Date: Indicates Requirement Date MRP Element: Defines Type of Requirement

This document provides an overview of the MD04 - Stock Requirements List transaction in SAP. It displays the planning parameters, current stock, and requirements for a material by plant. The key fields shown are the date, MRP element type (e.g. sales order, production order), associated document number or requirement type, quantity received/required, and available stock. MD04 consolidates all current demands, requirements, and the stock situation for a given material in one place.

Uploaded by

Naveen Bhai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
126 views2 pages

Date: Indicates Requirement Date MRP Element: Defines Type of Requirement

This document provides an overview of the MD04 - Stock Requirements List transaction in SAP. It displays the planning parameters, current stock, and requirements for a material by plant. The key fields shown are the date, MRP element type (e.g. sales order, production order), associated document number or requirement type, quantity received/required, and available stock. MD04 consolidates all current demands, requirements, and the stock situation for a given material in one place.

Uploaded by

Naveen Bhai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Click here to edThis is important transaction to view current status of the material - MD04 - Stock

Requirements List.It will display planning parameters maintained material master like MRP type, MRP
controller, Procurement Type, Strategy group, availability check and Lot size etc at header level for the
respective plant.

It will display the current stock available as on date and time.

There are 5 important fields as given below:

Date : Indicates requirement date

MRP Element : Defines Type of requirement.

Examples:

1. If PIR is maintained for the Material then it will display as IndReq


2. Is sales order is created or material then CustSt
3. If production order is created then PrdOrd
4. If process order is created then PrcOrd
5. If planned order is created then PldOrd
6. If it is dependend requirement for some other demand then DepReq
7. If it is reservation generated for some other order then OrdRes
8. Similarly for Raw materials if Purchase requsition created then PurRqs
9. If PO is generated then POitem

Various requirements for the material like PIR, sales order, production order, planned orders etc are displayed
in MD04

MRP Element data: Defines against the MRP element relevent data.

Examples:

1. In case of PIR it displays the requirement type or requirement plan if demand is created against the
plan
2. In sales of Sales Order (CustSt) - Displays respective sales order number which is created for the
material
3. In case of production order PrdOrd - It displays the respective production order number
4. In case of planned order PldOrd - Displays planned order number which was generated after MRP run.
5. In case of purchase requsition it displays the PR number or PO number if converted to PO.

Receipt/Requirement qty: Quality Received or quantity required based on MRP element.

Eg:

1. In caseof purchase requsition it is required.


2. In case of process order/prduction order it is received
Available Quantity ; Defines the system calculated quantity available considering the receipts,issues and
current stock

In nut shell MD04 display all the current demand/requirements for the material along with current stock
situation.