9SEAGC1987 Case Studies of The Use of Grouting To Protect Buildings, Thailand
9SEAGC1987 Case Studies of The Use of Grouting To Protect Buildings, Thailand
9SEAGC1987 Case Studies of The Use of Grouting To Protect Buildings, Thailand
BANGKOK, THAILAND
7-11 December 1987
J.N. SHIRLAW
Singapore Mass Rapid Transit Corporation
Singapore
INTRODUCTION
8-159
fore often selected.
CASE A
BUILDING A
FILL
DRILLED-IN SLEEVED
MARINE TUBES
BUILDING A DEPOSITS
SCALE
()n 10m
L-...J
SECTION A-A
8-160
Calculations for the likely settlement of the building were
based on the 'error function' curve proposed by Peck (1967). Peck
suggested that the surface settlement over tunnels could be repre-
sented by an error function curve, shown in figure 2.
8-161
1978). Analysis of short lengths of tunnel driven through similarly
treated ground suggested that the maximum tunnel se~tlement ratio
would be reduced by the treatment to under 1%, although the informa-
tion was limited.
20
~30
90
8-162
The lower westbound tunnel was driven using the NA!M (New
Austrian Tunnelling Method). A combination of steel arches, shot-
crete and rockbolts was used for temporary support. The tunnel was
driven in free-air, relying on the chemical treatment to stabilize
the ground. It was found that the rock bolts, which penetrated to
the edge of the treated zone, allowed slight drainage into the tunn-
el. Total water make due to seepage both at the face and at rock
bolt positions was estimated at 25 to 45 /minute. After driving
48.6m in free air, the tunnel was lined with SGI segments, an air-
lock was installed and the rest of the tunnel was driven in comp-
ressed air. The settlement due to the free air drive is shown in
figure 3. Quite clearly the settlement bears little relation to
an error function curve, and CATER et al (1984) have suggested that
most of this settlement was due to dewatering. Even though the
absolute magnitude of settlement on building A, at 41mm, was double
the settlement due to drilling, the angular distortion was small.
....__
M AHEAD OF FACE M BEHIND FACE
---..
10 10 20 30
(TREATED ZONE)
...z
u.J
::;:
u.J
......
-l
POINT BllS (UNTREATED)
u.J
(Jl
~
E
E
50
8-163
During tunnelling, a thick layer of uniform alluvial sand was
found in the upper third of the face, which, when treated, was
strong and stable. However, once the shield was driven on out of
the treated area the sand was unstable as it became dried by the
compressed air. Despite the use of timbers and movable gates, voids
developed over the shield. In addition when grout plugs were re-
moved to grout the rings, sand poured in through the grout holes.
Figure 4 shows the development of settlement with the passage of the
shield on points B (treated area) and point B115 (untreated area).
CASE B
BASEMENTS OF
BUILDING B FILL
ALLUVIUM
WEATHERED.
TUNNEL GRANITE
SCALE
EXTRADOS
0 4m
L-.....J
LIMIT OF
TREATMENT
8-164
OCT. NOV. DEC. JAN. FEB. MAR.
w
~
w 5
:r:
+
PASSES
0
10
POINT 506 (UNTREATED ZONE)
CASE C
8-165
BUILDING C
0 SCALE 10m
FILL
MARINE
DEPOSITS
ALLUVIUM
WEATHERED
GRANITE
FIGURE 8
8-166
They suggested that the settlement of individual piles could be
greater than the ground surface settlement. The simple predictive
methods based on the error function curve are obviously inappro-
priate in this case, and more sophisticated techniques are needed.
However, one simple method of analysis is to estimate the settlement
of the pile to be equal to the soil movement just above the tunnel
crown. Based on a 3% settlement ratio, a movement of about 100mm
can be postulated at crown.
The tunnel was driven using compressed air and a shield. The
settlement of the building due to tunnelling was just 7mm. However,
ground surface point G4 (see figure 7), which was located over the
centre line of the tunnel 15m before it reached the treated zone,
suffered only 8mm settlement due to tunnelling.
DISCUSSION
8-167
SHIELD DRIVEN TUNNELS IN COMP. AIR
BEFORE DECOMPRESSION
0
z 10
FIGURE 9
8-168
settlement ratio of 1%, the surface settlement over a typical 6m dia
tunnel, 20m deep, would be 11mm. Based on the work of ATKINSON and
MAIR (1981) with model tunnels in granular materials, the factor of
safety against failure of the tunnels in untreated c.w.g. would have
generally been high, at least 2. In these circumstances the bene-
fits of the treatment in this soil must be doubted.
8-169
shown in figure 4 the benefits of treatment in certain specific soil
layers can be significant. However in these cases it is important
to accurately define the precise location of the layer to be treated.
This will help minimise the need for treatment and any resulting soil
movements, while also minimising costs.
CONCLUSIONS
It has been shown that the decision to treat around the tunnels
in the three cases studied was based on conse•vative assumptions.
Because of this it is likely that the real benefit of the treatment
was minor, except in the case where uniform sands were encountered
in the crown of the tunnel. Installation of the treatment, however,
itself caused significant g•ound movements.
REFERENCES
8-170