Cell Name Original Value Final Value

The document contains the results of a linear programming model that assigns shipments of topsoil from three farms (A, B, C) to three projects to minimize total transportation costs. The optimal solution assigns 100 units from Farm A to Project 3, 50 units from Farm B to Project 1, 150 units from Farm B to Project 2, and 200 units from Farm C to Project 3, for a total cost of $1800.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views15 pages

Cell Name Original Value Final Value

The document contains the results of a linear programming model that assigns shipments of topsoil from three farms (A, B, C) to three projects to minimize total transportation costs. The optimal solution assigns 100 units from Farm A to Project 3, 50 units from Farm B to Project 1, 150 units from Farm B to Project 2, and 200 units from Farm C to Project 3, for a total cost of $1800.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 15

Microsoft Excel 16.

0 Answer Report
Worksheet: [06 Trans-Transship-Assign (LP approach).xlsx]Transport
Report Created: 31-10-2019 17:30:27
Result: Solver found a solution. All Constraints and optimality conditions are satisfied.
Solver Engine
Engine: Simplex LP
Solution Time: 0.015 Seconds.
Iterations: 7 Subproblems: 0
Solver Options
Max Time Unlimited, Iterations Unlimited, Precision 0.000001, Use Automatic Scaling
Max Subproblems Unlimited, Max Integer Sols Unlimited, Integer Tolerance 1%, Assume NonNegative

Objective Cell (Min)


Cell Name Original Value Final Value
$B$20 Total Transporatation Cost = 0 1800

Variable Cells
Cell Name Original Value Final Value Integer
$B$13 Farm A Project 1 0 0 Contin
$C$13 Farm A Project 2 0 0 Contin
$D$13 Farm A Project 3 0 100 Contin
$B$14 Farm B Project 1 0 50 Contin
$C$14 Farm B Project 2 0 150 Contin
$D$14 Farm B Project 3 0 0 Contin
$B$15 Farm C Project 1 0 0 Contin
$C$15 Farm C Project 2 0 0 Contin
$D$15 Farm C Project 3 0 200 Contin

Constraints
Cell Name Cell Value Formula Status Slack
$B$18 Actual demand met = 50 $B$18=$B$16 Binding 0
$C$18 Actual demand met = 150 $C$18=$C$16 Binding 0
$D$18 Actual demand met = 300 $D$18=$D$16 Binding 0
$G$13 Qty_Supply_A 100 $G$13=$E$13 Binding 0
$G$14 Qty_Supply_B 200 $G$14=$E$14 Binding 0
$G$15 Qty_Supply_C 200 $G$15=$E$15 Binding 0
Microsoft Excel 16.0 Sensitivity Report
Worksheet: [06 Trans-Transship-Assign (LP approach).xlsx]Transport
Report Created: 31-10-2019 17:30:27

Variable Cells
Final Reduced Objective Allowable Allowable
Cell Name Value Cost Coefficient Increase Decrease
$B$13 Farm A Project 1 0 0 4 2 0
$C$13 Farm A Project 2 0 2 2 1E+030 2
$D$13 Farm A Project 3 100 0 8 0 8
$B$14 Farm B Project 1 50 0 5 0 2
$C$14 Farm B Project 2 150 0 1 2 1E+030
$D$14 Farm B Project 3 0 0 9 1E+030 0
$B$15 Farm C Project 1 0 8 7 1E+030 8
$C$15 Farm C Project 2 0 11 6 1E+030 11
$D$15 Farm C Project 3 200 0 3 8 1E+030

Constraints
Final Shadow Constraint Allowable Allowable
Cell Name Value Price R.H. Side Increase Decrease
$B$18 Actual demand met = 50 5 50 0 50
$C$18 Actual demand met = 150 1 150 0 150
$D$18 Actual demand met = 300 9 300 0 50
$G$13 Qty_Supply_A 100 -1 100 50 0
$G$14 Qty_Supply_B 200 0 200 0 1E+030
$G$15 Qty_Supply_C 200 -6 200 50 0
Microsoft Excel 16.0 Limits Report
Worksheet: [06 Trans-Transship-Assign (LP approach).xlsx]Transport
Report Created: 31-10-2019 17:30:27

Objective
Cell Name Value
$B$20 Total Transporatation Cost = 1800

Variable Lower Objective Upper Objective


Cell Name Value Limit Result Limit Result
$B$13 Farm A Project 1 0 0 1800 0 1800
$C$13 Farm A Project 2 0 0 1800 0 1800
$D$13 Farm A Project 3 100 100 1800 100 1800
$B$14 Farm B Project 1 50 50 1800 50 1800
$C$14 Farm B Project 2 150 150 1800 150 1800
$D$14 Farm B Project 3 0 0 1800 0 1800
$B$15 Farm C Project 1 0 0 1800 0 1800
$C$15 Farm C Project 2 0 0 1800 0 1800
$D$15 Farm C Project 3 200 200 1800 200 1800
Harley’s Sand and Gravel (Topsoil Shipment)
UNIT COST TABLE
Projects
Farms Project 1 Project 2 Project 3
Farm A 4 2 8
Farm B 5 1 9
Farm C 7 6 3

SHIPMENT TABLE
Projects
Farms Project 1 Project 2 Project 3 Supply
Farm A 0 0 100 100 =
Farm B 50 150 0 200 =
Farm C 0 0 200 200 =
Demand 50 150 300 500
= = =
Actual demand met 50 150 300

Total Transporatation Cost 1800


Actual Qty Supplied
100
200
200
Harley’s Sand and Gravel (Topsoil Shipment)
UNIT COST TABLE
Projects
Farms Project 1 Project 2 Project 3
Farm A 4 2 8
Farm B 99999 1 9
Farm C 7 6 3

SHIPMENT TABLE
Projects
Farms Project 1 Project 2 Project 3 Supply
Farm A 50 0 50 100 =
Farm B 0 150 50 200 =
Farm C 0 0 200 200 =
Demand 50 150 300 500
= = =
Actual demand met 50 150 300

Total Transporatation Cost 1800

NOTE: B1 --- very large unit cost for prohibited route


Actual Qty Supplied
100
200
200
Harley’s Sand and Gravel (Topsoil Shipment)
UNIT COST TABLE
Projects
Farms Project 1 Project 2 Project 3 Dummy Demand
Farm A 4 2 8 0
Farm B 5 1 9 0
Farm C 7 6 3 0

SHIPMENT TABLE
Projects
Farms Project 1 Project 2 Project 3 Dummy Demand
Farm A 50 0 0 50
Farm B 0 150 0 50
Farm C 0 0 200 0
Demand 50 150 200 100
= = = =
Actual demand met 50 150 200 100

Total Transporatation Cost 950


Supply Actual Qty Supplied
100 = 100
200 = 200
200 = 200
500
Harley’s Sand and Gravel (Topsoil Shipment)
UNIT COST TABLE Penality for
Projects not meeting
Farms Project 1 Project 2 Project 3 the demand
Farm A 4 2 8
Farm B 5 1 9
Farm C 7 6 3
Dummy Supply 20 20 20

SHIPMENT TABLE
Projects
Farms Project 1 Project 2 Project 3 Supply
Farm A 0 0 100 100 =
Farm B 50 150 0 200 =
Farm C 0 0 120 120 =
Dummy Supply 0 0 80 80 =
Demand 50 150 300 500
= = =
Actual demand met 50 150 300

Total Transporatation Cost 3160


Penality for
not meeting
the demand

Actual Qty Supplied


100
200
120
80
Transshipment Problem
Warehouses
Farms Warehouse 1 Warehouse 2 Supply Qty Shipped
Farm A 0 100 100 100
Farm B 0 200 200 200
Farm C 200 0 200 200
Qty Received 200 300

Projects
Warehouses Project 1 Project 2 Project 3 Qty Shipped
Warehouse 1 0 0 200 200
Warehouse 2 50 150 100 300
Demand 50 150 300

Demand met 50 150 300

Total Cost 3050


Shipping Costs
Warehouses
Warehouse 1 Warehouse 2
Farm A 3 2
Farm B 4 3
Farm C 2.5 3.5

Shipping Costs
Projects
Project 1 Project 2 Project 3
Warehouse 1 2 1 4
Warehouse 2 3 2 5
999999
Job-Employee Assignment Problem

Cost of each assignment


Employee
A B C D
1 15 20 18 24
2 12 17 16 15
Job
3 14 15 19 17
4 11 14 12 13

Employee
A B C D Job Available Job Assigned
1 1 0 0 0 1 = 1
2 0 0 0 1 1 = 1
Job
3 0 1 0 0 1 = 1
4 0 0 1 0 1 = 1
Emp. Available 1 1 1 1
= = = =
Emp. Assigned 1 1 1 1

Total Cost 57