Method Statement: Al Andalus Trdg. & Elect. Cont. Co. L.L.C
Method Statement: Al Andalus Trdg. & Elect. Cont. Co. L.L.C
JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 1 of 31
METHOD
STATEMENT
FOR
ELECTRICAL WORKS
Page 2 of 31
METHOD STATEMENT:
ELECTRICAL
Table of Contents:
1. Scope / Objectives.
2. Activities.
3. Responsibilities.
4. Resource Requirements.
Material.
- Drawings.
5. Procedure.
8. Manpower.
9. Records.
10. Approvals.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 3 of 31
1. Scope / Objectives.
Page 4 of 31
3. Responsibilities.
3.3 Al Andalos Project Manager / Project Engineer will ensure that the
Resources are available to carry out the works as scheduled.
3.4 The Project Engineer / Site Engineer are responsible to carry out the
works as per approved Shop Drawings, Method statements.
3.5 The Site Engineer / Supervisor are responsible to ensure that the work
has been carried out as per drawings and inspections are done as per
contract.
4. Resource Requirement.
General
4.1 Materials
All materials shall comply with the specifications regarding quality, dimensions,
strength, etc. Samples will be submitted for the approval of the Engineer.
Making sure all material as per consultant’s approval before any installation.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 5 of 31
4.2 Drawings.
Page 6 of 31
Before casting any column in the site, we have to check if there is any Switch
Socket, bell or break glass fixed on the column. If there is any, we have to fix
the GI or PVC box in the proper way so that it will be touch with shatter of the.
Column from inside and the conduit will be extended to the top of the column.
Before casting any column in the site, we have to check if there is any Switch
Socket, bell or break glass fixed on the column. If there is any, we have to fix
the GI or PVC box in the proper way so that it will be touch with shatter of the
Column from inside and the conduit will be extended to the top of the column.
After finishing the block work in each floor, we will start marking the location
of all the switches, sockets, telephone outlets, TV outlets, break glass and bells
as per the approved shop drawings. Then we will start chasing and chipping the
marked locations by using the grinder, accordingly we will fix the GI boxes with
minimum 5 mm away from the wall to make sure that the box is flush with the
plaster. Next day we will terminate the conduits with the GI boxes.
Usually, we always inform the main contractor, before starting the block work to
use a blocks of 200 mm. width instead of 100 mm. and to locate plaster level
points only in the location where is coming recessed DB’s, so that we can fix the
enclosures properly and to ensure the enclosures are completely flush with
plaster. The mounted height of the enclosures will be 1300 (bottom of panel).
Distribution board will be aligned, leveled and securely fastened to the wall.
The surface mounted panel boards will be fixed at least 25 mm from wall:
ensuring supporting members do not prevent flow of air.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 7 of 31
Distribution board interiors will not be installed in cabinets until all conduits
connections to the cabinet have been completed.
Trim for flush mounted cabinets will be installed in plaster frame, flushed with
furnished wall. Trim will be installed plumb and square to finish painting.
Before starting the wiring for the above mentioned activities, we have to make
sure that the plasterwork is finished completely in that area / floor & there is no
more water still on the walls.
Before start pulling the wires we will be sure that there is no water or any
rubbish inside the conduits.
At the false ceiling area (60 x 60), we have to use a ceiling rose with a heat
resistance wire & where are coming a gypsum board ceiling, we have to extend
the wires from the slab to the expected level of the gypsum ceiling through a
flexible conduits.
For the light & Power circuits, wires & cables will be used as per the approved
material submittal (2.5mm2 for the lighting circuits & 4.0mm2 for the power
circuits).Lighting & Power circuits will be run in separate conduits.
The wires & cables will be installed in conduits, trunking and ladders as per the
approved shop drawings.
For branch circuit work, originating from light & power panel boards will be
arranged as per the approved drawings. Loads on various phases of panel boards
will be balanced as per he approved load schedules.
For avoiding any damaged for the conductors, insulation or jacket of he wire or
cable during the pulling stage, and lubricants will be used properly to prevent
any stresses on conductors.
For pulling the wires, we will install 3mm galvanized standard steel wire with
wooden blocks fastened at ends in empty service conduits.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 8 of 31
At every branch circuit outlet & pull-box, every cable passing through will be
left slack to allow inspection & for connection to be made. Cables terminating
in outlet boxes will be left with at least 250mm extra length for terminations.
All circuits will be properly labeled during the pulling work to facilitate the
terminations at the respective devices.
After the pulling circuit works completely, all the circuits will be checked &
tested if any open circuits, short circuits, earthing continuity & excessive
resistance or leakage.
Cable Trays & Ladders will be “as specified” type as per the approved material
submittal.
All accessories used such as “bends”, intersections, risers, reducers, elbows, etc.
“used in cable trays & ladders will be of the same manufacturer as that of the
trays & ladders.
Prior to start any installation of Trays & Ladders, a complete coordination will
be carried out with other mechanical services to avoid any interference or
interrupted for the service.
Tray / ladders routes will be marking at the ceiling before start any fixing of
these items.
Each run of cable trays & ladders will be completed before installation of any
cables. Each run will be aligned, leveled & securely fastened to the ceiling /
wall.
Page 9 of 31
The fitting of trays & ladders such as tees, bends & crossings will be connected
with radial to permit cable-bending standards.
Minimum clearance of 250mm will be maintained between top of tray & ceiling.
Cable arrangement will be in one layer only, evenly spaced, with minimum
spacing of two diameters of he larger of the two adjacent cables, or of a trefoil
formation of single core cable circuit.
Cable trays will provide direct support to the cables without cleats or saddles
wherever practicable purpose made straps, cleats or saddles will however be
used to maintain a neat or regular disposition of cables. In vertical tray
installation or where trays not directly support the cables, load bearing cable
cleats or saddles will be employed and securely fixed to the tray. Manufacturer’s
recommendations will be followed in selection of cable cleats or saddles, on the
basis of individual application.
Earthing jumpers will be installed on trays & ladders between the lengths and
where required to ensure effective electrical continuity irrespective of whether a
separate protective earth conductor is required or not.
After we finished from fixing the cable tray, C-channels in the proper way, we
will start pulling the armored cables from the main electrical room to the all
electrical rooms one by one and with more care to avoid any damage for the
cables, after that it will be tied strongly with the vertical C-channels using cable
cleats then it will be terminated to the MDB’s, SMDB’s through cable glands.
Use and install cables only as shown on consultants approved shop drawings &
as directed by the manufacturer
Lay cables in one length unless otherwise indicated. Obtain permission from
Engineer for all through joints, and where overall length requirement exceeds
practical drum size.
Use drum stands, drum axles, fair leads, rollers, cable stockings and other
equipment as recommended by the cable manufacturer and as appropriate to the
method of installation.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 10 of 31
Install cables so that they are orderly and capable of being withdrawn.
Place cables side by side or as indicated. Fix using cable ties so that any cable
may be individually removed.
Ensure all joints and terminations and glanding are made by appropriately
qualified Person, using, components and workmanship recommended by the
cable manufacturer& as per local authorities & DEWA recommendation.
Cut all cable ends immediately prior to jointing or terminating. Seal cables left
unconnected for more than 24 hours to prevent the ingress of moisture.
Strip cables to bring out the cores and expose conductors, for the minimum
length required for connection, to leave no exposed length of conductor after
termination. Ensure that strands are not damaged when stripping cable cores.
Twist strands together. Do not reduce number of strands. Secure all strands at
terminations.
Clean arm our thoroughly prior to jointing or terminating. At connections to
equipment and switchgear without integral cable clamping terminals, use
compression type lugs for bolted terminal connections.
Do not bunch more than three cores at clamping terminals or bolted connections.
Mark cable conductor phasing, or other core identification, at each end of all
cables.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 11 of 31
The Contractor shall be responsible for testing all cables before finally making
off ends and connecting up.
Where cable sheaths are used as earth continuity conductors, glands shall have
the necessary contact surfaces or straps to provide a low resistance path under
fault conditions.
All cable connections to plant shall be made with approved cable lugs,
compression type together with the usage of proprietary tools.
All glands in outdoor situations and wherever else specified, shall be of
weatherproof and water tight type. Gland manufacturers shall be subject to
approval. Glands shall be selected to suit location and type of cable used.
Earthling tags shall be fitted to each gland, on assembly, prior to the lugs being
attached. Ensure to order cable glands in kit form complete with earth tag,
shroud, locknut, neoprene seal etc.
The Panel boards will be in accordance with Local Dewa rules & Requirement.
“Standard for Panel Boards” and standard for cabinets and boxes. Manufactures
380 / 220V, 3-phase, 4 wires, 50Hz.
All the equipments will be installed in accordance with the manufactures
recommendations / installation instructions and as per the site requirements /
approved master project program.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 12 of 31
A nameplate will be provided with Manufacturer’s name, Panel type and
Ratings.
A Samples of DBs enclosures (Surface and Flush) type circuit breaker
arrangements in DBs will be delivered at site for the Consultants / Client
inspection and to be proceed with the installation upon obtaining the approval.
The assembly of distribution boards will be completely wired and rested at the
factory ready for installation when received at site. Bracing will be provided to
prevent distortion in handling and shipping.
Distribution boards will be incorporate plug-in type miniature circuit breakers of
tripping characteristics B, C or D for lighting, miscellaneous power or motor
loads on necessary complete as specified as shown in the approved drawings.
Interiors will be so designed that circuit’s breakers can be replaced without
disturbing adjacent units and without removing the main bus connectors.
All exterior and interior steel surfaces of the Panel Boards will be properly
cleaned after completion of work and all rubbish, dust or concrete spatter will be
removed from inside and around the Panel Boards by using brushers, vacuum
cleaner etc.,
Final Distribution Boards:
A – Fixing of DB’s enclosures:(Refer 4.7)
B – Panel Boards Interiors:
Install the connecting conduits to the panel board, ensuring these conduits will
not be used to support the distribution board and all the unused opening will be
properly closed.
The panel Boards will be equipped with circuit breakers with frame size and trip
setting as shown in the approved document.
Before pulling wires inside the Panel Board conduits, conduits will be checked
to be free of burrs, dry and clean.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 13 of 31
The arrangement will permit cables to enter bottom and top of the enclosures
and connect to their respective terminals without interference.
Insulation to be removed from the end of each wire and cable with a
pocketknife, being careful not to nick the wire conductor.
Incoming and outgoing feeder panel will be labeled, engraved and a nearly typed
schedule inside the boards, will describe all the outgoing final sub-circuits, their
rating, the areas and points served.
Light and power circuits will be arranged in the Panel Boards as per the
approved Load Distribution Schedule.
Tags of feeder cables to identify cable or circuit number and conductor size in
accordance with the schedules.
D – Dressing of DBs:
A professional electrician will be carrying out for this work.
Cable terminals will be suitable for the specified cable sizes. Adequate space
will be provided for cable terminations.
Dressing of standard cables will be done by using ferrules of sizes suitable for
accommodating all stands of the cables.
After finishing the 1st coat near the final DB’s, we will start fixing the inside
components and numbering, terminating the wires as per the Load Distribution
Schedules, in addition to fixing a suitable identification labels to clearly indicate the
location and the purpose of each item or circuit.
The neutral cable is connected to the neutral strip, which is turning in grounded
with a bare wire.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 14 of 31
Armored cable will be strapped properly, a hacksaw is used to cut the cables, a
suitable angle to the cable for making a cut through one section of the spiral
amour and care will be taken not to cur the wires.
The glands for various single core and multi core cables will be on the purposed
made and suitable for rigid mounting to the enclosure.
Finally, after the dressing completed, the door will be fixed and covered for
protect the panels from any damaged, ensuring that all the engraved labels fixed
for the DB sections, main isolator, ELCBs etc.,
We will start fixing the SMDBs after painting at least 1 st coat in the Electrical
rooms completed. The fixing height for the SMDB’s will be at 800 mm. from
finished floor level as per DEWA regulations as well as trunking arrangement
for the meters or (at height not exceeding 2 meters to the top of the Panel Boards
from the finished floor level)
SMDBs will be wall or floor mounted type depending of the frame size of the
board. All the trunking arrangements will be done as per the approved shop
drawings.
In case of floor mounted boards (MCC-R) a depressed floors will be provided
with galvanized steel support structures to raise the level of the panel.
Wiring, cabling and dressing for the SMDBs will be nearly similar to dressing of
the DBs and all the connections will have front access only.
Page 15 of 31
1st coat painting should be completed in the Main Electrical Room before the
panels are delivered to site upon the Consultants inspection and approval of the
Panels.
Cable ladders and cable trays start assembling at main electric room as per the
approved layout for incoming and outgoing cable which is top or bottom entries.
Incoming and outgoing feeder will be installed.
Dressing and termination for the feeders will be done by a electrical specialist
and well experienced and professional electricians.
All the meters (CT’s meter and check meters) will be installed in the respective
main distribution boards after tested and calibrated by DEWA.
Testing:
On completion of the installation and prior to its being made “Alive” for service,
all the electrical test will carried out all sections of the works in the presence of
the Consultants’ and all the tests will be carried out in compliance with the
DEWA regulations and the contract specifications. All the test reports will be
submitted to the Consultants’ along with the As-built drawings and Operation
and Maintenance documents.
Page 16 of 31
After finishing the pre-final coat for the building, we will start fixing the wiring
Accessories, light fittings, fire alarm devices. Of course the fitting where is
coming in the false ceiling should be fixed in the proper way with more
supports if required:
Cover plate finish, all accessories to match - Molded plastic, color - white.
Neon indicator with red lens, illuminated in `ON’ position, for connection
units.
Installation General.
All accessories shall be properly aligned with vertical edges; plumb and
horizontal edges level and mounted at the height recommended below and shall
be to the approval of the Engineer.
All flush accessories shall have cover plates fitted correctly onto the wall or
ceiling or any other services. Any accessories found to be incorrectly aligned
after installation will have to be removed and re fixed.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 17 of 31
Local lighting switches for the control of lighting circuits shall be of the
following types:
For single and multi-gang units in locations in the building where installation
work is on the surface switches shall be of the surface pattern and shall be
mounted in proprietary metal boxes.
For single and multi-gang units in all areas throughout the building where
installation work is concealed, switches shall be of the 10A grid switch type
flush pattern and shall be mounted in suitable metal boxes..
For areas where switches are shown connected to different phases, in the same
location, multi-gang switches are to be used with an approved phase barrier and
shall also be to the requirement of the local authority..
ii) Obtain Etisalat / DIC (Dubai Internet City) approval for telephone workshop
drawing.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 18 of 31
iii) Install sleeves for main telephone incomer. Install telephone boxes &
telephone junctions boxes. Prior co-ordination with Etisalat is required for
exact location of telephone main cable entry sleeve.
vi) Run wires from various telephone / data outlets in to intermediate telephone
distribution frames, via trunking / pipes in corridors false ceiling area.
vii) Run telephone / data cables from intermediate distribution frame panel into
main distribution frames in ground floors low current room via trunking /
cable riser.
viii) Install distribution frame panels, telephone / data outlets and terminate
relevant wires and cables.
Obtain Civil Defense Department approval on the fire alarm system after
consultant’s approval.
Page 19 of 31
Install fire alarm panel in ground floor and terminate loops and bell circuit wires.
Page 20 of 31
The Following are the tests that will be carried out on final electrical circuits and
distribution boards. The observations and readings will be recorded in the
appropriate formats.
a) Visual Check
Check the installation of distribution boards and the internal wiring to ensure
electrical and mechanical connections, identification, labeling etc.
Check that all the metallic components are properly earthed / binded.
b) Polarity Check
Ensure that single pole switches are installed in the live conductor.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 21 of 31
Where Screw type lamp holders are in circuit, ensure that the outer or screwed
conductor is connected to the neutral conductor.
The Continuity resistance of the protective conductor from the furthest point to
the main earth terminal is to be measured for each final circuit with a DC ohm
meter and the value recorded and verified to be within the permissible limit.
The continuity resistance between the open ends of each of the three rings of
circuit (i.e. phase, neutral and earth) is to be measured for all ring final circuit
conductors with D.C. ohm meter and the value to be verified with the
permissible limits.
The following are the tests that will be carried out on distribution cables. The
observation / readings of the tests will be recorded in the appropriate formats.
a) Visual Check
The installation of the cable to be checked to ensure the correct laying, proper
glanding, corrects termination, adequate supports, labeling, identification etc.
b) Insulation Resistance Test
Page 22 of 31
c) Phase Rotation Test
After completion of tests (a) and (b) stated above, the relevant breaker is to be
switched on and the phase rotation at the down stream point is to be checked and
ensured that it is same as elsewhere (i.e. RYB ).
d) Performance Test
Upon verification of the correct phase rotation to the connected equipment,
switch on the isolator ( if any ) and run the equipment to verify the complete
performance of the connected equipment and minimum 24 hrs. To check for any
abnormal temperature rise in cables, terminals, switches and protective devices
etc.
e) Insulation Resistance
Note:- The mains supply can be switched on to the final circuit to enable
further tests to be carried out, which require supply voltage.
Earth fault loop impedance is to be checked for each final circuit with an
impedance tester. (RCCB to be by passed during test) and the reading is to be
verified with the permissible limit.
g) RCCB Test.
All RCCB (ELCB) are to be checked by means of a RCCB tester with minimum
3 different set currents (One setting above, one below and one rated sensitivity
currents of an ELCB) and the trip times are to be recorded. The values to be
verified with the permissible limits.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 23 of 31
h) Circuit Performance
After all the above tests are conducted and observed that they are satisfactory,
and operational test to verify the desired performance of the circuits need to be
carried out. They are as follows:
In case of lighting circuits, operate all the switches connected in the circuit one
ensures their functioning to the desired light fixture in the desired manner.
In case of ring / radial circuits, test all the sockets with a test lamp to ensure the
availability of power.
In case of any other fixed equipment, operate the relevant switch and observed
the functioning of the equipment.
- Measure and record the current in all phase of the incoming cables in lighting
DB’s keeping all the lights “ON”.
The following are the tests that will be carried out on the MDB’s / SMDB’s /
MCC’s.
The Complete panel is to be inspected and checked against the shop drawing to
ensure that right components of correct ratings are installed and properly labeled
and identified.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 24 of 31
All the bolts / nuts and bus bar connections are to be checked to ensure that all
are properly tightened.
All the meters and selector switches are to be checked to ensure that correct
selection and ratings.
Insulation resistance between phases, neutral and earth are to be measured with a
500 volts meggar and the valves to be verified with the permissible limits.
(During this test, care is to be taken to disconnect components such as lamps,
meters etc. Which will get damaged upon application of 500 volts).
c) Interlock Tests.
Interlocks between NEC (Normal Electric Connector) and generator incomers to the
essential feeders are to be verified to ensure proper operation.
d) Functional Test.
To start the functional tests, check the control circuit of each starter / system for
its correct operation in regard to switching on actuation of thermal overload and
emergency stop – lock etc.
The operation of starter for various equipment such as pumps, fans etc. is to be
checked to ensure the desired function and currents at various stages of loads are
to be recorded.
The operation of the indicating lamps and meters are to be verified to ensure
proper functioning.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 25 of 31
All equipment which are supposed to be “ ON “ simultaneously are to be run at
full load for a minimum period of 2 hrs and check for any abnormal rise in
temperature on bus bars, jumper cables, terminals and various devices.
All the earth leakage circuit breakers are to be checked by means of RCCB
tester, setting 50%, 100% and 150% of the rates sensitivity currents and the
respective trip times to be recorded. The readings are to be recorded. The
readings are to be compared with the characteristic values of the ELCB’s to
ensure their correct operation.
Where core balance CT’s and EL, relays are provided for earth leakage
protection, an earth leakage current of known valve is simulated by external
means and the trip times is to be recorded for 50 %, 100% and 150% of the rated
sensitivity currents. The readings are to be compared with the characteristic
values of the EL relay (RCCB tester can be used for simulation of earth
leakage currents).
a) Visual Check
All the earth electrode in the earth pits is to be visually inspected proper
installation and connections.
All the protective conductors from the earth electrode to the main boards and
distributions are to be visually inspected for proper installation and connections.
The earth electrode resistance of each earth pit is to be measured with a Meggar
after removing the protective conductor connection and the readings to be
recorded and verified with the permissible limit.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 26 of 31
c) Continuity Test.
The continuity resistance between the main earth terminal at the distribution
board and the metallic frame works of farthest equipment to be measured a D.C.
ohm meter and the value to be recorded and verified with the permissible limit
to ensure proper bonding.
The following are the tests that will be carried out on the lighting protection
system.
a) Visual Check.
All the joints are to be cleaned & lightened to maintain good continuity
resistance.
The earth electrode resistance of each earth pit is to be measured with an earth
meggar after removing the lightning system continuity conductor connection and
the readings are to be recorded and verified with permissible limits.
c) Continuity Test.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 27 of 31
The Continuity resistance between lightning protection conductor at the selected
farthest points and the earth electrode is to be measured with a D.C. ohm meter
and the readings to be verified with the permissible limits.
The continuity resistance between the lightning protection conductor and the
metallic frame works bonded with the lightning protection system is to be
checked with a D.C. ohm meter and the reading to be verified with the
permissible limits.
6.6) TESTS ON FIRE ALARM SYSTEM.
The following are the tests that will be carried out on the Fire Alarm System.
a) Visual / Wiring Check.
All the cables connected to the fire Alarm system control panel and battery is to
be inspected and checked for proper connections as recommended by the
manufacturer.
The whole of the installation in general is to be checked to ensure proper
installation.
b) Functional Test.
After restoring the power supply to the panel, the necessary adjustments and
settings are to be made so that the panel is put into operation.
Once the panel is in operation, all the detectors / break glasses are simulated to
be activated by giving smoke and the display of zone nos. of the detector
activated is
witnessed on the panel and the operation of he LED on the detector is to be
noted. Further, the indication on the repeated control panel is to be checked and
verified for correct functioning.
During the above testing the sounder circuits and bells should be checked and
ensured that they function correctly.
Faults such as power supply failures, battery, and open circuit of zones are
simulated and the respective visual indications on the panel by means of LED
are to be checked and ensured for proper functioning.
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 28 of 31
The following are the tests that will be carried out on the Fire Alarm Cables. The
observations / readings of the tests will be recorded in the appropriate format.
a) Visual Check.
The installation of the cable to be checked to ensure the correct laying proper
termination, adequate clipping, labeling identification etc.
b) Insulation Resistance Tests.
- Insulation Resistance between cores is to be measured with a 500 volts meggar
and the readings to be verified with the permissible limits.
7. TEST REPORTS
8. Manpower.
Page 29 of 31
9. Records.
No. Document
1. Inspection Request
2. Area clearance form
10.Approvals
Project Manager
Engineer
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 30 of 31
TEST REPORT
FOR
ELECTRICAL WORKS
Doc. No. JB-GN / ELECTRICAL
Al Andalus Tr. & Elect. Cont. REV. 0.
Page 31 of 31
3. Power Cables.
6. Intercom System.
8. Generator Set
@@@@@@@@@@
**END**@@@@@@@@@@@