Risk Assessment/Management Form

Ref:
Section / Dept: civil Activity: Risk Assessment- Location/Area :
Contractor :- Sand Filling

Proba

Resid
bility
Sl Basic Job Potential Consequence Current control measures

Proba
Init Addition

ual
Risk rating Ri

risk
bility
N Steps Hazard ial al s
o. Ris control k
k measure ra
P E A R P
ti E A R
Use stopper at the time of n
unloading g

Collapse of No motor boy will stay behind


Unloading of soil/pits,hit to the vehicle and maintained
1 aperson,collaps-e
Get Injury/Fatality
safe distance from the vehicle 2 0 0 2 2 4
sand at site
of soil.

Safe access shall be provided


for unloading the sand/soil
Strict supervision to be provided for
the job 1 0 0 0 2 2
Shifting of sand to Slip of iron pan
2 the tunnel from the hand, Get Injury Persons shall be deployed in the job
manually Slip of man with safety shoe , helmet, jacket,
goggles and rubber hand gloves
1 0 0 0 2 2
Workers will provided with full body
Falling from Get Injury due to safety harness
3 Working at height
height fall Take height work permit before
starting the activity
Prepared By Approved By Reviwed By
Contractor Contractor Contractor
Date Date Date