CASH FLOW Conventional
CASH FLOW Conventional
CASH FLOW Conventional
1 acre = 4 boreholes
16.20 acres = 64 boreholes
ii. Syarikat Bekalan Air Selangor (SYABAS) Unit 130 RM 75.00 RM 9,750.00
iv. Jabatan Pengairan dan Saliran (JPS) Acre 16.20 RM 6,000.00 RM 97,200.00
5 PROFESSIONAL FEES
275,400.00
198,220.00
91,000.00
405,000.00
16,200.00
2,443,670.00
CONVENTIONAL
A BUILDING COST
1 Intermediate unit 92 RM 1,170.00 RM 107,640.00 104
2 Corner unit 111 RM 1,170.00 130% RM 168,831.00 26
3 Surau 137 RM 1,005.00 RM 137,685.00 1
4 Community centre 600 RM 3,500.00 RM 2,100,000.00 1
5 Garbage house 24 RM 100.00 RM 2,400.00 1
TOTAL BUILDING COST
TOTAL COST (RM)
RM 11,194,560.00
RM 4,389,606.00
RM 137,685.00
RM 2,100,000.00
RM 2,400.00
RM 17,824,251.00
SUMMARY OF GDC (CONVENTIONAL)
PRE-DEVELOPMENT COST
CONSTRUCTION COST
3 Preliminaries
(10% of items 1-2) RM 2,026,792.10
RM 22,294,713.10
4 Design Reserve
(5% of items 1-3) RM 1,114,735.66
RM 23,409,448.76
TOTAL ESTIMATED GROSS DEVELOPMENT COST
TOTAL COST (RM)
RM 4,471,628.81
RM 23,409,448.76
RM 27,881,077.56
TYPE UNIT (NO) GFA (M2) COST/M2 (ANALYSED)
INTERMEDIATE 104 92 RM2,489.21
END 26 111 RM2,601.95
TOTAL
SELLING COST (RM)
RM 23,816,761.28
RM 7,509,227.70
RM 31,325,988.98
Days of Usage Average Cost
HALL
Weekdays Weekend Weekdays Weekend
Proposed Community Hall 4 2 RM5,500.00 RM6,000.00
Total Rent/month Total Rent/year
RM136,000.00 RM1,632,000.00
DISCOUNTED CASHFLOW RETURN ANALYSIS
Year
1
Total Cost
35
CASH INFLOWS
Sales of building unit 8,920,000.00
CASH OUTFLOWS
Year
1
Total Cost
35
CASH INFLOWS
Sales of building unit 8,920,000.00
Total Cash Inflows 8,920,000.00 3,122,000.00
CASH OUTFLOWS
COMMENTS : Above are two options differing in the timing, Option A has an NPV of RM
1,595,735.49 while Option B is RM 1,865,467. Both options are profitable but Option B is
much more promising and worthy. The client may opt for Option B.
SCHEDULE OF INCOME
2 3 4 5
30 20 10 5
YEAR
1
2,676,000.00 1,784,000.00 892,000.00 446,000.00 2
3
2,560,134.36 4
397,306.89 5
264,970.97
142,196.25
149,306.06
3,513,914.53 0.00 0.00 0.00
(837,915) 1,784,000 892,000 446,000
0.9612 0.9423 0.9238 0.9057
(805,377.29) 1,681,103.04 824,070.12 403,955.94
2 3 4 5
30 20 10 5
2,560,134.36 2,560,134.36
170,274.38 397,306.89
618,265.61 264,970.97
142,196.25 142,196.25
149,306.06 149,306.06
0.00 3,640,176.66 3,513,914.53 0.00
2,676,000.00 (1,856,176.66) (2,621,914.53) 446,000.00
0.9612 0.9423 0.9238 0.9057
2,572,087.66 (1,749,116.72) (2,422,243.75) 403,955.94
SCHEDULE OF INCOME SCHEDULE OF PAYMENT
Description Amount %
Building Cost 5,120,268.72 50%
Infrastructure co 567,581.27 30%
Other pre-develo 883,236.58 70%
Preliminaries 284,392.50 50%
Contingencies an 298,612.12 50%
1st Year % 2nd year
2,560,134.36 50% 2,560,134.36