Method Statement Welding

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 9
At a glance
Powered by AI
The document discusses the method statement for pipe welding at a power generation building. It outlines the required equipment, materials, hazards, safety procedures, responsibilities and sequence of work.

Fire precautions like removing combustible materials within 35 feet, maintaining a fire watch and having a fire extinguisher available are mentioned. It also says not to cut or weld closed vessels that previously contained flammables without testing and cleaning them first.

The supervisor is responsible for ensuring workers are qualified and aware of hazards before starting work. They must also ensure all safety procedures are followed.

METHOD STATEMENT

Description of
Task/ Activity: METHOD STATEMENT FOR PIPE WELDING AT POWER GENERATION
BUILDING.

Project Name:
Al Ba’itha Mine Infrastructure and Utilities

Company: Ma’ameer General Contracting, MGC

Document Reference:

Reference Number Attached


Associated JSA
Yes No

Prepared By: Anand Subi

Position: Qc inspector Date:

Contractor Project Sumesh.G.P


Manager Review:
Position: Site Manager Date:

DL Discipline
Engineer/Manager Review:
Position: Construction Manager Date:

DL HSE Manager Review: George Kennedy

Position: HSE Manager Date:

WPF Review: HENRY

Position: HSE Manager Date:

Page 1 of 9
METHOD STATEMENT

Key Plant and Tools Chainblock,welding machines etc.

Required:

Key Materials N/A

Required:

(i.e.: access platforms, Lifting Ropes,Barricade,Signage,Flags,


Other Essential Winches, Chain block)
Equipment:

Specific Identified
Residual Hazards:
(or refer to the task N/A
specific risk
assessment(s))
(i.e.: Confined Spaces/Abrasive Wheels/Working at Height/Plant Operators etc)
Specific Staff Training , crane operator, riggers

Requirements:

(If none, state none.)


Temporary Supports
and Props needed to None
facilitate the works:

Method of Access and N/A

Egress to the work


area:

Fall Protection (i.e.: Guard Rails/Toe Boards/Brick Guards/Safety Harnesses/Exclusion Zones etc)

Measures:
(Where work at height cannot Exclusion zone with barricade , signage and flag man.
be eliminated - consider both
Personnel & Materials)
Hazardous (i.e.: Lubricants/Solvents/Flammable Materials/Refrigerants/Welding Gases etc)
Substances:
(Attach COSHH Assessments
and MSDS)
Very Toxic Harmful/ Corrosive Dangerous Oxidising Highly Explosive

Irritant for the flammable


environment

Applicable: No No No No No No No

Page 2 of 9
METHOD STATEMENT

(Detail any limits on the loadings applicable to temporary plant/equipment or fixed elements of the
structure where the work is taking place.)
SWL's:

OTHER:
1: Coveralls

Yes Yes Yes Yes No Yes

Required Personnel Safety Hard Hats Safety Hearing Respiratory Eye


Boots Gloves Protection Protection Protection
Protective Equip.: Yes
Yes Yes Yes Yes :
Yes

High Welder Face Shield Fall Arrest Disposable Goggles


Visibility Shield Mask

Emergency The duties, responsibilities, and names of employees assigned with rescue
Procedures: and medical tasks.

Name of On-Site First Aider: Umer

First Aid Box Location: Power Generation biulding

First Aid Facilities: Location of Nearest Hospital: Qiba Hospital

Other Information & Mechanical Engineer – Hamayoun Nawaz


Comments:
Communication methods : Face to Face - team briefings, meetings
and presentations.

Page 3 of 9
METHOD STATEMENT

1) All work will be undertaken by qualified competent persons


with experience of the type of work described above, and in all
cases in full accordance with safety procedures specified.

2) It is the responsibility of the supervisor to ensure prior to


giving any personnel the job of installation that they are fully
aware of the hazards involved and are competent to carry out
the work safely.

3) The supervisor must ensure that this procedure is


fully complied with.
3.1) All mechanical workers must check by a mechanical supervisor
before starting of any work.
3.2)All workers must also sign in on each piece of equipment before
doing any work on it. All required information must be entered legibly.
Users should request a replacement for full sign in sheets.

4) Site In Charge(Sumesh G.P) – has an ultimate responsibility of


compliance of work to, relevant methodologies, standards,
RESPONSIBILITIES
specifications listed, while assuring adequate organization
resources.
5) HSE Supervisor(Saiuj) – shall be responsible to implement
HSE Plan.
6) QA/QC Inspector(Anand) – responsible for the Inspection

Request (IR) preparation, 100% inspection activities and


ensure compliance with quality requirements and
specifications.
7) Field Engineer(H.Nawas) – ensure that all related works are

carried out in accordance with approved released for


construction drawings, specifications, schedule, quality and
safety. Reports to Site Manager
8) Fabricators– will do all the fabrication work as per approved

drawings and standards


9) Helpers- These are to assist the technicians for the technical

works ,cleaning etc.

10) Supervisor / Foreman(Umar,Afsal) – Supervise all


field installations and reports to Field Engineer.
Page 4 of 9
METHOD STATEMENT

11) Welders- the qualified welders will give production joints as


per approved welding procedure specification.
12) Ensure that Hoisting and Rigging accessories are free
from damage.

13 ) Provide third party inspection certificates for the welding


accessories.
14) Surveyors report is required for the level of foundation,
centre line etc.
15) All personnel must have competency certification cards to
be in date.
16) Users are required to clean up all chips, dirt, oil, etc.
produced during the use of any piece of equipment.
Compressed air shall not to be used to clean the machines.
17) Cleanup starts 15 minutes before the posted closing time.

SAFETY:

1. Every employee should be trained in work place safety.

2. To prevent accident sharpedges of materials, wooden or


metal lining should be properly handled.
3 Clamps to be used for piping welding must be suitable,
sufficient and fit for purpose.

4. When welding the all mechanical equipment must be


protected with flags, watch man barriers etc.

6. Concerned persons are allowed during welding..

7 The technicians working on top, must handle the parts


andtools
Carefully so as to prevent them to fall down.

8. All tools and equipment are to be returned to their proper location


before the user leaves the area.

9. No equipment is to be left running while physically


or mentally unattended

Page 5 of 9
METHOD STATEMENT

10. Any personal injuries are to be reported immediately. Those


giving first aid to others should use the gloves provided to protect
themselves from blood borne disease. All injuries must be reported
immediately. Depleted first aid supplies should also be reported
immediately.
11. No food or drink is permitted in the site. No audio equipment,
either with or without headsets may be operated in the lab.
12. Users must receive proper instruction on each piece of
equipment prior to using it for the first time. Typically, this will
occur in during a regularly scheduled training program.
13. Users must not undertake any actions that may injure or distract
other users or result in damage to equipment or the work of others

CUTTING AND WELDING PROCEDURES:


All cutting and welding operations performed at tuft by tuft
personnel or contractors must be carried out in accordance
with standards set forth by the American Welding Society and
the appropriate American National Standard institute standard
concerning cutting and welding.
Designated Areas should be barricaded.
Cutting and welding is only permitted by designated areas.
FIRE PRECAUTIONS
When cutting or welding outside a designated area, remove
the work to a safe location free of combustible materials if
possible.
If the work cannot be moved ,clear flammable materials and
rubbish from the area for about a 35 feet radius.
If these precautions are not feasible, shield or cover such
materials with fire resistive materials to protect them for
combustion.
Holes in the floor and walls must be covered to prevent sparks
from falling through unnoticed onto people or combustible
materials below.
Maintain a fire watch when doing this kind of work and have

Page 6 of 9
METHOD STATEMENT

a charged fire extinguisher readily available.


Do not cut or weld any closed vessel that has contained or has
suspected to have contained flammable or toxic materials until
it has been tested, thoroughly cleaned , purged and vented.
Traces of the material may still be in the vessel and result in a
fire or explosion ,or create a toxic exposure.
Accident Prevention
Common sense and safe working practice is the key to
accident prevention. If you are unsure about an
operation, request assistance.

SEQUENCE OF WORK
The following working sequences are to be followed in site.
1. Identify the materials and equipments in site.
2. Refer the drawings and ensure the proper locations and
dimensions by concerned engineer.
3. Arrange all tools,materials and equipments orderly near to the work
area.The following tools and equipments to be used
a)welding machine
b)electrodes
c)grinder
d)pipe supports
e)spirit level f)right
angle g)measuring
tape h)permanent
marker i)argon
cylinder etc.
4. Prepare the pipes and other fittings as per approved drawings and
standards.
5. Start to fitup process as per approved welding procedure
specifications by qualified fabricators ,fitters and welders.
6. Check and ensure all welders and other technicians are qualified.
7. Monitor all welding and related works by approved supervisors and
qc inspector
8. Prepare all quality and related documents by qc inspector.
9. Coordinate with the owner and client inspectors or engineers for final

Page 7 of 9
METHOD STATEMENT

inspection and keep all records as per client procedures.

INSTALLATION AND INSPECTION

Prior to final installation, the mechanical discipline shall release the and
verifying the activities of bolting, chipping work and other cleaning.

Each installation procedure shall follow the Inspection plan as per QC


document.The qc inspector is responsible for all qc documents to
submit and keep updated records.

Page 8 of 9
METHOD STATEMENT

I HAVE READ AND UNDERSTOOD THE METHOD STATEMENT


FOR THE WORK ACTIVITIES ABOVE

DATE TRADE NAME


PRINT SIGNATURE

RESPONSIBLE ENGINEER / SUPERVISOR

Page 9 of 9