I/c P/A Primer Evenly A Priming/tack Coat With Bitumen (80/100) 15.14.1. - 5kg/10sqm

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Item - 3 Providing 25mm thick semi-dense carpeting course aggregate fine aggregate and filler required grading conforming

to Table 500.11 of IRC


specification in sufficient to yield specified thickness after compaction including through dressing of surface, screening and cleaning of stone materials
making component including coarse aggregate, fine aggregate and filler to obtain homogeneous mixture with requisite quantity of binder @ 5.50% by
weight to mix, mixing the quantity in hot mix plant conforming to IS 3066 and laying the mixture uniformly to specified grade line and cross section over
the existing surface. 15.28.2 Using Bitumen (80/100)

p/166 = Rs.333.90 / sqm


i/c P/A primer evenly a priming/tack coat with bitumen (80/100) 15.14.1. - 5kg/10sqm
p/166 0.50 x Rs.33.60 /sqm = Rs.16.80 / sqm
Transportation charges (Quarry toMixing yard)
a) Stone metal below 40mm 0.03400 cum/sqm@ Rs.700.86 /cum = Rs.23.83 / sqm
b) Bitumen
i) Carriage charge (Source to W/site)
( 0.5 / 1000 ) MT/sqm x Rs.210.63 = Rs.0.11 / sqm
ii) Carriage charge (Source to mixing yard)
( 316.25 )/ (1000 x100) MT/sqm x Rs.210.63 = Rs.0.67 / sqm
iii) Mixed material from yard to site
= 2.3MT/CUM' 0.0575 x Rs.210.63 = Rs.12.11 / sqm
Rs.387.41 / sqm

Section Officer, Assistant Engineer-II,


Imphal East Divn., Imphal East Divn..