P2 Bautista
P2 Bautista
P2 Bautista
What are the equivalent units of production for the month of May,
2001 using average?
a. 13,000 units b. 12,500 units c. 14,000
d. 15,000
C
Answer:
C. 14,000
Equivalent unit of production = Transferred unit + Closing inventory
What are the materials equivalent units of production for the month
of January 2001 using average method?
a. 1,900 b. 2,000 c. 2,200
d. 2,500
D
Answer: d .
Computing equivalent units of production for materials:
= (Units completed and transferred out x Completion percentage for materials) + (Units in ending work-in
process x Completion percentage for materials)
= (2,100 x 100%) + (400 x 100%)
3. Department A is the first stage of Mann Company’s production
cycle. The following information is available for conversion costs for
the month of April 2001:
Units
Work-in-process, beginning (60% complete) ……………………….
20,000
Started in April ………………………………………………………..
340,000
Completed in April and transferred to department B ……………….
320,000
Work-in-process, ending (40% complete) …………………………..
40,000
Using fifo method, the equivalent units for the conversion cost
calculation are:
a. 324,000 b. 336,000 c. 340,000 d.
360,000
A
4. Bart Co. adds materials at the end of the process in Department
M. The following information pertain to Department M’s work-in-
process during April:
Units
Work in process, April 1 …(60% complete as to conversion cost)
…………………………. 3,000
Started in April ………………………………………………………
25,000
Completed………………………………………………………… …
20,000
Work-in-process, April 30
(75% complete as to conversion cost) …………………………..
8,000
What are the equivalent units of production for the month of April
using average?
Materials Conversion Materials Conversion
a. 28,000 28,000 c. 20,000
26,000
b. 26,000 26,000 d. 26,000
20,000
C
Answer: c .
To compute the EUP, we add beginning inventory, units started and completed, and ending inventory. The
number of units completed is 20,000, and the beginning inventory is 3,000, which means that the units
started and completed is 17,000 (20000 - 3000). This will be true for either material and conversion cost.
Since materials are added at the end of production, then there is no material for ending inventory. For
conversion cost, it is 75% complete:
Units
WIP, April 1 (50% complete) …………………………………..
40,000
Started in April ………………………………………………….
240,000
WIP, April 30 (60% complete) ………………………………….
25,000
Equivalent Units
Transfer Materials Conversio
Costs n
a. 108,000 100,000 103,200
b. 108,000 100,000 100,000
c. 108,000 108,000 103,200
d. 109,000 101,000 104,200
C
7. BWIP was 60% complete as to conversion costs, and EWIP was
45% complete as to conversion costs. The peso amount of the
conversion cost included in EWIP (using the weighted average
method) is determined by multiplying the average unit conversion
cost by what percentage of the total units in EWIP?
10. If 100 units are 70% complete, 30 units 60%, complete, 200
units 40% complete, and 60 units 5% complete, how many EUP
have been produced?
a. 70 b. 171 c. 175
d. 390
B
Answer: b .
Answer: Option b is correct.
Rationale: Computation of equivalent units of production:
Units Completion percentage of Equivalent units
100 70% 100 x 70% = 70
P56
Assume that spoilage loss is charged to all production during August.
What would be the unit cost of the good coats produced on Job 501?
a. P53.00 b. P55.00 c. P56.00
d. 58.60
C
4. Using the same information in No. 13 assume instead that the
spoilage loss is attributable to the exacting specifications of Job 501
and is charged to this specific job. What would be the unit cost of
the good coats produced on Job 501?
a. P55.00 b. P57.50 c. P58.60
d. 61.60
B
5. Under Heller Company’s job order cost system, estimated costs
of defective work (considered normal in the manufacturing process)
are included in the predetermined factory overhead rate. During
March, Job No. 210 for 2,000 hand saws was completed at the
following costs per unit:
Direct materials P5
Direct labor 4
Factory overhead (applied at 150% of direct labor cost
6
P15
Final inspection disclosed 100 defective saws, which were reworked at
a cost of P2 per unit for direct labor, plus overhead at the
predetermined rate. The defective units fall within the normal range.
What is the total rework cost and to what accounts should it be
charged?
a. P200 to WIP
b. P200 to factory overhead control
c. P500 to WIP
d. P500 to factory overhead control
D
11. Hamilton Company uses job order costing. Factory overhead is
applied to production at a determined rate of 150% of direct-labor
cost. Any over-or under applied factory overhead is closed to the cost
of goods sold account at the end of each month. Additional information
is available as follows:
Job 101 was the only job in process at January 31,
2001, with accumulated costs as follows:
Direct materials P4,000
Direct labor 2,000
Applied factory overhead 3,000
P9,000
Jobs 102, 103 and 104 were started during
February.
Direct materials requisitions for February totaled
P26,000.
Direct-labor cost of P20,000 was incurred for
February.
Actual factory overhead was P32,000 for February.
The only job still in process at February 28, 2001
was Job 104, with costs P2,800 for direct materials and P1,800
for direct labor.
The cost of goods manufactured for February 2001 wwas:
a. P77,700 b. P78,000 c. P79,700 d.
85,000
A
12. Using the same information No. 11, any over-or under applied
factory overhead should be closed to the cost of goods sold account at
February 28, 2001, in the amount of
a. P700 overapplied c. P1,700 underapplied
b. 1,000 overapplied d. 2,000 underapplied
D
13. Simpson Company manufactures electric drills to the exacting
specifications of various customers. During April 2001, Job 203 for the
production of 1,100 drills was completed at the following costs per
unit:
Direct materials P10
Direct labor 8
Applied factory overhead 12
Total P30
Final inspection of Job 403 disclosed 50 defective units and 100 spoiled
units. The defective drills were reworked at a total cost of P500, and
the spoiled drills were sold to a jobber for P1,500. What would be the
unit cost of the good units produced on Job 403?
a. P33 b. P32 c. P30
d. 29
B
Answer: b .
Production unit = 1,100 drills
Direct material = P 10
Direct labor = P 8
Factory overhead cost = P 12