Inspection and Test Plan For Earthworks NSCR-PSC-N05-CRKDPT-PRO-QA-000000
Inspection and Test Plan For Earthworks NSCR-PSC-N05-CRKDPT-PRO-QA-000000
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
Mr. ANTONIO SABALBERINO Mr. Youngsuk Kong Mr. Sang Yeob Lee
(QA/QC Manager) (Construction Engineer) (Project Manager)
Date: 2nd of December, 2020 Date: 2nd of December, 2020 Date: 2nd of December, 2020
※ ISSUE TYPE: “Class 1” for Approval, “Class 2” for Review, “Class 3” for Information and Record
REVISION LOG
-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
TABLE OF CONTENT
3. RESPONSIBILITIES………....................................................2
4. CLASSIFICATION OF TEST/INSPECTION…………………..3
5. FLOW CHART……..…………………………………………….4
-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
1.SCOPE
This Inspection & Test Plan covers the tests and inspections to be performed on the Earth
Works –Excavation and Backfill at the site for the Building and Civil Engineering Work
for Depot Building Including Related Infrastructure and Track Work Ballast The
Inspection & Test Plan is to be considered as a summary of information necessary for a
correct performance of these tests and examinations and as an interface document for
the SUBCONTRACTOR, CONTRACTOR, the ENGINEER and any other organizations
concerned to clarify the relevant interventions and duties.
Routine checks, examinations and inspection activities, which do not require the issue of
final records are not covered by this Inspection & Test Plan. They shall in any case be
carried out to the extent necessary to satisfy the contractual requirements and to ensure
correct work execution and control.
Any Inspection & Test Plan updates will take into account any changes to the reference
documents (testing procedures, qualification records, etc.) and recording forms, and any
additional requirements that may be requested by CONTRACTOR and/or the ENGINEER,
or other organization involved, for test witnessing and acceptance.
2. DEFINITIONS / ABBREVIATIONS
-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
the examination and testing for conformity and acceptance as identified in the Inspection
and Test Plan (ITP) during the stages of work activity.
TEST: An element of inspection for the determination of the capability of an item to meet
specified requirements, by subjecting the item to a set of physical, chemical,
environmental or operating conditions.
3. RESPONSIBILITIES
a. Responsibilities of SUBCONTRACTOR
SUBCONTRACTOR shall perform all checks; examinations and tests required for
acceptance of the work and report to CONTRACTOR the results unless otherwise
specified.
SUBCONTRACTOR shall perform all preparation for checks, examinations and tests
including scaffolding necessary for witness by CONTRACTOR/ENGINEER.
Raise Inspection Request form for each inspection activity, 1(one) working days in
advance.
Checks, examinations and tests which are defined to be in SUBCONTRACTOR’s scope
of work in this Inspection & Test Plan.
Interpret and evaluate the results.
-
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
b. Responsibilities of CONTRACTOR
CONTRACTOR shall perform the following:
Make sure that SUBCONTRACTOR raises Inspection Request form for each
inspection activity at beginning of each shift.
Witness and approve the checks, examinations and tests which are defined to be in
CONTRACTOR’s scope of work in this Inspection & Test Plan.
Interpret, evaluate and submit the results.
M-Monitoring Point: An identified point in the installation work during which an activity,
work or function is observed by the Engineer. Formal notice is not required to be given.:
To monitor work in progress without notice to SUBCONTRACTOR
CP N-05 : Building and Civil Engineering Work for Depot Building Including
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)
advance. Inspection or test shall not be carried out without the QA/QC organization
representative in attendance
Drawing / Procedure
; Sub -Contractor QC
Inspection/Test
REJECT
Accept
Next Works
SUBCONTRACTOR shall formally request the relevant parties to the witness inspection
of the items marked as W (Witness) and H (Hold Point) in the column of Attachment 1 of
this Inspection & Test Plan. Notice for Inspection should be in writing detailing item to be
inspected, location, time and anticipated duration.
-
North-South Commuter Railway Extension Project
INSPECTION AND TEST PLAN FOR EARTHWORKS
VERIFICATION
Item Verifying
QUALITY CONTROL ACTIVITY APPLICABLE SPECIFICATIONS Remarks
No. Documents
SUBCONTRACTOR POSCO E&C ENGINEER
1.3 Ensure the IFC drawing is approved. Approved Drawing,Approved Method Statement H/S R R
1.4 Ensure the Earthwork Method Statement is approved. Approved Method Statement Approved Method Statement H/S R R
3.0 EARTHWORKS
3.1 Setting out Approved Method Statement Approved Method Statement H RI/W M
3.4 Classification and review of excavated materials Specification Laboratory Test and Record H/S R R
3.7 Final Fill Inspection/Final Level Check As per Design drawing,Approved Method Statement Survey Report H M M
4.1 Receiving Inspection of Soil/Backfill Materials As per Specification,Approved Method Statement Laboratory Test and Record H/S RI M
4.2 Receiving Inspection of Rocks/Aggregate Materials As per Specification,Approved Method Statement Laboratory Test and Record H/S RI M
LEGEND
Review R Hold Point H
Random Inspection RI Witness Point W
Monitoring M Submission S
CP N-05 : Building and Civil Engineering Work for Depot Building Including Date: 01-Dec-20
Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05) Rev. No.: Page: 1 of 1