PRINCE2 Practitioner
PRINCE2 Practitioner
QUESTION NO: 1
Which of the following principles describes this statement?" xxx defines tolerances for each project
objective to establish limits of delegated authority"
A. Manage by stages
B. Focus on products
C. Manage by exception
D. Learn from experience
Answer: C
Explanation:
QUESTION NO: 2
The Learn from Experience principle suggests that lessons should be actively sought...
Answer: B
Explanation:
QUESTION NO: 3
Which of the following principles uses Product Descriptions to provide clarity by defining each
product's purpose, composition, derivation, format, quality criteria and quality method?
Answer: B
QUESTION NO: 4
Which of the following statements is FALSE regarding the Continued Business Justification?
A. The justification for the project must remain the same throughout the project
B. The justification for the project should remain valid
C. The justification for the project may change
D. If the project is no longer justified it should be stopped
Answer: B
Explanation:
QUESTION NO: 5
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and
Quality are three of them, what are the other three?
Answer: A
Explanation:
QUESTION NO: 6
Which statement best explains the purpose of Tailor to suit the project environment?
A. Ensure project controls are based on project's scale, complexity, importance, capability and risk
B. To use a set of pre-defined templates for the size of project
C. To tailor the use of the principles to suit the project
D. To pick which PRINCE2 processes to apply and which to leave out
Answer: D
Explanation:
QUESTION NO: 7
Answer: B
Explanation:
QUESTION NO: 8
A. Reasons
B. Major Risks
C. Business options
D. Business approach
Answer: D
Explanation:
QUESTION NO: 9
When considering the business options in the business case, which of these is NOT an option?
A. Do nothing
B. Do the maximum
C. Do the minimum
D. Do something
Answer: B
Explanation:
QUESTION NO: 10
Answer: C
Explanation:
QUESTION NO: 11
Who is responsible for ensuring that the value-for-money solution is constantly reassessed?
A. Business Assurance
B. Senior User
C. Corporate or Programme Management
D. Reject Support
Answer: A
Explanation:
QUESTION NO: 12
Answer: B
Explanation:
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
replacement staff have not been recruited due to the reduced operation. If the project is
successful, a recruitment campaign will be required to fill the existing staff vacancies and there
may be a requirement for additional staff. Operational costs are likely to increase because skilled
staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would last
into a second year. She has forecast the same increase in orders for a second year and predicts
that the annual employee satisfaction survey will show a measurable improvement in staff morale.
- 20% discount for all repeat customers - not cost-effective and very short term
- A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
- A series of television and press advertisements was too expensive
- A direct mail shot to all customers - benefit would be short term
- Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
A. The Marketing department believes that sending a promotional calendar to current and
prospective customers will increase orders by at least 10%.
Answer: B,E
Explanation:
QUESTION NO: 14
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
replacement staff have not been recruited due to the reduced operation. If the project is
successful, a recruitment campaign will be required to fill the existing staff vacancies and there
may be a requirement for additional staff. Operational costs are likely to increase because skilled
staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would last
into a second year. She has forecast the same increase in orders for a second year and predicts
that the annual employee satisfaction survey will show a measurable improvement in staff morale.
- 20% discount for all repeat customers - not cost-effective and very short term
- A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
A. Produce a promotional calendar as a free Christmas gift to current and prospective customers.
B. Use a professional photographer to create the photographs for the calendar.
C. Create the photographs for the calendar internally.
D. Outsource the creation of the calendar to a professional marketing company.
E. Do nothing.
Answer: A,E
Explanation:
QUESTION NO: 15
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
replacement staff have not been recruited due to the reduced operation. If the project is
successful, a recruitment campaign will be required to fill the existing staff vacancies and there
may be a requirement for additional staff. Operational costs are likely to increase because skilled
staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
- 20% discount for all repeat customers - not cost-effective and very short term
- A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
- A series of television and press advertisements· was too expensive
- A direct mail shot to all customers - benefit would be short term
- Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
A. Increase orders by at least 10% with a minimum of 10 further orders from the list of prospective
customers within 12 months.
B. It will be similar to calendars sent out in previous years
C. The Marketing department believes that the benefits of a good company image, as portrayed by
a successful calendar, will last into a second year and bring the same increase in orders.
D. The calendar will contain photos of both staff and company products.
E. The Marketing department want a very high quality, glossy product as they believe this will be
more appealing to customers.
Answer: A,C
Explanation:
QUESTION NO: 16
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would last
into a second year. She has forecast the same increase in orders for a second year and predicts
that the annual employee satisfaction survey will show a measurable improvement in staff morale.
- 20% discount for all repeat customers - not cost-effective and very short term
- A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
- A series of television and press advertisements· was too expensive
- A direct mail shot to all customers - benefit would be short term
- Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
Answer: B,D
Explanation:
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
replacement staff have not been recruited due to the reduced operation. If the project is
successful, a recruitment campaign will be required to fill the existing staff vacancies and there
may be a requirement for additional staff. Operational costs are likely to increase because skilled
staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would last
into a second year. She has forecast the same increase in orders for a second year and predicts
that the annual employee satisfaction survey will show a measurable improvement in staff morale.
- 20% discount for all repeat customers - not cost-effective and very short term
- A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
- A series of television and press advertisements· was too expensive
- A direct mail shot to all customers - benefit would be short term
- Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
Answer: C,D
Explanation:
QUESTION NO: 18
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
replacement staff have not been recruited due to the reduced operation. If the project is
successful, a recruitment campaign will be required to fill the existing staff vacancies and there
may be a requirement for additional staff. Operational costs are likely to increase because skilled
staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would last
into a second year. She has forecast the same increase in orders for a second year and predicts
that the annual employee satisfaction survey will show a measurable improvement in staff morale.
- 20% discount for all repeat customers - not cost-effective and very short term
- A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
- A series of television and press advertisements· was too expensive
- A direct mail shot to all customers - benefit would be short term
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
Answer: B,E
Explanation:
QUESTION NO: 19
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
replacement staff have not been recruited due to the reduced operation. If the project is
successful, a recruitment campaign will be required to fill the existing staff vacancies and there
may be a requirement for additional staff. Operational costs are likely to increase because skilled
staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would last
into a second year. She has forecast the same increase in orders for a second year and predicts
- 20% discount for all repeat customers - not cost-effective and very short term
- A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
- A series of television and press advertisements· was too expensive
- A direct mail shot to all customers - benefit would be short term
- Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
Which 2 statements correctly define a Business Case risk which should be recorded under the
Major risks heading?
Answer: C,D
Explanation:
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more
about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the
increased marketing activities of its competitors. 10% of customers have not re-ordered in this
financial year and staff morale is poor. A number of skilled staff have left as a result and
replacement staff have not been recruited due to the reduced operation. If the project is
successful, a recruitment campaign will be required to fill the existing staff vacancies and there
In financial terms, there were a total of 1,500 orders in the last financial year, each with an
average profit of £2k. The Marketing department believes that sending a promotional calendar to
our current and prospective customers would increase orders by at least 10% with a minimum of
10 further orders from the list of prospective customers within 12 months from the date of
distribution.
The Marketing Director will be funding the project from the business marketing budget. She
believes that the effect of a good company image portrayed by a successful calendar would last
into a second year. She has forecast the same increase in orders for a second year and predicts
that the annual employee satisfaction survey will show a measurable improvement in staff morale.
- 20% discount for all repeat customers - not cost-effective and very short term
- A promotional calendar as a free Christmas gift - would target current and prospective
customers and the benefits would last into a second year
- A series of television and press advertisements· was too expensive
- A direct mail shot to all customers - benefit would be short term
- Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase
their marketing activity. Whilst the Marketing department wants a very high quality, glossy product,
the project management team must be aware of the cost this will incur.
Using the Project Scenario and the additional Information provided for this question In the
Scenario Booklet, answer the following question.
Lines A to E in the table below consist of an assertion statement and a reason statement. For
each line identify the appropriate option, from options A to E, that applies. Each option can be
used once, more than once or not at all.
Answer:
Explanation:
QUESTION NO: 21
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure
to cut costs, better manage suppliers’ performance and reduce the confusion caused by
inadequate internal controls, outdated standards and outdated technology. External consultants
were employed to conduct a feasibility study to identify options to address the problems, and the
likely costs and benefits. The following options were considered:
Do nothing.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations
were:
One service provider should be contracted to provide the services currently provided by the
The feasibility study developed high-level designs of the current organization, processes, systems
and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief Executive
Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been
appointed from within MFH. Staff within the business functions being outsourced will work with the
external consultants who conducted the feasibility study to define the detailed designs.
A. The lack of up-to-date technology in MFH means a re-engineering of existing services will not
necessarily deliver the performance improvements required.
Answer: C,D
Explanation: http://www.whatisprince2.net/prince2-theme-business-case.php
QUESTION NO: 22
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure
to cut costs, better manage suppliers’ performance and reduce the confusion caused by
inadequate internal controls, outdated standards and outdated technology. External consultants
were employed to conduct a feasibility study to identify options to address the problems, and the
likely costs and benefits. The following options were considered:
Do nothing.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations
were:
One service provider should be contracted to provide the services currently provided by the
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems
and
also made the following recommendations for the management of the project:
Use PRINCE2.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief Executive
Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been
appointed from within MFH. Staff within the business functions being outsourced will work with the
external consultants who conducted the feasibility study to define the detailed designs.
A. The re-engineering of selected business functions would not provide the required outcome.
B. The lack of up-to-date technology in MFH means a re-engineering of existing services will not
necessarily deliver the performance improvements required.
C. Use external consultants to provide guidance on the detailed design of the outsourced services.
D. Set up a PRINCE2 project to deliver the outsourced services.
E. Review a list of service providers to determine a short-list of possible service providers.
QUESTION NO: 23
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure
to cut costs, better manage suppliers’ performance and reduce the confusion caused by
inadequate internal controls, outdated standards and outdated technology. External consultants
were employed to conduct a feasibility study to identify options to address the problems, and the
likely costs and benefits. The following options were considered:
Do nothing.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations
were:
One service provider should be contracted to provide the services currently provided by the
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems
and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief Executive
Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been
appointed from within MFH. Staff within the business functions being outsourced will work with the
external consultants who conducted the feasibility study to define the detailed designs.
Answer: C,D
Reference: http://www.whatisprince2.net/prince2-theme-business-case.php
QUESTION NO: 24
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure
to cut costs, better manage suppliers’ performance and reduce the confusion caused by
inadequate internal controls, outdated standards and outdated technology. External consultants
were employed to conduct a feasibility study to identify options to address the problems, and the
likely costs and benefits. The following options were considered:
Do nothing.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations
were:
One service provider should be contracted to provide the services currently provided by the
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems
and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief Executive
Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been
appointed from within MFH. Staff within the business functions being outsourced will work with the
external consultants who conducted the feasibility study to define the detailed designs.
Answer: C,E
Reference: http://www.whatisprince2.net/prince2-theme-business-case.php
QUESTION NO: 25
Scenario
Do nothing.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations
were:
One service provider should be contracted to provide the services currently provided by the
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems
and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief Executive
Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been
appointed from within MFH. Staff within the business functions being outsourced will work with the
external consultants who conducted the feasibility study to define the detailed designs.
A. The contract with the selected service provider will be agreed during stage 3.
B. The expected benefits will be calculated over 10 years from completion of the project.
C. If more MFH divisions are added to the scope of the services to be outsourced, the project
timescale will be extended and the realization of benefits will be delayed.
D. The expected benefits should start to be realized as soon as the outsourced services become
operational at the end of stage 4.
E. The transfer of equipment and staff is estimated to take six weeks.
Answer: A,B
Explanation:
QUESTION NO: 26
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure
to cut costs, better manage suppliers’ performance and reduce the confusion caused by
inadequate internal controls, outdated standards and outdated technology. External consultants
were employed to conduct a feasibility study to identify options to address the problems, and the
likely costs and benefits. The following options were considered:
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations
were:
One service provider should be contracted to provide the services currently provided by the
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems
and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief Executive
Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been
appointed from within MFH. Staff within the business functions being outsourced will work with the
external consultants who conducted the feasibility study to define the detailed designs.
A. Due to market conditions a suitable service provider may not be found, possibly leading to
premature closure of the project.
B. Owing to employment contract changes staff may resist outsourcing, which would make it
difficult to transfer staff to the selected service provider.
C. MFH's operations may be reduced and the 1a-year contract may not achieve its estimated
value of £80m, which would reduce the service provider's profit.
D. The initial estimates, taken from the feasibility study report, indicate that the project will take two
years to complete, which means that the business problems would remain for this period.
E. The management stages recommended by the consultants may not be appropriate, resulting in
confusion in planning.
Answer: B,D
Explanation:
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure
to cut costs, better manage suppliers’ performance and reduce the confusion caused by
inadequate internal controls, outdated standards and outdated technology. External consultants
were employed to conduct a feasibility study to identify options to address the problems, and the
likely costs and benefits. The following options were considered:
Do nothing.
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations
were:
One service provider should be contracted to provide the services currently provided by the
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems
and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used
once, more than once or not at all.
Answer:
Explanation:
QUESTION NO: 28
Answer: B
Explanation:
QUESTION NO: 29
Which of the following statements is true of the business interest on the project?
Answer: A
Explanation:
QUESTION NO: 30
Which of the following represents the four key characteristics a good Project board should
display?
Answer: B
Explanation:
QUESTION NO: 31
In which Management product would the Project Board specify where the authority for change
requests lies?
Answer: D
Explanation:
QUESTION NO: 32
Who is responsible for ensuring that Communication Management Strategy is appropriate and that
planned communication activities actually take place?
A. Project Assurance
B. Project Manager
C. Corporate or Programme Management
D. Project Support
Answer: A
Explanation:
QUESTION NO: 33
Answer: C
Explanation:
QUESTION NO: 34
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very
well. He injured his leg two years ago which has restricted his visits to the engineering area. As
CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful
career with a publicity company. She has the ability to represent the needs of the business,
particularly as this is a marketing project. She has the authority to commit the annual business
marketing budget, from which the project will be funded, as she sees appropriate. She will be
responsible for monitoring the expected benefits of the calendar, in particular the improvement of
the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part of the
project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control.
They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Which 2 statements explain why the Marketing Director should be appointed as the Executive for
this project?
Answer: C,D
Explanation:
QUESTION NO: 35
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very
well. He injured his leg two years ago which has restricted his visits to the engineering area. As
CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful
career with a publicity company. She has the ability to represent the needs of the business,
particularly as this is a marketing project. She has the authority to commit the annual business
marketing budget, from which the project will be funded, as she sees appropriate. She will be
responsible for monitoring the expected benefits of the calendar, in particular the improvement of
the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part of the
project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control.
They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Which 2 statements explain why the CEO should be appointed as the Executive for this project?
QUESTION NO: 36
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very
well. He injured his leg two years ago which has restricted his visits to the engineering area. As
CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful
career with a publicity company. She has the ability to represent the needs of the business,
particularly as this is a marketing project. She has the authority to commit the annual business
marketing budget, from which the project will be funded, as she sees appropriate. She will be
responsible for monitoring the expected benefits of the calendar, in particular the improvement of
the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part of the
project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control.
They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Which 2 statements explain why the Marketing Director should be appointed as a Senior User for
this project?
QUESTION NO: 37
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very
well. He injured his leg two years ago which has restricted his visits to the engineering area. As
CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful
career with a publicity company. She has the ability to represent the needs of the business,
particularly as this is a marketing project. She has the authority to commit the annual business
marketing budget, from which the project will be funded, as she sees appropriate. She will be
responsible for monitoring the expected benefits of the calendar, in particular the improvement of
the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part of the
project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control.
They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Which 2 statements explain why the Sales Manager should be appointed as a Senior User for this
project?
QUESTION NO: 38
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very
well. He injured his leg two years ago which has restricted his visits to the engineering area. As
CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful
career with a publicity company. She has the ability to represent the needs of the business,
particularly as this is a marketing project. She has the authority to commit the annual business
marketing budget, from which the project will be funded, as she sees appropriate. She will be
responsible for monitoring the expected benefits of the calendar, in particular the improvement of
the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part of the
project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control.
They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Which 2 statements explain why the Purchasing Manager should be appointed as a Senior
Supplier for this project?
QUESTION NO: 39
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very
well. He injured his leg two years ago which has restricted his visits to the engineering area. As
CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful
career with a publicity company. She has the ability to represent the needs of the business,
particularly as this is a marketing project. She has the authority to commit the annual business
marketing budget, from which the project will be funded, as she sees appropriate. She will be
responsible for monitoring the expected benefits of the calendar, in particular the improvement of
the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part of the
project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control.
They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Which 2 statements explain why the Sales Manager should be appointed as User Assurance for
this project?
A. He joined the company last year with huge enthusiasm and is keen to increase sales.
B. He can provide an evaluation of the potential impact the calendar will have on sales.
C. He is able to advise on suitable stakeholder engagement of current and prospective customers.
D. He would like to move into the Marketing department in the future and sees this as an
opportunity to work closely with the Marketing Director.
E. He can resolve any conflict in requirements between the Sales department and the Marketing
Answer: B,C
Explanation:
QUESTION NO: 40
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very
well. He injured his leg two years ago which has restricted his visits to the engineering area. As
CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful
career with a publicity company. She has the ability to represent the needs of the business,
particularly as this is a marketing project. She has the authority to commit the annual business
marketing budget, from which the project will be funded, as she sees appropriate. She will be
responsible for monitoring the expected benefits of the calendar, in particular the improvement of
the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part of the
project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control.
They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Which 2 statements explain why Central Records should be appointed as Project Support for this
project?
A. They control the receipt, identification, versions, storage and issue of all project products within
the company's projects.
B. They already exist within the organization and have been with the company for many years.
C. They will ensure compliance with all company policies and procedures.
Answer: A,E
Explanation:
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very
well. He injured his leg two years ago which has restricted his visits to the engineering area. As
CEO he has an overall perspective of the business strategic requirements and the authority to
commit resources as required.
Marketing Director: She has been with the company for three years, following a successful
career with a publicity company. She has the ability to represent the needs of the business,
particularly as this is a marketing project. She has the authority to commit the annual business
marketing budget, from which the project will be funded, as she sees appropriate. She will be
responsible for monitoring the expected benefits of the calendar, in particular the improvement of
the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the
company and is still as keen and energetic as the day he started. VVhilst he will not be part of the
project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control.
They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office
equipment needs of the company and will supply the stationery for this project.
Using the additional Information provided for this question In the Scenario Booklet, answer the
following question.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used
once, more than once or not at all.
Answer:
Explanation:
QUESTION NO: 42
Additional Information
Director of Finance Division: She was transferred from the Information Technology Division 12
months ago. She is responsible for ensuring a cost-conscious approach is adopted in all
operational and project activities across the Ministry of Food Hygiene.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient
qualified accountant who has much of the responsibility of running the Finance Division on behalf
of the Director of Finance. He has been involved in drafting the Ministry's business strategy and
assisting in a full business risk assessment. He also drafted the corporate Business Case
standards.
Which 2 alternative actions apply to the proposed Executive for this project?
Answer: B,C
Explanation:
QUESTION NO: 43
Additional Information
Director of Finance Division: She was transferred from the Information Technology Division 12
months ago. She is responsible for ensuring a cost-conscious approach is adopted in all
operational and project activities across the Ministry of Food Hygiene.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient
qualified accountant who has much of the responsibility of running the Finance Division on behalf
of the Director of Finance. He has been involved in drafting the Ministry's business strategy and
assisting in a full business risk assessment. He also drafted the corporate Business Case
standards.
Which 2 alternative actions apply to the proposed Senior User for this project?
A. Retain because he provides the outsourcing resources required to support the project.
B. Replace with 'Director of Research and Development' because she deals with both the
Answer: B,C
Explanation:
QUESTION NO: 44
Additional Information
Director of Finance Division: She was transferred from the Information Technology Division 12
months ago. She is responsible for ensuring a cost-conscious approach is adopted in all
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient
qualified accountant who has much of the responsibility of running the Finance Division on behalf
of the Director of Finance. He has been involved in drafting the Ministry's business strategy and
assisting in a full business risk assessment. He also drafted the corporate Business Case
standards.
Which 2 alternative actions apply to the proposed Senior Supplier for this project?
A. Retain because she is responsible for the design of the future Information Technology
organization and working practices.
B. Add 'Director of Facilities' because he is responsible for the design of the future organization,
processes, systems and operation models for Facilities.
C. Add 'Hardware Manager' because he provides computer hardware to all business functions and
will be impacted by the outcome.
D. Remove because she only represents the Information Technology Division.
E. Replace with 'Director of Facilities' because he supports the initiative and has many ideas about
how to improve the service.
Answer: A,B
Explanation:
QUESTION NO: 45
Additional Information
Director of Finance Division: She was transferred from the Information Technology Division 12
months ago. She is responsible for ensuring a cost-conscious approach is adopted in all
operational and project activities across the Ministry of Food Hygiene.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient
qualified accountant who has much of the responsibility of running the Finance Division on behalf
of the Director of Finance. He has been involved in drafting the Ministry's business strategy and
assisting in a full business risk assessment. He also drafted the corporate Business Case
standards.
Which 2 alternative actions apply to the proposed business assurance for this project?
A. Remove because he will be impacted by the project and therefore represents a user.
B. Replace with 'Project Manager' because this is a simple project that does not require additional
Answer: D,E
Explanation:
QUESTION NO: 46
Additional Information
Director of Finance Division: She was transferred from the Information Technology Division 12
months ago. She is responsible for ensuring a cost-conscious approach is adopted in all
operational and project activities across the Ministry of Food Hygiene.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient
qualified accountant who has much of the responsibility of running the Finance Division on behalf
of the Director of Finance. He has been involved in drafting the Ministry's business strategy and
assisting in a full business risk assessment. He also drafted the corporate Business Case
standards.
Which 2 alternative actions apply to the proposed supplier assurance for this project?
A. Retain because he has a professional facilities qualification and so is in a position to specify the
needs of his division.
B. Retain because he will be able to advise on many of the products that will enable outsourcing to
happen, such as the 10-year outsourcing service contract.
C. Retain because he is well-regarded within the Ministry because of the efficiencies, superb
service and savings he has achieved in the Facilities Division.
D. Add 'Outcome Account Manager' because he will advise on potential changes and their impact
on the integrity of the project's products.
E. Remove because he is involved with the project and is therefore NOT independent.
Answer: B,D
Explanation:
QUESTION NO: 47
Additional Information
Director of Finance Division: She was transferred from the Information Technology Division 12
months ago. She is responsible for ensuring a cost-conscious approach is adopted in all
operational and project activities across the Ministry of Food Hygiene.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient
qualified accountant who has much of the responsibility of running the Finance Division on behalf
of the Director of Finance. He has been involved in drafting the Ministry's business strategy and
assisting in a full business risk assessment. He also drafted the corporate Business Case
standards.
Which 2 alternative actions apply to the proposed user assurance for this project?
A. Retain because they are both very positive about outsourcing the selected business functions.
B. Retain because their divisions will be the major users of the outsourced services and they can
Answer: B,E
Explanation:
Additional Information
Director of Finance Division: She was transferred from the Information Technology Division 12
months ago. She is responsible for ensuring a cost-conscious approach is adopted in all
operational and project activities across the Ministry of Food Hygiene.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient
qualified accountant who has much of the responsibility of running the Finance Division on behalf
of the Director of Finance. He has been involved in drafting the Ministry's business strategy and
assisting in a full business risk assessment. He also drafted the corporate Business Case
standards.
Using the Project Scenario and the additional information provided for this question in the
Scenario Booklet, answer the following question about roles on the Outsourcing project.
Answer:
Explanation:
Which principle is central to the quality theme and provides explicit understanding of what the
project will create?
A. Manage by stages
B. Focus on products
C. Manage by exception
D. Learn from experience
Answer: B
Explanation:
QUESTION NO: 50
1. Quality management is the complete set of quality standards, procedures and responsibilities
for a site or organization.
2. Quality planning is about defining products required of the project with their respective quality
criteria, methods and responsibilities.
3. Quality control focuses on the operational techniques and activities used to carry out quality
inspections
4. Quality assurance ensures that quality methods are being correctly followed.
A. 1, 2 & 3
B. 1, 3 & 4
C. 1, 2 & 4
D. 2, 3 & 4
Answer: A
Explanation:
QUESTION NO: 51
Which of the following statements would NOT be included in the Project Product Description?
Answer: D
Explanation:
QUESTION NO: 52
In the PRINCE2 Quality review technique, who would most likely carry out the role of
administrator:
A. Project manager
B. Project support
C. Team Manager
D. Project Assurance
Answer: B
Explanation:
QUESTION NO: 53
Which role is responsible for providing the customer's quality expectations and acceptance criteria
for the project?
A. Executive
B. Corporate or Programme Management
C. Senior User
D. Project Assurance
Answer: C
Explanation:
QUESTION NO: 54
Which management product defines the detailed nature, purpose and function of a product?
A. Plan
B. Quality Register
Answer: D
Explanation:
Column 1 is a list of objectives. For each objective in Column 1, select from Column 2 the quality
activity that addresses it. Each selection from Column 2 can be used once, more than once or not
at all. Drop down the right answer.
Answer:
Explanation:
The information in Column 1 may be entered in the Product Description for the chosen label
design. Column 2 is a list of the quality headings (excluding Quality Method) in a Product
Description. For each entry in Column 1 decide if it should be included in the Product Description
headings shown and select the heading from Column 2 under which it should be recorded.
Answer:
Explanation:
QUESTION NO: 57
Answer: A,B
Explanation:
QUESTION NO: 58
A. Move entry 9 to Composition because this is within the scope of the project.
B. Delete entry 10 because this is NOT a source product for this project.
C. Delete entry 11 as this is already correctly shown under Development Skills required.
D. Move entry 12 to Composition, because this is within the scope of this project.
E. Add 'Professional photographer'.
Answer: C,D
Explanation:
QUESTION NO: 59
A. Move entry 13 to Composition because the appointment of the photographer is within the scope
of this project.
B. Move entry 13 to Derivation because this is a source of information for this project.
C. Delete entry 14 because this skill is NOT required within this project.
D. Delete entry 15 because this skill is NOT required within this project.
E. Add 'Knowledge of Data Protection Act.
Answer: D,E
Explanation:
QUESTION NO: 60
A. Delete entry 16 because this should be shown on the Product Description for the photos.
B. Delete entry 17 because this is beyond the scope of this project.
C. Delete entry 18 because standards should NOT be shown here.
D. Delete entry 19 because this should appear in the Product Description for the calendar and not
the Project Product Description.
E. Delete entry 20 because this is an expected benefit and should be recorded in the Business
Case.
Answer: B,E
Explanation:
QUESTION NO: 61
Answer: A,C
Explanation:
QUESTION NO: 62
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the service level agreement (SLA) with the
selected service provider?
A. The SLA must extend for the full duration of the service contract.
B. Any changes to the SLA must be managed through formal change control.
C. External consultants are to assist in the creation of the SLA.
D. The selected service provider should be located locally.
Answer: A
QUESTION NO: 63
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
Which is a correctly defined acceptance criterion for the transferred facilities computer system?
Answer: C
Explanation:
QUESTION NO: 64
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
Answer: C
Explanation:
QUESTION NO: 65
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the running cost of the outsourced service?
Answer: D
Explanation:
QUESTION NO: 66
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
A. Obtain agreement from the Director of Facilities Division to amend this within the remaining +2
days tolerance.
B. Raise an issue (off-specification).
C. Raise an issue (request for change).
D. Accept this error as a concession.
Answer: C
Explanation:
QUESTION NO: 67
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
The service level agreement looks like any other MFH document.
A. Obtain agreement from the Director of Facilities Division to redesign the service level
agreement within the remaining +2 days tolerance.
B. Raise an issue (off-specification).
C. Accept this error as a concession.
D. No action required.
Answer: D
Explanation:
QUESTION NO: 68
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
A. Record an action to request that Project Assurance identify a proof-reader who can, within the
next 2 days, complete the check for typographical errors.
B. Ask the reviewers present at the meeting to conduct a proof-reading exercise and pass any
comments to the author within 2 days.
C. Contact Project Assurance to find appropriate resources to come into the review.
D. No action required.
QUESTION NO: 69
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
The service level agreement contains a number of technical terms that are missing from its
glossary of terms.
A. Obtain agreement from the Director of Facilities Division to add these into the glossary of terms
within the remaining +2 days tolerance.
B. Raise an issue (off-specification).
C. Raise an issue (request for change).
D. No action required.
Answer: A
Explanation:
QUESTION NO: 70
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
A. Delete entry 1 because the project approach is defined in the Project Brief.
B. Delete entry 2 because this is the Project Manager's responsibility.
C. Delete entry 3 because it is the Project Manager's responsibility to implement the Quality
Management Strategy.
D. Move entry 3 to the Roles and responsibilities section because this is a quality responsibility.
Answer: D
QUESTION NO: 71
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
A. Delete entry 4 because external suppliers are responsible for applying any relevant standards
to their work.
B. Delete entry 5 because the lack of a change management procedure makes the MFH
document standards unsuitable.
C. Add 'All contracts must conform to current employment laws".
D. Add 'PRINCE2 change control procedures will be used to manage any changes to baselined
products'.
Answer: C
Explanation:
QUESTION NO: 72
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
A. Delete entry 6 because this information should be included in Stage or Team Plans.
B. Move entry 6 to the Reporting section because the information should be used to report on
quality activities.
C. Delete entry 7 because this should be included in the Configuration Management Strategy.
D. Delete entry 8 because the results of quality reviews are recorded in the Quality Register.
Answer: C
QUESTION NO: 73
Additional Information
Product Description
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
4. The selected service provider will operate to industry standards for providing outsourced
services.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
A. Delete entry 9 because this should only be recorded in the Product Description.
B. Delete entry 10 because this is the responsibility of the quality review chair.
C. Delete entry 11 because only the Project Manager can update the Quality Register.
D. Amend entry 12 because this is the responsibility of supplier assurance.
Answer: D
Explanation:
QUESTION NO: 74
Answer: D
Explanation:
QUESTION NO: 75
Having completed designing the plan, in which order should the next steps take place to produce a
plan?
1. Prepare Estimates
A. 2, 4, 3, 1
Answer: D
Explanation:
QUESTION NO: 76
2. Identifying activities
A. 1, 2, 3
B. 2, 3, 4
C. 1, 3, 4
D. 1, 2, 4
Answer: A
Explanation:
QUESTION NO: 77
Answer: B
Explanation:
A. Pre-requites
B. Assumptions
C. Quality responsibilities
D. Product descriptions
Answer: C
Explanation:
QUESTION NO: 79
A. Senior User
B. Senior Supplier
C. Executive
D. Project Board
Answer: A
Explanation:
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department
about current customers, and existing information from the Marketing department about
prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be
produced to allow the CEO and the Marketing Director to decide whether to continue with the
project. If they decide to continue, they will give the approval to launch the internal label design
competition. Competition rules will be required to communicate details of the competition to the
staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the
Marketing department. The selected photos will be chosen from these. Monthly calendar displays
will be created to show the required layout of each page.
(All entries are true statements but may not be shown under the correct heading or in the correct
document).
Using the Product Summary and Product Breakdown Structure provided as additional Information
for this question In the Scenario Booklet, answer the following question.
Column 1 is a list of some of the entries in the product breakdown structure. Determine whether
each entry in Column 1 has been correctly shown in the product breakdown structure. Select from
Column 2 the appropriate statement that correctly describes that entry. Each selection from
Column 2 can be used once, more than once or not at all.
Explanation:
QUESTION NO: 81
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be
produced to allow the CEO and the Marketing Director to decide whether to continue with the
project. If they decide to continue, they will give the approval to launch the internal label design
competition. Competition rules will be required to communicate details of the competition to the
staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the
Marketing department. The selected photos will be chosen from these. Monthly calendar displays
will be created to show the required layout of each page.
(All entries are true statements but may not be shown under the correct heading or in the correct
document).
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional
intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Engineering Manager insists that there are to be no interruptions to operations whilst
photographs are being taken of the engineering staff performing their everyday duties and
operating machinery. Two weeks ago the professional photographer produced the photo session
schedule based on the operational staff schedule. The operational staff schedule is produced
weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
A. Delete entry 2 because these are project benefits not prerequisites of the stage.
Answer: A,C
Explanation:
QUESTION NO: 82
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department
about current customers, and existing information from the Marketing department about
prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be
produced to allow the CEO and the Marketing Director to decide whether to continue with the
project. If they decide to continue, they will give the approval to launch the internal label design
competition. Competition rules will be required to communicate details of the competition to the
staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the
Marketing department. The selected photos will be chosen from these. Monthly calendar displays
will be created to show the required layout of each page.
(All entries are true statements but may not be shown under the correct heading or in the correct
document).
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional
intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Engineering Manager insists that there are to be no interruptions to operations whilst
photographs are being taken of the engineering staff performing their everyday duties and
operating machinery. Two weeks ago the professional photographer produced the photo session
schedule based on the operational staff schedule. The operational staff schedule is produced
weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
A. Delete entry 5 because the new company logo is being delivered by a separate project and will
Answer: D,E
Explanation:
QUESTION NO: 83
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department
about current customers, and existing information from the Marketing department about
prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be
produced to allow the CEO and the Marketing Director to decide whether to continue with the
project. If they decide to continue, they will give the approval to launch the internal label design
competition. Competition rules will be required to communicate details of the competition to the
staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the
Marketing department. The selected photos will be chosen from these. Monthly calendar displays
will be created to show the required layout of each page.
(All entries are true statements but may not be shown under the correct heading or in the correct
document).
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional
intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Engineering Manager insists that there are to be no interruptions to operations whilst
photographs are being taken of the engineering staff performing their everyday duties and
operating machinery. Two weeks ago the professional photographer produced the photo session
schedule based on the operational staff schedule. The operational staff schedule is produced
weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
A. No change to entry 8 because this cannot be confirmed until all of the label designs entries
Answer: A,E
Explanation:
QUESTION NO: 84
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department
about current customers, and existing information from the Marketing department about
prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be
produced to allow the CEO and the Marketing Director to decide whether to continue with the
project. If they decide to continue, they will give the approval to launch the internal label design
competition. Competition rules will be required to communicate details of the competition to the
staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the
Marketing department. The selected photos will be chosen from these. Monthly calendar displays
will be created to show the required layout of each page.
(All entries are true statements but may not be shown under the correct heading or in the correct
document).
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional
intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Engineering Manager insists that there are to be no interruptions to operations whilst
photographs are being taken of the engineering staff performing their everyday duties and
operating machinery. Two weeks ago the professional photographer produced the photo session
schedule based on the operational staff schedule. The operational staff schedule is produced
weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
A. Delete entry 11 because this relates to the monitoring and controlling of the Project Plan, not
Answer: A,B
Explanation:
QUESTION NO: 85
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department
about current customers, and existing information from the Marketing department about
prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be
produced to allow the CEO and the Marketing Director to decide whether to continue with the
project. If they decide to continue, they will give the approval to launch the internal label design
competition. Competition rules will be required to communicate details of the competition to the
staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the
Marketing department. The selected photos will be chosen from these. Monthly calendar displays
will be created to show the required layout of each page.
(All entries are true statements but may not be shown under the correct heading or in the correct
document).
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional
intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Engineering Manager insists that there are to be no interruptions to operations whilst
photographs are being taken of the engineering staff performing their everyday duties and
operating machinery. Two weeks ago the professional photographer produced the photo session
schedule based on the operational staff schedule. The operational staff schedule is produced
weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
A. Amend entry 15 because it should also include the cost of management activities.
Answer: A,D
Explanation:
Answer:
Explanation:
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used
once, more than once or not at all.
Answer:
Explanation:
QUESTION NO: 88
Which of the following statements is False regarding the Risk Management Strategy?
A. It captures and maintains all relevant information on identified threats and opportunities
B. It documents the risk tolerances
C. It documents the approach to risk
D. It identifies responsibilities towards risk for the project
Answer: A
Explanation:
QUESTION NO: 89
There are four steps in the Risk Management procedure, what are they?
Answer: C
Explanation:
QUESTION NO: 90
Which of the following risk responses can be used for either an opportunity or a threat?
A. Reduce
B. Share
C. Reject
D. Enhance
Answer: B
Explanation:
QUESTION NO: 91
Which of the following reports does not contain any information on risk?
A. Issue Report
B. Highlight report
C. Lessons Report
D. End Stage Report
Answer: A
Explanation:
QUESTION NO: 92
Which of the following statements best describes what a risk owner is?
QUESTION NO: 93
Who is responsible for reviewing the risk management practices to ensure they are in line with the
project's risk management strategy?
A. Project Support
B. Project Manager
C. Team Manager
D. Project Assurance
Answer: D
Explanation:
Additional Information
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
Answer:
Explanation:
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
Answer:
Explanation:
QUESTION NO: 96
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
Which 2 statements should be recorded under the Risk management procedure heading?
A. When a new problem arises, a full impact analysis will be undertaken to assess the impact on
the project' objectives and Business Case.
B. Probability will be assessed against the scales defined in this Risk Management Strategy.
C. Any risk which has an expected value of more than £1 k will NOT be registered.
D. Every threat and opportunity identified must be clearly defined in terms of cause, event and
effect.
E. 'Reduce' Response actions which result in a lower impact and/or probability rating.
Answer: B,D
Explanation:
QUESTION NO: 97
Scenario
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
Which 2 statements should be recorded under either the Records or Reporting headings?
Answer: B,C
Explanation:
QUESTION NO: 98
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
Which 2 statements should be recorded under the Timing of risk management activities heading?
A. During stage 4, the selected service provider will manage any risks to their Business Case and
report these to the Project Manager on a weekly basis.
B. The Project Board should hold monthly meetings to review project progress.
C. When closing a project, the follow-on action recommendations should be updated with any risks
relating to the realization of benefits after the outsourced services go live.
D. Any new risks identified during product development should be reported to the Project Manager
by the Team Manager when delivering the completed Work Package.
E. When authorizing a stage, the Project Board will check that the exposure to risk is still
acceptable.
Answer: B,E
Explanation:
QUESTION NO: 99
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
Which 2 statements should be recorded under the Roles and responsibilities heading?
Answer: B,D
Explanation:
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
A. Proximity categories for this project are: Imminent; Within the stage; Within the project; Beyond
the project.
B. The risk of MFH having no outsourcing experience will be categorized as Stage 4 proximity.
C. Imminent risks are those which may occur within two weeks.
D. Any risk with a proximity category of imminent will be estimated as having a very high impact.
E. The risk of staff leaving the organization will be categorized as beyond the project proximity.
Answer: C,D
Explanation:
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
A. Corporate management's threshold level of risk exposure is any combination of high and very
high impact and probability.
B. The Project Board's threshold level of risk exposure is any combination of medium, high and
very high impact, with high and very high probability.
C. The Project Manager's threshold level of risk exposure is low impact and probability.
D. The cost of all fallback plans must be contained within the project's tolerance.
E. The risk budget will have a tolerance of +/~ 10%.
Answer: B,D
Explanation:
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
Column 1 contains a number of risk responses identified by the Project Manager following an
assessment of this risk. Column 2 contains a list of threat response types. For each risk response
in Column 1, select from Column 2 the type of response it represents. Each option from Column 2
can be used once, more than once or not at all.
Column 1 contains a number of possible risk responses to the above risk. For each risk response,
select from Column 2 the appropriate risk threat response type that it represents. Each selection
from Column 2 can be used once, more than once or not at all.
Answer:
Explanation:
1 – Accept
2 – Fallback
3 – Share
4 – Accept
5 – Fallback
6 - Avoid
Answer: B
Explanation:
Answer: B
Explanation:
If the Project Board are too busy to authorize all change requests themselves they can appoint?
A. A Change Authority
B. A Change Board
C. A Change Committee
D. A Change Budget
Answer: C
Explanation:
Answer: D
Explanation:
1. Performance targets
2. Business Case
3. Resources
4. Risk
A. 1, 3, 4
B. 2, 3, 4
C. 1, 2, 4
D. 1, 2, 3
Answer: C
Explanation:
A. Project Manager
B. Project Support
C. Project Assurance
D. Team Manager
Answer: B
NO: 7 HOTSPOT
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
Using the Project Scenario answer the following question. The Plan for stage 3 has been
approved and work has commenced.
Column 1 contains a number of issues for this project. Select from Column 2 the appropriate
category for each issue. Each selection from Column 2 can be used once, more than once or not
at all.
Answer:
Explanation:
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of
Team Manager after taking some time to understand the requirements of the project. A contract
for their services has been set up and is being monitored by the Purchasing Manager and a Work
Package has been agreed. This contract specifies that the photographer must arrange a meeting
with the Engineering Manager to establish a schedule for the photo sessions to minimize the
impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that
he has received no communication from the photographer. The Project Manager has tried to call
the photographer and has had no response. The Project Manager believes there is a risk that
Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver
on schedule the project will be delayed and the expected benefits will be reduced.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor
also producing a calendar to be delivered earlier than the target date for this project. There is a
threat that the early release of a competitor's calendar may weaken the impact of the MNO
Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar
project.
For each concern listed in Column 1, select from Column 2 the configuration management task
that could help address the problem. Each selection from Column 2 can be used once, more than
once or not at all.
Answer:
Explanation:
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH's
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
According to PRINCE2, which statement about the Configuration Management Strategy for the
Outsourcing project is correct?
A. Every project needs a Configuration Management Strategy, even if the organization has
existing configuration management standards, because every project has different circumstances.
B. A separate Configuration Management Strategy will be required for each of the suppliers within
this project because each will have a different way of managing and storing products.
C. A Configuration Management Strategy is unnecessary for this project because the MFH
document control process is documented. It is acceptable simply to reference this in the Quality
Management Strategy.
Answer: A
Explanation:
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH's
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
According to PRINCE2, which statement about appointing the MFH Quality Manager to administer
the configuration management procedure is correct?
Answer: C
Explanation:
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH's
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
Having created the Issue Report and analyzed the impact of removing the Facilities Division from
the scope of the Outsourcing project, the proposed option exceeds tolerance. \Nhat is the next
action the Project Manager should consider?
A. Create an Exception Report to inform the Project Board of the situation and the available
options.
B. Update the associated Configuration Item Records with details of the Issue Report that caused
the change.
C. Amend the Stage Plan for stage 3: remove all products related to the Facilities Division and add
the activities required to deliver the new Government initiative.
D. Create an Exception Plan to change all of the project's products to reflect the exclusion of
services provided by the Facilities Division.
Answer: A
Explanation:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH's
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
Answer: D
Explanation:
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH's
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
A. None because risks associated with the centralization and rationalization of the Facilities
Division will be managed by another project.
B. These changes will delay stage 3 by three weeks.
C. There is only £70k left in the project change budget.
D. The reduced value of the contracted services required by the Outsourcing project may result in
an insufficient number of proposals being received.
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a
document control process to manage all documentation requirements. The document
control process was created by the MFH Quality Manager, who now maintains all of MFH's
documents and performs an organization-wide configuration management role. The MFH
Quality Manager will administer the configuration management procedure for the
Restructuring project since this must comply with the MFH document control process.
Answer: A
Explanation:
Answer: C
Explanation:
A. Controlling a Stage
B. Initiating a Project
C. Managing a Stage Boundary
D. Directing a Project
Answer: D
Explanation:
Which of the following is not a factor to consider when determining the length of a stage?
Answer: A
Explanation:
Answer: C
Explanation:
There are two time driven controls in PRINCE2, which are they?
Answer: B
Explanation:
Who is responsible for confirming stage and project progress against agreed tolerances?
A. Project Support
B. Executive
C. Project Assurance
D. Project Manager
Answer: C
Explanation:
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in
- Design for each month - correctly showing at public holidays and new company logo
- Selected photographs- 12 professionally-produced photographs, showing different members of
staff
- Selected paper and selected envelope - for printing and mailing the calendar
- Chosen label design - a competition to design a label will be held as part of this project
- List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
- Create the customer fast using information from the Accounts and Marketing departments
- Confirm compliance with the Data Protection Legislation
- Create a design for each month - this will be done by the internal creative team
- Select and appoint a professional photographer
- Gather photograph design ideas from previous project and agree photographic session schedule
- Prepare a production cost forecast
- Select paper and envelope.
A production cost forecast, based on the options and costs for the paper, envelope, printing and
marketing of the calendar is to be produced in stage 2. However, the actual production and
distribution of the calendars is not within the scope of the project. The product cost forecast will be
reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk
budget.
At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement
is true?
Answer: B
Explanation:
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in
part to the increased marketing activities of its competitors. To help counter this, the company has
decided to create a promotional calendar for next year for all its current and prospective
customers. The end product of this project will be a prepared calendar pack, ready for printing.
The design of the calendar will be similar to one sent out previously, and must reflect the company
image as described in the existing corporate branding standards. Another project is currently
producing a new company logo when is to be printed on each page of the promotional calendar.
The prepared calendar pack will consist of:
- Design for each month - correctly showing at public holidays and new company logo
- Selected photographs- 12 professionally-produced photographs, showing different members of
staff
- Selected paper and selected envelope - for printing and mailing the calendar
- Chosen label design - a competition to design a label will be held as part of this project
- List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
- Create the customer fast using information from the Accounts and Marketing departments
- Confirm compliance with the Data Protection Legislation
- Create a design for each month - this will be done by the internal creative team
- Select and appoint a professional photographer
- Gather photograph design ideas from previous project and agree photographic session schedule
- Prepare a production cost forecast
- Select paper and envelope.
A production cost forecast, based on the options and costs for the paper, envelope, printing and
marketing of the calendar is to be produced in stage 2. However, the actual production and
distribution of the calendars is not within the scope of the project. The product cost forecast will be
reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk
budget.
During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to
finish three weeks later, which statement is correct?
Answer: B
Explanation:
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in
part to the increased marketing activities of its competitors. To help counter this, the company has
decided to create a promotional calendar for next year for all its current and prospective
customers. The end product of this project will be a prepared calendar pack, ready for printing.
The design of the calendar will be similar to one sent out previously, and must reflect the company
- Design for each month - correctly showing at public holidays and new company logo
- Selected photographs- 12 professionally-produced photographs, showing different members of
staff
- Selected paper and selected envelope - for printing and mailing the calendar
- Chosen label design - a competition to design a label will be held as part of this project
- List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
- Create the customer fast using information from the Accounts and Marketing departments
- Confirm compliance with the Data Protection Legislation
- Create a design for each month - this will be done by the internal creative team
- Select and appoint a professional photographer
- Gather photograph design ideas from previous project and agree photographic session schedule
- Prepare a production cost forecast
- Select paper and envelope.
A production cost forecast, based on the options and costs for the paper, envelope, printing and
marketing of the calendar is to be produced in stage 2. However, the actual production and
distribution of the calendars is not within the scope of the project. The product cost forecast will be
reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk
budget.
During stage 2, an early review of the photo design ideas from the Marketing department has
highlighted the need for engineering machinery to be operating in the background during the photo
sessions. This requires a change to the baselined Product Description for the photos. What action
should the Project Manager take?
Answer: A
Explanation:
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in
part to the increased marketing activities of its competitors. To help counter this, the company has
decided to create a promotional calendar for next year for all its current and prospective
customers. The end product of this project will be a prepared calendar pack, ready for printing.
The design of the calendar will be similar to one sent out previously, and must reflect the company
image as described in the existing corporate branding standards. Another project is currently
producing a new company logo when is to be printed on each page of the promotional calendar.
The prepared calendar pack will consist of:
- Design for each month - correctly showing at public holidays and new company logo
- Selected photographs- 12 professionally-produced photographs, showing different members of
staff
- Selected paper and selected envelope - for printing and mailing the calendar
- Chosen label design - a competition to design a label will be held as part of this project
- List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
- Create the customer fast using information from the Accounts and Marketing departments
- Confirm compliance with the Data Protection Legislation
- Create a design for each month - this will be done by the internal creative team
- Select and appoint a professional photographer
- Gather photograph design ideas from previous project and agree photographic session schedule
- Prepare a production cost forecast
- Select paper and envelope.
A production cost forecast, based on the options and costs for the paper, envelope, printing and
marketing of the calendar is to be produced in stage 2. However, the actual production and
distribution of the calendars is not within the scope of the project. The product cost forecast will be
reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk
budget.
As the project approaches the end of stage 2, the Project Manager has requested a Product
Status Account to ensure that all products are at their expected point of development. Although
the list of customers has been quality reviewed, it has not been baselined because the Marketing
department have not provided all of the prospective customers' details. What initial action should
the Project Manager take?
A. Delay producing the End Stage Report until the list of customers has been baselined.
B. Raise an Exception Report to the Project Board to highlight the issue.
C. Check the target sign-off date for the list of customers.
D. Update the product status to baselined and obtain a commitment from the Marketing
department to finish this work within the next few days.
Answer: C
Explanation:
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in
part to the increased marketing activities of its competitors. To help counter this, the company has
decided to create a promotional calendar for next year for all its current and prospective
- Design for each month - correctly showing at public holidays and new company logo
- Selected photographs- 12 professionally-produced photographs, showing different members of
staff
- Selected paper and selected envelope - for printing and mailing the calendar
- Chosen label design - a competition to design a label will be held as part of this project
- List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
- Create the customer fast using information from the Accounts and Marketing departments
- Confirm compliance with the Data Protection Legislation
- Create a design for each month - this will be done by the internal creative team
- Select and appoint a professional photographer
- Gather photograph design ideas from previous project and agree photographic session schedule
- Prepare a production cost forecast
- Select paper and envelope.
A production cost forecast, based on the options and costs for the paper, envelope, printing and
marketing of the calendar is to be produced in stage 2. However, the actual production and
distribution of the calendars is not within the scope of the project. The product cost forecast will be
reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk
budget.
Whilst identifying the mailing costs for the calendars the Project Manager was surprised to find the
costs could vary considerably depending on the size of the package and the delivery service used.
For the purpose of this project, the Project Manager has selected an appropriate service but feels
that a corporate standard for postage would have reduced the time and effort invested. It could
A. Produce a project mandate, outlining the potential savings to be achieved by the introduction of
a corporate standard.
B. Make a note of the observation in the Daily Log to be transferred to a Benefits Review Plan at
the end of the project.
C. Record the observation in an Exception Report to the Project Board.
D. Make an entry in the Lessons Log for future consideration by corporate management.
Answer: D
Explanation:
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in
part to the increased marketing activities of its competitors. To help counter this, the company has
decided to create a promotional calendar for next year for all its current and prospective
customers. The end product of this project will be a prepared calendar pack, ready for printing.
The design of the calendar will be similar to one sent out previously, and must reflect the company
image as described in the existing corporate branding standards. Another project is currently
producing a new company logo when is to be printed on each page of the promotional calendar.
The prepared calendar pack will consist of:
- Design for each month - correctly showing at public holidays and new company logo
- Selected photographs- 12 professionally-produced photographs, showing different members of
staff
- Selected paper and selected envelope - for printing and mailing the calendar
- Chosen label design - a competition to design a label will be held as part of this project
- List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
- Create the customer fast using information from the Accounts and Marketing departments
- Confirm compliance with the Data Protection Legislation
- Create a design for each month - this will be done by the internal creative team
- Select and appoint a professional photographer
A production cost forecast, based on the options and costs for the paper, envelope, printing and
marketing of the calendar is to be produced in stage 2. However, the actual production and
distribution of the calendars is not within the scope of the project. The product cost forecast will be
reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk
budget.
The team member collating the list of customers has now forecast that it will NOT be complete by
the end of this stage as originally planned, due to a number of new prospective customers' details
not yet being available. What action should the team member take?
A. Report the forecast delay in the next Checkpoint Report to the Executive.
B. Add the product to the next Stage Plan in order to allocate additional resources and complete
the work.
C. Make an entry in the Risk Register so the Project Manager can decide on appropriate action.
D. Raise an issue to inform the Project Manager.
Answer: D
Explanation:
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.)
There has been a reduction in fie number of orders at the MNO Manufacturing Company due in
- Design for each month - correctly showing at public holidays and new company logo
- Selected photographs- 12 professionally-produced photographs, showing different members of
staff
- Selected paper and selected envelope - for printing and mailing the calendar
- Chosen label design - a competition to design a label will be held as part of this project
- List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
- Create the customer fast using information from the Accounts and Marketing departments
- Confirm compliance with the Data Protection Legislation
- Create a design for each month - this will be done by the internal creative team
- Select and appoint a professional photographer
- Gather photograph design ideas from previous project and agree photographic session schedule
- Prepare a production cost forecast
- Select paper and envelope.
A production cost forecast, based on the options and costs for the paper, envelope, printing and
marketing of the calendar is to be produced in stage 2. However, the actual production and
distribution of the calendars is not within the scope of the project. The product cost forecast will be
reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30
November, to enable printing and distribution of the calendar in time for Christmas. The cost of the
activities to develop the specialist products and the cost of the project management activities are
estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost
tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk
budget.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement For each
line identify the appropriate option, from options 1 to 6, that applies. Each option can be used
Answer:
Scenario:
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
"Pass Any Exam. Any Time." - www.actualtests.com 168
PRINCE2 PRINCE2 Practitioner Exam
7. +£10,000 / -£25,000.
Reporting arrangements
9. The report must contain a summary of all products worked on during the previous week.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion.
Which 2 statements apply to either the Development Interfaces or Operations and maintenance
interfaces sections?
A. Delete entry 2 because this interface will be contained in the Communication Management
Strategy.
B. Delete entry 3 because this interface will be contained in the project control section of the
Project Initiation Documentation.
C. Amend entry 4 to 'The transferred products relating to the services provided by the Facilities
Division'.
D. Add 'Project Board, with responsibility for communicating progress to corporate management'
to
E. Operations and maintenance Interfaces.
F. Add 'Facilities Team Manager, with responsibility for the transfer of services provided by the
Facilities Division' to Development Interfaces.
Answer: D,F
Explanation:
Scenario:
Joint agreements
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
9. The report must contain a summary of all products worked on during the previous week.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Techniques, processes and procedures or Constraints
sections?
A. Delete entry 1 because this section should contain the techniques, processes and procedures
required for specialist product development.
B. Add 'There must be minimum disruption to current services' to Constraints.
C. Move entry 5 to Techniques, processes and procedures because this is a technique which staff
should be aware of.
D. Delete entry 6 because this applies to Office Moves Limited and is therefore outside the Work
Package.
Answer: D,E
Explanation:
Scenario:
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
9. The report must contain a summary of all products worked on during the previous week.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Reporting arrangements or Problem handling and
escalation sections?
A. Replace entry 8 with 'Checkpoint Report every Monday by 10.00 am' because Highlight
Reports are intended for the Project Board.
B. Delete entry 9 because this level of detail is unnecessary.
C. Move entry 10 to Problem handling and escalation because that section describes how issues
are handled.
D. Add 'Any risks identified to be added to the Risk Register' to Reporting arrangements.
E. Delete entry 11 because the impact analysis should be provided when the issue is notified.
Answer: D,E
Explanation:
Scenario:
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
9. The report must contain a summary of all products worked on during the previous week.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Which 2 statements apply to either the Extracts or references or Approval method sections?
A. Delete entry 12 because this should be the Team Plan not the Stage Plan.
B. A suitable entry for Extracts or references would be 'Product Descriptions are available from
Project Support'.
C. Move entry 13 to Reporting arrangements because this describes how completion will be
advised to the
D. Project Manager.
E. Delete entry 13 because this is NOT a Project Assurance responsibility.
F. Add 'The Project Manager is to be advised of completion of the Work Package by email'.
Answer: A,B
Explanation:
Scenario:
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
9. The report must contain a summary of all products worked on during the previous week.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
At the end of stage 3, the service provider will be selected and the contract awarded. During stage
4, the Account Manager for the selected service provider will work with the Project Manager to
complete the transition of the services to the selected service provider.
Answer:
Explanation:
Scenario:
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
7. +£10,000 / -£25,000.
Reporting arrangements
9. The report must contain a summary of all products worked on during the previous week.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Column 1 is a list of actions that occur during the Controlling a Stage process. For each action in
Column 1, select from Column 2 the PRINCE2 theme that is being applied. Each selection from
Column 2 can be used once, more than once or not at all.
Answer:
Explanation:
1 – Organization
2 – Progress
3 - Risk
A. Legislation
B. Corporate Strategy
C. Risks
D. Mandate
Answer: D
Answer: C
Explanation:
During which of the following activities is the Project Product Description created?
Answer: B
Explanation:
Answer: B
Explanation:
Which other management product is created when the Business case is updated during Initiating a
Project?
Answer: C
Explanation:
Who is responsible for the initial creation of the Configuration Item records?
A. Project Manager
B. Team Manager
C. Project Assurance
D. Project Support
Answer: D
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues. lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
There is no project schedule in the Project Initiation Documentation. How can project progress be
tracked without a schedule to track against?
Answer: B
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues. lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
There is no Project Brief. How can there be a common understanding of the desired outcomes for
the prepared calendar pack?
A. The simple Project Initiation Documentation contains the Quality Management Strategy. This
contains details of the acceptance criteria for this project.
B. The Project Brief should have been produced and approved before the project progressed into
the initiation stage.
C. The simple Project Initiation Documentation contains the project definition.
Answer: C
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
There is no mention of any Stage Plans, yet there are two further stages proposed. How will this
be resolved?
Answer: A
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
No Benefits Review Plan has been developed. Where should the schedule of benefit reviews be
recorded?
Answer: C
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
Without a Risk Register how can project risks, the progress of risk actions taken to date and the
current status of residual risks be measured?
A. The Daily Log was correctly used to monitor risks during the Starting up a Project process. It
will be used to capture all risks, actions, decisions, assumptions
B. It was not appropriate to use the Daily Log to capture all risks and issues during the Starting up
a Project process. Separate registers should have been set up for risks, issues and lessons
learned. This will now be done.
C. In a simple project, the Project Initiation Documentation (PID) should contain a register for
recording risk information and monitoring project risks throughout the delivery stages. The register
will now be added to the PID.
Answer: A
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
A. No change to entry 1 because this shows the purpose and content of this document.
B. Amend entry 1 to read 'This document contains the controls and reporting to be established for
the project management team'.
C. Amend entry 1 to read 'This document contains the means and frequency of communication
between the project management team, the print company and other external parties.
Answer: A
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
Answer: B
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
A. Delete entry 3 because the activities required to create the products should be documented in
the relevant plan(s).
B. Move entry 4 to Reporting because this describes a report on the performance of the
Communication procedures used.
C. Delete entry 5 because the customers are not within the scope of this project.
Answer: B
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
A. Move entry 6 to the Configuration Management Strategy because it defines the identification
scheme for the project's products.
B. Move entry 7 to Communication procedure because it refers to the method to be used for
communication to external parties.
C. Move entry 8 to Tools and techniques because it refers to a filing technique.
Answer: A
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
A. Delete entry 9 because activities for controlling the project should be planned as part of Project
controls in the Project Initiation Documentation.
B. No change to entry 9 because it describes the timing of performance reports.
C. Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which
should be recorded in the Project controls section of the Project Initiation Documentation.
Answer: B
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
Using the Project Scenario, select the appropriate response to each of the following 5 questions
which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
Answer: A
Explanation:
Additional Information
The project information in the table below is true, but it may not be recorded under the correct
heading or be in the correct document.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a
relatively simple project, the Project Manager combined the Starting Up a Project process and the
Initiating a Project process. No Project Brief has been produced. Instead the Project Manager
used the project mandate to produce a simple Project Initiation Documentation (PID). The PID
includes the Business Case, a product checklist and several Product Descriptions, Including the
Project Product Description. Short sections are also included for each of the strategies and the
controls to be applied. The Project Manager has elected to use the Daily Log to record all risks,
issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work
Packages will be authorized. While these are being managed, the Project Manager will hold
regular checkpoints, which will support the production of weekly Highlight Reports to the Project
Board.
This question provides a number of changes which may or may not be required to the Extract from
the Communication Management Strategy provided in the additional information.
Which statement applies to the Information needs for each interested party section?
A. Delete entry 13 because the activity to provide the weekly updates should be scheduled in the
relevant Stage Plan.
B. Move entry 13 to Tools and techniques because it describes the method to be used to
communicate to the individual producing the staff newsletter.
C. Delete entry 14 because this relates to the development of a particular product and should be
recorded under Development interfaces within the relevant Work Package.
Answer: C
Explanation:
A. This is the first time that the Ministry of Food Hygiene (MFH) has been involved in outsourcing.
B. Based on feedback from other government departments, the Ministry of Trade and Industry has
provided the names of two outsourcing companies that are unreliable and should not be included
as potential service providers.
C. The feasibility study estimated that the outsourcing project would take two years to complete.
D. Only the Information Technology Division and Facilities Division will be outsourced.
M1ich statement is an appropriate entry for the outline Business Case heading within the Project
Brief?
A. 10 year service contract should be agreed with the selected service provider.
B. External consultants were employed to conduct a feasibility study to identify the options, their
likely costs and benefits.
C. The project will run for two years and the benefits will be realized over 1a years.
D. The project should be split into four management stages.
Answer: C
Explanation:
Which statement is an appropriate entry for the project approach heading within the Project Brief?
A. The initial estimates from the feasibility study will be verified during the initiation stage.
B. MFH must better manage suppliers' performance.
C. The Information Technology Division and the Facilities Division will be outsourced to a single
service provider.
D. The Project Manager will be responsible for ensuring that the agreed project approach remains
an appropriate choice.
Answer: C
Explanation:
A. The Daily Log has been updated with the new risks which were identified while preparing the
Initiation Stage Plan.
B. The plan is based on the external outsourcing consultants being available at the start of the
Answer: B
Explanation:
During stage 1 the level of performance expected from the service provider was changed.
After this change was agreed which of these products will require updating?
A. Project Brief because this is maintained throughout the project to reflect the customer's quality
expectations.
B. Project Product Description because this contains details of the expected performance of the
project's products.
C. Quality Management Strategy because this is where all of the customer's quality expectations
of the project's products should be documented.
Answer: B
Explanation:
While capturing previous lessons, the Project Manager discovered several interesting facts about
outsourcing.
Answer: C
Explanation:
While deciding on how the work of the project should be approached the following were
considered.
Which statement is appropriate for inclusion in the project approach heading in the Project Brief?
A. The Project Manager will involve the selected service provider in the creation of the Stage Plan
for stage 4.
B. New up-to-date software will be obtained to produce the graphical sections of the Project and
Stage Plans.
C. The detailed designs (future process, systems, operating and organization models) will be
based on the existing high-level designs.
Answer: C
Explanation:
While planning the initiation stage, the Project Manager reviewed some threats that had been
recorded in the Daily Log.
Which threat should have been assessed for possible risk responses to be included in the
Initiation Stage Plan?
A. MFH has no experience in outsourcing and this may affect understanding of what is required,
resulting in inadequate plans and strategies.
B. The Project Brief is a complex document and may not be approved by the Executive.
C. There is a shortage of service providers so there is a possibility that no suitable service
providers respond to the request for proposals. This would prevent the Outsourcing project from
proceeding.
Answer: C
Explanation:
Answer: C
Explanation:
While preparing the Configuration Management Strategy, the Project Manager considered the
options for change control. He decided to recommend a change budget of £250k, but was
undecided on the Change Authority to recommend.
Answer: B
Explanation:
While preparing the Quality Management Strategy, the Project Manager noticed that the corporate
quality management system does not specifically cover project management.
Which option provides an appropriate way for the Project Manager proceed?
A. Record the development of a corporate quality management system for project management as
a prerequisite of the Project Plan.
B. Proceed with the project without a Quality Management Strategy and adopt the selected
Answer: C
Explanation:
A. Highlight Reports to the Project Manager; Exception Reports to the Project Board when project
tolerances are forecast to be exceeded.
B. Highlight Reports to the Project Board; Exception Reports to corporate management when
stage tolerances are forecast to be exceeded.
C. Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or
project tolerances are forecast to be exceeded.
Answer: C
Explanation:
Topic 10, Directing a Project, Controlling a Stage and Managing Product Delivery
Answer: C
Explanation:
Which management product do the Project Board use to decide whether to authorize initiation?
A. Project Brief
B. Business Case
C. Project Initiation Documentation
D. Project Product Description
Answer: A
Explanation:
Which of the following is NOT a trigger for the project manager to authorize a work package?
A. Stage Authorization
B. Corrective Action
C. Exception plan approved
D. Reporting highlights
Answer: D
Explanation:
Which activity is responsible for updating the stage plan with actual during Controlling a Stage?
Answer: C
Explanation:
A. Team Plan
B. Checkpoint Report
C. Quality Register
D. Configuration Item Record
Answer: C
Explanation:
During a work package the Team manager needs to keep the project manager informed, which
management product is used for this?
A. Highlight report
B. Checkpoint Report
C. Issue Report
D. End Stage Report
Answer: B
Explanation:
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a
Stage process. For each entry in Column 1, select the first management product from Column 2
that should have been updated, or created, as a result of the entry. Each selection from Column 2
can be used once, more than once or not at all.
Answer:
Explanation:
While producing the Team Plan to deliver the agreed Work Package, it became apparent that the
user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?
Answer: A,B
Explanation:
The chair of a quality review meeting advised the Team Manager that, because there were so
many major issues, the product had been rejected. The presenter estimated that the corrections
would take about two weeks. The re-assessment of the product will take a further week, resulting
in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?
Answer: C,E
Explanation:
Two weeks after starting work the Team Manager noticed that each completed product had
exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed
its agreed cost tolerance of 5%.
Which 2 actions should the Team Manager take in response to this situation?
A. Check the status of the products currently being worked on and analyze the effort expended, to
determine if the trend is continuing.
B. Update the Team Plan by increasing all future work estimates by 10%.
C. Amend the Work Package and ensure that the revised targets are met.
D. Escalate the situation in the next Checkpoint Report.
E. Raise an issue that costs will exceed tolerance if the current trend continues.
Answer: A,E
Explanation:
The Team Manager has received notification that the new hardware and software solution has
been installed and completed, but there is a concern that it has not been approved by the
appropriate people.
Which 2 actions should the Team Manager take to check that the completed products have been
approved as required?
A. Check the Work Package to ascertain who should approve the completed Work Package.
B. Check the Product Descriptions to ascertain who should have approved the products.
C. Check the Configuration Management Strategy for product handover procedures.
D. Check the approval records as required in the Work Package.
E. Check the Product Descriptions for the quality method required.
Answer: B,D
Explanation:
The Work Package has been in progress for four weeks and has four weeks remaining. The
Information Technology Team Manager is concerned that he has no idea what the service
provider is doing about preparing to accept the transfer of Information Technology equipment and
staff. He is uncertain about what should be happening.
Which 2 initial actions should the Team Manager take in response to this concern?
Answer: D,E
Explanation:
When updating the project plan as part of Managing a stage boundary, what else might be
updated?
A. Exception Plan
B. Project Management team
C. Business Case
D. Project Initiation Documentation
Answer: A
Explanation:
Which of the following management products ARE updated as part of Managing a stage
boundary?
1. Business Case
4. Project Brief
A. 1, 2, 3
B. 1, 3, 4
C. 1, 2, 4
D. 2, 3, 4
Answer: A
Explanation:
Which of the following activities could trigger the production of an exception plan?
Answer: B
Explanation:
Which of the following statements is FALSE regarding the Continued Business Justification?
A. The justification for the project must remain the same throughout the project.
B. The justification for the project should remain vabd.
C. The justification for the project may change.
D. If the project is no longer justified it should be stopped.
Answer: B
Explanation:
Which of the following activities is NOT an action of preparing for planned closure?
Answer: B
Explanation:
Answer: C
Explanation:
It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO's customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Which product should show that the photos could be used for other promotional material for the
company?
Answer: D
Explanation:
It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO's customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Answer: B
Explanation:
It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO's customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Which product should show that if anybody has any remaining resource costs to be charged to the
project, they should ensure this is done by 10 November?
Answer: D
Explanation:
It is now late October and the project is in stage 3. The label design competition has been held
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Which product should show that the project has been closed prematurely and has not achieved
the objectives defined in the Project Initiation Documentation (PID)?
Answer: B
Explanation:
It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO's customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Which product should show that without the calendar the company is going to experience
difficulties recovering its decline in orders, and alternative solutions are required if the company is
going to recover its position?
Answer: C
It is now late October and the project is in stage 3. The label design competition has been held
and the photos of the staff have been taken. The CEO and Marketing Director still need to choose
the winning label design and the 12 photos for the calendar. However, the Executive has learned
that two competitors are issuing calendars to MNO's customers by the middle of November. After
analyzing the impact of this Issue, one of the options the Project Manager has presented to the
Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the
project Y-e to be closed now.
Which product should register that the risk of a competitor producing a calendar at the same time
was identified at the beginning of the project but the assessment of this risk appears to have been
poor?
A. Issue Register
B. Follow-on action recommendations
C. Lessons Report
D. Risk Register
Answer: C
Explanation:
The Calendar project was delivered as originally planned, and Is now preparing for planned
closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each
line identify the appropriate option, from options A to E, that applies. Each option can be used
once, more than once or not at all.
Answer:
Explanation: