100% found this document useful (1 vote)
501 views2 pages

Activity 14: Start 2 4 6 8 10 12 14 16 18 20 A B C D E F G H

The document describes a project with 8 activities (A-H) and their time estimates and predecessors. It provides the Gantt chart showing the earliest start and finish times of each activity. The earliest project completion time is 15 months. Activities A, C, E, and G cannot be delayed without delaying the whole project. Activity B can be delayed by 1 month, D by 1 month, and F by 6 months without delaying the whole project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
501 views2 pages

Activity 14: Start 2 4 6 8 10 12 14 16 18 20 A B C D E F G H

The document describes a project with 8 activities (A-H) and their time estimates and predecessors. It provides the Gantt chart showing the earliest start and finish times of each activity. The earliest project completion time is 15 months. Activities A, C, E, and G cannot be delayed without delaying the whole project. Activity B can be delayed by 1 month, D by 1 month, and F by 6 months without delaying the whole project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

SIMBALA, Andi Te’a Mari O.

ID Number: 2204965

Production and Operations Management (1498) BS Accountancy 2

Activity 14
Given the activities of a project, their time estimates, and their immediate predecessors shown below:

Activities Activity Times, months Immediate Predecessors


A 2 -
B 3 -
C 2 A
D 4 B
E 4 C
F 3 C
G 5 D, E
H 2 F, G

1. Draw the Gannt chart for this project.

2. Months after start


Start 2 4 6 8 10 12 14 16 18 20

A
B

C A

D B

E C

F C

G D, E
H F, G

3. What’s the earliest expected time to finish the project?

The earliest project completion time is 15 months after the project has been started.

4. Which activities should not be delayed?

5. Months after start

Start 2 4 6 8 10 12 14 16 18 20

A
B

C A

D B
E C

F C

G D, E
H F, G

6. Which activities can be delayed?

7. Months after start

Start 2 4 6 8 10 12 14 16 18 20

A
B

C A

D B

E C

F C

G D, E
H F, G

8. What’s the maximum amount of time that each of the activities can be delayed without delaying the whole
project?

A 0
B 1
C 0
D 1
E 0
F 6
G 0
H 0

You might also like