Machine Reliability in Parallel Operations: Re (%) 100 PF Liability P
Machine Reliability in Parallel Operations: Re (%) 100 PF Liability P
Reliability
PF
Re liability (%) 100
P
where:
P= hours in measurement period
F= hours of downtime caused by forced outages in period
Availability
PF S
Availability (%) 100
P
where:
S= hours of downtime in period caused by scheduled outages (maintenance)
Explanation
The period P is often taken as the expected length of a continuous run of the plant
in which the rotating machinery is installed. However, most published reliability and
availability values are based on average annual downtimes. In the case of availability,
averaging is necessary because a particular machine probably does not have
consistent maintenance needs from year to year. For example, a hypothetical machine
may only require 100 hours of downtime annually for routine inspection and
maintenance for the first four years. But in the fifth year, it might need fifteen days or
more of downtime for a major overhaul. The availability of the machine should be
compatible with the desired availability of the plant.
In some process plants, a forced outage may pose a risk of losses in addition to
production losses.
For example, an emergency trip of a recycle compressor could cause a damaging high
temperature excursion in the reactor if the backup quench system failed to respond
soon enough. This might be a rare double-jeopardy situation, and it would be difficult
to do a numerical evaluation of the risk because there would probably have to be a
number of excursions before the reactor failed. Nevertheless, a qualitative
consideration of the potential catastrophic loss might give reliability the utmost
priority among the major factors to be considered in selecting the compressor.
The availability and reliability of equipment in a particular service can, of course,
be improved by increasing the number of machines performing the service duty.
Two 100%-capacity machines installed in parallel would obviously be more reliable
than single machine. Likewise, the reliability of three 50% machines in parallel
would be better than that of one 100% machine.
Calculations for Machine Relaibility vs No. of Machines
Nomenclature:
R = Reliability
U = Unreliability
Reliability factor assumed as 0.9
One 100% Machine numbered a
Ra Rb 0.9
U a U b 1 Ra 1 Rb 1 0.9 0.10
U a U b U c 1 0.9 0.10
U ab 1 Ra Rb 1 0.81 0.19
Ra Rb Rc Rd 0.9
U a U b U c U d 0.10
Case of One Machine in Series for Capacity Boosting of Three Parallel Machines
If a 100%-capacity booster machine with an individual reliability of 97% were put in
series with the three 50% machines in the foregoing example, the overall reliability
would be 0.952 (0.97 x 0.981).