A Study On Employing of Optimum Resources in Multi Project Scheduling

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Volume IV, Issue III, March 2015 IJLTEMAS ISSN 2278 - 2540

A Study on Employing of Optimum Resources


In Multi Project Scheduling
K.Karuppasamy1, S.Christopher Gnanaraj2
1
M.Tech(CEM)., Kalasalingam University
2
Assistant professor, Kalasalingam University

Abstract: Resources management plays a key role in the operation research: Resource-Constrained Multi-Project
success of any construction project. Incapable resources Scheduling (RCMPS) .The scheduling of multiple projects
usage has its effect on the cost and schedule of a project. under resource constraints demands extreme difficult
Construction contractors usually deploy simultaneous computation.
multiple projects under limited resources e.g. labors and
machines condition. The resources are always limited in
On most projects it is possible to carry out
nature.. The main problem of the construction people to
make use of the resources in fruitful manner. The most multiple activities simultaneously. Usually it is possible to
important part of a construction project scheduling is the perform several activities at the same time; however there
assignment of resources and the harmonization of their work will be activities which cannot begin until a preceding
to minimize the project duration. These problems can activity has been completed. Such relationships are
reputedly be solved as the well-known problem in the referred to as dependencies or precedence and when
operation research: Resource-Constrained Multi-Project planning a project it is important to establish the order of
Scheduling (RCMPS).The ever increasing project complexity precedence of dependent activities, and to establish those
is the key driver for construction mangers to take up the activities which can be performed in parallel with other
critical path method (CPM) based scheduling software like
activities. Regardless of the nature or size of the project a
Primavera Project Planner.
successful outcome can only be achieved by using sound
Keywords-. Resources management, Resource-Constrained project management techniques.
Multi-Project Scheduling (RCMPS), Primavera Project
Planner. II. RESEARCH SIGNIFICANCE

I. INTRODUCTION For most of the civil engineering projects the


resources in the form of material, labor and equipment are
well defined. However, anticipated availability of these
A project is an interrelated set of activities that has
definite starting and ending points resulting in the
accomplishment of a unique, often major outcome. A
resources is seldom available throughout the multi-project
which leads to fluctuation in the project duration. The
scarcity of resources can be envisaged as constraints
project may be defined as a means of moving from a within which the project has to be operated. Such a study
problem to a solution via a series of planned activities. It enables one to have a foresight on the how the project will
can be of any size and duration, a project has a definite progress as and when the constraints strike the project
beginning and end, a project consists of several activities. during its different phases of execution. Though the effect
Essential features in every project are; they must be of constraints has been studied in a generic manner,
planned out in advance and the execution of the project specific study with reference to typical Indian medium
must be controlled to ensure that the desired results are size projects is not found in the literature. Such a study
achieved. will have enormous research significance since the results
of which can be straightaway applied to many
Construction contractors usually deploy
infrastructure projects being undertaken in India.
simultaneously multiple projects under limited resources
Therefore this multi-project work is undertaken to study
(e.g.labors and machines) condition. To perform multiple
the impact of multi resource constraints on the project
projects, a construction contractor can access two sources
duration with reference to the two constructions of Green
of resources: internal resources, which are under the
Square apartment at and godown building at Madurai.
contractor ownership and external resources which can be
obtained from the open market. The common objective is III.DATA COLLECTION
to create the most efficient schedule possible to maximize
the usage of the contractor‟s internal resources and just Green Square Apartment in Madurai is a type of
use the market to balance the contractor‟s operation residential building construction.
Because the project duration is one of the main factors of
competiveness on the difficult construction market, the Details about the project
most important part of a construction project scheduling is
the assignment of resources and the harmonization of their Flat -1= 977Sqft
work to minimize the project duration. These problems
can reputedly be solved as the well-known problem in the Flat -2= 880Sqft

www.ijltemas.in Page 58
Volume IV, Issue III, March 2015 IJLTEMAS ISSN 2278 - 2540

Flat -3= 977Sqft Overall activity in project is 85 activities.

Flat -4= 1040Sqft IV. RESULTS AND DISCUSSION

Flat -5= 1103Sqft 4.1. General:


Plinth area = 4558Sqft Using the Primavera Project Planner the impact of
identified constraints on the duration of the project is
Total area of the building = 22790Sqft (G+4) studied and presented in this chapter. The original
duration of the project without any crucial relationship
Godown building in Madurai is a type of commercial
and constraints either on the machine or the labour is
building construction.
found to be as follows
Details about the project
Table 1.Scheduling of the project without any constraints
Plinth area = 4095.38Sqft
Project Duration Start date Finish
Total area of the building = 6401.35Sqft date
Green 18 April
for the (relatively) short duration of a construction project. Square months October4,2012 20
Overtime or double shift work also provide some Apartment ,2014
flexibility.

Scheduling for the project: The schedule report gives us the following details
Major activities Total number of activities = 85
1. Basement

2. Stilt floor

3. First floor structure

4. Second floor structure

5. Third floor structure

6. Fourth floor structure

7. Finishing work for ground floor

8. Finishing work of first floor structure

9. Finishing work of second floor structure

10. Finishing work of third floor structure

11. Finishing work of fourth floor structure


Figure 1. Scheduling report
12. External finishing work
The Figure 1. shows scheduling for various activities for
13. Painting work for ground floor executing the project. Communicating the project
schedule is a vital ingredient in successful project
14. Painting work for first floor management. A good presentation will greatly ease the
15. Painting work for second floor manager‟s problem of understanding the multitude of
activities and their inter-relationship. Moreover, numerous
16. Painting work for third floor individuals and parties are involved in any project and
they have to understand their assignments.
17. Painting work for fourth floor
4.2. Baseline resources allocation of the project
18. External painting

Total of 18 major activity Table 2. Standard labour estimate(As per CPWD)

www.ijltemas.in Page 59
Volume IV, Issue III, March 2015 IJLTEMAS ISSN 2278 - 2540

Activity Quantity Labours(per day) The baseline resources allocation fields show the total
planned resources, number of resources for all assigned
Excavation 320 cum JCB 1 tasks, or for work to be performed by a resource an a task.
From the above Figure 3. we can assess the resources for
P.C.C 10 cum HM ¼,M 2,L 20 the project.

R.C.C 10 cum HM 1/2,M 3,L 23 4.3. Resources over allocation

Brick work 10 cum HM 1/2,M 9,L 18,B The resources over allocation report shows us the
2 following details

Plastering 100 sqm HM 1,M 7,L 10,B 1

Flooring 100 sqm HM 1/2,M 4,L 4

*HM-Head Mason ,M-Mason-Labour,B-Bhisti

Table 3. Resource allocation (Parametric estimation)

Activity Quantity No.of Labours(perday)


days

(Per H M L B
floor) M
Excavation 320 cum 4 - - 2 -

P.C.C 10 cum 4 2 16 160 - Figure 4. Resources over allocation

The Figure 4. reveals the over allocation of the resources


R.C.C 10 cum 7 4 21 161 -
in the project. The over allocation of resources over
certain time period can be seen in the above figure. The
Brick work 10 cum 7 14 42 70 28
resources can be leveled and over allocation can be
eliminated by leveling the resources.
Plastering 100 sqm 21 32 22 315 42
4.4. Resources leveling:
Flooring 100 sqm 14 7 28 28 -
The resource leveling report show us the following details
The resources report shows the following details

Figure 2. Listing of resources

Figure 5. Resources leveling

Table 4.Scheduling of the project with resource


constraints

Project Duration Start date Finish date


Green Square 12 months October September
Apartment 4,2012 25 ,2014
Figure 3. Baseline resources allocation

www.ijltemas.in Page 60
Volume IV, Issue III, March 2015 IJLTEMAS ISSN 2278 - 2540

VI. CONCLUSION

The use of Primavera Project planner, which


proved to be very useful during the execution stage, which
avoided many problems have arisen if had it been done in
office or any other place. An attempt has been made for
sharing the various resources for the project, which has
been utilized.

By resources constraints concept, the


uncertainties of the project will be defined at the early
stages of the project.

Construction projects are often deployed in an


open execution environment, during the execution phase
of construction projects, the initial scheduling always has
to be adapted to the reality state due to dynamic and
incomplete data.

Hence project activities must be subject to


considerable uncertainty, which may lead to numerous
schedule disruptions. Further research should focus on
finding the solution that to make the stability for the
project scheduling.

It is visualized that successful implementation of


this system will enable generation of reliable plans and
constraints-free assignments, in turn, reduce production
risks and improve on- site productivity.

REFERENCES

[1] Hans,W. Herroelen, R. Leus, G.Wullink. (2007): „‟A hierarchical


approach to multi-project planning under uncertainty‟‟. Omega,
Vol. 35, pp. 563 – 577. 108
[2] Kolisch R. (1996). “Serial and parallel resource-constrained
project scheduling methods revisited: Theory and computation”,
European Journal of Operational Research, Vol. 90(2), pp. 320-
333.E.W.
[3] Kolisch, R. and A. Sprecher (1996): “PSPLIB - A project
scheduling library”. European Journal of Operational Research,
Vol. 96, pp. 205--216.
[4] Lova A. and Tormos P. (2001). “Analysis of Scheduling Schemes
and Heuristic Rules Performance in Resource-Constrained Multi-
project Scheduling”. Annals of Operation Research 102, pp. 263-
286.

www.ijltemas.in Page 61

You might also like