Department of The Interior and Local Government Bottom-Up Budgeting Detailed Project Proposal
Department of The Interior and Local Government Bottom-Up Budgeting Detailed Project Proposal
Bottom-up Budgeting
I. BASIC INFORMATION
and
Banawang
Municipality of Bato, Catanduanes
The area for the construction and rehabilitation of drainage systems are the
Poblacion Barangays of the municipality – the Barangays of Libod Poblacion, Ilawod
Poblacion and Banawang.
The completion of the project will redound to the realization of a well-planned and
aptly functional network of drainage systems in the Poblacion area. It shall reduce
the risk of infestation of diseases such as malaria and dengue caused by stagnant
and grimy canals. The resulting favorable conditions of drainage systems will
encourage the growth of entrepreneurial activities in the Poblacion Barangay,
considering further the finished construction of the Bato Public Market.
1
The Project is expected to further boost the living situation of the residents of the
Poblacion Barangays. As such, along with other priority poverty alleviation projects of
the Municipal Government and other National Government Agencies, poverty
incidence in each Poblacion barangay is expected to reduce by 40% by the end of
2017 – from 43.85% to 26.15% (57 to 34 HHs) in Barangay Banawang, 25.11% to 15.25%
(56 to 34 HHs) in Libod Poblacion, and 22.73% to 13.64% (45 to 27 HHs) in Barangay
Ilawod Poblacion.
2. Project objective
In line with the National Government’s thrusts and the LGU’s goal of poverty
reduction through more improved infrastructure, the main objective of the project is
to create a more conducive and business-friendly environment within the Poblacion
area, thus, encourage the growth of entrepreneurial activities that will help reduce
the rate of poverty incidence.
3. Expected Output
810 linear meter line open canal and 150 linear meter covered canal within the
target barangays.
5. Target Beneficiaries
The beneficiaries of the project are the whole residents of Barangays Libod Poblacion
consisting of 1016 individuals in 223 households, Ilawod Poblacion with 851 individuals
in 198 households and Banawang with 584 individuals in 130 households (September
2014 CBMS Survey). The rest of the barangays in the municipality are indirect
recipients of the Project since they will also benefit from the resulting growth of
business activity in the Poblacion area.
6. Project Partners
The administration of the Project will be a joint undertaking of the Department of the
Interior and Local Government, the Municipal Government of Bato and the
Barangays of Libod Poblacion, Ilawod Poblacion and Banawang. In the barangay
level, the direct partner during the construction phase is the Barangay Council. They
shall assist in ensuring the safety in traffic and disposal of waste material. Municipal
Government shall facilitate all necessary undertakings to assure the sound
implementation of the Project.
Financial Requirements
Project Component / Physica Cost per
Beneficiar
Particular l Target Item LGU-Bato DILG Total
y Equity
A. Pre-Implementation Phase
1. Conduct of Drainage 6,000.00 9,000.00 15,000.00
Assessment and
community consultation
2. Preparation and 2,000.00 2,000.00 2,000.00
submission of Project
Proposal, Program of
Work and Detailed
Engineering
Design
3. Approval and submission
of SB Resolution
approving the list of
Poverty Reduction
Projects and authorizing
the LCE to enter into MOA
regarding
Project implementation
4. Preparation, submission 2,000.00 2,000.00 2,000.00
and approval of other
necessary materials
5. MOA signing and transfer 5,000.00 5,000.00 5,000.00
of fund
Sub-Total 6,000.00 18,000.00 24,000.00
B. Implementation Phase
1. Procurement and Delivery 4,000.00 2,000.00
of Supplies and Materials
2. Concrete breaking, 810 l.m 15,000.00 30,000.00 2,400,000.00 2,445,000.00
excavation and masonry line (in-kind:
works open labor)
canal
and
150 l.m
covere
d canal
3. Liquidation of Expenses 500.00 500.00 500.00
through preparation and
submission of Statement of
Expenditures (SOE) and
Receipt of Disbursement
Subtotal 15,000.00 34,500.00 2,400,000.00 2,449,500.00
C. Project Monitoring /
Post Implementation
Phase
1. Project Monitoring 10,000.00 10,000.00 10,000.00
Sub-Total 10,000.00 10,000.00
TOTAL PROJECT COST 21,000.00 62,500.00 2,400,000.00 2,483,500.00
Project Share (%) 0.85% 2.52% 96.64%
IV. Project Management
V. Project Sustainability
Once completed, the project shall be turned over to Barangays of Libod Poblacion,
Ilawod Poblacion and Banawang through the Barangay Council. For the
sustainability of the project, the Municipal Local Government Unit thru the Municipal
Engineering Office shall ensure that Detailed Engineering Design and Specifications
are carefully followed during the construction phase. Maintenance of project after
completion will be shouldered by the municipal government through its Economic
Development Fund.