Assignment 8: Unit 9 - Week-8
Assignment 8: Unit 9 - Week-8
(https://swayam.gov.in) (https://swayam.gov.in/nc_details/NPTEL)
Announcements (announcements)
Unit 9 - Week-8
Course
outline Assignment 8
How to access The due date for submitting this assignment has passed. Due on 2019-09-25, 23:59 IST.
the portal As per our records you have not submitted this assignment.
Week-1 1) PERT analysis computes the variance of the total project completion time as: 1 point
https://onlinecourses.nptel.ac.in/noc19_mg31/unit?unit=61&assessment=121 1/4
28/07/2020 Project management for managers - - Unit 9 - Week-8
Feedback week- Is the amount of time a task may be delayed without changing the overall project completion time
8 (unit?
Is the latest time an activity can be started without delaying the entire project
unit=61&lesson=67)
Is a task or subproject that must be completed
Week-9 Marks the start or completion of a task
No, the answer is incorrect.
Week-10 Score: 0
Accepted Answers:
Week-11 Is the amount of time a task may be delayed without changing the overall project completion time
6) Four experts A, B, C, D examined an activity and arrived at the following time 1 point
Week-12
estimates.
DOWNLOAD
Determine which expert is more certain about his estimates of time:
VIDEOS Experts Time Estimate
to tm tp
Text A 4 6 8
Transcription B 4 7 10
C 5 8 12
WEEKLY D 4 7 11
FEEDBACK
FORM A
B
C
D
No, the answer is incorrect.
Score: 0
Accepted Answers:
A
7) 0 points
https://onlinecourses.nptel.ac.in/noc19_mg31/unit?unit=61&assessment=121 2/4
28/07/2020 Project management for managers - - Unit 9 - Week-8
Questions 7 to 10 are linked questions use given data (use normal probability distribution
table
for appropriate question, you can refer to video for table or other resources).
A project consists of seven activities with the following time estimates.
Optimistic Most likely Pessimistic
Predecessor
Activity time estimate time estimate time estimate
activity
(to) (tm) (tp)
A - 2 5 8
B A 2 3 4
C A 6 8 10
D A 2 4 6
E B 2 6 10
F C 6 7 8
G D, E, F 6 8 10
Determine the critical path of the project.
1-2-3-5-6
1-2-4-5-6
1-2-5-6
Inefficient data provided
No, the answer is incorrect.
Score: 0
Accepted Answers:
1-2-4-5-6
22 weeks
28 weeks
17 weeks
None of the above
No, the answer is incorrect.
Score: 0
Accepted Answers:
28 weeks
1.414
2.414
1.69
2.25
No, the answer is incorrect.
Score: 0
Accepted Answers:
1.414
10)Find the probability that the project will be completed in 30 week or less. 1 point
0.92
0.65
0.95
0.98
No, the answer is incorrect.
Score: 0
A dA
https://onlinecourses.nptel.ac.in/noc19_mg31/unit?unit=61&assessment=121 3/4
28/07/2020 Project management for managers - - Unit 9 - Week-8
Accepted Answers:
0.92
https://onlinecourses.nptel.ac.in/noc19_mg31/unit?unit=61&assessment=121 4/4