Investment Decision Rules
Investment Decision Rules
28 28 28 28
NPV 81.6
1 r (1 r )2 (1 r )3 (1 r ) 4
We can also use the annuity formula:
28 1
NPV 81.6 1 4
r (1 r )
If the company’s cost of capital is 10%, the NPV is $7.2 million and
they should undertake the investment
Using the NPV Rule
The NPV depends on cost of capital
NPV profile graphs the NPV over a range of discount rates
Based on this data the NPV is positive only when the discount
rates are less than 14%
IRR is defined as the discount rate(s) that set the NPV equal to
zero.
8.2 Using the NPV Rule
Payback Rule
1. Calculate the amount of time it takes to pay back the initial
investment, called the payback period.
2. Accept the project if the payback period is less than a pre-
specified length of time—usually a few years.
3. Reject the project if the payback period is greater than that
pre-specified length of time
Payback Example
Considering the following four projects:
Payback
Project CF0 CF1 CF2 CF3 CF4 Period NPV @10%
Q -5,000 0 5,000 0 0 2 ?
R -5,000 2,500 2,500 0 0 2 ?
S -5,000 2,500 2,500 2,500 0 2 ?
T -5,000 2,000 2,000 2,000 2,000 ? ?
Question:
What is the IRR for this project?
Assume that the cost of capital is 10%, should you take
the project or not?
What is NPV when r=10%?
Pitfall: Delayed Investment
500,000 500, 000 500, 000
NPV 1, 000,000 2
3
$243,426
1.1 1.1 1.1
Multiple IRRs
When the cash flows flip signs more than once, there are,
in general, multiple IRRs.
For example, a ten-year project has following cash flows:
CF0 = +1,000,000
CF1 = CF2 = CF3 = -500,000
CF10 = +600,000
CFn = 0 for other n
After
=> IRR=15.25%
Modified IRR
There is now only a single IRR, at 15.25%. Because our cost
of capital is 15%, we would properly accept the project using
the IRR rule
Modified IRR
It solves the problem of multiple IRRs.
But there is considerable debate about whether it is
appropriate to move cash flows of projects.
It does not solve other pitfalls:
Delayed Investment
Different Project Scale
Different Cash Flow Timing
IRR - Different Project Scale
Project C0 C1 IRR NPV at 10%
E -10,000 +20,000 100% +8,182
F -20,000 +35,000 75% +11,818
As you can see, solving for the crossover point is just like
solving for the IRR, so we will need to use a financial
calculator or spreadsheet
Steps:
(1) Forecast cash flows (amount and timing of each).
(2) Estimate the opportunity cost of capital.
(3) Calculate the profitability index for each project.
(4) Rank projects by the profitability index and go down
the list until you run out of money.
Profitability Index Example
McKesson Inc. has $15 million to invest in the following projects: