Monitoring Checklist Edited
Monitoring Checklist Edited
Monitoring Checklist Edited
Permit Holder/Representative:
Date of Monitoring:
Coverage of Monitoring
BASIC INFORMATION
Permit No.
Date Approved
Contractor/Permit Holder
Contract/Permit Area (hectares)
Location of the Contract/Permit Area
Commodity/Product
Allowable Volume
Mining Method
Type of Processing, if any
For items not requiring level of compliance, fill-up the information required as derived from the actual monitoring.
b. 3D Quarry Plan
c. Environmental Protection and Enhancement
Program
d. Community Development Program
a.
b.
c.
d.
e.
Mine Design Parameters
a. Bench Height
b. Bench Width
c. Bench Slope
d.
e.
f.
(Note: In case of late or non-submission of reportorial requirements mentioned, the penalty stipulated in Item 9.3 Section 27 Article IV of SP Ordinance No.
3617-2010 shall be imposed)
a. Facilities
CONSTRUCTED BUT
CONSTRUCTED AND IN NOT YET
FACILITIES DILAPIDATED/NEEDS REMARK/S
GOOD CONDITION CONSTRUCTED
REPAIR/RENOVATION
Other/s (specify)
b. Human Resources
HUMAN RESOURCES
Total number of personnel/laborers (Male/Female)
Total number of locals hired (Male/Female)
Total number of migrant workers (includes workers from Provinces, other than the host
c. Technical/Key Persons
COMPLIAN
HIRED/EMPLOYE T REMARK/S
TECHNICAL/KEY PERSONS
D (Provide Details of Hiring/Employment)
YES NO
Licensed Mining Engineer, Geologist or Metallurgical Engineer on-site to
supervise the activities under the approved 5Yr DUWP
Environmental Officer on-site to supervise the activities under the approved
EPEP
Safety Engineer/Safety Inspector on-site to supervise/manage the
implementation of the Safety and Health Program
Other findings
d. Equipment
STATUS
LIST OF EXISTING EQUIPMENT REMARK/S
O B PM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
(Note: O – Operational; B – Breakdown; PM – Under Preventive Maintenance)
e. Mine Plan/Layout Showing the Location and Extent of Development/Extraction Activities
COMPLIANT REMARK/S
REQUIREMENTS (Provide Date of Last Revision/Updating)
YES NO
COMPLIANT REMARK/S
REQUIREMENTS
YES NO
Other Finding(S)/Observation(S)
___________________________________________________________________________________________________________________________
___________________________________________________________________________________________________________________________
___________________________________________________________________________________________________________________________
___________________________________________________________________________________________________________________________
___________________________________________________________________________________________________________________________
___________________________________________________________________________________________________________________________
Annexes
a. Photographs
b. Copy of pertinent documents
COMPLIANT
PARAMETERS LEGAL BASIS REMARK/S RECOMMENDATIONS
YES NO
1. Environmental Section 74 and
Protection and 169 of DAO 2010-
Enhancement Program 21
(EPEP)
A. Physical Accomplishments
1. Land Resource
a. Progressive Rehabilitation
b. Access Roads
c. Stockpiles
d. Waste Dumps
e. Settling/Siltation pond
f. Tree Planting/Vegetation enhancement
g.
2. Water Resource and Quality
a. Maintenance of settling/siltation pond
d.
e.
3. Air Quality
b.
c.
I. Reportorial Requirements
1st Q
Date
submitted to &
1. Quarterly 2nd Q
Section 5.b of received by
Compliance
DAO No. CMRB within
Monitoring
2015-02 15 days 3rd Q
Report
Coverage
Period
4th Q
COMPLIANT
PARAMETERS LEGAL BASIS REMARK/S RECOMMENDATIONS
YES NO
a.
b.
c.
d.
e.
GRAND TOTAL
COMPLIANT
PARAMETERS LEGAL BASIS REMARK/S RECOMMENDATIONS
YES NO
2. Strict
Implementation of
Mine Labor Age Section 163 of
Limit (18 y/o for DAO 2010-21
Surface and
Underground)
COMPLIANT
PARAMETERS LEGAL BASIS REMARK/S RECOMMENDATIONS
YES NO
Section 2 of Rule
1. No. of Safety
8-11 of DAO No.
Engineer/Inspector
2000-98
2. Proper
Section 163 of
Housekeeping in
DAO 2010-21
the Workplace
Section 63, Rule
3. Provision of PPE 849 of DAO No.
2000-98
Section 63, Rule
4. Strict
850-856 & 858-
Implementation of
859 of DAO No.
wearing PPE
2000-98
FUND UTILIZATION
ELEMENTS OF SAFETY AND HEALTH
COMMENTS/RECOMMENDATIONS
PROGRAM ANNUAL BUDGET AMOUNT UTILIZED PERCENTAGE (%)
A. Proper Housekeeping
B. Provision of PPE
C. Others
TOTAL
*Safety and Health Activities are not limited to the above-mentioned elements.
COMPLIANCE COMPLIANT
PARAMETERS LEGAL BASIS REMARKS/RECOMMENDATIONS
INDICATOR YES NO
Monthly Accident
1. On-Time Submission of
Section 155 (b.1) of and Sicknesses
Monthly Accident and
DAO 2010-21 Report on MGB
Sicknesses Report
Form 15-5