Danem Engineering Works - WLL: Inspection & Test Plan
Danem Engineering Works - WLL: Inspection & Test Plan
WLL
INSPECTION & TEST PLAN
CONTRACTUAL DESIGN
APPROVED CONTRACTUAL DRAWINGS
DOCUMENTS ENGR.: H R
1.0 ENGINEERING DRAWINGS DOCUMENTS CALCULATIONS NA
RELEVENT PROJECT
SITE SURVEY RELEVENT REQUIREMENTS
STANDARDS MNGR.
STANDARDS
PRELIMINARY
ACTIVITIES
DRAWING APPROVED
APPROVED APPROVED
APPROVAL LETTER OF PROJECT
2.0 DRAWING - DRAWING H NA R
TECHNICAL SIGNATURE ON MANAGER
SPECIFICATIONS SPECIFICATIONS
DOCUMENTS DOCUMENTS
PRIOR TO
START OF
MANUFACTURE
SHOP
DIMENSION
3.0 FABRICATION APPROVED INSPECTION QA/QC
HEAT No., GARDE, APPROVED
PRIOR TO DRAWING REPORT FAB. H NA R
SIZE, SPECS DRAWING
CUTTING OF SUPVR
PIPE
NA
WELDING APPROVED WPS/ PQR ASME SECVIII DIV I, -
5.0 WPS/PQR,WELDERS WELDERS ASME B 31.3, QA/QC H H/W
CERTIFICATE CERTIFICATE CLIENT SPEC
QP SPEC.
CONTROL POINTS: H: HOLD S: SURVEILLANCE R: REVIEW W: WITNESS WI: WELDING INSPECTOR JO: JOB OFFIC PAGE 1 OF 3
DANEM ENGINEERING WORKS.WLL
INSPECTION & TEST PLAN
NO SURFACE AND
VISUAL 100% VISUAL APPROVED SUB SURFACE
6.0 INSPECTION INSPECTION DRAWINGS DEFECTS INSPECTION H NA R/S
ON COMPLETED WELD WELD MAP ,CLIENT SPEC, REPORT QA / QC
ASME B 31.3
ASME B 31.3/ QG
WELD MAP
AS PER THE DRG AND SPEC,ASME SEC VIII TEST REPORTS H NA R/S
7.0 NDT
SCOPE OF WORK
DRAWING
DIV I
LEVEL II
INSPECTOR
CONTROL POINTS: H: HOLD S: SURVEILLANCE R: REVIEW W: WITNESS WI: WELDING INSPECTOR JO: JOB OFFIC PAGE 2 OF 3
DANEM ENGINEERING WORKS.WLL
INSPECTION & TEST PLAN
QUALITY
18.0 QUALITY CONTRACTUAL DOCUMENTS AND INSPECTION TEST QA/QC NA
QC DOSSIER H R/H
DOSSIER REQUIREMENTS REPORTS PLAN ENGINEER
CLIENTS
REQUIREMENTS
CONTROL POINTS: H: HOLD S: SURVEILLANCE R: REVIEW W: WITNESS WI: WELDING INSPECTOR JO: JOB OFFIC PAGE 3 OF 3