Sabghat

The document outlines an 8-task project schedule from July 12 to August 12. Task 1 is project initiation. Task 2 involves 3 days of requirements gathering by the planning team. Task 3 is a 4-day system design period involving various teams and resources. Task 4 estimates effort/cost over 2 days with documentation and acceptance teams. Task 5 is a 6-day coding period by the coding team. Task 6 is 2 days of testing with a testing team and changes. Task 7 is a 5-day implementation with customer interaction and real-time work. Task 8 is a 1-day project closeout. The document provides task names, durations, start/finish dates, predecessors, resources, and costs for each step.

Uploaded by

abu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views1 page

Sabghat

The document outlines an 8-task project schedule from July 12 to August 12. Task 1 is project initiation. Task 2 involves 3 days of requirements gathering by the planning team. Task 3 is a 4-day system design period involving various teams and resources. Task 4 estimates effort/cost over 2 days with documentation and acceptance teams. Task 5 is a 6-day coding period by the coding team. Task 6 is 2 days of testing with a testing team and changes. Task 7 is a 5-day implementation with customer interaction and real-time work. Task 8 is a 1-day project closeout. The document provides task names, durations, start/finish dates, predecessors, resources, and costs for each step.

Uploaded by

abu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Duration Start Finish Predecessors Resource Names Cost Jul 12, '20 Jul 19,

esource Names Cost Jul 12, '20 Jul 19, '20 Jul 26, '20 Aug 2, '20 Aug 9, '20 Aug 16, '20
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 Initiation 0 days Sun 7/12/20 Sun 7/12/20 $0.00 7/12
2 Requirement 3 days Mon Wed 1 Planing Team $50.00 Planing Team
Gathering 7/13/20 7/15/20
3 System Designing 4 days Thu 7/16/20 Tue 7/21/20 2 Designing Team,Paid Softwares,High
$90.00
End Hardware Designing Team,Paid Softwares,High End Hardware
4 Estimation, Effort, 2 days Wed Thu 7/23/20 3 Document $210.00 Document Softwaree,Acceptance team
Cost 7/22/20 Softwaree,Acceptance
5 coding 6 days Fri 7/24/20 Fri 7/31/20 4 coding Team $73.00 coding Team
6 Tesing 2 days Mon 8/3/20 Tue 8/4/20 5 Testing Team,Changes Need $78.00 Testing Team,Changes Need
7 Implimentation 5 days Wed 8/5/20 Tue 8/11/20 6 customer Interaction,real time work
$80.00 customer Interaction,real time work
8 Project Close Out 1 day Wed 8/12/20Wed 8/12/207 $50.00

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 8/16/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1