Aramcoinspectionhandbook 150311084705 Conversion Gate01 PDF
Aramcoinspectionhandbook 150311084705 Conversion Gate01 PDF
Aramcoinspectionhandbook 150311084705 Conversion Gate01 PDF
&
Inspection Division
INSPECTOR’S
HANDBOOK
Published:
Page 2 of 111
Handbook Team:
Approved
______________ _________
A.F. Al Shammari Date
General Supervisor SACCID
Page 3 of 111
Preface
Page 4 of 111
Table of Contents
7.0 Piping
10.0 Vessels
11.0 Fittings
13.0 Supports
Page 5 of 111
PAINTS & COATINGS
1.0 Paints & Coatings
Inspection Methods And Acceptance Criteria
8.1 General
This section gives the mandatory inspection methods and acceptance criteria
that shall be met before the FBE-coated welds can be put into service.
8.2.2 Thickness checks shall be made on each coated weld joint using an
approved, correctly calibrated magnetic dry film thickness gauge
(e.g. Microtest, Elcometer or equivalent). The instrument shall be
calibrated in accordance with SSPC PA-2.
8.2.3 On the first 5 joints of the job and twice each day thereafter, the
quality of cure shall be checked by maintaining a MEK soaked pad in
contact with the coating surface for one minute and then rubbing
vigorously for 15 seconds. There shall be no softening of the
coating or substantial color removal from the coating.
8.2.4 The finished coating shall have a uniform, glossy appearance and be
free of defects such as holidays, fish eyes, lumps, dry spray, sags
and runs.
Page 6 of 111
conducted if the surface temperature of the coated girth weld
area exceeds 88oC.
Patch Coating
6.3 Repairs
6.3.1.2 Areas larger than 1450 sq mm and smaller than 0.2 sq m - use an
epoxy-patching compound approved by the RSA.
6.3.1.4 The repair coating shall overlap the adjacent sound coating by at
least 13 mm. Coating application shall be according to the
Manufacturer's recommendations.
6.3.2.1 Isolated holidays less than 150 mm in any direction - Use a heat
shrink patch approved by the RSA. An average of no more than 1
field patch per 12 meter joint shall be acceptable for any
consecutive 100 meters. Damage in excess of this shall be sleeved
in accordance with paragraph 6.3.2.2 or cut out in accordance with
paragraph 6.3.2.3. The patches shall overlap the adjacent, sound
coating by at least 50 mm.
Page 7 of 111
per paragraph 6.3.2.1) - Use a full encirclement heat shrink sleeve
approved by the RSA. The sleeve shall overlap the adjacent sound
coating by at least 50 mm. Where more than one sleeve is
required, the sleeves shall be overlapped by at least 50%. A total
of no more than 3 meters shall be sleeved in the field in any
consecutive 100 meters in mountain terrain or 1000 meters in
other terrain.
Page 8 of 111
5.4 External Pipe Coatings, Cross-Country
Page 9 of 111
5. 4. 4 Buried APCS-104 APCS-113 On sleeved crossings, the
Road Crossings APCS-105 APCS-19B carrier pipe shall be
APCS-113 APCS-107 coated with APCS-104,
APCS-19B APCS-109 APCS-105, APCS-19B, or
APCS-113. The casing shall
be externally coated with
any of these systems or
with APCS-3.
Page 10 of 111
5. 6. 2 Insulated APCS-104 Same as Applies to pipe that will be
(Cold System) APCS-2A new operated continuously or
APCS-10 Constructi intermiiently below
APCS-105 on atmopheric dew point.
APCS-108 Cover with polyurethane or
foam glass insulation. For
APCS-2A, contact RSA if
applied onto cold surfaces.
Use APCS17A or APCS-17B
for temperatures less than
minus 40 0C.
5. 6. 4 Mild APCS-4
Atmospheric APCS-6
Exposure APCS-26B
Page 11 of 111
5.2 Materials
5.2.1 Abrasive shall be kept dry and clean. Regardless of the type of
abrasive, the sulphate, chloride, and calcium carbonate content (if
any) shall not exceed the levels given in Appendix I of this
standard.
5.2.3.1 The sand shall meet the requirements given in Appendix I of this
standard.
Page 12 of 111
Appendix I - Qualification Procedure For Sand For Abrasive Blasting
Prior to use, the Responsible Technical Organization shall certify in writing that the
sand meets the requirements below:
3. Loss on ignition in accordance with ASTM C146: at 1000 deg C the sand shall
not lose more than 1% by weight.
4. Water solubles (1:1 extract): The abrasive shall be less than 250 ppm
sulfates and less than 250 ppm chlorides, in accordance with ASTM D516
Method B and D512 Method A respectively.
5. Profile: The anchor pattern created on mild steel plate at 620 kPa (90psi)
nozzle pressure during abrasive flow must be in accordance with the
specified requirements of the applicable APCS Data Sheet.
% Solids by volume
Solvent added DFT = WFT x 1+ % thinner by volume
Theoretical Coverage
1000
Coverage (sq. m) = No. L X % Solids per L x DFT (micrometers)
1604
Coverage (sq. ft) = No. Gal coating X % Solids per L x
DFT (mils)
Page 13 of 111
Table I – Dew Point Calculation Chart Ambient Air Temperature
(Degrees Celsius)
Relative -7 -1 4 10 16 21 27 32 38 43 49
0 0 0 0 0 0 0 0 0 0 0
Humidity C C C C C C C C C C C
90 -8 -2 3 8 14 19 25 31 36 42 47
85 -8 -3 2 7 13 18 24 29 35 40 45
80 -9 -4 1 7 12 17 23 28 34 39 43
75 -9 -4 1 6 11 17 22 27 33 38 42
70 -11 -6 -1 4 10 16 20 26 31 36 41
65 -11 -7 -2 3 8 14 29 24 29 34 39
60 -12 -7 -3 2 7 13 18 23 28 33 38
55 -13 -8 -4 1 6 12 16 21 27 32 37
50 -14 -9 -5 -1 4 10 15 19 25 30 34
45 -16 -11 -6 -2 3 8 13 18 23 28 33
40 -17 -12 -8 -3 2 7 11 16 21 26 31
38 -19 -13 -9 -5 -1 4 9 14 18 23 28
30 -21 -16 -11 -7 -2 2 7 11 16 21 25
Example: if the air temperature is 21 deg. C the relative humidity is 70%,
the dew point is 16 deg. C.
Page 14 of 111
Sigma Phenguard Overcoating Times (Maximum Interval)
30
25
20
Time in Days
15
10
0
0 10 15 20 25 30 35 40 45 50
Temperature in Degrees C
Page 15 of 111
Sigma Phenguard Overcoating Times (Minimum Interval)
16
14
12
10
Time in Hours
8
0
0 10 15 20 25 30 35 40 45 50
Temperature in Degrees C
Page 16 of 111
Sigma Phenguard Overcoating Times (Time to Immersion)
16
14
12
10
Time in Days
8
0
0 10 15 20 25 30 35 40 45 50
Temperature in Degrees C
Page 17 of 111
Sigma Phenguard Times (Pot Life)
7
Time in Hours
4
0
0 10 15 20 25 30 35
Temperature in Degrees C
Page 18 of 111
Sigma Phenguard Induction Time
25
20
15
Time in Hours
10
0
0 10 15 20 25 30
Temperature in Degrees C
Page 19 of 111
SACCID Inspection
Reports
http://saoo.aramco.com.sa/data/saccid/saccid%20forms/GenlInsp/
SACPID-INSPECTION
INSP-9000
Ultrasonic Thickness Measurements
for Hot Tap/Sleeve Calculations
Equip./Pipe
Diameter Grade Schedule Flange Rating
Details:
Header
Branch per
Dwg.
Continuous Scanning
Measurement of Header in mm Min Max
B
4 Reinforcing Sleeve Ends -Line D-D
Note: For
Sleeve
connection
reinforcement
reinforcement
is required
requirements,
when the branch
referdiameter
to ASME is more
B31.3,than
B31.4,
70%B31.8,
of the header
ASME Section VIII & SA Standard Drawing L-AB-036719.
REFERENCE: DATE:
1) ORIGINATOR:
6) MANAGER, OPERATIONS:
10
11
12
13
14
15
16
DATA
Equipment: Plant Name: On Plot: Yes / No
From:
To: Service: * ( Oil / Gas / Water / Sewer / Firewater/
Disposal / Chem. / Air / Seawater
Installation Date: (Year) N2 / SO2 / S / SO2 SOL
Material: * CS / SS / PVC / FRP / GI / CI/RTR Injection Water / Supply Water )
Nominal Diameter: (Inches)
Nominal Wall Thickness: (Inches) Restrained: Yes / No
INSPECTOR'S REPORT
LEAK INFORMATION
Leak Location:
Leak Position: Buried: Yes / No
Length / Dia.: HOLE " : Backfill Type: Sand / Subkah / Marl / Rocky
RUPTURE " :
CAUSE : * Corrosion / Erosion / Mechanical / Crack EXISTING COATING APPEARANCE
TYPE: * Internal / External Details:
Corrosion Form: * General / Pit / Lake / Bands/ Groove 1. * Smooth / Cracked / Damaged
2. * Adherent / Detatched
Data Base Comments: Coating Type: APCS -
I.
II.
A.
B.
C.
Test Details:
Test Procedure in Initial Test Repair
Accordance with: Revalidation Modification
Preliminary Tests: Test Type:
[Hydro /Pneu/ Leak
Repairs During Tests: Test Fluid:
MAOP: Test Temp:
Relief Valve Tag #: Test Pressure:
Relief Valve Test Date: Test Duration:
Relief Valve Set Pressure: Test Date:
Pressure Gauge Cal Date: Gauge Range:
Sketch:
Test Results:
Accept: Reject: Conditional:
Comments:
C:\Data\Word\INSP-9008_Form_(Template).dot
SACCID
INSP-9009
RADIOGRAPHY REQUEST SHEET
Radiography Corrosion
Scale
FILM SIZE
INDENT. LINE IDENTIFICATION DIA. x THKS TYPE* FINDINGS/REMARKS
Page 25 of 111
SACCID
INSP-9011
Ultrasonic Testing Inspection Report
Date:
Description / Sketch:
Scale
______
Flow
12 12
1 1
2 2
3 3
4 4
5 5
CLOCK
6 6
POSITION
7 7
8 8
9 9
10 10
11 11
12 12
LENGTH
Page 26 of 111
SACCID
INSP-9013
FREQUENT INSPECTION FORM
Plant Name
Plant Number
System Number
Frequency Weekly Monthly 6 Monthly Yearly Other: Specify
Start Date
End Date
Letter Book#
Job
Remarks
Inspector
Field Supv.
Plant Name
Plant Number
System Number
Frequency Weekly Monthly 6 Monthly Yearly Other: Specify
Start Date
End Date
Letter Book#
Job
Remarks
Inspector
Field Supv.
Plant Name
Plant Number
System Number
Frequency Weekly Monthly 6 Monthly Yearly Other: Specify
Start Date
End Date
Letter Book#
Job
Remarks
Inspector
Field Supv.
cc: Supervisor
File: D:\DATA\INSPFORM\INSP9013 Revised: Dec. 1995
Page 27 of 111
SACCID
INSP-9014
VESSEL INSPECTION REPORT
VESSEL DATA
Heads:
COATING DATA
ANODES
Old
Type: Number: % Consumed: Date Installed: ____/____/_____
REMARKS:
Recommendations:
Signed:
Page 28 of 111
SACCID
Aramco 4719-0 INSP-9030
ARAMCO INSPECTION PROCEDURES
LIQUID PENETRANT EXAMINATION REQUEST & REPORT SHEET
Log No. B.I. No. Job. No. Plant No. Plant Name Contractor
Technician Date Acceptance Criteria Material Type Approved by (Proj. Insp.) Date
Sch/Wall ThicknPenetrant System Penetrant batch Penetrant Mfg. Penetrant Part No. Cleaner/Remover Part No.
A-3 ____ B-3 ____ Batch No:
Ultraviolet Light Used Measured UV light Intensity Developer Part No. Surface Condition
ITEM DRAWING EQUIPMENT NO/DIA/ SYSTEM WELD WELDER EXAM RESULTS REPAIR LOCATION COMMENTS
NO. NO. LINE REFERENCE NO. NO. SYMBOL ACC. REJ. AND DEFECT TYPE
Page 29 of 111
SACCID
INSP-9024
COATING SURVEY
PLANT # :
PLANT NAME :
SYSTEM # : DATE:
EXISTING COATING COATING FAILURE COATING REPAIR CORROSION WELD ANODES
EQUIP. YEAR SIZE % REPAIRS
# BUILT DIA L. AREA YEAR YEAR
COATED TYPE APPLIED % LOCATION TYPE COATED TYPE LOCATION DEPTH YES/NO TYPE #
Page 30 of 111
SACCID
INSP-9027
Hydrotest Date: / /
MAOP: PSIG
Comments:
Inspector:
Field Supervisor:
Page 31 of 111
SACCID
Aramco 4719-8 INSP-9031
ARAMCO INSPECTION PROCEDURES
MAGNETIC PARTICLE EXAMINATION REQUEST & REPORT SHEET
Log No. B.I. No. Job. No. Plant No. Plant Name Contractor
Technician Date Acceptance Criteria Material Type Approved by (Proj. Insp.) Date
Sch/Wall Thick. Magnetic Particles, Mfg. Particle Color Wet Method Particles Part No. Particles Batch No.
or Dry?
Particle Size Power Supply Descrptn. & Mfg. Pwr. Sup. Model No. & Sl. No. Magnettizing Current:
Amps. _____ AC _____ DC _____
Prod or Probe Method Prod of Probe Mfg/Model No./Serial No. Demagnetization Performed? Yes ___ No___
Equipment and Method Used:
Surface Condition & Cleaning
ITEM DRAWING EQUIPMENT NO/DIA SYSTEM WELD WELDER EXAM RESULTS REPAIR LOCATION COMMENTS
NO. NO. LINE REFERENCE # NO. SYMBOL ACC REJ. AND DEFECT TYPE
Page 32 of 111
SACCID
INSP-9035
Ultrasonic Testing Inspection Report
Date: _________________________
Plant Name: ______________ Palnt Number: _________ Plant Name: ______________ Palnt Number: _________
Equipment Name: _________________________________ Equipment Name: _________________________________
Size / Line #: ____________________________________ Size / Line #: ____________________________________
System #: _______________ Pressure: _____________ System #: _______________ Pressure: _____________
OSI DWG. #: ____________ Nominal Thk.: _____________mm OSI DWG. #: ____________ Nominal Thk.: _____________mm
U.T. Location: ____________ Retirement Thk: ____________mm U.T. Location: ____________ Retirement Thk: ____________mm
U.T. Equipment: ___________ U.T. Measurement: U.T. Equipment: ___________ U.T. Measurement:
Probe Size: _________mm Probe Size: _________mm
Frequency: _________Mhz Min: _____ mm Max: _____mm Frequency: _________Mhz Min: _______ mm Max: _______mm
Gain: _________db Gain: _________db
Range: _________mm Technicians: ________Verified: _______ Range: _________mm Technicians: ________Verified: _______
12 12 12 12
1 1 1 1
2 2 2 2
3 3 3 3
4 4 4 4
CLOCK 5 5 CLOCK 5 5
POSITION 6 6 POSITION 6 6
7 7 7 7
8 8 8 8
9 9 9 9
10 10 10 10
11 11 11 11
12 12 12 12
LENGTH LENGTH
Equipment Name: _________________________________ Equipment Name: _________________________________
Size / Line #: ____________________________________ Size / Line #: ____________________________________
System #: _______________ Pressure: _____________ System #: _______________ Pressure: _____________
OSI DWG. #: ____________ Nominal Thk.: _____________mm OSI DWG. #: ____________ Nominal Thk.: _____________mm
U.T. Location: ____________ Retirement Thk: ____________mm U.T. Location: ____________ Retirement Thk: ____________mm
U.T. Equipment: ___________ U.T. Measurement: U.T. Equipment: ___________ U.T. Measurement:
Probe Size: _________mm Probe Size: _________mm
Frequency: _________Mhz Min: _____ mm Max: _____mm Frequency: _________Mhz Min: _______ mm Max: _______mm
Gain: _________db Gain: _________db
Range: _________mm Technicians: ________Verified: _______ Range: _________mm Technicians: ________Verified: _______
12 12 12 12
1 1 1 1
2 2 2 2
3 3 3 3
4 4 4 4
CLOCK 5 5 CLOCK 5 5
POSITION 6 6 POSITION 6 6
7 7 7 7
8 8 8 8
9 9 9 9
10 10 10 10
11 11 11 11
12 12 12 12
LENGTH LENGTH
Page 33 of 111
SACCID
INSP-9036
Justification Comments:
Originator
CONCURRENCE:
Page 34 of 111
SACCID
COATING ENVIRONMENT RECORD SHEET
Plant Name: Plant Number: INSP-9038
NOTES
Page 35 of 111
HYDROSTATIC
TESTING
3.0 Hydrostatic Testing
Types of Pressure Tests and Their Purposes
The following describes various types of pressure tests and their purposes.
Each test can either be a hydrostatic test or, if approved by the Chief
Inspection Engineer, a pneumatic test. As previously noted, pressure tests
will normally by hydrostatic.
Strength Test
A Strength Test is a pressure test at an internal pressure that is high
enough to verify the integrity of the piping and/or equipment for service at
the Maximum Allowable Operating Pressure (MAOP). During this test, the
equipment shall not be subject to impact. The test pressure shall be
maintained for a duration of not less than 30 minutes for piping and 60
minutes for exchangers.
A strength test is applied in the following cases:
• Before piping system is initially placed in service.
• After repairs or alterations have been made that affect the strength of
pressure containing parts, except as noted in SAES-A-004/SAES-L-56.
• At intervals as specified by Equipment Inspection Schedules.
Tightness Test
A Tightness Test is a pressure test, which is conducted at a reduced
pressure from the strength test pressure, and is done immediately after the
strength test. A tightness test only applies to cross-country pipelines,
boilers, and pneumatic tests. The pressure must be maintained long enough
to permit inspection of the entire system for leaks, and for at least 10
minutes in all cases.
Page 37 of 111
Leak Test
A Leak Test is a pressure test to demonstrate that there are no leaks in the
system at the test are normally conducted by Operations during start-up or
commissioning of the facilities, using approved plant procedures, and are
outside the scope of SAES-A-004.
System Test
A System Test is an in-situ strength test which is applied to a system that
is comprised of piping and other equipment that operate at one MAOP, as
limited by the weakest element in the system.
Service Test
A Service Test is a strength test for low-pressure utility services that is
conducted at the operating pressure with the service fluid.
Revalidation Test
A Revalidation Test is a pressure test, which is meant to prove the integrity
of buried cross-country pipelines. This test is conducted at the option of,
and at the intervals set by, the responsible operating organization.
Saudi Aramco Engineering Standard SAES-A-004 and the applicable
industry code provide test pressure requirements. The following sections
discuss test pressures for plant piping and cross-country pipelines.
The above was taken from the Saudi Aramco 1998 Engineering
Encyclopedia.
Page 38 of 111
Gauge Calibration
good for 1 month 12
80% of test 13 14
pressure
12
12
5 11
8 16
1 4
2
1. Hand or reciprocating test pump
2. Union (TYP.)
3. Gate Valve (TYP.)
4. Check Valve.
5. Pressure Gauge with necessary valves and piping to release the pressure in the transition
piping between the valve on the mainline and pressure.
6. Relief valve by-pass-piping assembly when pressures exceed relief valve setting.
7. Pressure Relief Valve
8. Drain installed at 6.00 O’clock position on the mainline and preferably at the lowest point of
the line being tested. A hose should be installed to the drain valve and run clear of any
excavations to an improved dumping area.
9. Weld Neck, Raised Face, Ring Joint and Blind Flange (TYP.)
10. Vent with valve and piping assembly located at the high point of the piping network.
11. Plug Valve in an open position during a typical hydrotest of more than one component.
12. Spectacle plate illustrating an opening position during a hydrotest.
13. Weld Neck, Raised Face or Ring Joint companion flanges.
14. Calibrated pressure gauge and piping assembly for release of pressure following the mainline
liquid dump.
15. Calibrated pressure gauge liquid filled (Ethylene Glycol, thick liquid alcohol).
16. Water discharge and suction.
Page 40 of 111
HYRDROSTATIC TEST PRESSURES
FLANGE AND VALVE FLANGE AND VALVE BODY VALVE VALVE SEAT
BODY RATING TEST PRESSURE RATING TEST PRESSURE
150 450 150 315
300 1125 300 815
600 2225 600 1630
900 3350 900 2440
1500 5575 1500 4075
2500 9275 2500 6785
Page 41 of 111
WELDING
PROCEDURES
4.0 Welding Procedures
Page 43 of 111
and Ni-based (P42-47) alloys to
themselves. Dissimilar metal welds
include: Ni-based alloys to carbon
steels, low alloy steels, stainless
steels, nickel and Monel alloys;
Monel alloys joined to carbon steels;
nickel joined to stainless steels; and
stainless steels joined to carbon
steels.
Positions All
Current Direct (DC)
Polarity Reverse (electrode +)
Weld Progression Uphill
Joint Type Single vee
Bevel Angle 45o (± 5o)
Root Face None
Root Opening 1/4" (± 1/16")
Metal Backing Carbon steel backing strip
Root/Fill/Cap E308, 308L, E309, E310, E316 or
E316L (3/32", 1/8")
Diameter Range 2.5" NPS & greater
Filler Metal (Root/Fill/Cap):
Stainless Steels EXXX-15/16 (A5.4)
Nickel Alloys Ni-based (A5.11)
Dissimilar Welds Ni-based (A5.11)
Page 44 of 111
alloys; monel alloys joined to carbon
steels; nickel joined to stainless
steels; stainless steels to carbon
steels.
Positions All
Current Direct (DC)
Polarity Reverse (electrode +)
Weld Progression Uphill
Joint Type Single vee
Bevel Angle 60o (± 5o)
Root Face 1/16" (± 1/32")
Root Opening 1/8" (± 1/32")
Metal Backing None
Root/Fill/Cap EniCrFe-3 (1/8", 5/32")
Diameter Range 2.5" NPS & greater
Filler Metal Ni-based (A5.11)
Page 46 of 111
tubing. The OIU Inspector shall witness
the welding and the weld radiographed.
Page 47 of 111
SAEP-1109 Aluminum (TIG Welding)
Material Form Plate or Pipe
Base Metal Thickness 0.474" maximum
Process GTAW
Base Material Aluminum and aluminum alloys (P21, P22,
P23, P25) to each other
Positions All
Current AC (Alternating)
Shielding Gas Argon (10-20 CFH)
Gas Backing Argon (2-5 CFH)
Tungsten Electrode 1/8" 1/2-1% Zirconium oxide
Weld Progression Uphill
Joint Type Single vee
Bevel Angle 60o (± 5o)
Root Face 1/16" (± 1/32")
Root Opening 1/8" (± 1/32")
Metal Backing None
Root/Fill/Cap ER4043 (1/8")
Filler Metal ERXXXX, (A5.10)
Diameter Range 2.5" NPS and greater
Formula for Cross Section Area Formula for Cross Section Area CSA = RO x T
CSA = 1/2(S)2 CSA = 1/2(S1 x S2) RO
S
S
1
S S
T
2
RF
RO RF
T
Single V
RO
Double V
Page 50 of 111
ELECTRODES FOR WELDING SIMILAR AND DISSIMILAR METALS
1. Inco Inco A
Incoloy A
2.
E310*
1. Hast.
Hastello B
y
B
Page 51 of 111
ELECTRODES FOR WELDING SIMILAR AND DISSIMILAR METALS (Continued)
1-1/4% &
Hastelloy 3-1/2% 2-1/4% 5% 9% 12%
C Monel Brass Nickel Chrome Moly Chrome Moly Chrome Moly Chrome SS
Hast. C 1. Monel Braze 1. E7018 A 1. E7018 B 1. E7018 B 1. E9018 B3 B 1. Inco A A
Carbon 190 (Oxweld 2. Inco A A 2. E9018 B3 B 2. E9018 B3 B 2. E502 B 2. E310 A
Steel 2. Inco A 25M) 3. E8018 C2 A 3. E502 B 3. Murex 3. E410 B
4. E310* A Croloy 9A B
4. E310* A
Hast. C 1. Monel Braze 1. E7018 A 1. E7018 B 1. E7018 B 1. E9018 B3 B 1. Inco A A
Killed 190 (Oxweld 2. Inco A A 2. E9018 B3 B 2. E9018 B3 B 2. E502 B 2. E310 A
Steel 2. Inco A 25H) 3. E8018 C2 A 3. E502 B 3. Murex 3. E410 B
4. E310* A Croloy 9A B
4. E310* A
Hast. C 1. Monel Braze 1. E7018 A 1. E7018 B 1. E7018 B 1. E9018 B3 B 1. Inco A A
Carbon 190 (Oxweld 2. Inco A A 2. E9018 B3 B 2. E9018 B3 B 2. E502 B 2. E310 A
Moly 2. Inco A 25H) 3. E8018 C2 A 3. E502 B 3. Murex 3. E410 B
Steel 4. E310* A Croloy 9A B
4. E310* A
X Braze Braze Braze Braze Braze Braze Braze
Cast (Oxweld (Oxweld (Oxweld (Oxweld (Oxweld (Oxweld (Oxweld
Iron 25H) 25H) 25H) 25H) 25H) 25H) 25H)
Page 52 of 111
1-1/4% &
Hastelloy 3-1/2% 2-1/4% 5% 9% 12%
C Monel Brass Nickel Chrome Moly Chrome Moly Chrome Moly Chrome SS
1. Hast. C Inconel X 1. E309 A 1. E309 A 1. E309 A 1. E309 A 1. Inco A A
316 SS 2. Inconel 182 2. Inco A A 2. Inco A A 2. Inco A A 2. Inco A A 2. E310 A
182
3. E310
Inco A Inconel Braze 1. Inco A A Inco A A Inco A A Inco A A 1. Inco A A
Inconel 182 (Oxweld 2. E310 A 2. E310 A
25H)
Inco A Inconel Braze 1. Inco A A Inco A A Inco A A Inco A A 1. Inco A A
Incoloy 182 (Oxweld 2. E310 A 2. E310 A
25H)
Hast. B 1. Monel X Hast. B A 1. Hast. B A X X X
Hastelloy 190 2. Inco A A
B 2. Inco A
Hast. B 1. Monel X Hast. B A 1. Hast. B A X X X
Hastelloy 190 2. Inco A A
C 2. Inco A
Monel Braze 1. Monel A Inco A A X X X
Monel 190 (Oxweld 190
25H) 2. Inco A A
Braze X X X X X
Brass (Oxweld
25H)
3-1/2% 1. E8018 C2 B X X X X
Nickel 2. Inco A A
E9018 B3 B 1. E9018 B3 B 1. E9018 B3 B Inco A A
1-1/4% & 2. E502 B 2. E502 B
2-1/4% 3. E310* B 3. Murex
Chrome Moly Croloy 9A B
4. E310* B
E502 B 1. E502 B Inco A A
5% 2. Murex
Chrome Moly Croloy 9A B
3. E310* B
1. Murex Inco A A
9% Croloy 9A B
2. E310* B
12% 1. E410 B
Chrome SS 2. Inco A A
3. E310* B
Page 53 of 111
1-1/4% &
3-1/2% 2-1/4% 5% 9% 12%
Monel Brass Nickel Chrome Moly Chrome Moly Chrome Moly Chrome SS
Monel Braze 1. Monel A Inco A A X X X
Monel 190 (Oxweld 190
25H) 2. Inco A A
Braze X X X X X
Brass (Oxweld
25H)
3-1/2% 1. E8018 C2 B X X X X
Nickel 2. Inco A A
E9018 B3 B 1. E9018 B3 B 1. E9018 B3 B Inco A A
1-1/4% & 2. E502 B 2. E502 B
2-1/4% 3. E310* B 3. Murex
Chrome Moly Croloy 9A B
4. E310* B
E502 B 1. E502 B Inco A A
5% 2. Murex
Chrome Moly Croloy 9A B
3. E310* B
1. Murex Inco A A
9% Croloy 9A B
2. E310* B
12% 1. E410 B
Chrome SS 2. Inco A A
3. E310* B
Page 54 of 111
Page 55 of 111
Page 56 of 111
INSPECTION TOOLS
5.0 Inspection Tools
The following is a list of some auxiliary items that can be used to assist in
conducting an effective visual inspection.
• Standard forms/inspection checklist
This item includes the Saudi Aramco EIS form, if appropriate; as well as any
other approved procedural checklists.
• Cleaning tools
When needed, use simple cleaning tools such as a scraper or steel brush to
clean a surface before making a preliminary visual inspection. Chalk or similar
marking device. Use marking materials such as chalk to identify potential or
suspected problem areas.
Pit Gauges
Description/Operation. Pit gauges are instruments used to measure the
depth of pitting by placing a calibrated rod in the pit.
Application. Pit gauges are used to access the severity of localized
corrosion pitting. They can be used to measure the depth and width of a
depression or cavity in a pitted metal surface. The distribution of the attack
and an indication of the rate of corrosion can be determined by using these
tools.
Page 58 of 111
Advantages and Limitations. Pit gauges are relatively simple to use and the
data gathered by using them is easily interpreted. These tools can be used
to measure the depth of pitting on any accessible surface.
Mirrors
Description/Operation. To handle a variety of circumstances, mirrors of
varying sizes should be available, from a small dentist-style mirror for small
openings too much larger mirrors for larger exterior surfaces. Miniature
light sources can be attached to mirrors in order to illuminate dark areas.
Application. Mirrors can be used to observe inaccessible areas such as the
external surfaces of pipelines that are near the ground or a wall. They can
also be used to inspect the underside of a pipe that is difficult to see.
In addition, mirrors can be used to look around corners or through small
openings.
Advantages and Limitations. The advantages of mirrors include the fact
that they are simple to “operate” and easy to use. They are also inexpensive.
Their greatest limitation is the fact that, although mirrors are an effective
tool for close-up observation, their usefulness is limited to short-range
viewing.
Magnets
Application. Magnets can assist in identifying the individual material
composition of a piece of equipment by checking the magnetic properties.
Since only a few metals are easily identified by visual observation alone, a
magnet can be used to distinguish, for example, between magnetic types of
steel and nonmagnetic stainless steel and other alloys.
Advantages and Limitations. Magnets provide a simple, easy, and
inexpensive means of identifying certain types of metal. This simplicity is
also a limitation since the use of magnets as an inspection tool is limited to
this single application.
Page 59 of 111
6.0 Safety Guidelines
Basic Safety Precautions
Burn Protection
Molten metal sparks, molten slag, and welding, cutting and other
related processes produce hot metal surfaces. Serious burns can
occur if correct precautionary measures are not taken.
Appropriate footwear, clothing and eye protection should be used.
Radiation Burns
Arc welding produces ultra-violet and infrared radiation rays,
which will severely burn exposed eyes and skin. Always wear
protective clothing and eye protection to protect the skin and eyes
from radiation burns.
Electrical Hazards
Electric shock can kill. However, it can be avoided if the correct
safety precautions are practiced. Never touch live electrical
parts. The manufacturer's instructions and recommended safe
practices should be read and understood. Faulty installation,
improper grounding and incorrect operation and maintenance of
electrical equipment are all sources of danger.
Page 60 of 111
PIPING
7.0 Piping
ANSI B36.10Welded and Seamless Wrought Pipe
Nominal Out
Pipe Side Sched Sched Sched Stand Sched Sched
Size Diam. 10 20 30 ard 40 60
1 1.315 - - - 0.133 0.133 -
2 2.375 - - - 0.154 0.154 -
2½ 2.875 - - - 0.203 0.203 -
3 3.5 - - - 0.216 0.216 -
3½ 4.0 - - - 0.226 0.226 -
4 4.5 - - - 0.237 0.237 -
5 5.563 - - - 0.258 0.258 -
6 6.625 - - - 0.280 0.280 -
8 8.625 - 0.250 0.277 0.322 0.322 0.406
10 10.75 - 0.250 0.307 0.375 0.365 0.500
12 12.75 - 0.250 0.330 0.375 0.406 0.562
14 14.0 0.250 0.312 0.375 0.375 0.438 0.594
16 16.0 0.250 0.312 0.375 0.375 0.500 0.656
18 18.0 0.250 0.312 0.438 0.375 0.562 0.750
20 20.0 0.250 0.375 0.500 0.375 0.594 0.812
22 22.0 0.250 0.375 0.562 0.375 - 0.875
24 24.0 0.250 0.375 - 0.375 0.688 0.969
26 26.0 0.312 0.500 0.625 0.375 - -
28 28.0 0.312 0.500 0.625 0.375 - -
30 30.0 0.312 0.500 0.625 0.375 - -
32 32.0 0.312 0.500 0.625 0.375 0.688 -
34 34.0 0.312 0.500 0.625 0.375 0.688 -
36 36.0 0.312 0.500 0.625 0.375 0.750 -
38 38.0 - - - 0.375 - -
40 40.0 - - - 0.375 - -
Page 61 of 111
ANSI B36.10Welded and seamless Wrought Pipe
Nominal Out
Pipe Side Extra Sched Sched Sched Sched XX
Size Diam. Strong 80 100 120 160 Strong
1 1.315 0.179 0.179 - - 0.250 0.358
2 2.375 0.218 0.218 - - - 0.436
2½ 2.875 0.276 0.276 - - 0.375 0.552
3 3.5 0.300 0.300 - - 0.438 0.600
3½ 4.0 0.318 0.318 - - - -
4 4.5 0.337 0.337 - 0.438 0.531 0.674
5 5.563 0.375 0.375 - 0.500 0.625 0.750
6 6.625 0.432 0.432 - 0.562 0.719 0.864
8 8.625 0.500 0.500 0.594 0.719 0.906 0.875
10 10.75 0.500 0.594 0.719 0.844 1.125 1.000
12 12.75 0.500 0.688 0.844 1.000 1.312 1.000
14 14.0 0.500 0.750 0.938 1.094 1.406 -
16 16.0 0.500 0.844 1.031 1.219 1.594 -
18 18.0 0.500 0.938 1.156 1.375 1.781 -
20 20.0 0.500 1.031 1.281 1.500 1.969 -
22 22.0 0.500 1.125 1.375 1.625 2.125 -
24 24.0 0.500 1.219 1.531 1.812 2.344 -
26 26.0 0.500 - - - - -
28 28.0 0.500 - - - - -
30 30.0 0.500 - - - - -
32 32.0 0.500 - - - - -
34 34.0 0.500 - - - - -
36 36.0 0.500 - - - - -
38 38.0 0.500 - - - - -
40 40.0 0.500 - - - - -
Page 62 of 111
Plant Piping
• Unless limited by flanges or by valves in the line, the hydrostatic strength-
test pressure shall be calculated to produce a hoop stress of 90% of the
specified minimum yield strength (SMYS), but shall not be less than the
minimum test pressure that is determined per ASME/ANSI B31.3. For new
installations, the test pressure shall be calculated based on nominal pipe wall
thickness less mill tolerance (manufacturer's minus tolerance). Strength
test pressures for existing piping shall be per ASME/ANSI B31.3, based on
the design pressure.
• Based on ASME/ANSI B31.3, Paragraph 345.4, for hydrostatic leak tests,
the hydrostatic test pressure at any point in a metallic piping system shall
be as follows:
(a) Not less than 1-1/2 times the design pressure.
(b) For design temperatures that are above the test temperature, the
minimum test pressure shall be calculated as follows, except that the value
of ST /S shall not exceed 6.5:
1.5 PS T
PT =
S
where: PT = Minimum hydrostatic test gauge pressure.
P = Internal design gage pressure.
ST = Allowable stress at test temperature.
S = Allowable stress at design temperature.
(c) If the test pressure as defined above would produce a stress in excess
of the yield strength at test temperature, the test pressure may be
reduced to the maximum pressure that will not exceed the yield strength at
test temperature.
• Pneumatic strength tests, when approved, shall be conducted per Paragraph
345.5 of ASME/ANSI B31.3. The tightness test shall be per Paragraph
345.5.4 of ASME/ANSI B31.3. Only during the tightness test shall the
piping be approached and inspected for leakage
Based on ASME/ANSI B31.3, Paragraph 345.5, for pneumatic leak tests, the
test pressure is 110% of the design pressure.
• Underground pressure piping that is in process water service and employs
non-welded girth joints (bell and spigot) shall be strength tested to 1.5
times the system design pressure prior to backfilling. The test pressure
shall be maintained for two hours while the joints are inspected for leakage.
Page 63 of 111
If for operational safety reasons the line must be back-filled, then the
joints shall remain exposed during testing, or be subjected to a 24-hour
recorded test.
• Lube and seal oil piping shall be strength tested with the service fluid. The
test pressure shall be 1.5 times the design pressure or 690 kPa (ga) (100
psig), whichever is greater.
• Low-pressure lines that are designed for less than 690 kPa (ga) (100 psig)
may be pneumatically strength tested. The pneumatic strength test shall be
the lesser of 110% of the design pressure or 125% of the normal operating
pressure, but never less than 170 kPa (ga) (25 psig). A tightness test at 21-
35 kPa (ga) (3-5 psig) shall be conducted and the piping checked for leakage
with a soap solution.
• Instrument take-off piping and sampling system piping, up to the first
block valve, shall be strength tested with the piping or equipment to which it
is connected.
• Instrument lead lines, between the first block valve and the instruments to
which they are connected, shall be subjected to the same strength test as
the piping or equipment the instruments are connected to. Elements that
may be damaged shall be disconnected.
• Piping systems in vacuum service shall be strength tested to 100 kPa (ga)
(15 psig)
Page 64 of 111
Cross-Country Pipelines
• Unless limited by flanges or valves in the line, hydrostatic strength test
pressure of newly constructed pipelines shall be calculated to produce a hoop
stress of 90% of the SMYS of the pipe material based on the nominal wall
thickness. The test pressure at the lowest point of the pipeline, including
the static head, shall not result in a hoop stress greater than the
SMYS. The strength test pressure shall be maintained for two hours.
• The strength test temperature shall not result in a combined longitudinal
stress exceeding the SMYS. The combined longitudinal stress is calculated
based on 0.7 hoop stress at the test pressure plus temperature stress plus
bending stress.
• Tightness test of newly constructed pipelines shall be conducted at 95% of
the strength test pressure immediately at the completion of the strength
test. The tightness test pressure shall be maintained long enough for the
inspector to examine all exposed joints. A 24-hour recorded tightness test
shall be applied when the pipeline is buried or covered by insulation, or is
partially buried with a total buried length of more than 300 m (1000 ft).
• Where pressure variations caused by test-water temperature changes can
occur, such as in cross-country pipelines, a sufficient number of
thermocouples shall be installed to obtain accurate pipe metal temperature
measurements that are required in order to determine the acceptance of
the pressure test. The Consulting Services Department shall be consulted
with regard to any deviations that are noted in the 24-hour pressure chart.
Page 65 of 111
P T = 1.25PD
The above was taken from the Saudi Aramco Engineering Encyclopedia
Page 66 of 111
Page 67 of 111
Plidco Split Sleeves
Plidco split sleeves are used to:
• Permanently repair small splits, holes, or ruptures which cannot be plugged
or patched readily and where downtime for draining oil from a line is
excessive.
HOT TAPS
Inspection Requirements
The engineer responsible for inspection must do the following:
• Inspect weld areas, and 50 mm (2 in.) on each side of them, using
continuous ultrasonic examination to determine minimum pipe wall thickness.
The measured thickness must be at least that calculated for the hot tap
conditions, and no less than 5 mm (0.2 in.).
• Identify laminations, cracks or any discontinuities in the area.
• Approve welding procedure.
• Inspect connection before and during installation for compliance with
specification.
Page 68 of 111
• Confirm that hydrostatic test pressure conforms to that specified.
• Witness and approve the hydrostatic test of equipment and connection.
• Confirm that the connection is opened, drained, and vented after
completing hydrostatic test.
• Inspect the removed coupon. Evaluate the extent of header internal
corrosion and verify wall thickness.
Testing Requirements
The engineer responsible for testing must apply the following test
requirements:
• The hot-tap machine must be periodically pressure tested based on GI
441.010 requirements.
• The hot-tap valve shall be pressure tested prior to installation.
• Pressure test the branch-to-pipe weld, and then pressure test the final
branch assembly.
• The reinforcing pad of a welded branch shall be tested with air at 173 kPa
(25 psig) through a tapped vent hole.
• The pressure for the test of the hot-tap connection shall be 1.5 times the
system design pressure (1.25 times for cross-country pipelines), however,
not to exceed the following: - The design hydrostatic test pressure of the
pipe or vessel being hot tapped, or - The minimum pressure in the pipe or
vessel being hot tapped, while the test is in progress, plus a calculated
differential pressure. The differential pressure shall be 1.25
times the allowable external pressure calculated per the ASME Code
Section VIII Division 1. The length, L, that is used in this calculation shall be
the total length of a split tee, or the inside diameter of the welded nozzle,
based on the actual design detail used.
• The test pressure of the hot-tap connection may be lower than the original
hydrostatic test pressure. This is acceptable since the purpose of the test
is to provide some assurance of the integrity of the connection weld, not a
proof test of the weld. The system being tapped need not be down rated if a
lower test pressure is used at a hot-tapped connection.
Page 69 of 111
Page 70 of 111
CONVERSION
FACTORS
8.0 Conversion Factors
FRACTION OF INCH DECIMAL INCHES MILLIMETERS
1/64 0.016 0.397
1/32 0.031 0.794
3/64 0.047 1.191
1/16 0.063 1.587
5/64 0.078 1.984
3/32 0.094 2.381
7/64 0.109 2.778
1/8 0.125 3.175
9/64 0.141 3.572
5/32 0.156 3.969
11/64 0.172 4.366
3/16 0.188 4.762
13/64 0.203 5.159
7/32 0.219 5.556
15/64 0.234 5.953
1/4 0.250 6.350
17/64 0.266 6.747
9/32 0.281 7.144
19/64 0.297 7.540
5/16 0.313 7.937
21/64 0.328 8.334
11/32 0.344 8.731
23/64 0.359 9.128
3/8 0.375 9.525
25/64 0.391 9.922
13/32 0.406 10.319
27/64 0.422 10.715
7/16 0.438 11.112
29/64 0.453 11.509
15/32 0.469 11.906
31/64 0.484 12.303
1/2 0.500 12.700
Page 71 of 111
33/63 0.516 13.097
17/32 0.531 13.494
35/64 0.547 13.890
9/16 0.563 14.287
37/64 0.578 14.684
19/32 0.594 15.081
39/64 0.609 15.478
5/8 0.625 15.875
41/64 0.641 16.272
21/32 0.656 16.668
43/64 0.672 17.065
11/16 0.688 17.462
45/64 0.703 17.859
23/32 0.719 18.256
47/64 0.734 18.653
3/4 0.750 19.050
49/64 0.766 19.447
25/32 0.781 19.843
51/64 0.797 20.240
13/16 0.813 20.637
53/64 0.828 21.034
27/32 0.844 21.431
55/64 0.859 21.828
7/8 0.875 22.225
57/64 0.891 22.621
29/32 0.906 23.018
59/64 0.922 23.415
15/16 0.938 23.812
61/64 0.953 24.209
31/32 0.969 24.606
63/64 0.984 25.003
1 1.000 25.400
Page 72 of 111
ENGLISH TO METRIC
TO CHANGE TO MULTIPLY BY
Inches Millimeters 25.4
Inches Centimeters 2.54
Inches Meters 0.0254
Feet Meters 0.3048
Miles Kilometers 1.609347
Square Inches Square Centimeters 6.452
Square Feet Square Meters 0.0929
Cubic Inches Cubic Centimeters 16.3872
U.S. Gallons Liters 3.7854
Pounds Kilograms .45359
Ounce Avoir Grams 28.3495
BTU Calories 252
METRIC TO ENGLISH
TO CHANGE TO MULTIPLY BY
Millimeters Inches .03937
Centimeters Inches .39371
Meters Inches 39.371
Meters Feet 3.281
Kilometers Miles .62137
Square Centimeters Square Inches .1550
Square Meters Square Feet 10.7649
Cubic Centimeters Cubic Inches .061
Cubic Meters Cubic Feet 35.314
Liters U.S. Gallon .26417
Kilograms Pounds 2.20462
Grams Ounces Avoir .03527
Calories BTU .003968
Page 73 of 111
MEASURE
TO CHANGE TO MULTIPLY BY
Cubic Feet Cubic Inches 1728
Cubic Inches Cubic Feet .00058
Cubic Feet Gallons 7.480
Gallons Cubic Feet .1337
Cubic Inches Gallons .00433
Gallons Cubic Inches 231
Barrels Gallons 42
Gallons Barrels .0238
Imperial Gallons U.S. Gallons 1.2009
U.S Gallons Imperial Gallons .8326
Square Feet Square Inches 144
Square Inches Square Feet .00695
Long Tons Pounds 2240
Short Tons Pounds 2000
Long Tons Short Tons 1.12
PRESSURE
TO CHANGE TO MULTIPLY BY
Pounds per Square Inch Pascals 6.895 x 103
Pounds per Square Inch Kilograms per Square CM 7.03 x 10-2
Pascals Pounds per Square Inch 1.45 x 10-4
Kilograms per Square CM Pounds per Square Inch 1.422 x 101
TEMPERATURE
TO CHANGE TO MULTIPLY BY
Centigrade Kelvin 1.0 + 273
Centigrade Fahrenheit 1.8 + 17.78
Fahrenheit Centigrade -32 x 0.555
Fahrenheit Kelvin -32 x 0.555 + 273.15
Page 74 of 111
8.0
b
Area = ab
9.0
h
bh
Area =
b 2
Area = πab
a b
(
Circ. = π 2 a 2 + b 2 )
a = 2.598a 2
Circ. = 2πr
r
or
d Circ. = πd
Area = πr 2
Page 75 of 111
c
Total Surface Area (S)
S = 2πr (r + h )
d
Volume
V = πr 2 h
h r or
c 2h
V=
4π
Page 76 of 111
INSPECTION
TERMINOLOGY
9.0 Inspection Terminology
GLOSSARY (Saudi Aramco Eng Encyclopedia)
back reflection The ultrasonic signal received from the back surface of a
test object.
Page 77 of 111
cold crack A flaw that appears as a straight line, usually continuous
throughout its length, and generally singly. These cracks start at the
surface.
couplant A substance used between an ultrasonic transducer face and the
test surface to permit or improve transmission or reception.
crack A material separation that has a relatively large cross-section in one
direction and a small or negligible cross-section when viewed in a direction
perpendicular to the first.
defect A discontinuity whose size, shape, orientation, location, or properties
make it detrimental to the useful service of the part in which it occurs, or
which exceeds the accept/reject criteria of the particular design.
developer A finely divided material applied over the surface of a part to
help bring out penetrant indications.
discontinuity Any interruption in the normal physical structure or
configuration of a part such as cracks, laps, seams, inclusions, or porosity. A
discontinuity may or may not affect the usefulness of the part.
dry powder Finely divided ferromagnetic particles selected and prepared
for magnetic particle inspection by the dry method.
examination Applies to quality control functions performed by the
manufacturer, fabricator, or erector.
false indication An indication that may be interpreted incorrectly as a
discontinuity or a defect; a non-relevant indication.
filled crack A crack open to the surface but filled with some foreign
material, such as oxide, grease, etc.
flaw An imperfection, which may not be harmful. If harmful, it is a defect
or discontinuity.
flux lines Imaginary lines used to explain the behavior of magnetic fields.
fusion The complete joining of two parts in such a manner that loads are
effectively transferred across their common boundary.
hot crack A flaw that appears as a ragged dark line of variable width and
numerous branches. It has no continuity, may exist in groups, and may
originate internally or at the surface.
hot tear A fracture formed in a metal during solidification.
indication An response that requires interpretation to determine its
significance.
Page 78 of 111
inspection The process of examining and checking materials and parts for
possible defects, or deviation from acceptance standards.
interpretation The process of determining the nature of an indication.
magnet A material having the power to attract iron and other substances to
itself and exhibit polarity.
magnetic flux The total number of magnetic lines existing in a magnetic
circuit.
Magnetic discontinuity A break in the magnetic continuity of a part,
possibly caused by a defect.
Nondestructive examination Testing to detect internal, surface, or
concealed defects or flaws in a material using techniques that do not damage
the item being tested.
Non-relevant indications These are true indications produced by
uncontrolled or incorrect test conditions. They have no relation to
discontinuities that might be defects.
normal fluid service As defined in ASME/ANSI B31.3, a fluid service
pertaining to most piping covered by this Code, i.e., not subject to the rules
for Category D, Category M, or High-Pressure Fluid Service, and not subject
to severe cyclic conditions.
pores Small voids in the body of a metal.
porosity charts Standard charts for comparing porosity size, spacing, and
number in a given area.
pressure-containing weld A weld that joins two pressure-containing
components such as at a branch connection.
prods Two hand-held electrodes, which are pressed against the surface of a
part to make contact for passing magnetizing current through the metal.
radiography The use of radiant energy in the form of neutrons, x-rays or
gamma rays for NDE of opaque objects. It produces graphical records on
sensitized films, which indicate the comparative soundness of the object
being tested.
Reference radiographs A group of radiographs containing images of
discontinuities. They are used as comparison standards for material
acceptability.
severe cyclic conditions As defined in ASME/ANSI B31.3, those in which
SE, computed in accordance with Paragraph 319.4.4, exceeds 0.8SA (as
defined in Paragraph 302.3.5), and the equivalent number of cycles (N in
Page 79 of 111
paragraph 302.3.5) exceeds 7000; or other conditions which the designer
determines will produce an equivalent effect.
suspension The liquid bath in which ferromagnetic particles used in the wet
method are suspended.
Page 80 of 111
PRESSURE VESSELS
10.0 Vessels
PRESSURE VESSELS
Retirement Thickness:
It is advisable to use the safety instruction sheet (SIS) of the vessel
to determine the retirement thickness, as in most cases the calculation
may be complex.
Therefore, prior to a pressure vessel inspection, the inspector should
obtain a copy of the SIS for the equipment.
Thickness of Shell Under Internal
Pressure:
Cylindrical
Shell:
(1) t= PR P= SEt
SE - 0.6P R + 0.6t
or
(2) t= PR 2SEt
2SE + 0.4P R – 0.4t
or
Spherical
Shell:
(3) t= PR P= 2SEt
or
2SE – 0.2P R – 0.2t
Page 81 of 111
Conditions for (1) above:
T Does not exceed ½ R or P does not exceed 0.385
SE
Thicknesses of shells under external pressure see ASME Sec. VIII Para.
UG-28)
(For conditions exceeding the above limits, see ASME sec. VIII
Div.1Appendix –1)
Thickness of Formed Heads Under Internal Pressure (Pressure on Concave Side)
Refer to the following figure for the typical types of heads and their dimensions
t
D
t
h L
r L
D D t
D
L
D
r
α
t
t D1
α
t
(d) Conical
(e) Toriconical
(Cone Head With Knuckle)
Page 82 of 111
(1)
Ellipsodial Heads
PD 2SEt
t= or
2SE - 0.2P R + 0.2t
Torispherical
(2)
0.885PL SEt
t= or
PL 2SEt
t= or
2SE - 0.2P L + 0.2t
Conical
(4)
PD 2Set α
t= or
2 cos α (SE- 0.6P) D + 1.2t cos α
Toriconical
(5)
t for the conical section – use formula (4) above using Di in place of
D
Di = D – 2r (1 – cos α)
Page 83 of 111
Conditions For the Above Formulae:
For (1) Half the minor axis = 1/4 of the ID of the head
above: skirt
Note: Approximate values of knuckle radius and spherical
radius of a 2.1 ellipsoidal head are 0.17D and 0.90D,
respectively.
Page 84 of 111
Thickness of Heads Under External Pressure (Pressure on Convex Side)
Page 85 of 111
FITTINGS
11.0 Fittings
Page 86 of 111
Y Y Y
O O O
Page 87 of 111
Q
O 1/
16
"
Blind Flanges
150 LB. 300 LB. 400 LB. 600 LB.
Nom Outside Outside Outside Outside
Pipe Diam Of Thick Diam Of Thick Diam Of Thick Diam Of Thick
Size Flange ness Flange ness Flange ness Flange ness
O Q (1) O Q (1) O Q (2) O Q (2)
1
/2 3 1 /2 7
/16 3 3 /4 9
/16 3 3 /4 9
/16
3
/4 3 7 /8 1
/2 4 5 /8 5
/8 For 4 5 /8 5
/8
1 4 1 /4 9
/16 4 7 /8 11
/16 Sizes 4 7 /8 11
/16
1 1 /4 5
4 /8 5
/8 1
5 /4 3
/4 3 1 /2 1
5 /4 13
/16
1 1 /2 5 11
/16 6 1 /8 13
/16 and 6 1 /8 7
/8
smaller
2 6 3
/4 6 1 /2 7
/8 use 6 1 /2 1
2 1 /2 7 7
/8 7 1 /2 1 600 Lb. 7 1 /2 1 1 /8
3 7 1 /2 15
/16 8 1 /4 1 1 /8 standard 8 1 /4 1 1 /4
3 1 /2 8 1 /2 15
/16 9 1 3/16 9 1 3 /8
15
4 9 /16 10 1 1 /4 10 3/4 1 1 /2
10 1 3 /8
15
5 10 /16 11 1 3 /8 11 1 1 /2 13 1 3 /4
6 11 1 12 1/2 1 7/16 12 1/2 1 5 /8 14 1 7 /8
8 13 1/2 1 1 /8 15 1 5 /8 15 1 7 /8 16 1/2 2 3/16
10 16 1 3/16 17 1/2 1 7 /8 17 1/2 2 1 /8 20 2 1 /2
12 19 1/2 1 1 /4 20 1/2 2 20 1/2 2 7 /8 22 2 5 /8
14 21 1 3 /8 23 2 1 /8 23 2 3 /8 23 3/4 2 3 /4
16 23 1/2 1 7/16 25 1/2 2 1 /4 25 1/2 2 1 /2 27 3
18 25 1 9/16 28 2 3 /8 28 2 5 /8 29 1/4 3 1 /4
20 27 1/2 1 11/16 30 1/2 2 1 /2 30 1/2 2 3 /4 32 3 1 /2
22 29 1/2 1 13/16 33 2 5 /8 33 2 7 /8 34 1/4 3 3 /4
24 32 1 7 /8 36 2 3 /4 36 3 36 4
26 34 1/4 2 38 1/4 3 1 /8 38 1/4 3 1 /2 40 4 1 /4
30 38 3/4 2 1 /8 43 3 5 /8 43 4 44 1/2 4 1 /2
34 43 3/4 2 5/16 47 1/2 4 47 1/2 4 3 /8 49 4 3 /4
36 46 2 3 /8 50 4 1 /8 50 4 1 /2 51 3/4 4 7 /8
42 53 2 5 /8 57 4 5 /8 57 5 1 /8 58 3/4 5 1 /2
Page 88 of 111
SAES-L-009 also lists standard Saudi Aramco drawings that provide
mandatory dimensional standards for specific size ranges, ratings, flange
types, and facings.
where:
WN = Weld neck.
RF = Raised face.
RJ = Ring joint.
Lap = Lapped flange.
Blind = Blind flange.
Page 89 of 111
CODES
&
STANDARDS
12.0 Codes & Standards
Typical construction codes in use internationally are:
• American Society of Mechanical Engineers Boiler and Pressure Vessel
Code (ASME-BPVC).
• American Petroleum Institute (API 650- Storage Tanks)
• British Standards (BS5500 Pressure Vessels)
• AD-Merkblatt (German Pressure Vessel Code)
• TRD (German Boiler Code, normally read in conjunction with VGB
Directives).
• CODAP (France)
• Stoomwezen (Netherlands)
• ASME 31.1- Boiler Piping Code
• ASME 31.3 – Chemical Piping
• ASME 31.4- Gas transportation piping
• ASME 31.8- Liquid Hydrocarbon transportation piping.
The European codes are currently under review and the following product
standards will eventually supercede the existing National Standards:
• CEN/TC54 Unfired Pressure Vessels
• CEN/TC267 Industrial Piping
• CEN/TC269 Boilers.
Typical codes and standards that address pressure equipment that has seen
service are:
Page 91 of 111
SAES-E-007 Design Criteria of Air Cooled Heat Exchangers
SAES-E-014 Design Criteria of Plate and Frame Heat Exchangers
SAES-E-015 Design Criteria of Electric Heat Exchangers
SAES-F-001 Design Criteria of Fired Heaters
SAES-F-007 Design Criteria of Flares
SAES-H-001 Selection Requirements for Industrial Coatings
SAES-H-002 Internal and External Coatings for Steel Pipelines and Piping
SAES-H- Approved Saudi Aramco Data Sheets
002V
SAES-H-101 Approved Protective Coating Systems
SAES-H-101V Approved Saudi Aramco Data Sheets- Paints and Coatings
SAES-H-200 Storage, Handling and Installation of Pipe Externally Coated with
Fusion Bonded Epoxy or Polyethylene
SAES-H-201 General Specification for Over-The-Ditch External FBE
Coating of Field Girth Welds
SAES-H-203 Hand Applied Tape-Wrapping of Buried Pipe
SAES-H-204 General Specification for Applying Heat-Shrink Sleeves to
Coated Pipe
SAES-H- Approved Vendor Installation Procedures for Heat-Shrink Sleeves
204V
SAES-L-001 Basic Criteria for Piping Systems
SAES-L-002 Design Conditions for Pressure Piping
SAES-L-003 Design Stress Criteria for Pressure Piping
SAES-L-004 Pressure Design of Piping Components
SAES-L-005 Piping Material Specifications
SAES-L-006 Metallic Pipe Selection
SAES-L-007 Selection of Metallic Pipe Fittings
SAES-L-008 Selection of Valves
SAES-L-009 Metallic Flanges, Gaskets and Bolts for Low and Intermediate
Temperature Service
SAES-L-010 Limitations on Piping Joints
SAES-L-011 Flexibility, Support and Anchoring of Piping
SAES-L-012 Design of Piping Systems inside Plant Areas
SAES-L-022 Design of Wellhead Piping, Flowlines, Trunklines and Testlines
SAES-L-032 Material Selection of Piping Systems
SAES-L-033 Corrosion Protection Requirements for Pipelines/ Piping
SAES-L-041 Utility Piping Connections to Process Equipment
Page 92 of 111
SAES-L-042 Plant Utility Stations
SAES-L-043 Thermal Expansion Relief in Piping
SAES-L-044 Anchors for Cross-Country Pipelines
SAES-L-045 Scraper Trap Station Piping and Apparatus
SAES-L-046 Pipeline Crossings Under Roads and Railroads
SAES-L-047 Valve Boxes
SAES-L-050 Construction Requirements for Metallic Plant Piping
SAES-L-051 Construction Requirements for Cross-Country Pipelines
SAES-L-052 Hot Tap Connections
SAES-L-056 Pressure Testing of Plant Piping and Pipelines
SAES-L-060 Nonmetallic Piping
SAES-L-062 Technically Acceptable Class 04 Valve Manufacturers
SAES-L-070 Technically Acceptable Manufacturers of API 6A 10000 PSI
Gate Valves and Chokes
SAES-N-100 Refractory Systems
SAES-N-110 Installation Requirements- Castable Refractories
SAES-W-010 Welding Requirements for Pressure Vessels
SAES-W-011 Welding Requirements for On-Plot Piping
SAES-W-012 Welding Requirements for Pipelines
SAES-W-014 Weld Overlays and Welding of Clad Materials
SAES-W-015 Strip Lining Application
SAES-W-016 Welding of Corrosion Resistant Materials
SAES-W-017 Welding Requirements for API Tanks
SAES-X -400 Cathodic Protection of Buried Pipelines
SAES-X -500 Cathodic Protection of Vessel and Tank Internals
SAES-X -600 Cathodic Protection of Plant Facilities
SAES-X -700 Cathodic Protection of Onshore Well Casings
Page 93 of 111
SAEP- 315 Installation of Stopple Fittings
SAEP- 316 Performance Qualification of Coating Personnel
SAEP- 317 Testing and Inspection (T & I) of Shell & Tube Heat Exchangers
SAEP- 318 Pressure Relief Valve Program Authorization for
Installation, Deletion and Changes
SAEP- 319 Pressure Relief Valves- Routine Test, Inspection,
Quality Assurance and Regulation
SAEP- 321 Performance Qualification Testing and Certification of
Saudi Aramco Welders
SAEP- 323 Performance Qualification Testing of Contract
Welders and Brazing
SAEP- 324 Certification Review and Registration of Project Welders and
Brazers
SAEP- 325 Inspection Requirements for Pressurized Equipment
SAEP- 1131 Pressure Relief Valve Program Use of Form 3099A,
RV Authorization
SAEP- 1132 Instructions for Using the Relief Valve Stand
SAEP- 1133 Form 3750, Pressuring Relieving Device Valve Test Stand
SAEP- 1135 On-Stream Inspection Administration
SAEP- 1140 Qualification and Certification of Saudi Aramco NDT Personnel
SAEP- 1141 Industrial Radiation Safety
SAEP- 1142 Qualification of Saudi Aramco NDT Personnel
SAEP- 1143 Radiographic Examination
SAEP- 1144 Magnetic Particle Examination
SAEP- 1145 Liquid Penetrant Examination
SAEP- 1150 Inspection Coverage on Projects
Page 94 of 111
NGL PIPELINE DEPT.
B31.8( 1)
WELLHEAD PIPING
SSD Fence
B31.4( 2) B31.4( 3)
B31.8(1)(4)(5) DF=0.72 DF=0.5 ON-PLOT
OFF-PLOT
DF=0.5(2)
ZV SWD WELL
B31.3(1) Water
RECEIVER
LAUNCHER
B31.3(1)
B31.4( 2)
FLARE STACK
zv
B31.3( 1) Flare Gas
B31.3(1)(5) B31.4(1)
Gas
zv
Oil PIPELINE DEPT.
Condensate ZV PROD. HDR.
B31.3
B31.4, GAS Wasia Well
DF=0.5 B31.3(5)
WATER+GAS
B31.3(1)
B31.8(2) B31.3
DF=0.5
FLOWLINE
ON-PLOT
OFF-PLOT(1)
B31.8(3)
DF=0.72(2)
FLOWLINE
WELLHEAD PIPING
Page 95 of 111
Page 96 of 111
Page 97 of 111
SUPPORTS
13.0 Supports
• Tanks
• Vessels
• Piping
Page 98 of 111
Table 1
SHOE SADDLE
BASE ADJUSTABLE
DUMMY SUPPORT TRUNNION
SUPPORT
RESTRAINTS/GUIDES
LOAD AND
DEFLECTION
SCALE
LARGE CHANGE
IN EFFECTIVE
LEVER ARM CONSTANT LOAD SUPPORT
RELATIVE
CONSTANT LOAD
ANCHOR ANCHOR
BEARING SURFACE
BEARING
SURFACE
TYPICAL THRUST BLOCK FOR 90 TYPICAL THRUST BLOCK FOR 45 TYPICAL THRUST BLOCK FOR
DEGREE BEND OR ELBOW DEGREE BEND OR ELBOW TEE CONNECTION
BEARING
SURFACE
Common abbreviations used for NDT methods are P.T (Penetrant Testing),
The listed SAEP’s outline how the particular method is to be applied within
Saudi Aramco and outlines all necessary steps to perform the test and
report the test result. Table 1 outlines the Acceptance Criteria for the
applicable SAEP’s and the Saudi Aramco form to be used. Figure 5 provides
guidance on how to interpret and evaluate radiographs.
Log No. B.I. No. J.O. No. Plant No. Plant Name Contractor
Technician Level Code / Acceptance Criteria Material Type Material Form Sch. / Thickness
Liquid Penetrant System: Penetrant Mfg Penetrant Batch No. Penetrant P/N Remover P/N. Developer P/N.
A-1____A-2____A-3____
B-1____B-2____B-3____
Surface Temperature White Light Intensity UV Light Intensity UV Light Model No. UV Meter Material Form
Model No.
Surface Condition / Part Description
Item Drawing No. Equipment P/N Weld Welder Exam Results REPAIR DEFECT
No. Line Reference. No. Symbol LOCATION TYPE & SIZE
ACC REJ
NOTES:
S C A L E JO or BI Number?
Component, Vessel or Piping Identification?
SAEP-1143 Seam or Weld Identification?
RADIOGRAPHIC R1 for Repair (if applicable)?
EXAMINATION
C O D E
Cutouts NW1 (if applicable)?
(30-SEP-98) Date of Radiography?
Weld Thickness?
Pipe Diameter and Thickness?
C O R R O S I O N
Material Type?
Maps of Location Markers (if applicable)?
SAEP-1141 DEALING WITH THE CORRECT RADIOGRAPH? Film Brand and Designation?
INDUSTRIAL No of Films per Cassette?
RADIATION
RT REPORT ACCOMPANIES RADIOGRAPH?
FORM 4719-A-ENG (9/98) USED? Single or Double Wall Exposure?
SAFETY Single of Double Wall Viewing?
No of Exposures?
Isotope used or Max X-Ray voltage used?
VIEWING FACILITIES ACCEPTABLE? Effective Focal Spot Sizes
SUBDUED BACKGROUND LIGHTING? Minimum Source to Film Distance?
RADIOGRAPHIC VIEWER WITH SUFFICIENT LIGHT Welder Symbol?
OUTPUT VIA VARIABLE LIGHT SOURCE? (ISO 5580-85)
NO INTERFERING LIGHT FROM OUTER EDGES OF Defect Types?
FILM? Acc/Rej?
CALIBRATED DENSITOMETERS AS PER ASTM SE- Technician Name, Badge # & Signature?
1079?
DENSITOMETER CHECKED AGAINST CALIBRATED Technician Certified and to Level ?
DENSITY STRIP PRIOR TO USE? RTFI Name, Badge #, Signature, Certified &
Level?
REPORTING
saoo.aramco.com.sa - /data/saccid/saccid
forms/GenlInsp/
[To Parent Directory]