This document provides a rate analysis for transportation costs of materials for a road construction project from Imphal to Khomidok in Manipur, India. It calculates transportation costs over various distances from sources to the work site for materials like stone aggregate, sand, gravel, cement, bitumen, and others. Transportation costs per kilometer decrease with increasing distances and include a 15% charge. The total transportation cost per cubic meter is calculated for each material based on the distance involved and its weightage in the work.

Uploaded by

Hemam Prasanta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views3 pages

Add 12% GST On A

This document provides a rate analysis for transportation costs of materials for a road construction project from Imphal to Khomidok in Manipur, India. It calculates transportation costs over various distances from sources to the work site for materials like stone aggregate, sand, gravel, cement, bitumen, and others. Transportation costs per kilometer decrease with increasing distances and include a 15% charge. The total transportation cost per cubic meter is calculated for each material based on the distance involved and its weightage in the work.

Uploaded by

Hemam Prasanta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Rate Analysis

Based on MSR 2017


Name of work:-Impvt. of Imphal Saikhul Road from 0.20Km (Lamlong Bridge) to 2.40km (Khomidok)
Lead Chart
1. Carriage charge of stone aggregate from Bongmol
2 Km. 1 Km. (approach)
Khongnangkarak
290 km 298 km 317.0km km 320
Kanglatonbi Sekmai 316 km Imphal
4.20 km
Work site Add 12% GST on A
6.20 km
Mean Lead
( 4.20 + 6.20 )/2 = 5.20 km
Say = 5.00 km
Transportation Charges
Lead involved (Lead upto work site)
(i) Stone metal above 40 mm Lead:- ( 317.00 - 290.00 )+ 5.00 + 2.0 = 34.00 km
(ii) Stone metal below 40 mm Lead:- ( 317.00 - 290.00 )+ 5.00 + 2.0 = 34.00 km
(iii) Bitumen ( 317.00 - 316.00 )+ 5.00 = 6.00 km
(iv) Sand gravel ( 317.00 - 298.00 )+ 5.00 + 1.0 = 25.00 km
(v) Sand ( 317.00 - 298.00 )+ 5.00 + 1.0 = 25.00 km
(vi) Steel/Cement ( 320.00 - 317.00 )+ 5.00 = 8.00 km
From source to Mixing plant
(i) Stone metal above 40 mm Lead:- ( 316.00 - 290.00 )+ 2.0 = 28.00 km
(ii) Bitumen = 1.00 km
(iii) Sand ( 316.00 - 298.00 )+ 1.00 = 19.00 km
From Mixing plant to Work site
(i) Mix Material ( 317.00 - 316.00 )+ 5.00 = 6.00 km
Transportation Charges
From Source to work site
(i) Stone metal above 40 mm Lead:- 34.00 Km.
0 - 5 Km. = Rs.263.17/ Cum
5 - 10 Km. @ Rs.19.72 / Km. = Rs.98.60/ Cum
10 - 20 Km. @ Rs.15.27 / Km. = Rs.152.70/ Cum
20 - 34.00 Km. @ Rs.11.73 / Km. = Rs.164.22/ Cum
= Rs.678.69/ Cum
Add 15% C.P. (+) = Rs.101.80 / Cum
"A" = Rs.780.49 / Cum
(ii) Stone metal below 40 mm Lead:- 34.00 Km.
0 - 5 Km. = Rs.242.71 / Cum
5 - 10 Km. @ Rs.18.19 / Km. = Rs.90.95 / Cum
10 - 20 Km. @ Rs.14.08 / Km. = Rs.140.80 / Cum
20 - 34.00 Km. @ Rs.10.82 / Km. = Rs.151.48 / Cum
Rs.625.94 / Cum
Add 15% C.P. (+) = Rs.93.89 / Cum
"B" = Rs.719.83 / Cum
Stone metal above 40 mm 55% of "A" = Rs.429.27 / Cum
Stone metal below 40 mm 45% of "B" = Rs.323.92 / Cum
= Rs.753.20 / Cum
(iii) Stone shingle above 40mm 25.00 Km.
0 - 5 Km. = Rs.263.17/ Cum
5 - 10 Km. @ Rs.19.72 / Km. = Rs.98.60/ Cum
10 - 20 Km. @ Rs.15.27 / Km. = Rs.152.70/ Cum
20 - 25.00 Km. @ Rs.11.73 / Km. = Rs.58.65/ Cum
Rs.573.12/ Cum
Add 15% C.P. (+) = Rs.85.97 / Cum
(A) = Rs.659.09 / Cum
(iv) Stone shingle below 40mm 25.00 Km.
0 - 5 Km. = Rs.242.71 / Cum
5 - 10 Km. @ Rs.18.19 / Km. = Rs.90.95 / Cum
10 - 20 Km. @ Rs.14.08 / Km. = Rs.140.80 / Cum
20 - 25.00 Km. @ Rs.10.82 / Km. = Rs.54.10 / Cum
Rs.528.56 / Cum
Add 15% C.P. (+) = Rs.79.28 / Cum
(B) = Rs.607.84 / Cum
Carriage charge of Sand Gravel 5% of A = Rs.32.95 / Cum
95% of B = Rs.577.45 / Cum
Rs.610.41 / Cum
(v) Bitumen 5.00 Km.
0 - 5 Km. = Rs.183.16 / MT
5 - 6 Km. @ Rs.13.72 / Km. = Rs.13.72 / MT
Rs.196.88 / MT
Add 15% C.P. (+) = Rs.29.53 / MT
Bridge work 0 - 5 Km. == Rs.242.71 // MT
Rs.226.41 Cum
D' Earth /Mooram
0 - 5 Km. = Rs.225.61 / km
Add 15% C.P. (+) = Rs.33.84 / Cum
= Rs.259.45 / Cum
From Source to Mixing plant
(i) Stone metal above 40 mm Lead:- 28.00 Km.
0 - 5 Km. = Rs.263.17/ Cum
5 - 10 Km. @ Rs.19.72 / Km. = Rs.98.60/ Cum
10 - 20 Km. @ Rs.15.27 / Km. = Rs.152.70/ Cum
20 - 28.00 Km. @ Rs.11.73 / Km. = Rs.93.84/ Cum
= Rs.608.31/ Cum
Add 15% C.P. (+) = Rs.91.25 / Cum
= Rs.699.56 / Cum
(i) Stone metal below 40 mm Lead:- 28.00 Km.
0 - 5 Km. = Rs.242.71/ Cum
5 - 10 Km. @ Rs.18.19 / Km. = Rs.90.95/ Cum
10 - 20 Km. @ Rs.14.08 / Km. = Rs.140.80/ Cum
20 - 28.00 Km. @ Rs.10.82 / Km. = Rs.86.56/ Cum
Rs.561.02/ Cum
Add 15% C.P. (+) = Rs.84.15 / Cum
= Rs.645.17 / Cum
(ii) Bitumen
0 - 1 Km. = Rs.117.05 / MT
Rs.117.05 / MT
Add 15% C.P. (+) = Rs.17.56 / MT
= Rs.134.61 / MT
(iii) Sand 19.00 Km.
0 - 5 Km. = Rs.242.71/ Cum
5 - 10 Km. @ Rs.18.19 / Km. = Rs.90.95/ Cum
10 - 19 Km. @ Rs.14.08 / Km. = Rs.126.72/ Cum
Rs.460.38/ Cum
Add 15% C.P. (+) = Rs.69.06 / Cum
= Rs.529.44 / Cum
From Mixing plant to work site
(i) Mixed material Bitumen
0 - 5 Km. = Rs.183.16 / MT
5 - 6 Km. @ Rs.13.72 / Km. = Rs.13.72 / MT
Rs.196.88 / MT
Add 15% C.P. (+) = Rs.29.53 / MT
= Rs.226.41 / MT

Section Officer Assistant Engineer-II,