Inquiry for Gami_Hanam_Vietnam project:

1) Total heating capacity is 3656kw, we need two gas-fired hot water boilers, each with heating
capacity about 1830kw.
2) The supply/ return water temperature is 70/90℃ or 70/95℃, climate is 36℃,72%r.h. in
summer and 8℃, 59%r.h. in winter.
3) The main equipments are as following:
Item Equipment name Quantity Band Remarks

立卧式燃气承压热水锅
1 炉 2 sets
Gas-fired hot water
boiler

2 烟囱 chimney 1 set

锅炉循环水泵 boiler 两用一备 two for use,


3 3 sets KSB, Grundfog
circulating water pump one for backup

系统循环水泵 supply
4 water circulating water 2 sets KSB, Grundfog 如需要, if need
pump

膨胀水箱 expansion
5 calculated by supplier
tank

燃气泄漏探测器及收集
6 罩 Gas leak detector and calculated by supplier
collection hood

燃气流量计 gas
7 1 set
flowmeter

8 软水机 softening plant 1 set

软水补水箱 filling water


9 1 set
tank

补水水泵 filling water 一用一备 one for use,


10 2 sets
pump one for backup

11 除污器 dirt seperator 1 set

燃气紧急切断阀、电动
球阀、压差控制阀等 Gas
emergency shut-off
12 valve, electric ball Calculated by supplier
valve, differential
pressure control valve,
etc

由锅炉燃烧器燃气阀组
第一个阀门至燃烧器入口 锅炉房内 10m 范围,包
(含天然气放散管) From 括管道、安装
the first valve of the
13 gas train of the boiler 2 set Including the piping
burner to the burner and installation in
entrance (including the range of 10m nearby
natural gas venting boiler room.
pipe)

含台数控制盘、强电配电
柜、燃气计量、消防模块
集中控制系统
14 centralized-control 1 set Including control panel,
system power distribution
cabinet, gas meter and
fire control model.

含办理锅炉使用证等全
部。管道安装以锅炉房墙
各类管道的材料、辅料、 为界,接驳位置为锅炉房
人工等。All kinds of 内。
15 pipe materials, 1 set
auxiliary materials, Including the cost for
labor, etc. boiler license. All
connection pipe inside of
boiler room is in scope.

锅炉房方案图纸、相关技
术资料(锅炉系统工艺图
锅炉房内锅炉系统工艺 纸资料的设计,并通过质
图纸资料设计费 检部门报批。
4) Please quote the boiler room which is economical and reasonable, and meets the
local standard. Provide the flow chart of the boiler plant.
5) The project is in Vietnam, and the quotation shall be a turnkey price, including the package
and transportation fee (the package shall meet the export requirements, and transport to
Shanghai), the installation, commissioning, and training fee on site and etc.
6) Scope of supply is a turn-key Boiler Plant inclusive all extra work. The scope is functional
described. If there are any further components and assemblies necessary for operating the
Boiler Plant, it has to be specified in the quotation.