32 0 360 TC x1 x2 LHS Sign RHS 4360

The document describes a linear programming problem to maximize profit for a toy manufacturing company producing two doll models given plastic and time resource constraints. The current production plan yields $4,100 profit weekly. Solving the LP model graphically and in Excel yields a new optimal solution of 320 dozen Space Rays and 360 dozen Zappers for $4,360 weekly profit, fully utilizing resources while meeting all constraints.

Uploaded by

jemal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views2 pages

32 0 360 TC x1 x2 LHS Sign RHS 4360

The document describes a linear programming problem to maximize profit for a toy manufacturing company producing two doll models given plastic and time resource constraints. The current production plan yields $4,100 profit weekly. Solving the LP model graphically and in Excel yields a new optimal solution of 320 dozen Space Rays and 360 dozen Zappers for $4,360 weekly profit, fully utilizing resources while meeting all constraints.

Uploaded by

jemal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Solve the Following LPP using excel and discuss the new solution in comparison with the existing

one.
Galaxy manufactures two toy doll models: Space Ray and Zapper. Resources are limited to 1000
pounds of special plastic and 2400 hours of production time per week.
• Marketing requirement
– Total production cannot exceed 700 dozens.
– Number of dozens of Space Rays cannot exceed number of dozens of Zappers by more
than 350.
 Technological input
– Space Rays requires 2 pounds of plastic and 3 minutes of labor per dozen.
– Zappers requires 1 pound of plastic and 4 minutes of labor per dozen.
• The current production plan calls for:
– Producing as much as possible of the more profitable product, Space Ray ($8 profit per
dozen).
– Use resources left over to produce Zappers ($5 profit per dozen), while remaining
within the marketing guidelines.
• The current production plan consists of:
Space Rays = 450 dozen
Zapper = 100 dozen
Profit = $4100 per week ( = 8*450 + 5*100)
Problem: Management is seeking a production schedule that will increase the company’s profit.
A linear programming model can provide an insight and an intelligent solution to this problem.
• Decisions variables:
– X1 = Weekly production level of Space Rays (in dozens)
– X2 = Weekly production level of Zappers (in dozens).
• Objective Function:
– Weekly profit, to be maximized

Model:
Max 8X1 + 5X2 (Weekly profit)
Subject to
2X1 + 1X2 ≤ 1000 (Plastic)
3X1 + 4X2 ≤ 2400 (Production Time)
X1 + X2 ≤ 700 (Total production)
X1 - X2 ≤ 350 (Mix)
X j ≥ 0, j = 1,2 (Non-negativity)

Solution
(Graphical, simplex and excel)
Space Rays = 320 dozen
Zappers = 360 dozen
Profit = $4360
– This solution utilizes all the plastic and all the production hours.
– Total production is only 680 (not 700).
– Space Rays production exceeds Zappers production by only 40 dozens.

32
  0 360       TC
  x1 x2 LHS sign RHS 4360
c1 2 1 1000 less 1000  
c2 3 4 2400 less 2400  
c3 1 1 680 less 700  
c4 1 -1 -40 less 350  