0% found this document useful (1 vote)
217 views11 pages

Danem Engineering Works - WLL.: Quality Control & Inspection Test Plan

This document outlines a quality control and inspection test plan for the fabrication of a stainless steel tank. It details various quality control activities including engineering data verification, material inspection, welding procedures, electrode handling, shop fabrication, and bottom plate assembly. Acceptance criteria and responsible parties are defined for inspection of characteristics such as dimensions, welding, non-destructive testing, and more. The goal is to ensure fabrication meets specifications in drawings, material standards, and codes like API 650.

Uploaded by

Rejoy baby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
217 views11 pages

Danem Engineering Works - WLL.: Quality Control & Inspection Test Plan

This document outlines a quality control and inspection test plan for the fabrication of a stainless steel tank. It details various quality control activities including engineering data verification, material inspection, welding procedures, electrode handling, shop fabrication, and bottom plate assembly. Acceptance criteria and responsible parties are defined for inspection of characteristics such as dimensions, welding, non-destructive testing, and more. The goal is to ensure fabrication meets specifications in drawings, material standards, and codes like API 650.

Uploaded by

Rejoy baby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 11

DANEM ENGINEERING WORKS.WLL.

QUALITY CONTROL & INSPECTION TEST PLAN


CONTRACT NO: DOC # Rev-0 Date:

SCOPE OF WORK: FABRICATION OF SS TANK


Inspection
SL. Charecteristic to be Acceptance Criteria
NO Quality Control Activity verified /Control Documents Verifying Documents Responsible person
DEW TPI QP

1 Engineering

Approved Letter API 650/ QP Work Order API 650/QP


Scope of Work Specification
1.1 Engineering Data verification
Technical Data Drawings
Specification/Approved Specification/Approved Project Manager H R H
Drawings Drawings

2 Material

Material requisition
Material Receiving
Storage Colour coding
(/Specially located area Drawing /API 650 /Material Material
2.1 Purchase Plate/ Pipe- Purchace Officer H R R
Green/Fittings- Request requisition/Delivery Note
Yellow/Bolt & Nuts-
Yellow/Consumable-
White)

Scope/ Delivery Drawings/Scope/Plate:AST


M A240M
note/Material Test -Gr316L/Pipe:ASTM A312 Store Keeper
2.2 Inspection certificate/Drawing/ TP316L/Flange:ASTM A182 Material Inspection report /QA/QCInspector H H R
Dimension/Quantity/Col
our coding F316L/Bolt bolt:ASTM
A193/GrB7/A194Gr2H

3 Welding

1 of 11
Welding Procedure
3.1 Qualification (WPS)
Variables as per Approved
Procedure Qualification Drawing/API- 650 / ASME Drawings/
Section IX
API 650 / ASME WPS/PQR/Welder QA/QC Engineer H H H
3.2 Record ( PQR) Section IX certificates

Welder Performance
3.3
Qualification ( WPQ)

4 Electrode Handling

DE-WCC-01 DE-WCC-01 (Consumable


Storage/Baking/Holding/Issui
4.1 (Consumable Control Control Procedure) Batch Certificate Store Keeper/ QA/QC H S S
ng
Procedure) Mfrs.Reccomentation

5 Shop Fabrication

5.1 Bottom Plate Marking/Cutting


End Preparation

5.2 Roof Plate Marking/Cutting

End Preparation
Visual/Dimensional
Forming Approved Report
Drawing/Cutting Plan Fab.Supvr.
5.3 Shell Plate Marking/Cutting Check with Aproved QA/QC H R R

End Preparation Template

Rolling
5.4 Shell/Roof Man hole Marking/Cutting
End Preparation
Rolling Approved
Fit-up,Welding Drawing/Cutting Plan Visual/Dimensional Fab.Supvr. H R R
5.4.1 Inspection Visual Report QA/QC

2 of 11
Dimensional

Distortion

5.4.2 NDT DPT on Seam welds

5.5 Nozzle Fabrication

5.5.1 Fabrication Material ASTM A312TP 316L- ASME B16.5 Fab.Supvr


(Pipe) QA/QC H R R

Marking/Cutting ASTM A182F316L- Fit-up Inspection

End Preparation (Flange) Report

Drawing/Cutting Plan &


Nozzle Schedule
Material Certificate

5.5.2 Inspection Fit-up,Welding Complaince with Visual/Dimensional


Visual WPS Report
Dimensional Nozzle Schedule DEQ-FORM-QA/QC-006 Fab.Supvr H W R
Misalignment QA/QC

Distortion
Drawing. Weld map&
5.5.3 NDT RT test on Butt welds, QA/QC
Weld history
DP Test on fillet welds AS PER API 650 SEC.6

Butt welds 100%RT-Butt joints RT Film, Inspector H H R

API 650-SEC.6.4 NDT Reports


100%DP Fillet welds
5.6 Sump fabrication
5.6.1 Fabrication Material ASTM A240M TYP 316L

WPS,Marking/Cutting Drawing,Weldmap
End Preparation Weld history Fit-up Inspection report

Fit-up,Welding Drawing/Cutting Plan /NDT Report Fab.Supvr. QA/QC H W R

5.6.2 Inspection Visual 100% Seam weld

3 of 11
Dimensional 100% Fillet weld
API650 Sec.6 NDT Reports

DPT onSeam welds/Fillet


5.6.3 NDT/Testing ASME Sec.v Art.6
welds Test Reports QA/QC Inspector H H R
Water Fill Test
5.7 Crub angle fabrication
5.7.1 Cutting/End Preparation Material

Fit-up Approved Drawings Fit-up Inspection Fab.Supvr. R R


Check Curvature Template weld/NDT Report QA/QC

5.7.2 Inspection Continues Welding WPS


Visual/ Dimension
5.7.3 NDT DPT- total Weld 100% DPT
6 Bottom plate Assembly
6.1 Bottom plate Laying Fit-up,Welding/ Approved Drawings
Dimension Cutting Plan ,Orientation
6.2 Inspection Fit-up,Tacking WPS Fit-up Inspection
Misalignment Proj.Doc:API650/ weld/NDT Report
Distortion H H R
Visual
(Floor flatness tolerence
Dimensional shall be 15mm in any one Test Reports
meter)

6.3 NDT 10% RT onButt Weld API 650 Sec.6 Test Reports H W R
100% DPT total Weld API 650 Sec6.6
6.4 Testing Vaccum box Test Procedure Inspector

7 Shell Course Assembly

7.1 Shell Course 1st Lay-out


Vertical joint Fit-up
7.1.1 Inspection Fit-up,Tacking
Root-Gap
Misalignment Approved Drawings

4 of 11
Approved wps Fit-up Inspection Fab.Supvr. H W R
Check Curvature Template weld/NDT Report QA/QC

Plumpness 1.5mm /M/ of height Inspector


7.1.2 Vertical welding Check Curvature
Distortion
Plumpness
During Welding
7.1.3 Back Gouge /Weld Back Grinding and 100% DPTafter QA/QC H S R
DP Testing Back Gouging Inspector

7.2 Shell Course 2nd Vertical joint Fit-up

Horizontal joint fit-up

7.2.1 Inspection Fit-up,Tacking Approved Drawings Fit-up Inspection/ Fab.Supvr. H S R

Root-Gap Template 5 mm Plate NDT Report QA/QC

Misalignment

7.2.2 Vertical Weld Back Grinding and


DP Testing 100% DPTafter Back NDT Report QA/QC H S R
Gouging
7.2.3 Back Gouge / Weld Back Grind and DP Test Inspector

7.3 Shell To Shell Joint


7.3.1 Fit-up Fit-up,Tacking Approved Drawings
Root-Gap Approved wps
Misalignment
7.3.2 Welding
7.3.3 Back Gouge / Welding Back Grind / DP testing
7.3.4 Inspection Check Peaking, Approved Drawings ,wps Fit-up Inspection Fab.Supvr.
Banding Template weld/NDT Report QA/QC
Verticality During API 650 5-2-3-3 Inspector
Welding API 650 6-1-2-2/
Remove entrap slags 6-1-2-3 H W R
by Grinding Absence of defects.
7.3.5 NDT To be carried-out DPT 100%DP-after B/G

5 of 11
on Grinded Area 100%RT on T joints
Client's Instruction 10%RT on butt welds
100% DPT carried-out 100%DP-on all joints
External and internal
Welding

8 Man-Hole Opening (Shell)

Mark Location Approved Drawings _ Fab.Supvr. H R R


Check Orientation QA/QC

9 Crub Angle Assembly on Tank


Cutting/Endpreparation
Fit-up
Check Curvature Fit-up Inspection
Verticality WPS weld/NDT Report H R R
Continues Welding Approved Drawings Fab.Supvr.

9.1 Inspection/Testing Visual/Dimensional WPS QA/QC

10%DPT on Completed
API 650 Test report Inspector
weld

10 Roof
10.1 Roof Errection Mark Location WPS Fit-up Inspection Fab.Supvr.
Fit-up Approved Drawings weld/NDT Report QA/QC

Continues Welding Inspector H S R

100%DPT on Completed
Test report
weld

10.2 Inspection/ NDT Visual/Dimensional

10.3 Field joint with backing


strip
Seal run on backing strip
10.4 Man-Hole/ Nozziles Mark Location
Check Orientation WPS

6 of 11
Dimention Approved Drawings
Fit-up
Welding
10.5 Re-Inforcement Pad To be rolled to suit
roof plate curvature roof plate curvature
Fit-up Fit-up Inspection Fab.Supvr. H S R
Welding weld/NDT Report QA/QC

10.6 Inspection Visual


Dimention
Projection
Elevation
100%DPT on Completed
10.7 Testing API 650 5-3-3 Inspector H W R
weld
Pneumatic Testing Procedure Test report
No Leakage

11 Shell Plate to Bottom Plate

11.1 Assembly Fit-up

Dimention

Welding Fit-up Inspection

WPS

11.2 Inspection/Testing After Root-Run to be Approved Drawings weld/NDT Report H W W

carried-out Penetrant/ API 650 5-2-4-1-b Test report Fab.Supvr.

Developer Test QA/QC

100%DPT on Completed
100% DPT on both side Inspector
weld

Visual

Dimention

Peaking/ Banding

Verticality

7 of 11
12 Shell-Nozzles/Man-Hole

12.1 Assembly Mark Location

Cutting Approved Drawings Fit-up Inspection

Fit-up Orientation weld/NDT Report Fab.Supvr. H S R

Check Orientation QA/QC

Elevation Test report

Projection

Welding

12.2 Re-Inforcement Pad Pad to be rolled to suit WPS

Shell plate Curvature Approved Drawings

Fit-up Fit-up Inspection

Welding weld/NDT Report Fab.Supvr.

H S R

12.3 Testing/NDT 100% DPT on QA/QC

completed Weld

Pneumatic Testing API 650 5-3-3 Test report

13 External Fittings
13.1 Earthing Boss Mark Location
Fit-up
Welding
13.2 Bolting Braket Mark Location
Fit-up
Welding
13.3 Testing/Inspection 100% DPT on Fit-up Inspection Fab.Supvr.
completed Weld Approved Drawings weld/NDT Report QA/QC H S R
Visual Inspector
13.4 Lifting Lug Mark Location Test report
Fit-up

8 of 11
Welding
100% DPT on
completed Weld
13.5 Pad plate For N1 Mark Location
Fit-up
Welding
13.6 Davit for Manhole Flange Mark Location Approved Drawings Fit-up Inspection Fab.Supvr.
weld/NDT Report QA/QC

13.7 Roof Vents Welding Inspector H S R


Test report
13.8 Ladder/ Platform

13.9 Testing/Inspection 100% DPT on


completed Weld

14 Name Plate

14.1 Fixing of Bracket Mark Location

Letters,Numbers 150mm API 650 Sec.8 Client's


Report QA/QC Inspector H W R
high Black Painted. Instruction

Visual

15 Removal of Temparory Tack welds/ Cleats


15.1 Removal of Temparory
Tack Welds and Cleats 100%DP on grinded 100%DP on grinded H S R
15.2 NDT area area
16 Passivation
Stain Clean Pickling Slag Removal Absence of
16.1 Completed Weldment Visual Inspection Report
Paste shall be used Heat Tint QA/QC Inspector H W R
16.2 Inspection Visual
17 Final Inspection

9 of 11
17.1 Visual/Dimensional Dimention Approved Drawings
Inspection Verticality Specification
Plumpness Requirements Fab.Supvr.
Peaking/ Banding API 650 Inspection Reports QA/QC

Nozzile,Manhole Dimenion tolerance Inspector


H H W
Orientation API 650 Sec.5-5

Elevation
Projection
Weld Visual

18 Mechanical Completion
18.1 Punch List Punch List

Drawing Inspection Reports QA/QC H W R


Scope Inspector
API 650

19 Testing
19.1 Water Fill Test Preparation
Potable Water shall be API 650 5-3-6 H H W
Filling/Setting Test Procedure
Drawing Fab.Supvr.
Weld Map Test report QA/QC

Absence of Leakage Inspector

20 Painting

20.1 Galvanized Ladder Garnet Mfrs.Recommentation Report

External Structurals Climatic Condition Record H S R

Sweep Blasting Product Data Sheet DEQ/FORM/QAQC/013 QA/QC

Batch Certificate DEQ/FORM/QAQC/014 Painting Supvr.

10 of 11
Sweep Blasting AS PER: SMt.ci.002

21 Ladder/ Platform

21.1 Installation Install Ladder Platform Approved Drawings Fab.Supvr.

As per Drawing Report QA/QC H R R

21.2 Inspection Visual

22 QA/QC Dossier

22.1 Final Acceptance As Built Documents Quality Control And QC Dossier

Reports Inspection Test Plan Final Acceptance QA/QC H R H

Records Letter
Legends: DEW-Danem Engineering Works . QAFCO . TPI- Third Party Inspection