Lecture 2 - Project Risk Management Basics
Lecture 2 - Project Risk Management Basics
MS (PM)
Scheme
2
Importance of PRM
Basic Terminologies
Project Assumption, Project Fact and Project Risk
Risk Appetite and Risk Threshold
The context of risk
Project Risk Management Framework
Sources of risk in projects
Levels of risk
Categories of risk (Pure Risk and Speculative Risk)
Definition of PRM
Scheme
3
Iterations in PRM
Project Risk
11
Project Assumption
12
Project Fact
13
Project Risk
14
Within control of project Not in the direct control of Not in the direct
team project team control of project team
Risk Attitude
16
Risk attitudes exists on a continuous spectrum, but common risk attitudes include
risk averse, risk tolerant, risk neutral and risk seeking.
Risk attitude may differ from one stakeholder to other and from one project to
other.
A single stakeholder may adopt different risk attitudes at various stages in a single
project.
Basic Terminologies: Risk Attitude Risk Appetite Risk Threshold
Risk Attitude
17
Organization’s culture.
Risk Appetite
18
Risk Threshold
19
The level of risk exposure above which risks are addressed and below
which risks may be accepted.
This is defined by measurable risk thresholds that reflect the risk appetite
of the organization and project stakeholders.
Risk Threshold
20
In context of a situation.
Project Risk Management aims to identify and manage risks that are not
addressed by the other project management processes.
When unmanaged, these risks have the potential to cause the project to deviate
from the plan and fail to achieve the defined project objectives.
Risks exit in relation to objectives, it is, therefore, essential to clearly define the
project objectives right from the beginning of the project.
PRM Framework Sources Levels Categories Definition
Levels of Risk
24
Categories of Risk
25
▪ Risks that bring only loss but no ▪ Risks that may bring loss and benefit
benefit. as well.
Uncertainty in Risk
27
For a risk event, probability and impact elements of risk may change
over time.
Uncertainty in Risk Iterations Scalability Agile/Adaptive Considerations
Uncertainty in Risk
28
For a software development project, the probability of the risk of losing key
data may be constant throughout, but the impact is likely to increase over time.
Technical risk of accident caused by falling from height may be constant (in
terms of probability and impact) for full period of a pipeline project.
The probability of same risk might starts as low, then increase sharply and
finally decline again as a multi-storey building project emerges from ground,
structural floors are added. What about impact ?
Uncertainty in Risk Iterations Scalability Agile/Adaptive Considerations
Iterations in PRM
29
Some risks will occur while others will not, new risks will arise or
discovered and characteristics of those already identified may change.
Every step in the PRM processes should be scalable to meet the varying
degrees of risk.
Project Size
Project Complexity
Is a robust risk approach demanded by high levels of innovation, new
technology, commercial arrangements, interfaces, or external
dependencies that increase project complexity? Or is the project
simple enough that a reduced risk process will suffice?
Uncertainty in Risk Iterations Scalability Agile/Adaptive Considerations
Project Importance
Development Approach
Define how the elements of the PRM processes will be scaled for
this project.
Risk is considered when selecting the content of each iteration, and risks will
also be identified, analyzed, and managed during each iteration.
Requirements are kept as a living document that is updated regularly, and work
may be reprioritized as the project progresses, based on an improved
understanding of current risk exposure.
36
https://www.pmi.org/learning/library/manage-risks-didnt-know-were-taking-9275
Project Resilience
37
These are risks that can only be recognized after they have occurred.
Project Resilience
38
Risk exists at each of these levels, and risks should be owned and
managed at the appropriate level.
Non-event Risks
40
Most projects focus only on risks that are uncertain future events that
may or may not occur, i.e. event-based risks, such as:
The focus of PRM, however, is broadening to ensure that all types of risk
are considered, and that project risks are understood in a wider context.
Non-event Risks
41
Name taken from Latin word alea, which is a game played using a dice with a set
number of possible outcomes but we don’t know which one will actually occur.
For example, we plan to run a 15-day trial, but the actual duration could in fact
be anywhere between 10–25 days.
The probability of running the trial is 100%, but its duration is uncertain.
Non-event Risks
42
The best way to analyze variability risks is in a quantitative risk analysis model
using Monte Carlo simulation.
These ranges are specifically designed to reflect the degree of uncertainty in key
parameters such as time, cost etc., which makes them ideal for describing
variability risks.
Trends & Emerging Practices: Resilience Integrated RM Non-event Risks
Non-event Risks
43
Examples of project areas where imperfect knowledge might affect our ability to
achieve project objectives include:
Non-event Risks
44
Non-event Risks
45
These allow us to take small steps within the scope of our existing limited
knowledge, gradually extending the boundaries of our understanding.
Development Approach or Project Lifecycle
46
The project lifecycle is what you need to do to do the work, and the project
management process is what you need to do to manage the work.
Monitor Risk
48