MOUTING STRUCTURE INSTALLATION RECORD

150 MWac (DT1) Photovoltaic Solar Power


Project Client Dau Tieng Tay Ninh Energy Joint Stock Company
Plant in Vietnam
Area RFI No. Date
QA&QC-DT-
Element Format No. Page No.
FRMC-009
ITP No. DWG No.

String/ Circuit no.

The following items have been checked and cleared YES NO N/A

1 MOUTING STRUCTURE INSTALLATION


1.1 Checking mill test certificate
1.2 Visual inspection of galavanize coatings for damage
1.3 Thickness of galvanized coatings
1.4 Surface preparation done according to requirements
1.5 Check welding connection
1.6 Protective coating done after welding
1.7 Check type of string installation
1.8 Dimensional check of fit up components, holes, overall length, markings
1.9 Orientation, Elevation, Leveling & Alignment check

1.10 Tightness check of all connection including foundation bolts with requirements

Remarks:
1- Tolerance for installation
Slope at girder 12 degree
Slope deviation: ±1 °
Elevation of string< 10 mm
2 - Torque value setting for all
connection
Beam and Column
95.5 Nm
M14x50:
Pipe hoop M14x70: 95.5 Nm
Front/Backward brace
95.5 Nm
and pipe hoop M14x50:
Front/Backward brace
95.5 Nm
and beam M14x50:
Purlin and purlin
35.1 Nm
hanger M10:
Purlin splice M8: 17.6 Nm

Contractor(EPC) Owner's Engineer Owner

Name

Signature

Date