Aastho Code of Soil PDF
Aastho Code of Soil PDF
80
Percent Finer By Weight
70
60
50
40
30
20
10
0
10 1 0.1 0.01 0.001
B G Grain Size (mm)
C
Sand Cla
Boulders Gravel Silt
Coarse Fine y
Sample
Station / Offset / Line Dept, meters Elev. USCGS
Identification.
RB-5 SS-3 2+300 3.0m Lt. "A" 1.2 - 1.7 258.8 + 258.1
Spec. % % MC
Lab # Class pH % Silt % Clay LL PL PI
Gravity Gravel Sand %
Loam
N/A
A-4(1)
Appendix 3 Consolidation Test
(Specimen Data)
Date:
Project:
Boring No:
Classification:
Water WW WW WWF
Tare
Dry Soil WS
W W
Water Content W O % % F
HS WS
AG W
HWF
Degree of saturation after test, Sr %.
Hf Hs
Remarks:
Hf - Hs
Void ratio after tests =
Hs
Hw
Degree of saturation before test,So %
H - Hs
Ws
Dry Density lb/cu ft.
Hs x A
Technician: Computed by: Checked by:
Appendix 4 Consolidation Test
(Time-Consolidation Data)
Date:
Subject:
Technician:
Appendix 5 E-Log P Curve
Consolidation Test
Soil Description:
8000
7000
6000
5000
Pcf/kPa
4000
3000
2000
1000
0 1 2 3 4 5 6 7 8 9 10 11 12 13
Strain Percent
Sample Location:
Soil Description:
Soil Description:
Soil Description:
Project #: Des. #:
Road: County:
Location:
Appendix 7 Triaxial Compression Test
(Specimen Data)
Date:
Project:
Boring No: Sample No:
Type of Test: Confining Pressure tons/sq ft
Test No. Classification:
Before test
Specimen Trimmings Specimen
Tare No:
Tare plus wet soil
Tare plus dry soil
Weight,q
Date:
Project:
Deviator
P Axial ^corr =
Elapsed Dial Cumulative Stress =
P Axial Strain * A**
Time Time Reading Change (Δ H) ε P x 0.465
Load lb ΔH 1 - ε sq
min. 10-2 10- 2 in Corr tons/sq
H in.
ft
AASHTO
Sample Depth SPT Dry Dry %
Class.
Sta Offset Line Soil Type Moisture iMoisture Moi
No (ft.) (N) Density Density Comp
(%) (%) Diff
(pcf) (pcf) action
RB-06 276+00 20’ Lt “A” SS-1 2.0-3.5 Loam A-6 5 110.9 110.0 100.8 14.5 17.8 -3.3
Silty Clay
RB-09 290+00 20’ Rt “A” SS-2 3.5-5.0 A-6 13 111.5 110.0 101.4 17.6 17.8 -0.2
Loam
Silty Clay
RB-11 303+00 30’ Rt “A” SS-1 1.5-3.0 A-6 7 109.1 110.0 99.2 17.8 17.8 0.0
Loam
Silty Clay
RB-16 322+50 35’ Lt “A” SS-1 2.0-3.5 A-6 9 108.3 110.0 98.4 16.0 17.8 -1.8
Loam
RB-22 343+00 20’ Lt “A” SS-1 2.0-3.0 Loam A-6 9 119.5 110.6
Silty Clay
RB-27 385+00 35’ Lt “A” SS-1 2.0-3.0 A-6 10 109.8 110.0 99.8 12.7 17.8 -5.1
Loam
Silty Clay
RB-36 440+00 15’ Lt “PR-A” SS-2 1.5-3.5 A-6 12 108.2 110.0 98.3 18.7 17.8 0.9
Loam
Appendix 11: Peat Unit Weight (example)
Design Recommendations
Minimum Reinforcement Length/Height Ratio 0.75H (example)
Undercut required yes/no
Undercut depth X feet
Undercut area from Sta. XX to XX line "XX"
Undercut Backfill Material XXXXXXX
Seismic recommendation
Site Class
Seismic Zone
Peak Ground Acceleration As
Notes:
*more sheets can be added to include recommendations for each area of concern.
**if varying soil conditions encountered underneath the MSE wall, the table can be expanded to
include all soil profile information
Appendix 13: Example Pavement Core Report
Des No.:
Location:
Road Core No. Date Cored Core Dia. Station Offset Line
13 Asphalt
Geotechnical Engineering
Report Completion
Schedule Schedule
Exceeds - An acceptable final product was delivered more than 30 calendar days ahead of schedule.
Above Average - An acceptable final product was delivered more than 14 but less than 30 calendar days ahead of
schedule.
Satisfactory - An acceptable final work product was delivered within the scheduled time.
Improvement Required - An acceptable final work product was delivered up to two months behind schedule.
Unsatisfactory - An acceptable final work product was delivered more than two months behind schedule.
Budget Budget
Exceeds - The consultant improved the operations budget more than 10%.
Above Average - The consultant improved the operations budget more than 5%.
Exceeds - All samples were collected in accordance with INDOT standards also additional samples were collected to
accommodate any change in the scope of the project.
Above Average - All samples were collected in accordance with INDOT standards also additional samples were
collected to accommodate only one change in the scope of the project.
Improvement Required - Some samples were not collected in compliance with INDOT standards .
Unsatisfactory - Most samples were not in compliance with INDOT standards. As a result the consultant was
instructed to remobilize and collect the required samples.
Exceeds - Equipment mobilized was adequate and very good operating condition.
Above Average - Equipment mobilized was adequate and in good operating condition.
Geotechnical Engineering
Satisfactory - Equipment was generally adequate but needed some adjustment during the field operation.
Improvement Required - Some equipment mobilized was not adequate and required an adjustment in the scope of
work.
Unsatisfactory - Correct equipment was not mobilized causing delays, change in scope, and change in boring
locations.
Were 24 hour water levels recorded for boreholes at the appropriate time?
Above Average - 24hr water level readings were recorded in boreholes, some readings were taken after 72 hours or
more.
Improvement Required - 24hr water level readings were not recorded in boreholes.
Exceeds - All boreholes were backfilled and re-backfilled after the settlement period.
Above Average - All boreholes were backfilled and some were re-backfilled after the settlement period.
Satisfactory - All boreholes were backfilled but not checked for settlement.
Improvement Required - Some boreholes backfilled correctly, consultant requested to go back and fill unfilled holes.
Unsatisfactory - None of the boreholes were backfilled. Consultant was required to go back and fill the holes.
Unsatisfactory - Consultant did not have traffic control when it was required .
Exceeds - Laboratory tests performed in accordance with requirements and provided additional graphs and plots of test
data.
Above Average - All tests were performed in accordance with standards and requirements, some with additional
graphs and plots of test data.
Geotechnical Engineering
Satisfactory - All tests were performed in accordance with standards and requirements.
Improvement Required - Some tests were not performed in accordance with standards and requirements.
Unsatisfactory - None of the tests were performed in accordance with the standards and requirements.
Exceeds - Engineering recommendations were both technically correct and presented the most economical
engineering solutions. No revisions were required to the original submittal.
Above Average - Engineering recommendations were technically correct and presented the most economical
engineering solutions. Minor revisions were required to the original submittal.
Satisfactory - Engineering recommendations were adequate. Revisions were required to the original submittal.
Improvement Required - Initial engineering recommendations were inadequate. Revisions were required to the
original submittal.
Unsatisfactory - Initial engineering recommendations were inadequate and inappropriate. Multiple revisions were
required and multiple submittals were required to achieve an acceptable report.
Exceeds - Willingness to answer questions and make requested changes exceeded expectations and was proactive in
addressing project issues.
Above Average - The consultant revised plans/documents in accordance with comments and made additional
improvements that had not been suggested but resulted in an improved product. Readily explained revisions and
answered all questions.
Satisfactory - The consultant did revise the plans/documents in accordance with the comments and/or explained why
revisions were not made and showed a willingness to answer questions.
Improvement Required - The Consultant did not revise some of the plans/documents in accordance with the
comments and did not explain why some of the revisions were not made. Consultant showed some cooperation in
answering questions but required several requests.
Unsatisfactory - The consultant did not comply with any of the above.