0% found this document useful (0 votes)
165 views10 pages

Activity Network Diagram

Uploaded by

Oussema
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
165 views10 pages

Activity Network Diagram

Uploaded by

Oussema
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

What is a Project?

m
An interrelated set of activities with a
r
tf o
definite starting and ending point, which
l a
results in a unique outcome for a specific
P
allocation of resources.
B A
Copyright © BA.Platform.tn
Defining the Work Breakdown Structure

• Work Breakdown Structure (WBS)


r m
– A statement of all work that must be
completed. tf o
l a
• Activity
P
B A
– The smallest unit of work effort consuming
both time and resources that the project
manager can schedule and control.
Copyright © BA.Platform.tn
Work Breakdown
Structure
r m
St. John’s Hospital
tf o
Project
l a
P
B A
Work Breakdown Structure Copyright © BA.Platform.tn
Diagramming the Network (1 of 2)

r
Network Diagram – A visual display designed tom
tf o
depict the relationships between activities, that
l a
consist of nodes (circles) and arcs (arrows)
– P (PERT)
Program Evaluation and Review Technique
– Critical Path Method (CPM)
B A
Copyright © BA.Platform.tn
Diagramming the Network (2 of 2)

• Precedence relationship

r m
– A relationship that determines a sequence for undertaking

tf o
activities; it specifies that one activity cannot start until
a preceding activity has been completed.
l a
• Estimating Activity Times
– Statistical methods
P
– Learning curve models
B A
– Managerial opinions

Copyright © BA.Platform.tn
Example 1 (1 of 3)

• Judy Kramer, the project manager for the St. John’s Hospital project, divided
the project into two major modules.
r m
tf o
• She assigned John Stewart the overall responsibility for the Organizing and
Site Preparation module and Sarah Walker the responsibility for the
Physical Facilities and Infrastructure module.
l a
P
• Using the WBS shown in the previous Figure (see slide 7), the project team
developed:
– The precedence relationships,
B A
– activity time estimates,
– and activity responsibilities shown in the following table.

Copyright © BA.Platform.tn
Example 1 (2 of 3)
Immediate
Activity Activity Times (wks) Responsibility
Predecessors
St. John’s Hospital Project blank blank Kramer
Start blank 0 blank
Organizing and Site Preparation
A. Select administrative staff
blank
Start
blank
12
r m Stewart
Johnson
B. Select site and survey
C. Select medical equipment
Start
A
tf
9
10
o Taylor
Adams
D. Prepare final construction plans B
l a 10 Taylor
E. Bring utilities to site
F. Interview applicants for nursing and support staff
B
A
P 24
10
Burton
Johnson
Physical Facilities and Infrastructure
G. Purchase and deliver equipment
H. Construct hospital
B
C
D
A
blank blank
35
40
Walke
Sampson
Casey
I. Develop information system A 15 Murphy
J. Install medical equipment E,G,H 4 Pike
K. Train nurses and support staff F, I, J 6 Ashton
Finish K 0 blank
Example 1 (3 of 3)
Figure 7.2 Network Showing Activity Times for the St. John’s Hospital Project

r m
tf o
l a
P
B A
Copyright © BA.Platform.tn
Developing the Project Schedule

• Path
r m
– The sequence of activities between a project’s
start and finish. tf o
l a
• Critical Path
P
– The sequence of activities between a project’s

B A
start and finish that takes the longest time to
complete.
Copyright © BA.Platform.tn
Example 2 (2 of 6)

Paths are the sequence of activities between a project’s


start and finish.
r m
tf o
Path
A-I-K
Time (wks)
33
l a
A-F-K 28
P
A
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
B
Copyright © BA.Platform.tn

You might also like