Estimated working schedule for physical de
PHASE TITLE DAYS ACTIVITIES IN DETAIL DAYS 2021
J F M A M J J A S
Phase I: Boundary 90 Boundary Demarkation 180
Phase II: Land 90 Land Management 90
Mobilisation period & preliminaries 30
Phase III : Site Site Clearance 180
600
preparation Retaining Wall along Lake boundary 180
Land Development 540
Bus Parking & Bike Parking 60
Car Parking and Entrance Ground 60
Trail Construction 180
Surface Drain Construction 180
Lakeside Open Ground Development 180
Construction of Garden & Walkways 150
Construction of Staircase 150
Phase IV: Construction of Rampway 90
Construction of 660
Infrastructure Construction of Stall 120
Construction of Toilet Blocks 90
Construction of Pati 90
Construction of Boating Deck 30
Construction of View Deck 60
Construction of Central View Deck 90
Construciton of Admin Building 360
Exhibition Area Arangement 30
Phase V: Installation of Street Lamps 90
Installation of Installation of Benches 60
270
Infrastructure Installation of Dustbins 60
Facilities
Plantations 90
Phase VI: Descrepensies 60
60
Completion Completion of Works 0
Color Index
Administrative Works
Site Works
Construction Works
Completion of works
dule for physical development of lakeside, Jiri
1 2022 2023
O N D J F M A M J J A S O N D J F M A M J J A S O N
D
Estimated working schedule for phys
PHASE TITLE DAYS ACTIVITIES IN DETAIL DAYS 2021
J F M A M
Phase I: Boundary Etablishment of Project Office 180
Formation Etablishment of land valuation committee 90
270
Valuation of individual land plots 90
Issuing land acquisition notice to individual owners 30
Land acquisition 60
Phase II: Land Demarkation of different zones and individual plots 90
Management 450
Sales of Land for Commercial Purpose 360
Phase III : Site Mobilisation period & preliminaries 60
preparation Site Clearance 270
300
Retaining Wall along Lake boundary 180
Land Slope Stabilization 180
Phase IV: Construction of Central View Deck 60
Construction of Construction of Boating Deck 60
Infrastructure
Construction of View Deck 60
Construction of extension of District road 270
Construction of 3m Trail - Buffer Zone 180
Construction of Surface Drain -Buffer Zone 180
Construction of Staircase in Buffer Zone 60
Construction of Rampway in Buffer Zone 60
Construction of Bus Parking & Bike Parking 60
690
Construction of Car Parking and Entrance Ground 60
Construction of Toilet Blocks in Buffer Zone 120
Construction of Stall 120
Construction of Pati 60
Construction of Tourist Information Center 30
Development of Lakeside Open Ground 90
Construction of Garden & Walkways 120
Construciton of Admin Building 360
Construction of Exhibition Area 30
Phase V: Installation Installation of Street Lamps 90
of Infrastructure Installation of Benches 60
Facilities 270
Installation of Dustbins 60
Plantations 90
Phase VI: Descrepensies 60
Completion 60
Completion of Works 0
Color Index
Note: Administrative Works
An assumption of continuous availability of budget, Site Works
material and manpower, is made. Construction Works
Completion of works
ng schedule for physical development of lakeside, Jiri
2021 2022 2023
J J A S O N D J F M A M J J A S O N D J F M A M J J
Color Index
Administrative Works
Site Works
Construction Works
Completion of works
2023
A S O N D