Standard Operating Procedure FOR BCP Flushing
Standard Operating Procedure FOR BCP Flushing
Standard Operating Procedure FOR BCP Flushing
STANDARD OPERATING
PROCEDURE
FOR
BCP FLUSHING
List of Contents
1. Objective
2. Scope
3. Introduction
4. Technical Data
5. Responsibility
6. Safety Precaution During operation
7. Safety Ppe’s
8. Special Tools/ Equipments
9. Pre checks And Action By Field Engineer
10.Operating Procedure
11.Abbreviations / Notations
References
1. Objective
For Smooth Operation of Boiler Circulation Pump.
2. Scope
This SOP is applicable for 01 No. of BCP.
3. Introduction
Boiler Water Circulation Pump used in high capacity boiler (super critical or
sub critical), it assisted the circulation of water to overcome friction losses in
pipe lines.
Pump Data
Liquid Data
Liquid Temperature 287.3°C
Chemical Composition Boiler Water
5. Responsibility
Unit Control Engineer, Field Engineer and Desk Engineer.
6. Safety Precautions
Ensure no permit to work is pending on regarding this system by checking
with EE/MRSE.
References
1. Torishima BCP O & M manual
2. Catalogue of boiler interlock & protection
3. BCP P & I Drawing
4. P & I for BCP Cooling system