Unit-2 Time Scheduling and Techniques
Unit-2 Time Scheduling and Techniques
SARDARNAGAR, BHVANAGAR
SUBJECT: PROJECT MANAGEMENT CLASS: B.B.A SEM-V
UNIT-2: TIME SCHEDULING AND TECHNIQUES
Introduction
Time scheduling is a collection of techniques used to develop and present schedules that show when work will
be performed. The choice of tools and techniques used to develop a time schedule depends upon the level of
detail available about the work that needs to be done.
Where the work is well defined, modeling techniques can be used to show the sequence of working and
logical dependencies between each package of work. The resulting model can be used to predict start and
finish times, and identify where there is flexibility in the schedule. If requirements are clear but the means to
achieve them is less so, or where the requirements are subject to significant change as the work proceeds, then
modeling techniques are less appropriate.
Scheduling in project management is the listing of activities, deliverables, and milestones within a project. A
schedule also usually includes the planned start and finish date, duration, and resources assigned to each
activity. Effective project scheduling is a critical component of successful time management.
This is a schedule prepared by the contractor to the client in the very beginning stages of the project, even
before the project awarded to the contractor and usually it is a summary schedule clarifying how the
contractor intend to execute the project (sequence and duration). This time schedule does not contains lot of
details and issued as a part of the tender documents for future reference.
The master time schedule is the first schedule to be issued by the contractor after project is awarded from the
client and most contracts allow for a short duration (2 weeks approximate) to submit this schedule after the
letter of award, However the master schedule should contains more details to the project rather than the tender
schedule and could include budget cost, project cash flow and resources histograms.
The detailed time schedule is very important document and should be created carefully as per the client
requirements, detailed schedule should have the budget cost, resources and equipments assigned to each
The baseline schedule is the client approved version of the detailed schedule (or sometimes the master time
schedule) which the progress of works will be monitored against it. The dates and the values in this schedule
are fixed and cannot be changed.
The updated time schedule is a copy of the baseline schedule with actual dates and percentage which represent
the progress of work at certain date (Data Date). Once actual values applied to a baseline schedule it became
an updated schedule with forecast completion dates for each activity could be earlier than the baseline
schedule which mean (Ahead of schedule) or after the baseline schedule dates which mean (Behind the
Schedule).
The revised time schedule is a recovery schedule to recover schedule delays due to any reason, revised time
schedule could recover 100 % of the delays in the project and shorten the durations to complete the project as
planned or it could not recover any durations if it is not possible and just represent a new completion date of
the project.
➢ “A Gantt chart is a chart that shows all of the different sub-tasks of a project and how they relate to
each other over time.”
Line of Balance (LOB) is a method of showing the repetitive work that may exist in a project as a single line
on a graph. Unlike a Bar Chart, which shows the duration of a particular activity, a LOB Chart shows
the rate at which the work that makes up all of the activities has to be undertaken to stay on schedule,
the relationship of one trade or process to the subsequent trade or process is defined by the space
between the lines.
1.3.2: Definition:
➢ “Line of Balance (LOB) is a management control process for collecting, measuring and presenting
facts relating to time, cost and accomplishment.”
➢ “A time scheduling technique that is typically used in situations where skilled resources are
performing the same activity on multiple products within a project.”
Example: 2:
The solid lines make it clearer how each trade progresses at a different rate. The steeper the line the faster the
trade moved between the units. The start of each trade is scheduled so that the work is completed as soon as
possible with each trade having continuity of work. Natural buffers occur at the beginning or end of the trades
work and these can be used in a similar way to float in a schedule based on critical path analysis. Line of
balance charts are sometimes combined with physical layouts of the work on the vertical axis, and may be
referred to as a time chain age chart.
2. Has the ability to show and optimize the resources used for large number of repeated activities,
executed in several zones or locations.
3. Easier cost and time optimization analysis because of all the information available for each activity in
the project.
7. Allows for simpler and clearer resource management and resource optimization functions.
9. It allows project managers to see, in the middle of a project, whether they can meet the schedule if
they continue working as they have been.
Network technique is a technique for planning, scheduling (programming) and controlling the progress
of projects. This is very useful for projects which are complex in nature or where activities are subject to
considerable degree of uncertainty in performance time.
This technique provides an effective management, determines the project duration more accurately,
identifies the activities which are critical at different stages of project completion to enable to pay more
attention on these activities, analyze the scheduling at regular interval for taking corrective action well in
advance, facilitates in optimistic resources utilization, helps management for taking timely and better
decisions for effective monitoring and control during execution of the project.
The network is the framework that will be used by the project managers to make decisions concerning
project time, cost and performance. Once the network is developed, it is very easy to modify or change
when unexpected events occur as the project progresses. Developing the project networks takes time for
someone or some group to develop.
1.4.2: Definition:
➢ “The project network diagram displays the duration of activities in the project, their chronological
order and logical dependencies between the activities graphically or in tabular form.”
➢ “A project network is a graph (weighted directed graph) depicting the sequence in which a project's
terminal elements are to be completed by showing terminal elements and their dependencies. It is
always drawn from left to right to reflect project chronology”
❖ To minimize idle resources: Allowing for large variations in the use of limited resources may disturb
the whole plan. Thus, efforts should be made to avoid the cost incurred due to idle resources.
❖ To minimize the total project cost: The total cost of the project can be calculated and then efforts
can be made to minimize the total cost by calculating the cost of delay in the completion of an activity
of the project in addition to the cost of the resources required to carry out the jobs at various speeds
(i.e. normal or over time rates of pay).
❖ To trade off between time and cost of project: The idea of trade off between time and cost of project
is centered on the idea that duration of same activities can be cut down if additional resources are
allocated to them. For technical reasons, the durations may not be reduced indefinitely. Similarly,
there is also a most cost efficient duration called ‘normal point’ & stretching the activity beyond it
may lead to a rise in direct costs.
❖ To minimize production delays, interruption and conflict: This is achieved by identifying all
activities involved in the project, their precedence constraints, etc.
❖ Aid in planning, organizing and controlling: Since all project activities are shown in sequence with
relevant interrelationships, the network diagram of a project will help the project manager and team
during planning and organizing. Network diagram will be useful during project execution as well since
it is a snapshot of the project activities tied with the dependencies.
❖ Show interdependencies of activities: Since interdependencies of activities are visible in the network
diagram, it will be easier to see which activity can start after which one, which activity depends on
each other, predecessors and successors of each activity etc.
❖ Show workflow of the project activities: So the project team will know the sequence of activities. At
a certain point in the project, it will be easier to see in the network diagram what has been
accomplished and the remaining activities and their interdependencies with each other.
❖ Identify opportunities to compress the schedule: You may need to shorten the duration of the
remaining activities in a project. This can be because your project is behind schedule and in order to
complete the project on time, you need to compress the schedule. In this case, since network diagrams
show the order of the activities and durations, it will be easier to focus on how to compress the
remaining activities in the project.
❖ Show project progress. Since it shows the order of activities in a project and total path from the
beginning of the project till the end, it is a good instrument for showing the project progress.
2. Identifies the critical activities and focus them to provide greater managerial attention.
5. It provides a scientific basis for monitoring, review and control, to evaluate effect of slippages.
✓ To over-come delays,
✓ To crashing programme,
✓ Optimizing resources, and
✓ On other corrective actions.
8. It is an effective management tool through a common and simple language, providing common
understanding.
1. Activity
Any individual operation which makes use of resources and has an end and a starting is called as activity. An
arrow is generally used to characterize an activity with its head representing the direction of progress in the
project. These are divided into four classes
1. Predecessor activity - Activities that ought to be completed immediately previous to the start of
another activity are known as predecessor activities.
3. Concurrent activity - These are activities which can be achieved concurrently. It may be noted that
an activity can be a successor or a predecessor for an event or it may be concurrent with one or more
activities.
4. Dummy activity - An activity which does not use any type of resource but simply depicts the
technological dependence is known as dummy activity.
The dummy activity is included in the network to clear the activity pattern in the next two situations
• To discover and maintain the correct precedence relationship between activities that is not linked by
events.
For instance, take a situation where A and B are concurrent activities. C is reliant on A and D is reliant on A
and B both. This type of situation can be handled with the use of dummy activity as shown in the figure.
2. Event
An event signifies a point in time representing the completion of several activities and the starting of new
ones. This is typically symbolizes by a circle in a network which is also known as node or connector.
1. Merge event - Event in which more than one activity comes and connects an event is called as merge
event.
2. Burst event - It is event in which more than one activity leaves an event.
3. Merge and Burst event - An activity can be merge and burst event simultaneously, as regard some
activities it can be a merge event and with some other activities it may be a burst event.
The first requirement in the development of network is to keep the precedence relationships. In order to
prepare a network, the subsequent points must be taken into considerations
2. An activity cannot begin until all preceding connected activities have been completed.
3. Arrows on networks indicate precedence and flow. Arrows can cross over each other.
5. An activity identification number must be larger than that of any activities that precede it.
7. Conditional statements are not allowed (that is, this type of statement should not appear: If successful, do
something; if not, do nothing).
B) Approaches
The two approaches used to develop project networks are known as Activity-On-Node (AON) and Activity-
On-Arrow (AOA). Both methods use two building blocks—the arrow and the node. Their names derive from
the fact that the former uses anode to depict an activity, while the second uses an arrow to depict an activity.
Activity-on-node is a project management term that refers to a precedence diagramming method which uses
boxes to denote schedule activities. These various boxes or “nodes” are connected from beginning to end with
arrows to depict a logical progression of the dependencies between the schedule activities. Each node is
coded with a letter or number that correlates to an activity on the project schedule. Typically, an activity-
on-node diagram will be designed to show which activities must be completed in order for other activities to
commence. This is referred to as “finish-to-start” precedence – meaning one activity must be finished before
the next one can start.
In an activity-on-arrow network, activities are represented by a line between two circles. The first circle
represents the start of the activity and is known as the start event (sometimes called the i-node). The second
circle represents the finish of the activity and is known as the finish event (sometimes called the j-node).
The arrow diagramming method (ADM) or Activity-On-Arrow (AOA) refers to a schedule network
diagramming technique in which the schedule activities within a given project are represented by the use of
arrows. The beginning of the schedule activity is represented by the tail, or base, of the arrow. The pointed
end of the arrow represents the endpoint of a specific schedule activity, and the length of the arrow can
loosely represent the time in between.
Step 1: The first step in network construction is to split the work contents involved in the implementation of
the project to the level of activities which represent, individually, category of works, e.g. Preparation of
Quantity Survey involving drawings and specifications; Floating of Tender enquiries, Analysis of Tender and
further negotiation with the possible contractor; issue of purchase orders and finalising the contract etc.
One activity can then be started on completion of other preceding activity or activities, depending upon the
inter-relationship, e.g. the concretes can be poured for roofing only on completion of (1) construction of the
walls and (2) construction in concrete of the stairs, when required as per plan.
In order to minimize the project schedule, which is of utmost necessity to economize the project cost, some of
the activities can be started concurrently e.g. construction of the staircase and the construction for the brick-
walls can be carried out simultaneously.
Step 3: Identify Event: We know that an ‘event’ is happening a particular point of time representing
completion of one or more activities and, at the same time, some other activity or activities emerge out of it,
i.e. the starting time of such other activity.
We also know the ‘tail event’ from where the activity emerges and then terminates to another event the ‘head
event’ and the head event is the tail event of another succeeding activity till we reach the END of the project
schedule. We also know that, while an activity is represented by a straight line arrow from left to right with
one arrow for each activity the event is represented by a ‘circle’. The arrow showing an activity need not be
drawn to scale. In other words, the lengths of the arrows need not be proportionate with the duration of the
activities. The arrows may be also bent (by straight lines and not curves).
Step 4: Now that we have arranged the activities in a logical sequence we can establish their interrelationship
and show the schedule of works by diagram as shown below along with numbering the events and, in most
cases, the head event having a greater number than the tail event.
When one activity, i.e. from (2) to (3), as shown in the diagram below, is preceded by the completion of
another activity i.e. (1) to (2), Event (2) is the tail event of activity (2) to (3) and is the head event of activity
(1) to (2).
1. Loops: We have mentioned that the directions of arrows are from left to right. Care should be taken that the
arrows do not traverse right to left and form a loop as depicted below:
In the diagram shown above, the arrow from (7) comes back to (6) and thus forms a loop, which is illogical,
as it will indicate a never-ending situation—as the path will indicate an infinite circle between (6) to (7) and
back to (6).
2. Dangling: A dangling of an activity in the network will indicate an activity left over as shown, below:
Activity (4) to (7) left at event (7) represents a ‘dangling’ and is wrong.
Example: We are by now ready to construct a network for a project. The entire span of the project work has
been broken to, say, ten different activities.
Note:
1. The event numbers are indicated in an ascending order; with a logic that the head event is with a serial
number higher than the tail event. However, as three activities start from the event (1) leading to head events
(2), (3) and (4), it really does not matter which event should be (2) or (3) or (4).
2. The activity duration (time units) are also shown against the respective activities.
3. The lengths of the arrows do not have any direct relation with the duration it is stretched as much to
develop the network diagram as smart, clean and well-balanced. The length of G with only two weeks’
duration is stretched longer than that of activity A of 15 weeks, so that the entire drawing appears well-
balanced.
Total Float:
This is the type of Float that is commonly referred to as “Float”. Total float is the amount of time an activity
can be delayed without delaying the project completion date. So, Total Float is about flexibility at the
project level. It is about the flexibility that an activity has in its execution without delaying the Project finish
date.
Total float is calculated by subtracting the Early Start date of an activity from its Late Start date (Late Start
date – Early Start date), or Early Finish date from its Late Finish date (Late Finish date – Early Finish date).
PMBOK defines Total Float as: “The amount of time that a schedule activity can be delayed or extended
from its early start date without delaying the project finish date or violating a schedule constraint.”
Example:
Total float = duration of the critical path – duration of the non-critical path
= 20 – 12
=8
On the path A->C->D, Activity A and D lie on the critical path; therefore, they will not have a total float.
Only Activity C can have a total float. We can calculate the total float by using either the finish dates or start
dates.
First, we will go with the Late Finish and Early Finish dates:
Total float for Activity C = (LF of Activity C – EF of Activity C)
= 15 – 7
=8
Now, the second formula:
Total float for Activity C = (LS of Activity C – ES of Activity C)
= 14 – 6
=8
The durations are the same. This means that both formulas will give you the same result.
Total float, also called float or slack, is the amount of time an activity can be delayed without delaying the
overall project duration. Total float is shared between activities in a sequence.
Free Float
In the context of project management, the term “free float” is used to describe amount of time that spans from
the completion of one previously scheduled activity and extends to the point at which the next scheduled
activity is set to begin. Free float can be calculated by determining the amount of the time between the earliest
start date of the initial activity and the earliest start date of the succeeding activity, and then subtracting from
that total the amount of time that it is expected the first activity will take to complete.
So, Free Float is about flexibility at the activity level. It is about the flexibility that an activity has in its
execution without delaying its successor activity.
PMBOK Defines Free Float as: “The amount of time that a schedule activity can be delayed without delaying
the early start date of any successor or violating a schedule constraint”
In the above diagram, Activity G can have the free float because Activity D and G converge on one common
activity. Activity D will not have a free float because its successor, Activity E, is starting the day after the
completion of Activity D.
=6–3–1
=2
Free float is the amount of time an activity can be delayed without delaying the early start of any immediate
successor activity.
Defines flexibility of a path w.r.t project end Define flexibility of activity w.r.t its successor
date start
Can come into existence if network diagram has Can come into existence if successor is having
multiple path and there are activities which are more than one activity converging on it or the
not there on Critical Path successor activity is having a constraint applied
1.6.1: Introduction:
PERT is a project management planning tool used to calculate the amount of time it will take to realistically
finish a project. PERT stands for Program Evaluation Review Technique. PERT charts are tools used to
plan tasks within a project - making it easier to schedule and coordinate team members accomplishing the
work. PERT charts were created in the 1950s to help manage the creation of weapons and defense projects for
the US Navy. While PERT was being introduced in the Navy, the private sector simultaneously gave rise to a
similar method called Critical Path.
PERT is similar to critical path in that they are both used to visualize the timeline and the work that must be
done for a project. However with PERT, you create three different time estimates for the project: you
estimate the shortest possible amount time each task will take, the most probable amount of time, and the
longest amount of time tasks might take if things don't go as planned.
For every activity in PERT, three different time estimates are obtained.
➢ Optimistic time (to) – It is the time taken to perform an activity if everything goes smoothly while
performing the activity. It is the shortest possible time estimate for an activity.
➢ Pessimistic time (tp) – It is the time taken to perform an activity if everything goes wrong, while
performing the activity. It is the longest possible time estimate of an activity.
➢ Most likely time (tm) – It is the time which is most likely to be taken, under the given circumstances.
This is often based on the gut feeling or hunch of the project manager.
➢ expected time:(te) the best estimate of the time required to accomplish an activity
1.6.2: Definition:
“The program evaluation and review technique is a statistical tool used in project management, which was
designed to analyze and represent the tasks involved in completing a given project.”
1. Identify the specific activities and milestones: The activities are the tasks required to complete the
project. The milestones are the events marking the beginning and end of one or more activities. It is
helpful to list the tasks in a table that in later steps can be expanded to include information on sequence
and duration.
2. Determine the proper sequence of the activities: This step may be combined with the activity
identification step since the activity sequence is evident for some tasks. Other tasks may require more
analysis to determine the exact order in which they must be performed.
3. Construct a network diagram: Using the activity sequence information, a network diagram can be
drawn showing the sequence of the serial and parallel activities. For the original activity-on-arc model, the
PERT assumes a beta probability distribution for the time estimates. For a beta distribution, the expected time
for each activity can be approximated using the following weighted average:
5. Determine the critical path: The critical path is determined by adding the times for the activities in each
sequence and determining the longest path in the project. The critical path determines the total calendar
time required for the project. If activities outside the critical path speed up or slow down (within limits),
the total project time does not change. The amount of time that a non-critical path activity can be delayed
without delaying the project is referred to as slack time. If the critical path is not immediately obvious, it
may be helpful to determine the following four quantities for each activity:
➢ ES - Earliest Start time
➢ EF - Earliest Finish time
➢ LS - Latest Start time
➢ LF - Latest Finish time
6. Update the PERT chart as the project progresses: Make adjustments in the PERT chart as the project
progresses. As the project unfolds, the estimated times can be replaced with actual times. In cases where
there are delays, additional resources may be needed to stay on schedule and the PERT chart may be
modified to reflect the new situation.
1. PERT forces the management to plan carefully and study how the various parts fit into the whole
project.
2. PERT enables the business managers to predict time and cost of the project in advance.
3. PERT is a forward-looking control device for management. PERT calls attention on the timely
completion of the project and avoids delay.
4. PERT enables the determination of the probabilities concerning the time by which activity and
project would be completed.
6. It provides up-to-date information of the project programme so that the necessary steps may be taken
to minimize the delays and interruptions.
8. It provides a graphical display of project activities that helps the users understand the relationships
among the activities.
9. It is the ideal technique for tactical level planning and operational level control of projects.
1. In PERT, it is assumed that all the activities involved in the project are known in advance. In
projects like research and development (R and D), it is not possible to list out all the activities in
advance.
2. The assumption that a project can be sub-divided into a set of predictable and independent, activities
may not hold true always.
3. PERT emphasizes only on time and not the costs. PERT is based on time estimates and there may be
error in estimating time.
4. For active control of a project, PERT requires frequent updating and revising of calculations. It is time
consuming exercise, which requires highly trained personnel.
5. It cannot effectively handle situations in which two or more projects share available resources.
6. It fails when there is a change in the precedence and sequential relationships of project activities.
1. Estimated Duration: The duration which is supposedly required to accomplish a specific task is
termed as an estimated duration. It is calculated through the following formula:
2. Variance: The level of volatility of the time required to carry an activity from the average time is
termed as variance in PERT analysis.
Where,
Where,
D Competitive Analysis A 40 60 80
E Sample Study B 30 40 50
H Product Differentiation D 10 20 30
I Cost Estimation E 5 10 15
1. Project network;
Solution
1. Project network:
For Activity A:
For Activity A:
Likewise, we have calculated the expected duration and variance of all the activities in the table given below:
The earliest start time for the first event will always be 0.
With the help of given formula, the earliest start time is computed as follows:
For Event 3:
The latest completion time for event 10 is equivalent to the earliest start time of event 10.
Let us find out the LCi with the help of the given equation:
For Event 6:
1 0 0
2 50 50
3 70 140
4 70 80
5 110 110
6 110 180
7 140 140
8 180 180
9 190 190
10 220 220
As we know that the critical path is the longest path of the PERT Chart connecting the nodes which fulfil all
the four conditions mentioned above.
50+60+30+40+10+30=220 days
For this computation, we will require the summation of estimated duration and total variance of the activities
lying in the critical path. The following table will provide the required data:
A 50 2.56
D 60 0.44
G 30 1.78
J 40 1.31
K 10 0.64
L 30 1.00
Thus, to find out the probability, we have to use the Standard Normal Distribution Table, where the value of
1.80 is 0.9641. To convert this value in percentage, we have to multiply it with 100; hence we get:
Probability of project completion on or before 225 days = 96.41%
1.7.1: Introduction:
The term critical path method refers to a specific technique of schedule network analysis that is used to
determine the amount of flexibility that exists in regards to the scheduling of a particular and specific logical
network path with the network of the project schedule. The amount of flexibility within the scheduling here
can also be referred to by the term “float“. Another important element of the technique of critical path method
involves the determination of minimum total project duration. A forward pass is used to determine and
calculate the early start and finish dates, through utilization of a previously specified start date. A backward
pass is used to determine and calculate the late start and finish dates, again, through use of a previously
determined date, this time a previously determined finishing date. In some cases the previously determined
finish date is also the early finish date determined through the calculating done though the forward pass.
The Critical Path Method (CPM) was first developed in USA by the E.I DuPont Nemours & Co. in 1956 for
doing periodic overhauling and maintenance of a chemical plant.
1.7.2: Definition:
➢ “The term critical path method refers to a specific technique of schedule network analysis that is used
to determine the amount of flexibility that exists in regards to the scheduling of a particular and
specific logical network path with the network of the project schedule.”
❖ Forward Pass:
Forward pass is a technique to move forward through network diagram to determining project duration and
finding the critical path or Free Float of the project. In order to calculate Early Finish, we use forward pass.
Means moving from Early Start towards right to come up with Early Finish of the project.
Backward pass represents moving backward to the end result to calculate late start or to find if there is any
slack in the activity. In order to calculate Late Start (LS), we apply backward Pass moving from Late Finish
and deducting from activity duration.
LS = LF – Duration
❖ Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF) in a network diagram
Critical Path is the longest sequence of activity on a project that carry zero free float / slack.
The critical path is the sequence of activities with the longest duration. A delay in any of these activities will
result in a delay for the whole project. Below are some critical path examples to help you understand the key
elements...
The duration of each activity is listed above each node in the diagram. For each path, add the duration of each
node to determine its total duration. The critical path is the one with the longest duration.
1. It figures out the activities which can run parallel to each other.
2. It helps the project manager in identifying the most critical elements of the project.
3. It gives a practical and disciplined base which helps in determining how to reach the objectives.
6. CPM provides demonstration of dependencies which helps in the scheduling of individual activities.
Focus PERT is an event oriented tool, whereby CPM is an activity oriented tool, the
the network interest is focused upon start or network interest is focused upon the start
completion of events and not on activities and completion of activities and not
themselves. events themselves.
Usefulness PERT is useful for research and CPM is useful for the construction
development project as they comprise of projects because it comprises of the
the unpredictable tasks and activities. predictable tasks and activities.
Grouping of PERT does not categories activities into CPM categorizes activities into critical
Activities critical and non-critical activities. and non-critical activities.
Room For In PERT, allowance is made for In CPM, no allowance is made for
Uncertainty uncertainties in the duration of time uncertainties in the duration of time
involved. involved.
Application PERT is suitable in defense projects and CPM is suitable for problems in industrial
R&D where activity time cannot be reliably setting, plant maintenance, civil
predicted. construction projects etc.
1.8.1: Introduction:
The project manager is frequently confronted with having to reduce the scheduled completion time of a
project to meet a deadline. In other words, the manager must finish the project sooner than indicated by the
CPM/PERT network analysis. Project duration can often be reduced by assigning more labor to project
activities, in the form of overtime, and by assigning more resources (material, equipment, and so on).
However, additional labor and resources increase the project cost. Thus, the decision to reduce the project
duration must be based on an analysis of the trade-off between time and cost. Project crashing is a method for
shortening the project duration by reducing the time of one (or more) of the critical project activities to less
than its normal activity time. This reduction in the normal activity time is referred to as crashing. Crashing is
achieved by devoting more resources, usually measured in terms of dollars, to the activities to be crashed.
1.8.2: Definition:
➢ “Crashing is a schedule compression technique used to reduce or shorten the project schedule.”
➢ “Crashing refers to a particular variety of project schedule compression which is performed for the
purposes of decreasing total period of time (also known as the total project schedule duration).”
Example: The initial direct cost was 50 man days (5 men x 10 days) and now it is 60 man days (10 men x 6
days). Therefore, the direct cost has increased by 10 men- days. At the same time, because of the decrease in
duration of the activity by four days, the indirect cost (cost of supervision) decreases. Hence, we can conclude
1.8.3: Terminology:
❖ Crash time: It is the shortest time that could be achieved if all effort (at any reasonable cost) were
made to reduce the activity time. The limit beyond which the duration of the activity does not decrease
by adding any amount of resources is called the crash time. It is the shortest possible activity time.
❖ Crash cost: The direct cost associated with each crash time is called the crash cost.
❖ The normal time (10 days in our example) can be defined as the duration of an activity when the
minimum possible resources required for its performance are deployed.
❖ Normal cost: The lowest expected activity costs are called the normal costs.
❖ Project direct cost: It is the direct cost involved in all the activities of the project.
❖ Project indirect cost: It is the costs associated with sustaining a project. They include the cost of
supervision during the implementation of the project, overheads, facilities, penalty costs and lost
incentive payments.
1. To get the greatest schedule compression: The main reason for crashing your schedule is to get the
project done faster. If you need to bring your project’s end date forward then crashing gives you the most
schedule compression for the least impact and the smallest cost.
2. When part of the project jeopardizes progress: You could also look at crashing when you are facing one
part of the project putting the rest of the project at risk. If a particular work stream isn’t going well it could
suddenly become the route of the critical path. That might be OK, but equally you might feel that this difficult
strand of work is going to hold the rest of the project to ransom. Crashing the schedule around those tricky
tasks is one way to get you out of difficulty.
3. When meeting a fixed deadline: Projects require change and changes (however formal and appropriate
your change control processes) have a habit of adding more time into the plan. When you are dealing with
fixed date projects that’s not a good thing. So what happens when your necessary and obligatory changes start
adding more time to your fixed date project? You have two choices: tell the project sponsor that you can’t do
it and that your end date has to change or try crashing and see if you can claw back some time
4. When you are delayed: Delays early in the project necessarily have an impact on later work. You might
consider crashing your schedule as a way to make up for some of the lost time.
5. When the team is needed on other work: And now we reach the reasons that are to do with resources.
Your project simply might not be the most important thing happening in the business right now. Your team
might be needed on other projects – or at least a particular subject matter expert might be.Crashing your
6. When another resource is free: Sometimes the opposite happens – more resources suddenly become
available. More people for your project. The impact this can have on your schedule can go one of two ways:
• You add an additional resource, refocus the resource allocation and deliver on certain tasks faster
• You add an additional resource and it takes them ages to get up to speed so actually you don’t make
any time saving at all.
Only you will know which of these scenarios is most likely on your project, and who the extra resource is
matters hugely. A junior programmer who has no experience on your project is not likely to gain you much
time. But an experienced technical architect who has always kept half an eye on the project and now is
available to complete some solution design work alongside your existing resources should speed things up for
you dramatically.
7. When another resource needs training: Finally, you may face a situation where you have a resource who
is not contributing effectively to the project because they simply don’t have the skills. This hopefully doesn’t
happen to you too often – ideally as project managers we would select people for the project team who have
the skills we need to get the job done. However, I’m sure you are aware of situations where either ‘the skills
we need to get the job done’ were not defined or changed halfway through the project or we couldn’t get a
resource with the appropriate experience allocated to the project.
1.9.1: Introduction:
PERT cost is a managerial system for the planning and control of specific projects. It is a model thet enables
the managers to determine what must be done, how to schedule activities, what the best allocation of
resources will be, how much of the project will cost, and how to minimize the total costs. When planning is
completed, the plan becomes a standard against which to measure progress and deviation. Management by
exception is taken on those activities that exceed their allowed margin of error. This system is applicable to
any project that has specific beginning and ending point. In PERT COST, both cost and schedule are planned
and controlled on a common basis. This interrelation not only permits more accurate measurement of progress
but also enables managers to appraise more realistically the consequences of alternative course of action.
➢ “PERT cost is a management tool used to optimize the mix of time, resources, and cost for activities
having a definite beginning and end.”
1.9.3: Terminology:
❖ Project cost: in order to include the cost aspects in project scheduling we must first define the cost
duration relationships for various activities in the project. The total cost of any project comprises
direct and indirect costs.
❖ Direct cost: this cost is directly depends upon the amount of resources in the execution of individual
activities manpower loading materials consumed etc. the direct cost increase if the activity duration is
to be reduced.
❖ Indirect cost: This cost is associated with overhead expenses such as managerial services, indirect
supplies, general administration etc.
1. More Effective Planning: It provides a comprehensive planning discipline, which requires the
manager to do careful, detailed planning. By aiming at the end objective, all activities and decisions
are co-ordinate toward the most effective, efficient and economical way of completing the total project
under the given constraints.
2. Show Relationships: All activities are related to achieving to each other is identified. This
relationship determines whether a group of activities must be carried out in series or may be carried
out in parallel. One way of shortening the overall project time is to maximize the concurrency of
operations. Resources for each activity are constrained by the time and cost limitations for the project.
Within these outside constrains resources will be related to achieve the time, cost and performance
goals of the activity at the minimum cost.
3. Pinpoints Problem areas: As the above relationship is worked out many problems will be recognized
and solved before they become crisis. During execution, an imbalance in the interrelationships will
quickly pinpoint problem areas because time resources, or cost schedules will not be met.
4. Improves Communication: The manager learns of the critical areas by doing his homework on the
PERT COST model. This gives him the specific facts and figures he needs to properly explain the
situation to subordinates in order to work out the needed solution. He is also better prepared to justify
requests to higher authority for additional resources.
5. Better Resource allocation: Manpower, materials, equipments, money and time can all be related to
each other on this model. The optimum mix will be that which achieves the time and performance
objectives at the least total cost. The plan can be organized to best use scarce RESOURCES. The plan
may even have to be built around the use of scarce resources.
The PERT Cost model can also be used to develop a proposed project to determine its feasibility, cost
and time factor.