construction project. He decided to improve the forecasted completion date
for the project by doing in parallel several of the activities that were scheduled to be done
in sequence. This is called:
A. Crashing B. Priority setting C. Risk mitigation D. Fast tracking

Question #2
Crashing a schedule means:
A. Making the project shorter by any economic means.
B. Running the project team on overtime.
C. Doing activities that were sequence in parallel.
D. Removing the scope by creative means.

Question #3:
Resource leveling will generally:
A. Reduce the time needed to do the project.
B. Increase the total time necessary to do all the tasks.
C. Reduce the overutilization of resources.
D. Reduce resources to the lowest skill that is possible.

Question # 4

What is the critical path in the activity list to the left?

A. Start – A – B – C – Finish
B. Start – A – D – E – F – Finish
C. Start – G – H – I – J – Finish
D. Start – A – B – J - Finish

Question # 5
What is the float for activity F in the activity list above (question #4)?
A. 0 B. 7 C. 8 D. 10

PMPG 5004 Page 1


Public
Question #6
Activity Predecessor Time
A None 7
B A 3
C A 4
D B,C 5
E D 2
F D 4
G E,F 5

Activity Normal Crash Normal Crash Cost/Day


Time Time Cost Cost
A 7 6 $7,000 $8,000 $1,000
B 3 2 5,000 7,000 2,000
C 4 3 9,000 10,200 1,200
D 5 4 3,000 4,500 1,500
E 2 1 2,000 3,000 1,000
F 4 2 4,000 7,000 1,500
G 5 4 5,000 8,000 3,000

What will be the cost to crash the project by 4 days?

Question #7
A task scheduled to use two persons, full time, and take two weeks to complete. Instead,
the project manager was only able to assign one person to this task. At the end of two
weeks, the person assigned to the task was 75% complete. What is the cost performance
index?
A. 0.75 B. 1.5 C. 1.33 D. 0.5

PMPG 5004 Page 2