Suitable Method For Capital Cost Estimation in Chemical Processes Industries
Suitable Method For Capital Cost Estimation in Chemical Processes Industries
net/publication/282212066
CITATION READS
1 8,738
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by mohammad reza Shabani on 27 September 2015.
ABSTRACT: Selection of a cost estimation method is generally dependant upon the level of
progress in engineering and design in each project. The main capital cost estimation methods
for chemical processes, together with capital cost items, are introduced in this article. The main (equation 1)
capital cost estimation methods include capacity factored, equipment factored, parametric
model, semi-detailed and detailed cost estimation. This article will show how to use cost esti- The plant cost ($B) in new capacity
mation methods in different design stages of a project. (Cap B) is simply calculated by having the
cost of plant ($A) in another capacity (Cap
KEY WORDS: Cost estimation, capital cost, and chemical industries A). It is recommend [2] that the ratio of (Cap
B) to (Cap A) must be equal or smaller than
technical and economical feasibility main items of capital cost or fixed investment 2. (e) or the exponent generally is equal to
class 3, if good results were achieved in class determined by inserting factors on equipment Process type EF
4. cost. Use of the Lang Factor [2] is the simplest Solid 3.1
In this class, the cost of equipment is method as shown in equation 2. Solid + Fluid 3.63
multiplied by factors to estimate the total
Fluid 4.74
plant cost. The cost of equipment can be TPC = (TEC) X (E.F)
attained by direct quoting from (equation 2) Table 2— EF Values vs. Process Type
manufacturers or by estimating methods. for its installation is 2860$. The DFC factor
Equation 1 can also be used to estimate Where TPC is total plant cost, TEC is total ranges 2.4 - 4.3 (with instrument) and 2 - 3.5
the cost of equipment. The (e) value is given equipment cost and EF is a factor that relates (without instrument) for different equipment.
for some equipment as well as chemical to the process type, the EF values are given in The total direct field cost of the plant is the
processes by W.D. Bassel [1]. For equipment, table 2. sum of the DFC for each equipment and the
a key parameter such as surface area for heat total plant cost can be calculated as shown in
exchangers or flow rate for pumps is used In figure 2, a comparison of TPC costs Table 3-B on page 24.
instead of capacity as in equation 1. for different processes type is shown, the TEC
is equal to 100 in this figure. For example for a DFC equal to 100, the
The Hand method [2] is another EFE total project cost is 185.56, according to
Equipment Factored Estimation (EFE) method in which specific factors are specified equation 3 as shown in table 3-B. Referring to
Method in each discipline for equipment. An example table 4 gives one the other cost items of
In the equipment factored estimation is shown for a heat exchanger in table 3. equation 3.
(EFE) method, having the cost of main If we have a heat exchanger with 1000$ The factors in table 3 and equation 3 are
equipment, the total plant cost can be cost (f.o.b), the total direct field cost (DFC) given for illustrative purpose only. The real
values differ depending on the regional
conditions for installation. It is possible to
calculate the cost of each discipline and
compare it in different projects by this
method.
CBM = Cp* FBM Figure 2 — TPC for Different Processes According to Lang Factor Method (TEC = 100)
(equation 4) 7 = material factor; 8 = labor factor; 9 = Which FBM0 is the module factor for
in which, freight and insurance factor; 10 = overhead non-base case, Fp is the correction factor for
CBM = Bare module cost of equipment factor; and 11 = engineering factor. pressure and Fm is the correction factor for
(direct plus indirect costs)
material. B1 and B2 are calculated on the
Cp = Equipment cost in base case (carbon The bare module cost includes the
basis of fixed investment components
steel material at atmospheric pressure) direct and indirect cost only and doesn't
(equation 6) which obtained for different
FBM = Module factor (a factor that includes include contingency and auxiliary services
equipments in specified ranges [6]. Usually
all direct and indirect costs) each component costs.
the equipment cost (CP) is obtained by
of fixed capital investment can be considered For example, if one has the cost of a heat
as a factor of equipment cost. For example exchanger in a base case (with carbon steel parametric models with a cost relation as
the required material cost (CM) is calculated material and operating at ambient pressure) shown in figure 8.
as shown in equation 5. equal to 10000 $ then for (αM = 0.7, αL =
log10 CP = K1 + K2 log10 A + K3 (log10A)2
0.37, αFIT =0.08, α0 = 0.7, αE = 0.15) the
(equation 8)
CM = αMCP bare module cost can be calculated from
(equation 5) equation 4 to equal to 31800 $. in which A is a key parameter of
equipment and the pressure correction factor
And then the FBM can be written as shown in To obtain the equipment cost in a non-
(FP)can be calculated by a relation as shown
equation 6. base case, using the following as shown in
equation 7. in equation 9.
FBM = (1+αM7) (1+ αL8+ αFIT9+ αLα0+ αE11) log10 FP = C1 + C2 log10 P + C3 (log10P)2
FBM0 = (B1 + B2FpFm)
0 0 (equation 9)
(equation 6) CBM = CP * F BM
(equation 7)
The coefficients K1, K2, K3, C1, C2, C3
are given for different equipment [5].
Direct Field Labor Cost (DFL) = 0.25 * DFC By totaling the above module cost for
Indirect Field Cost (IFC) = 1.15 * DFL equipments, the total module cost can be
Total Field Cost (TFC) = DFC + IFC (equation 3) obtained. To calculate the total plant cost one
Home-Office Cost (HOC) = 0.3 * DFC needs to add the auxiliary services and
Other Project Cost (OTC) = 0.03 * DFC + 0.15 * (TFC + HOC) contingency costs, so 15 percent of the
Total Project Cost (TPC) = OTC + TFC + HOC module cost is considered for contingency,
5.
Maples R.E. Petroleum Refinery
Process Economics, Second
Edition,2000, ISBN.0-87814-779-9.
Mulet A., A.B. Corripio, L.B. Evans,
(equation 10) determine if a project should go forward, or Estimate Costs of Pressure Vessels Via
if the project should be rejected, in different Correlations, Chemical Engineering,
The auxiliary services and utilities do stages was emphasized. Oct.5, 1981, page.145.
not depend on the pressure or material of This article can be useful when read as 6. Turton R., R.C. Bailie, W.B. Whiting,
the battery limit. Its cost is 35 percent of the general guidelines for junior staff members, J.A. Shaeiwitz. Analysis, Synthesis and
module cost, at a base case of (CBM , i). In all or as an abstracted collection for senior staff Design of Chemical Processes, 1998,
of the EFE methods, equipment cost is the members in process cost estimation. The ISBM 0-13-064792-6.
basis from which to multiply the factors. parametric models (cost relations) as useful
tools and can be used by companies or ABOUT THE AUTHORS
Parametric Cost Estimation Method consulting engineers in preparing proposal Mohammad Reza Shabani and Reza
A parametric model is the or tender documents. Each company has its Behradi Yekta are with the Feasibility Study
mathematical relationship between own cost data that has been prepared as part Department of the Research Institute of
equipment cost and key parameters. The of the company’s projects archives. That Petroleum Industry of Iran. Contact can be
pressure and temperature correction factors data is the starting point for using these made by sending e-mail to:
or equipment type can also be written in capital cost estimation methods. ◆ [email protected].
relationships of key parameters. By using
Technical Articles - Each month, Cost
these relationships, a preliminary cost REFERENCES Engineering journal publishes one or more peer-
estimation for equipment can be attained. 1. Baasel W.D. Preliminiary Chemical reviewed technical articles. Unless noted
One can then calculate a plant’s total cost by Engineering Plant Design, Second otherwise, these articles go through a blind peer
exerting some other factors. Edition, 1990, ISBN.0-442-23440-6. review evaluation prior to publication. Experts in
2. Dysert L.R.Sharpen Your Cost the subject area judge the technical accuracy of
The best way to obtain these the articles, advise the authors on the strengths and
relationships is through the finished project Estimation Skills, Cost Engineering,
weaknesses of their submissions, and what changes
archives of an organization. A data bank of Vol. 45, No. 6, June 2003. can be made to improve the article before
equipment costs needs to be prepared. Then publication.
use regression methods and statistical tests,
such as F and t - tests, to drive the best
models [2, 5]. By using these models, it is
possible to fastly and easily prepare
feasibility reports or bid documents.