Question #1: Final Exam REVIEW
Question #1: Final Exam REVIEW
Question #1
Mark is a Senior Project Manager in the construction industry and currently working on a
large hi-way construction project. He decided to improve the forecasted completion date
for the project by doing in parallel several of the activities that were scheduled to be done
in sequence. This is called:
A. Crashing B. Priority setting C. Risk mitigation D. Fast tracking
Question #2
Crashing a schedule means:
A. Making the project shorter by any economic means.
B. Running the project team on overtime.
C. Doing activities that were sequence in parallel.
D. Removing the scope by creative means.
Question #3:
Resource leveling will generally:
A. Reduce the time needed to do the project.
B. Increase the total time necessary to do all the tasks.
C. Reduce the overutilization of resources.
D. Reduce resources to the lowest skill that is possible.
Question # 4
A. Start – A – B – C – Finish
B. Start – A – D – E – F – Finish
C. Start – G – H – I – J – Finish
D. Start – A – B – J - Finish
Question # 5
What is the float for activity F in the activity list above (question #4)?
A. 0 B. 7 C. 8 D. 10
Question #7
A task scheduled to use two persons, full time, and take two weeks to complete. Instead,
the project manager was only able to assign one person to this task. At the end of two
weeks, the person assigned to the task was 75% complete. What is the cost performance
index?
A. 0.75 B. 1.5 C. 1.33 D. 0.5