Contractual Data:: Allocation Releases Obligation Disbursement
Contractual Data:: Allocation Releases Obligation Disbursement
Name of project : Construction of 4 -Storey Regional Prosecutor's Office Building, Regional Office, Region 2, Regional Government Center,
Carig Sur, Tuguegarao City, Cagayan
PROJECT DESCRIPTION:
Construction of Office Building
PROJECT IMPACT :
Intends to provide better facility for the conduct of meetings and other judiciary activities in the region.
To-Date
Planned Accomplishment : 90.40% PROJECT DELAYED DUE TO 50% LIMITATION ON MANPOWER UNDER MODIFIED GENERAL
COMMUNITY QUARANTINE AREAS AS ORDERED BY THE PROVINCIAL GOVERNOR TO
Actual Accomplishment : 61.00% COMPLY WITH IMPLEMENTATION OF MINIMUM HEALTH STANDARDS.
Slippage : -29.40%
MANPOWER ON SITE:
1 - Project Engineer
1-Foreman
8-Skilled Laborers
10- Laborers