The document provides instructions to draw activity on arrow (AOA) and activity on node (AON) diagrams, calculate early start/finish dates, late start/finish dates, floats, identify the critical path, and form a final table for a list of 15 activities with durations and predecessors. The table includes the activity number, name, duration, and predecessor activity.
The document provides instructions to draw activity on arrow (AOA) and activity on node (AON) diagrams, calculate early start/finish dates, late start/finish dates, floats, identify the critical path, and form a final table for a list of 15 activities with durations and predecessors. The table includes the activity number, name, duration, and predecessor activity.
The document provides instructions to draw activity on arrow (AOA) and activity on node (AON) diagrams, calculate early start/finish dates, late start/finish dates, floats, identify the critical path, and form a final table for a list of 15 activities with durations and predecessors. The table includes the activity number, name, duration, and predecessor activity.
The document provides instructions to draw activity on arrow (AOA) and activity on node (AON) diagrams, calculate early start/finish dates, late start/finish dates, floats, identify the critical path, and form a final table for a list of 15 activities with durations and predecessors. The table includes the activity number, name, duration, and predecessor activity.
For the list of activities shown in the below table;
A. DRAW (AOA) & (AON) DIAGRAMS. B. THEN CALCULATE THE FOLLOWING: 1. Early start & Early finish dates to all activities. 2. Late start & Late finish dates to all activities. 3. All types of Floats. 4. Define the Critical Path route. 5. Form the final table of activities; showing all details.
NO. ACTIVITY DURATION PREDECSSOR
ACTIVITY 1 A 6 -- 2 B 2 -- 3 C 3 -- 4 D 5 A 5 E 1 B 6 F 4 C 7 G 6 C 8 H 6 D 9 I 9 D 10 J 5 E, F 11 K 12 G 12 L 5 G 13 M 3 H 14 N 5 I,J,K 15 O 17 L