Activity 14
Given the activities of a project, their time estimates, and their immediate predecessors shown below:
A
B
C A
D B
E C
F C
G D, E
H F, G
The earliest project completion time is 15 months after the project has been started.
Start 2 4 6 8 10 12 14 16 18 20
A
B
C A
D B
E C
F C
G D, E
H F, G
Start 2 4 6 8 10 12 14 16 18 20
A
B
C A
D B
E C
F C
G D, E
H F, G
8. What’s the maximum amount of time that each of the activities can be delayed without delaying the whole
project?
A 0
B 1
C 0
D 1
E 0
F 6
G 0
H 0