SECTION 01 78 24.00 10
05/18
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS AND ABBREVIATIONS
1.2.1 Assets
1.2.2 Attributes
1.2.3 Facility Data
1.2.4 Facility Document Set (FDS)
1.2.5 Facility Data Workbook (FDW)
1.2.6 Facility Data Project Execution Plan (FDPxP)
1.3 UNITS OF MEASURE
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.5.1 Facility Data Project Execution Plan (FDPxP)
1.5.1.1 Front Matter
1.5.1.2 Project Information
1.5.1.3 Submittal Schedule
1.5.1.4 Personnel
1.5.1.5 Facility Data Workbook(s)
1.5.1.6 Facility Document Set(s)
1.5.1.7 Protocols
1.5.2 Meetings
1.5.2.1 [Post-Award Kickoff Meeting][Pre-Construction Meeting]
1.5.2.2 FDPxP Coordination Meeting
1.5.2.3 Submittal Coordination Meeting
1.5.3 Facility Turnover and Contract Closeout
1.5.4 Facility Data Workbook Quality Requirements
1.5.5 Facility Document Set Quality Requirements
1.5.5.1 Document Files
1.5.5.2 Photograph Files
1.5.5.3 Drawing Files
1.5.6 Facility Document Set Integrity Requirements
1.5.6.1 File Protection
1.5.6.2 Manufacturer-Specific Documents
1.6 DELIVERY, STORAGE, AND HANDLING
1.6.1 Number of Copies
PART 2 PRODUCTS
2.1 FACILITIES
2.2 FACILITY DATA WORKBOOK(S)
2.2.1 Spaces
2.2.2 Assets
2.2.3 Attributes
2.3 FACILITY DOCUMENT SET
2.3.1 Organization
2.3.1.1 Design Data Hierarchy
2.3.1.2 O&M Data Hierarchy
2.3.1.3 Record Drawings Hierarchy
PART 3 EXECUTION
SECTION 01 78 24.00 10
**************************************************************************
NOTE: This guide specification covers the
requirements for maintenance and turnover of
electronic Facility Data for use by O&M personnel
and systems of record.
**************************************************************************
**************************************************************************
NOTE: Consult the appropriate Administering Public
Works Office on all construction contracts under the
stated threshold values to determine if insertion of
this guide specification is required.
**************************************************************************
NOTE: Facility Data Requirements are divided into
two primary deliverables:
**************************************************************************
NOTE: The Facility Document Set (FDS) is archived
with and serves as a supplement to the Facility Data
Workbook (FDW). Together, these two documents
comprise the Facility Data deliverables required by
this specification.
**************************************************************************
NOTE: Thoroughly edit this section throughout and
coordinate with any other electronic data
requirements stipulated by the project and Owner
requirements.
**************************************************************************
**************************************************************************
NOTE: Facility Data Exchange information is
available at https://cadbim.usace.army.mil.
**************************************************************************
PART 1 GENERAL
**************************************************************************
NOTE: Proper procurement of deliverables described
in this specification requires a high degree of
coordination between this specification, 01 33 00
**************************************************************************
NOTE: This guide specification contains bracketed
options for an array of procurement methods. This
specification may be used on design-only contracts,
design-build contracts, and design-bid-build
contracts. Edit the specification references below
as applicable using the appropriate bracketed
options.
**************************************************************************
1.1 REFERENCES
**************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in
this paragraph by organization, designation, date,
and title.
1.4 SUBMITTALS
**************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit
the following list to reflect only the submittals
required for the project.
**************************************************************************
NOTE: If desired, it is possible (but not required)
that FDW and FDS submittals be duplicated and
individually named for ease of tracking by the
Government. Each facility named in "Part 2" will
1.4 SUBMITTALS
**************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit
the following list to reflect only the submittals
required for the project.
**************************************************************************
NOTE: If desired, it is possible (but not required)
that FDW and FDS submittals be duplicated and
individually named for ease of tracking by the
Government. Each facility named in "Part 2" will
**************************************************************************
NOTE: For Design-Build Contracts, there is no
necessity for the Designer of Record to maintain
Facility Data during project design.
Provide the Government with a plan for the collection, organization, and
turnover of the Facility Data deliverables to the Government. At a
minimum, include the following items in the FDPxP:
List the Project Owner, Project Name, Project Location and address,
Contract Type, Project Description, Project/Contract Number, Project
Milestones.
1.5.1.4 Personnel
1.5.1.7 Protocols
Detailed procedures:
1.5.2 Meetings
To assure that Facility Data requirements are being met through the
duration of the project, organize the following meetings and discuss the
subsequent topics:
**************************************************************************
NOTE: For Design-Bid-Build, choose the
Pre-Construction Meeting bracketed option and
coordinate requirements with 01 30 00 ADMINISTRATIVE
REQUIREMENTS.. For design-build or design-only
contracts, choose the Post-Award Kickoff Meeting
bracketed option and coordinate requirements with 01
33 16 DESIGN DATA (DESIGN AFTER AWARD).
**************************************************************************
c. Identify and agree upon a date and attendance list for the meetings
described below:
**************************************************************************
NOTE: Choose the Commissioning Authority bracketed
option below when Commissioning is required for this
project.
c. The FDPxP serves as the primary agenda for this meeting. At a minimum,
**************************************************************************
NOTE: For design-bid-build contracts, design
submittals are most often not necessary (require
construction submittals only). For design-only
contracts, design submittals are likely the only
deliverable. For design-build contracts, both design
and construction submittals may be requested, but
construction submittals are the only required
deliverable. Edit the specification as applicable
using the appropriate bracketed options.
**************************************************************************
1.5.2.3 Submittal Coordination Meeting
For each submittal, ensure that the information contained in the FDW(s)
reflects the minimum content requirements defined in the PART 3 EXECUTION
portion of this section. Ensure that information provided as part of the
FDW(s) conforms to the standards described below:
**************************************************************************
NOTE: The paragraph below contains bracketed
options for submittal quality requirements. Unless
01 33 00 SUBMITTAL REQUIREMENTS and 01 78 23
OPERATION AND MAINTENANCE DATA clearly identify
submittal quality requirements across all project
submittals, select the "below:" bracket and include
all quality requirements listed below. Quality
metrics are default values and may be edited to suit
project needs.
**************************************************************************
Utilize PDF file format in accordance with ISO 32000-1 and ISO 19005-3 for
all document-based files. Provide files from original sources,
text-searchable, and saved in "Standard" (uncompressed) resolution.
Bookmark and label files as defined in the PART 2 PRODUCTS portion of this
section.
If photographs are required, utilize JPEG file format for all photograph
and image files. Provide full-color photos with photo resolution of not
**************************************************************************
NOTE: The paragraph below contains bracketed
options for submittal delivery requirements. Unless
01 33 00 SUBMITTAL REQUIREMENTS and 01 78 23
OPERATION AND MAINTENANCE DATA clearly identify
submittal delivery requirements across all project
submittals, include both bracketed options in this
paragraph.
**************************************************************************
b. The Sheet ID and Sheet Name as found in the Record Drawing Sheet Index
and in accordance with the AEC CAD Standard referenced in 01 78 00
CLOSEOUT SUBMITTALS. (e.g. G-001 - LEGEND; CS101 - SITE PLAN AREA 101;
A-101 - OVERALL FIRST FLOOR PLAN; P-601 - FIRST FLOOR DWS WATER RISER
DIAGRAM, etc.)
]PART 3 EXECUTION
**************************************************************************
NOTE: For design-bid-build contracts, design
submittals are typically not necessary (require
construction submittals only). For design-only
contracts, design submittals are the only required
deliverable. For design-build contracts, both design
and construction submittals may be requested, but
construction submittals are the only required
deliverable. Edit the specification as applicable
using the appropriate bracketed options.
**************************************************************************
[3.1 DESIGN SUBMITTALS
Submit the Facility Data Workbook and Facility Document Set design
submittals together. Meet the following completeness and formatting
requirements listed below:
**************************************************************************
NOTE: For Construction Progress FDW submittal,
recommended delivery is 60 days prior to BOD for
small projects and 90 days prior to BOD on large
projects. Specifier may insert alternative delivery
date if project requirements dictate differently.
**************************************************************************
Submit the FDW and FDS construction progress submittals together. Meet
the following completeness and formatting requirements listed below:
**************************************************************************
NOTE: Unlike the Construction Progress Submittal, it
is unlikely that the Contractor will be able to
submit the full Construction Final Submittal at one
time. The FDW(s) are most beneficially submitted
during commissioning of building systems, prior to
the Beneficial Occupancy Date (BOD). Components of
the FDS can only be compiled and finalized after
Government-Acceptance of its individual components
(Record Drawings, O&M Data Packages). This will
likely not occur until after BOD. Specifier should
edit this specification with this understanding and
tailor this paragraph as necessary to comply with
individual project requirements.
**************************************************************************
**************************************************************************
NOTE: For Facility Data, Construction Final
Provide one compiled FDW for each facility identified above. Complete all
portions of each FDW including facility, space, asset, and attribute data
in compliance with the FDW Requirements. [ An FDW with pre-populated
basis-of-design information is attached to this section. The Government will
provide electronic copy of the attached FDW(s) to the Contractor upon award
in [.xlsm][PDF][_____] format.][ The current FDW template (.xlsm format)
shall be downloaded from the USACE CAD/BIM Technology Center website at
https://cadbimcenter.erdc.dren.mil.]
2.2.1 Spaces
**************************************************************************
NOTE: This section includes minimum space
definition requirements for the FDW. Provide
additional requirements as appropriate for project
and stakeholder.
**************************************************************************
Provide data for all applicable spaces in the facility. Minimum space
definitions are as follows:
**************************************************************************
NOTE: The FDW Template contains a list of baseline
required assets that should be adequate for most
projects. The specifier should review the FDW
required assets and engage the appropriate
[DDC and EMCS Equipment] [Panels and consoles associated with the facility
automation and control systems integration.]
[_____] [__________]
2.2.3 Attributes
**************************************************************************
NOTE: For design-bid-build contracts, design
submittals are typically not necessary; require
construction submittals only. For design-only
contracts, design submittals are the only required
deliverable. For design-build contracts, both design
and construction submittals may be requested, but
construction submittals are the only required
deliverable. Edit the specification as applicable
using the appropriate bracketed options.
**************************************************************************
2.3 FACILITY DOCUMENT SET
2.3.1 Organization
a. The contract specification and title under which the Data Package and
the associated equipment or system references. (e.g. 26 23 00.00 40 -
SWITCHBOARDS AND SWITCHGEAR)
b. The Sheet ID and Sheet Name as found in the Record Drawing Sheet Index
and in accordance with the AEC CAD Standard referenced in 01 78 00
CLOSEOUT SUBMITTALS. (e.g. G-001 - LEGEND; CS101 - SITE PLAN AREA 101;
A-101 - OVERALL FIRST FLOOR PLAN; P-601 - FIRST FLOOR DWS WATER RISER
DIAGRAM, etc.)
]PART 3 EXECUTION
**************************************************************************
NOTE: For design-bid-build contracts, design
submittals are typically not necessary (require
construction submittals only). For design-only
contracts, design submittals are the only required
deliverable. For design-build contracts, both design
and construction submittals may be requested, but
construction submittals are the only required
deliverable. Edit the specification as applicable
using the appropriate bracketed options.
**************************************************************************
[3.1 DESIGN SUBMITTALS
Submit the Facility Data Workbook and Facility Document Set design
submittals together. Meet the following completeness and formatting
requirements listed below:
**************************************************************************
NOTE: For Construction Progress FDW submittal,
recommended delivery is 60 days prior to BOD for
small projects and 90 days prior to BOD on large
projects. Specifier may insert alternative delivery
date if project requirements dictate differently.
**************************************************************************
Submit the FDW and FDS construction progress submittals together. Meet
the following completeness and formatting requirements listed below:
**************************************************************************
NOTE: Unlike the Construction Progress Submittal, it
is unlikely that the Contractor will be able to
submit the full Construction Final Submittal at one
time. The FDW(s) are most beneficially submitted
during commissioning of building systems, prior to
the Beneficial Occupancy Date (BOD). Components of
the FDS can only be compiled and finalized after
Government-Acceptance of its individual components
(Record Drawings, O&M Data Packages). This will
likely not occur until after BOD. Specifier should
edit this specification with this understanding and
tailor this paragraph as necessary to comply with
individual project requirements.
**************************************************************************
**************************************************************************
NOTE: For Facility Data, Construction Final
Submit the FDW and FDS construction final submittals [as they are
completed][__________]. Coordinate the Facility Data Workbook,
Construction Final submittal with data verification procedures as defined
in the accepted FDPxP. Provide the Facility Document Set, Construction
Final submittal only after Government acceptance of its individual
components as defined by[ 01 78 00 CLOSEOUT SUBMITTALS][ and][ 01 78 23
OPERATION AND MAINTENANCE DATA].
**************************************************************************
NOTE: Choose the Commissioning Authority bracketed
option below when Commissioning is being required by
this project. Insert the appropriate commissioning
specification number and title used on this project.
**************************************************************************
**************************************************************************
NOTE: On-site verification of Facility Data
contained in the FDW(s) is required for assurance of
quality data. The best time to verify this data is
during facility commissioning procedures. If
commissioning of building systems is part of the
scope of this project, require that the Contractor
align verification of FDW with commissioning. If
commissioning is not required for the project, Data
Verification is most beneficial during Contract
Closeout, prior to BOD.
**************************************************************************
Verify the FDW through the quality control personnel and procedures as
defined in the FDPxP.[ Coordinate and conduct verification with
commissioning procedures defined in [_____].] One-hundred percent
accuracy of FDW information is required for Government acceptance of the [
Facility Data Workbook, Design submittal][ and][ Facility Data Workbook,
Construction Final submittal].
**************************************************************************
NOTE: The following bracketed option for
"Attachments" should only be included if the Project
requires a pre-populated FDW be included in the
contract. If a pre-populated FDW is necessary, edit
the "FACILITY DATA WORKBOOK(S)" and "Facility Data
Workbook Quality Requirements" paragraphs above to
indicate as such and include the bracketed reference
below. Print a PDF copy of the pre-populated FDW and
attach to the end of this specification in the
contract solicitation. Preserve a copy of the
pre-populated FDW for turnover to the Contractor
upon Contract Award.
--Attachments--
Project Facility Data Worksheets
-- End of Section --