Part II - Audit Observations and Recommendations
Part II - Audit Observations and Recommendations
A financial and compliance audit was conducted on the accounts and operations
of the Municipality of Compostela covering the period January 1, 2016 to December 31,
2016.
Presented and discussed below are the significant audit observations with the
corresponding corrective measures. Viz:
Section 287 of R.A. 7160 otherwise known as the Local Government Code of
1991 states that:
Item 2.3 of the Joint Memorandum Circular No. 2011-1 dated April 13, 2011 by
the Department of Interior and Local Government and the Department of Budget and
Management further provides the utilization of the 20% Development Fund that:
Item 5 of the same Joint Memorandum Circular identifies also the responsibility
of the Local Chief Executive, to wit:
83
“Responsibility for Delivery of Basic Services and Facilities. —
The LGUs shall, in addition to their existing functions and
responsibilities, provide basic services and facilities devolved to
them covering, but not limited to, the following:
For the Municipality xxxxxxxxxxxxxxxxxx;
(f) Provision of solid waste disposal or environmental
management systems and services or facilities related to general
hygiene and sanitation;
(g) Construction and maintenance of infrastructure facilities
funded by the municipality to serve the needs of the residents
including, but not limited to:
h) Construction, maintenance, and operation of municipal public
markets, slaughterhouses, and other economic enterprises;
84
c. Municipal Engineer
For calendar year 2016, a total of P33.4 Million was allocated for 20%
Development Fund of which P15.9 Million was intended for development projects, P12.5
Million for debt servicing and P5.0 Million as LGU counterpart for Bottoms Up
Budgeting (BUB) projects.
Further, as of yearend, there are still two projects under 20% Development Fund
(DF) for calendar year 2015 totaling P3,250,000.00. One (1) remained unimplemented
with a total cost of P750,000.00 for Drainage Development, while the other is still on-
going costing P2,500,000.00 for Cemetery Development with a percentage of completion
85
of 53% with construction duration of 712 calendar days as it was started last February 16,
2015 and still on-going as of the present.
On the other hand, for CY 2014, the Concreting and Widening of J.P. Laurel and
L.S. Sarmiento Streets under 20% DF remained unfinished with a total cost of
P1,396,226.85. The project was only started last December 1, 2015, with construction
duration of 396 days, and is only 29% completed as of December 31, 2016.
The status of project implementation under 20% Development Fund for CYs
2016, 2015 and 2014 is provide in the next page:
A. Completed
Pob.
1 Installation of Water System Compostela No Duration 500,000.00 100
Pob.
2 Rehabilitation of Water System Compostela No Duration 500,000.00 100
TOTAL 1,000,000.00 6.3
B. On-Going
Rehabilitation of Municipal Roads &
1 Bridges Compostela 395 1,500,000.00 85
Concreting of E. Blanco St. to Lapu-
2 Lapu St. Compostela 150 600,000.00 85
3 Drainage Development Compostela 376 800,000.00 94
Solid Waste Collection & Disposal
4 Facilities Compostela 330 400,000.00 90
TOTAL 3,300,000.00 20.7
C. Not Started/Unimplemented/For Detailed Estimates
Rehabilitation of Barangay Roads & 1,000
1 Bridges Compostela ,000.00 For DE
Pob.
2 Concreting of E. Aguinaldo Street Compostela 2,500,000.00 0
Pob.
3 Concreting of Bayubay Street Compostela 2,500,000.00 0
Pob.
4 Concreting of Senen Suarez St. Compostela 700,000.00 0
Improvement of Public Market Pob.
5 Facilities Compostela 1,000,000.00 0
6 Cemetery Development Maparat 1,000,000.00 For DE
86
7 Development of Eco-Park Maparat 500,000.00 0
Impr. Of Multi-Purpose Purok
8 Centers/Day Care Centers Compostela 1,378,225.00 For DE
Construction of MP Building-IP
9 Bldg. Compostela 400,000.00 0
Construction of CR-Crossing Gabi
10 Public Market Compostela 700,000.00 For DE
TOTAL 11,678,225.00 73
TOTAL 2016 20% Development Fund 15,978,225.00 100
CY 2015 - 20% Development Fund Projects
Completed
1 Rehab of Brgy. Roads & Bridges Compostela 365 1,000,000.00
2 Rehab of Mun. Roads & Bridges Compostela 280 1,500,000.00
3 Concreting of Municipal Ground Compostela no start date 500,000.00
4 Improvement of Public Market Facilities Poblacion 415 1,000,000.00
5 Drainage Development Poblacion 380 900,000.00
6 Installation of Water System Poblacion 375 900,000.00
TOTAL 5,800,000.00
On-going
1 Cemetery Development Maparat 712 2,500,000.00 53
Unimplement
ed
1 Development of Slaughterhouse Osmena 750,000.00 For DE
TOTAL 2015 9,050,000.00
CY 2014 - 20% Development Fund Projects
Conc. & Widening of J Laurel & L.S. Pob.
1 Sarmiento Compostela 1,392,226.85 29
26,420,451.8
GRAND TOTAL 5
A. CY 2016
On-going 1 500,000.00 17
87
Noted further that management was a long way behind in its action to carry through
the implementation of the CY 2015 planned projects costing P23,210,069.74. Out of the
14 projects, 10 projects were completed with a total cost of P4,751,808.43 which is only
20.5% of the total appropriation. While four (4) are still on-going with a total cost of
P4,150,000.00 and ten (10) remained unimplemented costing P9,519,421.38. See table in
the next page:
B. CY 2015
Unimplemented 10 9,519,421.38 41
The status of project implementation for CYs 2016 and 2015 are provided in the
next page:
B. On-Going
1 Construction of Bodega Pob. 196 500,000.00 98
88
Compostela
TOTAL 500,000.00 17
C. Not Started/Unimplemented/For Detailed Estimates
Improvement of Government
1 Buildings Compostela 450,000.00 0
2 Construction of Sports Complex Compostela 420,000.00 0
Construction of SB Office
3 Building Compostela 100,000.00 0
Construction of Multi-Purpose
4 Pavement Panansalan 100,000.00 For DE
Construction of Multi-Purpose
5 Pavement-P-7 Siocon 100,000.00 For DE
Construction of Multi-Purpose
6 Bldg. Compostela 293,545.42 0
Construction of Multi-Purpose
7 Pavement- P8 Mangayon 200,000.00 0
Construction of Multi-Purpose
8 Pavement-P 2 Maparat 200,000.00 0
Improvement of Public Market
9 Facilities Compostela 100,000.00 0
Const. of Activity Center-
10 Panansalan Panansalan 30,000.00 0
Construction of Multi-Purpose
11 Pavement Ngan 30,000.00 0
TOTAL 1,993,545.42 67.7
TOTAL 2016 - Locally Funded 2,943,545.42 100
CY 2015 - Locally Funded Projects
A. Completed
1 Improvement of Government Bldg. Compostela 371 450,000.00 100
2 Concreting of Masipag St. Poblacion 15 150,000.00 100
Concreting of Plaridel St. - Final
3 Phase Poblacion No Duration 250,000.00 100
Concreting of Sikatuna St. -
4 Final Phase Poblacion 31 300,000.00 100
Construction of Multi-Purpose 1,122,776.9
5 Building Compostela 571 3 100
1,400,000.0
6 Construction of SB Office Bldg. Poblacion 301 0 100
7 Improvement of Public Terminal Poblacion 55 500,000.00 100
8 Rehab of Water System Compostela 211 500,000.00 100
Const. of Multi-Purpose
9 Pavement - Purok 3 Maparat 46 42,000.00 100
Rehab of Health Center -
10 Bagongon Bagongon 31 37,031.50 100
4,751,808.4
TOTAL 3 20.5
B. On-Going
Concreting of San Miguel to 8/1/16- 1,500,000.0
1 Nat'l Highway Junction San Miguel 3/31/17 0 95
Construction of Market Stalls 1,250,000.0
2 (11 units) Poblacion -do- 0 98
Improvement of Multi- 9/1/16-
3 PurposePavement Panansalan 3/31/17 100,000.00 52
4 Const./Imprv.of Day Care Compostela 7/16/16- 1,300,000.0 80
89
Centers & Purok Houses 3/31/17 0
8,938,839.9
TOTAL 3 38.5
B. Not Implemented/For Detailed Estimates
Pob.
1 Construction of Sports Complex Compostela 420,000.00 0
Construction of Multi-Purpose Pob.
2 Building Compostela 562,990.00 For DE
Improvement of Multi-Purpose
3 Pavement Maparat 350,000.00 0
Improvement of Multi-Purpose
4 Building Compostela 436,431.38 For DE
Construction of Slaughterhouse
5 Building Compostela 1,750,000.00 For DE
Pob..
6 Rehabilitation of Timaya Bridge Compostela 2,000,000.00 For DE
Improvement of
7 Slaughterhouse Osmena 1,000,000.00 For DE
Construction of Public Market Pob.
8 Stalls Compostela 1,000,000.00 For DE
Const. of Multi-Purpose Bldg. Pob.
9 Drop In Center Compostela 1,500,000.00 0
Const./Impr. Of Multi-Purpose Pob.
10 Building Compostela 500,000.00 0
TOTAL 9,519,421.38 41
TOTAL - 2015 Locally Funded 23,210,069.74 100
The project data above revealed that the Municipal Engineer failed to carry out
the implementation of various infrastructure projects proposed to be pursued on the year
these were included in the budget.
The Municipal Planning and Development Coordinator was also lax in performing
his functions in monitoring and evaluating project implementation. Had religious
monitoring been conducted, causes for the delayed implementation of projects could have
been immediately addressed. His laxity also contributed on the magnitude of unutilized
project funds.
Recommendations:
90
We recommend the following courses of action:
The Municipal Engineer stated that the causes of delay in the implementation of
projects are as follows:
2. The lack of personnel to perform the technical aspects considering that aside
from the LGU funded projects, there are also special projects funded by the National
Government Agencies. There are only three (3) personnel under the MEO, one (1)
Licensed Civil Engineer, Building Inspector and Engineering Assistant, while the rest are
three (3) technical personnel on a job order status; 1 CE graduate and 2 Draftsmen. Out
of the six (6) personnel, only three are computer literate and CAD literate (Engr.1 and 2
Draftsmen);
4. She had overlooked the release of projects funds for some unimplemented
projects which were made on the 4th quarter of 2016;
5. There was a problem on the road right-of way for one (1) project in 2014 under
20% Development Fund since demolition of structures could not be immediately
undertaken due to some unavoidable circumstances and considerations;
91
6. Some projects are for reversion.
COA’s Rejoinders:
It can be noted on the foregoing project implementation data that there are projects
for more than two years which remained unfinished. These will probably entails additional
funding considering that estimates were made two years ago, thus, project completion will
be a problem. While lack of equipment for use in the project posed a problem due to old
age, the local government may have an alternative way, by renting equipment to be able to
finish what has been started and/or to implement projects with equipment component, to
be able to maximize the utilization of the project funds.
92
except where such failure, refusal or inability is through no fault of the said
bidder. (underscoring supplied for emphasis)
40.2 In the case of the failure, refusal or inability of the bidder with LCRB
or HRRB to submit the documents required under Section 37.1 of this IRR or to
enter into contract and post the required Performance Security, as provided in
this Section, the BAC shall disqualify the said bidder, and shall initiate and
complete the post-qualification process on the bidder with the second Lowest
Calculated/Bid.Highest Rated Bid: Provided, however, That in the case of
Consulting Services, the second Highest Rated Bid has successfully undergone
the negotiation stage in accordance with Section 33.2.5 of this IRR. This
procedure shall be repeated until the LCRB or HRRB is determining for award.
However, if no bidder passes the post-qualification, the BAC shall declare the
bidding a failure and conduct bidding with re-advertisment. Should there occur
another failure of bidding after the conduct of the contract’s re-bidding,
the Procuring Entity concerned may enter into a negotiated procurement.
(underscoring supplied with emphasis)
40.3 In case of failure, refusal or inability of the bidder with the SCRB or
SRRB to submit the documents required under Section 37.1 of this IRR or to
enter into contract and post the required Performance Security, as provided
in this Section, the BAC shall disqualify the said bidder, and shall declare the
bidding a failure and conduct a re-bidding with re-advertisement and/or
posting, as provided for in Sections 21 and 25 of this IRR. Should there occur
another failure of bidding after the conduct of the contract’s re-bidding, the
Procuring Entity may enter into a negotiated procurement.(underscoring
supplied with emphasis)
The performance security shall be in an amount not less than the required
percentage of the total contract percentage of the total contract price which are a) 5% for
goods and Consulting Services for cash or cashier’s/manager’s check issued by a
Universal or Commercial Bank, …. c) 30% for Surety bond callable upon demand issued
by a surety or insurance company duly certified by the Insurance Commission as
authorized to issue such security in accordance with Section 39.2 of the 2016 IRR of RA
9184.
In the Notice of Award signed by the Local Chief Executive, it clearly indicated
that the bidder is required to provide within ten (10) days the Performance Security in the
form and the amount as stipulated in Section 39.1 of RA 9184. Failure on the part of the
bidder to post the performance security shall constitute sufficient ground for cancellation
of the award and forfeiture of the bid security as provided under Section 40 of RA 9184
above.
93
Management awarded contracts to July Gas Station to supply or deliver fuel, oil,
lubricants for use by the heavy equipment and light vehicles of the municipality. July Gas
Station is the lone winning bidder to supply the said goods not only in calendar year 2016
but also in the past year. During the year a total of P3,984,851.58 was procured from the
said establishment.
DG Agrivet was also awarded a contract for the supply of goods for the
Sustainable Livelihood Program (SLP) worth P2.3 Million.
In AOM No. 2017-005 (16), DG Agrivet has also been remiss in its obligation to
deliver within six months the remaining goods for the SLP worth P1,070,000.00.
The General Services Office failed to check whether winning bidders had
promptly paid the Performance Security required of them before issuing the purchase
orders/contracts. Management’s neglect regarding the posting of performance security of
winning bidders is greatly prejudicial to the interest of the government.
Recommendations:
Require the General Service Office to see to it that Performance Security has been
provided by the winning bidders before the issuance of the contract/purchase orders as a
guarantee for their performance.
Management Comments:
The OIC-General Services Officer stated that when she assumed office, the
practice is that Purchase Order were prepared first before the Notice of Award is issued,
hence, some winning bidders failed to post performance security. However, she
promised to abide to the provisions of RA 9184 and upon her assumption she made it
sure that performance security will be posted by the winning bidder before the issuance
of the purchase orders/contracts.
COA’s Rejoinder:
94
See to it that winning bidders will have a guarantee in performing his obligations
to the government by way of paying the required performance security in order to protect
the interest of the government.
On the last quarter of calendar year 2015, bidding was conducted on the following
SLP programs, to wit:
Nature of SLP Program Program Cost
Organic Native Chicken Production 2,400.000.00
Fruit Trees Rehabilitation 2,999,500.00
Organic Sweet Corn Production 1,059,000.00
Organic Peanut Production 529,000.00
Organic Mungbean Production 441,500.00
Total 7,429,000.00
Renel’s Fruit Nursery had also been given a three (3) month period to deliver fruit
trees seedlings and seed worth P3,227,840.00 from January 25, 2016 (date of receipt of
the purchase order) up to April 24, 2016. Renel’s made partial deliveries for the goods on
June 8, 2016 worth P2,499,038.80 which was 45 days delayed and 6 staggered deliveries
worth P453,756.67 which were also beyond the 3 month period. A total 5,615 hills of
Lanzones seedlings worth P280,469.25 were not yet delivered as of December 31, 2016,
a delay of 246 days.
The failure of the suppliers to deliver the goods for the livelihood needs of the
identified beneficiaries resulted in the non-attainment of the poverty reduction goals of
the SLP and eventually affected the efficiency and effectiveness of the operations of the
local governance.
95
Recommendations:
Management shall see to it that program funds intended to the poor constituents
be efficiently and effectively be implemented in order to uplift their living conditions.
Direct the General Services Office to monitor the complete deliveries of goods on
schedule dates and the Municipal Agriculture Office to fast track the implementation of
Sustainable Livelihood programs in order to achieve program goals and objectives.
Management Comments:
The OIC-General Services Officer stated that she failed to monitor the deliveries
of goods for the SLP. However, she assured to communicate with the concerned suppliers
for the undelivered goods.
The Municipal Planning & Development Coordinator who is one of the members
of the Bids and Awards Committee stated that it was emphasized during the pre-bid
conference on their obligations to the local government. Also, site inspection and
evaluation conducted on Renel’s Nursery, they are capable to supply the goods.
COA’s Rejoinder:
4. Liquidated Damages totaling P 694,238.82 was not deducted from the claims of
Renel’s Fruit Nursery, DG Agrivet and North Davao Producers and Agri-
Services Inc. for delayed deliveries of goods.
In the event that suppliers failed to deliver goods on the scheduled delivery date,
liquidated damages and/or sanctions shall be imposed by management.
96
goods scheduled of delivery for every day of delay until such goods are
finally delivered and accepted by the procuring entity concerned.
3.2 The procuring entity need not prove that it has incurred actual
damages to be entitled to liquidated damages. Such amount shall be
deducted from any money due or which may become due to the supplier,
or collected from any securities or warranties posted by the supplier,
whichever is convenient to the procuring entity concerned. In no case
shall the total sum of liquidated damages exceed ten percent (10%) of the
total contract price, in which event the procuring entity concerned may
rescind the contract and impose appropriate sanctions over and above the
liquidated damages to be paid.” (underscoring supplied for emphasis)
Provided hereunder are the schedules of delayed deliveries of SLP goods of the
following suppliers, to wit:
A. Renel’s Fruit Nursery – Total amount of Purchase Order (PO) - P3,227,840.00
Cost of
Date of Terms of
Should be – Total Cost of No. of Undelivered Amount of
Receipt of Delivery – DR # /Date
Date of Delivered Days Goods (LD- Liquidated
PO by from PO of Delivery
Delivery Goods Delayed 1/10 of 1% Damages (Php)
Supplier recp’t
/day-delay)
1/25/2016 3 mos. 4/24/2016 0215 - 2,499,038.80 45 728,801.20 32,796.05
6/8/2016
1/25/2016 3 mos. 4/24/2016 566 63,919.72 122 664,881.48 81,115.54
-8/24/2016
1/25/2016 3 mos. 4/24/2016 565 – 286,426.80 136 378,454.68 51,469.84
9/7/2016
1/25/2016 3 mos. 4/24/2016 568– 103,410.15 166 275,044.53 45,657.39
10/7/2016
TOTAL 2,952,795.47 211,038.82
Cost of
Date of Terms of
Should be Total Cost of No. of Undelivered Amount of
Receipt of Delivery – DR # /Date of
– Date of Delivered Days Goods (LD-1/10 Liquidated
PO by from PO Delivery
Delivery Goods Delayed of 1% /day- Damages (Php)
Supplier recp’t
delay)
1/15/2016 6 mos. 7/16/2016 326-8/16/2016 240,000.00 31 2,060,000.00 63,860.00
1/15/2016 6 mos 7/16/2016 325-8/17/2016 240,000.00 32 1,820,000.00 58,240.00
1/15/2016 6 mos 7/16/2016 329-9/22/2016 150,000.00 68 1,670,000.00 113,560.00
1/15/2016 6 mos 7/16/2016 330-10/13/206 360,000.00 89 1,310,000.00 116,590.00
1/15/2016 6 mos 7/16/2016 331- 240,000.00 90 1,070,000.00 96,300.00
10/14/2016
TOTAL 1,230,000.00 448,550.00
97
C. North Davao Producers and Agri-Services Inc. - Total amount of PO- P550,000.00
Cost of
Date of Terms of Amount of
Should be Total Cost of No. of Undelivered
Receipt of Delivery- DR # /Date of Liquidated
– Date of Delivered Days Goods (LD-1/10
PO fr. PO Delivery Damages
Delivery Goods Delayed of 1% /day-
Supplier rep’t (Php)
delay)
1/25/2016 10 CD 2/4/2016 2265-4/8/2016 550,000.00 63 550,000.00 34,650.00
TOTAL 34,650.00
Moreover, in the schedule agreed upon by the BAC and the winning bidders, the
goods are to be delivered within three (3) months by Renel’s Fruit Nursery and within six
(6) months for DJ Agrivet in their Delivery Schedule. However, scrutiny of schedule
provided by Renel’s Fruit Nursery, it did not indicate the delivery dates, the nature of the
goods and its quantity. While, for DG Agrivet, it only indicated within six (6) months
from receipt of the purchase order which is also very vague as it did not also clearly
specify the quantity of goods to be delivered and scheduled dates of delivery.
The winning bidders were given ample time to satisfactorily deliver the goods
within the period given to them yet they still failed to completely supply the goods. The
BAC failed to carefully evaluate and assess the conditions as to the delivery schedule
provided by the bidders since they were given the liberty when, what, and how many
deliveries will be made. The delivery schedule should have been taken up during the pre-
bid conference.
The General Services Office, Municipal Accountant’s Office and the Bids and
Awards Committee incurred lapses in the discharge of their functions as provided below:
These deficiencies adversely affected the efficiency of the local governance and
eventually prejudicial to the interest of the government.
98
Recommendations:
Require the Municipal Accounting Office to carefully check and review claims of
suppliers for the proper imposition of liquidated damages that will be deducted from their
claims.
Management Comments:
The OIC-General Services Officer admitted that she had overlooked the
monitoring of deliveries of goods of some suppliers. She also stated that computation of
liquidated damages was relied to the Accounting Office.
The OIC-Municipal Accountant also admitted that she had overlooked the
computation of liquidated damages for the delayed deliveries made by the suppliers;
however, she assured that the liquidated damages incurred will be deducted from the final
payment to be claimed by the suppliers.
COA’s Rejoinder:
99
treasurers thereof monthly within fifteen days of every
succeeding month. No portion of the collections may be
transferred or diverted to the general or any of other fund of the
National Government, provinces, cities, municipalities, or used or
expended for any purpose other than those specified in this Act. It
shall be the ministerial duty of the Budget Commissioner, the
Treasurer of the Philippines, all municipal, provincial and city
treasurers, as well as the officials and employees under their
supervision and control to effect releases from the Fund within
fifteen days from receipt of the order and/or authorization by the
Secretary of Education, in respect to the share of the National
Government from the Fund, and by the municipal, city or
provincial school boards, in respect to their respective shares from
the Fund.” (underscoring ours)
Verification of transactions from January 2016 to November 2016 revealed that
the Municipal Treasurer incurred delays in the turnover of the 50% special education tax
share of the provincial government. A total of P4,558,646.07 was remitted comprising
collections from December 2015 to September 2016. The longest incurrence of delay is
85 days as reflected in the table below:
No.
Due
of
Check OR Date Date of
Date Payee Period Amount Days
Number Number Remitted Remitta
Dela
nce
yed
PTO - 1,017,049
7/12/2016 692297 Comval May 2016 .39 6501730 7/13/2016 6/15/16 28
PTO - 337,351.
8/3/2016 692301 Comval June 2016 70 6501739 8/5/2016 7/16/16 21
100
No.
Due
of
Check OR Date Date of
Date Payee Period Amount Days
Number Number Remitted Remitta
Dela
nce
yed
Comval 68
TOTAL 4,558,646.07
Recommendation:
Management Comment:
The Municipal Treasurer explained that due to the newly introduced Philippine
Public Sector Accounting Standards in the Accounting Office and the closing of
accounts, there was a delay on the remittance of the provincial share on Special
Education Tax (SET).
COA’s Rejoinders:
101
could have improved the operation of the elementary and public schools in the
locality contrary to the provisions of RA 7160, RA 5447 and other rules and
regulations issued by DECs, DBM and DILG.
Section 1 of RA 5447 provides among other, that the Special Education Fund
(SEF) shall be expended exclusively for the following activities:
Section 272 of RA 7160 also provides that the proceeds from the additional one
percent (1%) tax on real property accruing to the SEF shall be automatically released to
the local school boards, provided that the proceeds shall be allocated for the operation
and maintenance of public schools, construction and repair of school buildings, facilities
and equipment, educational research, purchase of books and periodicals, and sports
development as determined and approved by the Local School Board. (underscoring
supplied for emphasis)
102
On the other hand, Section 2.1 of DECS-DBM-DILG Joint Circular No. 01-B
dated June 25, 2001 clarified Section 2.0 of DEC-DBM-DILG Joint Memorandum
Circular No. 01-A to include among the priority items chargeable to SEF, the payment of
salaries and authorized allowances of teachers hired to handle new classes as extensions
of existing public elementary or secondary schools. (underscoring supplied for emphasis)
Audit of CY 2016 disbursements under the SEF for the period January to
November 2016 revealed that various expenses totaling P288,720.00 were improperly
charged against the fund. These consisted of the following nature of expenses:
Nature Amount
Meal Allowance for Boy Scouts/Advisers to Provincial Jamboree 25,000.00
Meal Allowance for Teachers – GSP Councilwide Star Holiday 43,720.00
Meal Allowance – CNHS Bulawanong Pasundayag Street Competition 10,000.00
Meal Allowance – Campus Journalism & Literacy Day 45,000.00
Cash Prizes for Best Heroes Park – Elementary Level 15,000.00
Cash Prizes for Classroom Restructuring – Elementary Level 15,000.00
Cash Prizes for Kindergarten Day 5,000.00
Cash Prizes for Festival of Talents – Values Education 5,000.00
Cash Prizes for Festival of Talents – Araling Panlipunan 5,000.00
Cash Prizes for Tribal Panaghiusa Festival 5,000.00
Cash Prizes for Kinder Day Program 90,000.00
Cash Prizes for MAPEH Festival - Dances 5,000.00
Cash Prizes for Math Quiz 10,000.00
Cash Prizes for Math Challenge 10,000.00
TOTAL 288,720.00
Noted above that there were payments made for salaries/honorarium of teachers
without established extension classes and the other aforementioned expenses are not also
allowed to be charged to SEF as the fund is intended only for the improvement of the
operation and maintenance of elementary and secondary public schools. Such other
expenses mentioned above shall be charged against the Maintenance and Other Operating
Expenses (MOOE) of the respective schools or District Offices which is annually
included in the General Appropriations Act of the Department of Education.
Recommendations:
We recommend that the Local School Board shall undertake the following
courses of action:
103
1. Consider and include only expenditures appropriately chargeable to Special
Education Fund pursuant to RA 5447, RA 7160 and DECS-DBM-DILG Joint
Circular No.2 01-A and 01-B during the planning and budget preparation.
3. For schools in dire need of establishing extension classes, submit request to the
DepEd Division Superintendent supported with the computation of the number of
pupils/students vis-à-vis number of regular DepEd teaching staff in the concerned
elementary/secondary public schools in order to accommodate the salaries of
teachers to be hired which can be appropriately charged against the Special
Education Fund.
Management Comment:
The District Supervisor assured that expenditures to be funded out of the Special
Education Tax will conform on the provisions of RA 5447 and DepEd guidelines and other
issuances.
COA’s Rejoinder:
See to it that future expenses to be charged under Special Education Fund Budget
will be in accordance with laws, rules and regulations to avoid audit suspensions and
disallowances.
Section 124 of the Manual on the New Government Accounting System (NGAS)
provides:
104
“xxx The Chief Accountant shall maintain the perpetual inventory
records comprising of Supplies Ledger Cards (SLC) for each
commodity /stock, Property, Plant and Equipment Ledger Card
(PPELC) for each category of plant, property and equipment xxx.
The provision of Section 124 of the NGAS Manual, Volume 1, requiring the
periodic physical inventory of property, plant and equipment, has been disregarded for two
years.
The OIC General Services Officer stated that physical inventory of the
municipality properties was conducted and an inventory report was prepared. This was
submitted to the OIC-Municipal Accountant for reconciliation with the books of
accounts.
As of December 31, 2016, the total net book value of the property, plant and
equipment accounts of P182,491,033.84 is 41.2% of the total assets of P442,579,492.13.
Details are as follows:
Nature Amount
Land 10,618,003.54
Other Land Improvements 6,208,543.38
Road Networks 12,049,194.19
Water Supply Systems 4,254,777.37
Other Infrastructure Assets 4,525,918.14
Parks, Plazas & Monuments 32,832.82
Buildings 17,954,430.44
School Building 4,288,266.87
Hospitals and Health Centers 389,463.87
Markets 28,488,480.27
105
Nature Amount
Slaughterhouse 500,272.57
Other Structures 16,529,574.24
Office Equipment 3,741,344.37
Information and Communication 3,427,844.29
Agricultural and Forestry Equipment 122,914.20
Communication Equipment 230,846.87
Construction and Heavy Equipment 14,368,448.35
Disaster Response and Rescue Equipment 4,703,233.44
Medical Equipment 494,702.76
Printing Equipment 299,545.00
Technical and Scientific Equipment 58,600.00
Other Machinery and Equipment 2,561,415.14
Motor Vehicles 3,328,829.11
Furniture and Fixtures 1,424,771.62
Books 34,775.60
CIP-Infrastructure Assets 26,981,682.67
CIP-Buildings and Other Structures 14,246,210.44
Work/Zoo Animals 491,311.98
Other PPE 491,311.98
TOTAL 182,491,033.84
The failure to completely conduct physical inventory and submit this inventory
report for reconciliation with the accounting books proved doubtful, the correctness and
existence of the reported PPE accounts of P182.5 Million as of December 31, 2016.
Recommendations:
Require the Municipal Property Inventory Team which should be composed of the
representatives of the Municipal Mayor, Municipal Treasurer/Municipal General Services
Officer, Municipal Assessor and the Accountable Officer of every Department of the
Municipal Government to conduct a complete physical inventory of all properties owned
by the municipality at least once a year. Also, for properties without proper costing, the
appraised value shall be the basis as recommended by the Appraisal Committee. All
unserviceable equipment or properties should be included in the physical count and render
a report thereon for possible disposal and/or dropping from the books of accounts.
Require the Municipal Government Services Office to prepare the Report on the
Physical Count of Property, Plant and Equipment (RCPPE), and furnish the Municipal
Accountant a copy of the report for reconciliation purposes in accordance to Section 124 of
106
the NGAS. Direct the Municipal Accountant and the Municipal General Services Officer to
maintain and update the necessary records on PPE as required in Section 114 of the NGAS
Manual. Property, Plant and Equipment Ledger Card shall be maintained by the Municipal
Accountant and Property Cards by the Municipal General Services Officer. Periodic
reconciliation of the accounting, general services records, and inventory reports of PPE
should be undertaken. Any discrepancies noted, necessary adjustments shall be effected in
order to present an accurate PPE balances in the financial statements.
Management Comments:
The OIC-General Services Officer stated that she had furnished the OIC-
Municipal Accountant of the Inventory Report for reconciliation with the accounting
records; however she missed to follow it up. She promised to submit it as soon as the
accounting finished its reconciliation.
The OIC-Municipal Accountant revealed that reconciliation will still be made and
assets purchased by the municipality for the barangays will also be transferred to the
barangay books.
COA’s Rejoinder:
Submission of a complete and reconciled inventory report of LGU’s property,
plant and equipment as of year-end is very vital so that the auditor can validate the
existence and the accuracy of the reported assets in the financial statements.
8. The General Services Office failed to regularly prepare and submit the
Summary of Supplies and Materials Issued (SSMI) for inventoriables to the
Accounting Office for proper adjustment of expenses, hence the correctness and
validity of the balance of the Inventory Accounts worth P14,112,106.67 is
doubtful.
Sec. 121 of the Manual on the New Government Accounting System, Volume I,
states:
107
Inventory Accounts Amount (Php) % to TOTAL
108
Welfare Good for Distribution 455,477.29 2.00
Agricultural Produce for Distribution 278,705.00 1.00
Other Supplies and Materials for Distribution 71,250.00 0.00
Office Supplies 1,804,663.18 7.00
Accountable Forms, Plates & Stickers 143,811.00 1.00
Non-Accountable Forms Inventory 16,585.00 0.00
Animal/Zoological Supplies 97,539.00 0.00
Food Supplies 59,940.00 0.00
Drugs and Medicines 300,483.45 1.00
Medical, Dental and Laboratory Supplies 455,034.65 2.00
Fuel, Oil and Lubricants 1,745,546.35 7.00
Textbooks and Instructional Materials 99,661.00 0.00
Agricultural and Marine Supplies 1,700.00 0.00
Construction Materials 15,860,017.99 65.00
Other Supplies and Materials 2,963,510.35 12.00
TOTAL 24,353,924.26 100
From the data above, it appears that the construction materials inventory of
P15,860,017.99 share the biggest bulk of the total inventories of P23,353,924.26.
The OIC Municipal Accountant stated that the General Services Office had
minimal submission of Summary of Supplies and Materials Issued (SSMI) on supplies
released to offices, thus adjustments could not be affected on the recorded inventory
accounts.
This resulted in the overstated asset and equity accounts and understated expense
account of the municipality.
Recommendations:
Require the OIC-General Services Officer to coordinate with all department heads
on all goods purchased and issued on prior years’ to be able to facilitate the adjustments
to be made on the inventory items reflected in the financial statements.
Management Comments:
The OIC-General Services Officer explained that the bulk of the inventoriables
pertained to prior years’ transactions. She found it difficult to prepare the SSMI for prior
109
years’ issuances of goods as there are no files of Requisition Slips as well as purchase
orders.
The OIC-Municipal Accountant stated that construction materials had the biggest
share on the inventory since various deliveries were made on the last month of the year.
COA’s Rejoinders:
Regular submission of the consumption reports is very important for the proper
recognition of the expense and an accurate valuation of the asset of the municipality.
COA Circular 2016 -005 dated December 19, 2016 stated that:
Moreover, the same circular provides the procedures in the write-off of dormant
accounts, to wit:
8.2 The Head of the government entity shall file the request for
authority to write-off dormant receivable accounts, unliquidated
cash advances, and fund transfers to the COA Audit team Leader
(ATL) and/or Supervising Auditor (SA). No filing fee is required.
110
b. Certified relevant documents validating the existence of
the conditions, as applicable, such:
b.1. Death Certificate issued by Philippine
Statistics Office
b.2. Proof of Insolvency
b.3. Certification from the Department of Trade
and Industry that the debtor has no registered
business
b.4. Certification from the Securities and
Exchange Commission that the Corporation is
no longer active
b.5. Certificate of no residence in the barangay of
the municipality/city of last known address
b.6. Proof of exhaustion of all remedies to collect
the receivables and demand to liquidated the
cash advances and fund transfers, such as but
not limited to copies of served or returned
demand letters
b.7. Certification by Legal Officer of the entity of
no pending case relative to the account
b.8. Certification by the responsible officials of the
entity to the effect that there are no
records/documents available to validate claim
b.9. Other justifications, like in the case of request
for write-off due to loss of documents, the
circumstances of the loss should be stated in
the letter request.
b.10. In case of fund transfer, the unliquidated
amount after reconciliation shall be supported
by certification by the Chief Accountants and
approved by the Heads of the Source and
Implementing entities that the fund was
utilized for the purpose, and certification from
the recipient that the project was partially or
fully implemented, supported by pictures of
the implemented projects.
8.4 The ATL and SA, upon receipt of the request, shall assign a
reference number, verify and validate the above documents and
decide on the requests for authority to write off for amounts not
exceeding P100,000.00 per accountable officer/debtor/government
entity and by account within 15 days from receipt thereof;
8.7 For amounts more than P100,000.00 but not exceeding
P1,000,000.00 per accountable officer/debtor/government entity
and by account, the ATL and SA shall forward the entire records
111
of the requests to the CD/RD, together with their comments and
recommendations, within 15 working days from receipt thereof;
The Other Receivables account (1-03-06-990) is used to record the amount due
from debtors and other agencies not falling under any of the specific receivable account.
112
Recommendations:
We recommend that management direct the offices concerned and/or create a task
force to develop strategies to expedite collections and to enforce loan payment per
provisions of the MOA/Contract.
Management Comment:
The OIC-Municipal Accountant stated that she had prepared letters to confirm the
existence of the associations, business establishments, cooperatives and individuals.
Some of these do no longer exist. While for the Department of Agriculture 10% retention
fee of P116,400.00, it was already collected last January 17, 2017.
COA’s Rejoinders:
Exert extra effort to collect from cooperatives and/or other borrowers who still
exist in order to augment funds for the local government unit.
10. Failure of the Municipal Accountant to effect the necessary adjustments in the
books of accounts on the full withdrawal of cash from unauthorized
government depository banks which were already deposited/transferred by the
Municipal Treasurer to Land Bank of the Philippines totaling P890,365.06,
resulted to the overstated cash-in-bank-account by the same amount.
113
The Municipal Treasurer stated that the aforementioned accounts maintained with
unauthorized government depository banks totaling P890,365.06 were already closed last
October 10,2014 as authorized under Sangguniang Bayan Resolution No. 2014-3346
dated September 12, 2014. The funds were deposited/transferred to the Land Bank of the
Philippines, Nabunturan Branch. The closure of the bank accounts and its transfer was
due to the audit recommendations embodied in the calendar year 2013 Annual Audit
Report of the municipality.
Recommendation:
Management Comment:
The OIC-Municipal Accountant stated that she had overlooked the preparation of
a Journal Entry Voucher to take up the adjustments of the closed bank accounts and its
fund transfers to LBP. She promised to take up the necessary adjustments in June 2017.
COA’s Rejoinder:
114