Method Statement Welding
Method Statement Welding
Method Statement Welding
Description of
Task/ Activity: METHOD STATEMENT FOR PIPE WELDING AT POWER GENERATION
BUILDING.
Project Name:
Al Ba’itha Mine Infrastructure and Utilities
Document Reference:
DL Discipline
Engineer/Manager Review:
Position: Construction Manager Date:
Page 1 of 9
METHOD STATEMENT
Required:
Required:
Specific Identified
Residual Hazards:
(or refer to the task N/A
specific risk
assessment(s))
(i.e.: Confined Spaces/Abrasive Wheels/Working at Height/Plant Operators etc)
Specific Staff Training , crane operator, riggers
Requirements:
Fall Protection (i.e.: Guard Rails/Toe Boards/Brick Guards/Safety Harnesses/Exclusion Zones etc)
Measures:
(Where work at height cannot Exclusion zone with barricade , signage and flag man.
be eliminated - consider both
Personnel & Materials)
Hazardous (i.e.: Lubricants/Solvents/Flammable Materials/Refrigerants/Welding Gases etc)
Substances:
(Attach COSHH Assessments
and MSDS)
Very Toxic Harmful/ Corrosive Dangerous Oxidising Highly Explosive
Applicable: No No No No No No No
Page 2 of 9
METHOD STATEMENT
(Detail any limits on the loadings applicable to temporary plant/equipment or fixed elements of the
structure where the work is taking place.)
SWL's:
OTHER:
1: Coveralls
Emergency The duties, responsibilities, and names of employees assigned with rescue
Procedures: and medical tasks.
Page 3 of 9
METHOD STATEMENT
SAFETY:
Page 5 of 9
METHOD STATEMENT
Page 6 of 9
METHOD STATEMENT
SEQUENCE OF WORK
The following working sequences are to be followed in site.
1. Identify the materials and equipments in site.
2. Refer the drawings and ensure the proper locations and
dimensions by concerned engineer.
3. Arrange all tools,materials and equipments orderly near to the work
area.The following tools and equipments to be used
a)welding machine
b)electrodes
c)grinder
d)pipe supports
e)spirit level f)right
angle g)measuring
tape h)permanent
marker i)argon
cylinder etc.
4. Prepare the pipes and other fittings as per approved drawings and
standards.
5. Start to fitup process as per approved welding procedure
specifications by qualified fabricators ,fitters and welders.
6. Check and ensure all welders and other technicians are qualified.
7. Monitor all welding and related works by approved supervisors and
qc inspector
8. Prepare all quality and related documents by qc inspector.
9. Coordinate with the owner and client inspectors or engineers for final
Page 7 of 9
METHOD STATEMENT
Prior to final installation, the mechanical discipline shall release the and
verifying the activities of bolting, chipping work and other cleaning.
Page 8 of 9
METHOD STATEMENT
Page 9 of 9