PMP Formulas Cheat Sheet
PMP Formulas Cheat Sheet
EV Earned Value
AC Actual Cost
Use the chart to help you understand the cost management formulas.
Cost Variance: CV = EV – AC
Schedule Variance: SV = EV – PV
Estimate at Completion: The expected total cost of completing all work expressed as the sum of the
actual cost to date and estimate to complete.
EAC = AC+(BAC-EV)/(CPI*SPI) If both CPI and SPI influence the remaining work.
Estimate to Complete: The expected cost to finish all remaining project work.
To Complete Performance Index: A measure of the cost performance that must be achieved with the
remaining resource in order to meet a specific management goal.
LS = Late Start
Float (or slack) = LS – ES ES = Early Start
Float (or slack) = LF – EF LF = Late Finish
EF = Early Finish