Appendix N - Architectural Specifications Eng Revised
Appendix N - Architectural Specifications Eng Revised
CANADA
380 SUSSEX DRIVE, OTTAWA, ONTARIO
RETAIL STORE
RENOVATION-
CONSTRUCTION
SPECIFICATIONS – VOLUME 1
LIST OF SPECIFICATIONS
Pages
Division 01 - General Requirements
Section 01 11 00 – Summary of Work ..................................................................................... 2
Section 01 31 19 - Project Meetings ........................................................................................ 2
Section 01 32 16.06 - Construction Progress Schedule –Critical Path Method
(CPM) ................................................................................................................................................. 8
Section 01 33 00 - Submittal Procedures ............................................................................... 5
Section 01 35 29.06 - Health And Safety Requirements ................................................... 4
Section 01 41 00 – Regulatory Requirements ....................................................................... 1
Section 01 45 00 - Quality Control ............................................................................................ 2
Section 01 51 00 - Temporary Utilities..................................................................................... 2
Section 01 52 00 - Construction Facilities .............................................................................. 2
Section 01 56 00 - Temporary Barriers and Enclosures .................................................... 1
Section 01 61 00 - Common Product Requirements ........................................................... 4
Section 01 73 00 - Execution ...................................................................................................... 2
Section 01 74 11 - Cleaning ........................................................................................................ 2
Section 01 77 00 – Closeout Procedures................................................................................ 2
Section 01 78 00 – Closeout Submittals ................................................................................. 7
Division 02 - Existing Conditions
Section 02 41 99 - Demolition .................................................................................................... 2
Division 05 – Metals
Section 05 50 00 – Metal Fabrications..................................................................................... 5
Division 06 - Wood and Plastics
Section 06 08 99 – Rough Carpentry for Minor Works ....................................................... 3
Section 06 20 00 – Finish Carpentry ........................................................................................ 6
Section 06 40 00 – Architectural Woodwork .......................................................................... 8
Section 06 47 00 – Plastic Laminate Finishing...................................................................... 4
Section 06 61 19 – Quartz Surfacing Fabrications ............................................................... 2
Division 07 - Thermal and Moisture Protection
Section 07 84 00 – Fire Stopping .............................................................................................. 5
Section 07 92 00 - Joint Sealants.............................................................................................. 5
Table of contents ‐ Section 00 01 10
Retail Store Renovation ‐ Construction
Division 08 - Openings
Section 08 11 00 – Metal Doors and Frames ........................................................................ 5
Section 08 14 16 – Flush Wood Doors .................................................................................... 4
Section 08 31 00 – Access Doors ............................................................................................. 1
Section 08 33 36 – Side Coiling Grilles ................................................................................... 4
Section 08 70 05 – Cabinet and Miscellaneous Hardware ................................................ 4
Section 08 71 00 – Door Hardware........................................................................................... 6
Section 08 80 50 - Glazing .......................................................................................................... 3
Section 08 87 53 – Architectural Window Films .................................................................... 4
Division 09 - Finishes
Section 09 21 99 – Partitions for Minor Works ...................................................................... 6
Section 09 23 00 – Gypsum Plastering (Honed Concrete) ............................................... 6
Section 09 30 13 – Ceramic Tiling ............................................................................................ 4
Section 09 51 99 – Acoustical Ceilings for Minor Works .................................................... 4
Section 09 64 29 – Wood Strip and Plank Flooring ............................................................. 4
Section 09 65 99 – Resilient Flooring for Minor Works....................................................... 3
Section 09 68 16 – Sheet Carpeting ......................................................................................... 7
Section 09 91 99 – Painting for Minor Works......................................................................... 6
Table of contents ‐ Section 00 01 10
Retail Store Renovation ‐ Construction
END OF TABLE
Summary of Work‐ Section 01 11 00
Retail Store Renovation ‐ Construction
Part 1 General
P a g e 1 | 2
Summary of Work‐ Section 01 11 00
Retail Store Renovation ‐ Construction
.2 Where unknown services are encountered, immediately advise Consultant and
confirm findings in writing.
.3 Construct barriers in accordance with Section 01 56 00 - Temporary Barriers and
Enclosures.
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 2 | 2
Project Meetings ‐ Section 01 31 19
Retail Store Renovation ‐ Construction
Part 1 General
1.1 ADMINISTRATIVE
.1 Contractor to schedule and administer project meetings throughout the progress
of the work.
.2 Contractor to prepare agenda for meetings.
.3 Contractor to distribute written notice of each meeting four days in advance of
meeting date.
.4 Contractor to preside at meetings.
.5 Contractor to record the meeting minutes. Include significant proceedings and
decisions. Identify actions by parties.
.6 Contractor to reproduce and distribute copies of minutes within three days after
meetings and transmit to meeting participants affected parties not in attendance.
.7 Representative of Contractor, Subcontractor and suppliers attending meetings
will be qualified and authorized to act on behalf of party each represents.
.8 National Gallery of Canada to provide progress meeting room space.
.9 Contractor’s office to be located within the hoarded and construction area.
P a g e 1 | 2
Project Meetings ‐ Section 01 31 19
Retail Store Renovation ‐ Construction
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 2 | 2
Construction Progress Schedule – Critical Path Method (CPM) ‐ Section 01 32 16.06
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Definitions:
.1 Activity: element of Work performed during course of Project. Activity
normally has expected duration, and expected cost and expected
resource requirements. Activities can be subdivided into tasks.
.2 Bar Chart (Gantt chart): graphic display of schedule-related information.
In typical bar chart, activities or other Project elements are listed down left
side of chart, dates are shown across top, and activity durations are
shown as date-placed horizontal bars.
.3 Baseline: original approved plan (for Project, work package, or activity),
plus or minus approved scope changes.
.4 Cash Flow: projection of progress payment requests based on cash
loaded construction schedule.
.5 Completion Milestones: they are firstly Substantial Completion and
secondly Final Certificate.
.6 Constraint: applicable restriction or limitation, either internal or external to
project, that will affect performance of Project. Factors that affect activities
can be scheduled.
.7 Control: process of comparing actual performance with planned
performance, analyzing variances, evaluating possible alternatives, and
taking appropriate corrective action as needed.
.8 Critical Activity: any activity on a critical path.
.1 Most commonly determined by using critical path method.
.9 Critical Path: sequence of activities that determines duration of Project.
Generally, it is the longest path through Project.
.1 Usually defined as those activities with float less than or equal to
specified value, often zero.
.10 Critical Path Method (CPM): network analysis technique used to
determine the amount of scheduling flexibility (amount of float) on various
logical network paths in Project schedule network, and to determine the
minimum total Project duration.
.11 Data Date: date through which project status and progress were last
determined and reported for analyses, such as scheduling and
performance measurements.
.12 Duration: total number of work periods (not including holidays or other
non-working periods) required to complete activity or other Project
element.
.1 Usually expressed as workdays or work weeks.
P a g e 1 | 8
Construction Progress Schedule – Critical Path Method (CPM) ‐ Section 01 32 16.06
Retail Store Renovation ‐ Construction
.13 Early Finish Date: in critical path method, earliest possible point in time on
which uncompleted portions of activity (or Project) can finish, based on
network logic and schedule constraints.
.1 Early finish dates can change as Project progresses and changes
are made to Project plan.
.14 Early Start Date: in critical path method, earliest possible point in time on
which uncompleted portions of activity (or Project) can start, based on
network logic and schedule constraints.
.1 Early start dates can change as Project progresses and changes
are made to Project Plan.
.15 Finish Date: point in time associated with activity's completion.
.1 Usually qualified by one of following: actual, planned, estimated,
scheduled, early, late, baseline, target, or current.
.16 Float: amount of time that activity may be delayed from its early start
without delaying Project finish date.
.1 This resource is available to both the NGC and Contractor.
.17 Impact Analysis: schedule analysis technique that adds a modeled delay
to an accepted construction schedule to determined possible outcome of
that delay on project completion.
.18 Lag: modification of logical relationship that directs delay in successor
activity.
.19 Late Finish Date (LF): in critical path method, latest possible point in time
that activity may be completed without delaying specified milestone
(usually Project finish date).
.20 Late Start Date (LS): in critical path method, latest possible point in time
that activity may begin without delaying specified milestone (usually
Project finish date).
.21 Lead: modification of logical relationship that allows acceleration of
successor task.
.22 Logic Diagram: see Project network diagram.
.23 Master Schedule: summary-level schedule that identifies major
deliverable; work breakdowns structure and key milestones.
.24 Milestone: significant point or event in Project, usually completion of
major deliverable.
.25 Monitoring: capture, analysis, and reporting of Project performance,
usually as compared to plan.
.26 Non-Critical Activities: activities which when delayed, do not affect
specified Contract duration.
.27 Project Control System: fully computerized system utilizing commercially
available software packages.
.28 Project Network Diagram: schematic display of logical relationships of
Project activities.
.1 Always drawn from left to right to reflect Project chronology.
P a g e 2 | 8
Construction Progress Schedule – Critical Path Method (CPM) ‐ Section 01 32 16.06
Retail Store Renovation ‐ Construction
.29 Project Plan: formal, approved document used to guide both Project
execution and Project control.
.1 Primary uses of Project plan are to document planning
assumptions and decisions, facilitate communication among
stakeholders, and document approved scope, cost, and schedule
baselines.
.2 Project plan may be summary or detailed.
.30 Project Planning: development and maintenance of Project Plan.
.31 Project Planning, Monitoring and Control System: overall system
operated to enable monitoring of Project Work in relation to established
milestones.
.32 Project Schedule: planned dates for performing activities and planned
dates for meeting milestones.
.33 Quantified days duration: working days based on 5 day work week,
discounting statutory holidays.
.34 Risk: uncertain event or condition that, if it occurs, has positive or
negative effect on Project's objectives.
.35 Start Date: point in time associated with activity's start, usually qualified
by one of following: actual, planned, estimated, scheduled, early, late,
target, baseline, or current.
.36 Work Breakdown Structure (WBS): deliverable-oriented hierarchical
decomposition of Work to be executed by contractor to accomplish
project objectives and create required deliverables. It organizes and
defines total scope of Project. Each descending level represents an
increasingly detailed definition of Project Work. WBS is decomposed into
Work packages.
P a g e 3 | 8
Construction Progress Schedule – Critical Path Method (CPM) ‐ Section 01 32 16.06
Retail Store Renovation ‐ Construction
P a g e 4 | 8
Construction Progress Schedule – Critical Path Method (CPM) ‐ Section 01 32 16.06
Retail Store Renovation ‐ Construction
1.3 SUBMITTALS
.1 Submit in accordance with Section 01 33 00 - Submittal Procedures.
.2 Submit to Consultant Project Control System for planning, scheduling, monitoring
and reporting of project progress.
.3 Submit Project Control System to Consultant for approval.
.1 Failure to comply with each required submission, may result in progress
payment being withheld in accordance with Federal Government's GC 5
Terms of Payment.
.4 Include costs for execution, preparation and reproduction of schedule submittals
in bid documents.
.5 Submit letter ensuring that schedule has been prepared in co-ordination with
major sub-contractors.
.6 Refer to article "PROGRESS MONITORING AND REPORTING" of this
specification Section for frequency of Project control system submittals.
.7 Submit impact analysis of schedule for changes that result in extension of
contract duration.
.1 Include draft schedule update and report as outlined in article
"PROGRESS MONITORING AND REPORTING".
.8 Submit Project planning, monitoring and control system data as part of initial
schedule submission and monthly status reporting in following form.
.1 Master Schedule Bar Chart.
.2 Construction Detail schedule Bar Chart.
.3 Listing of project activities including milestones and logical connectors,
networks (sub-networks) from Project start to end. Sort activities by
activity identification number and accompany with descriptions. List early
and late start and finish dates together with durations, codes and float.
.4 Criticality report listing activities and milestones with zero total float used
as first sort for ready identification of critical paths through entire project.
List early and late starts and finishes dates, together with durations,
codes and float for critical activities.
P a g e 5 | 8
Construction Progress Schedule – Critical Path Method (CPM) ‐ Section 01 32 16.06
Retail Store Renovation ‐ Construction
.5 Progress report in early start sequence, listing for each trade, activities or
finished within 2 months from monthly update date. List activity
identification number, description and duration. Provide columns for entry
of actual start and finish dates, duration remaining and remarks
concerning action required.
P a g e 6 | 8
Construction Progress Schedule – Critical Path Method (CPM) ‐ Section 01 32 16.06
Retail Store Renovation ‐ Construction
.3 Approvals.
.4 Procurement.
.5 Construction.
.6 Installation.
.7 Site works.
.8 Testing.
.9 Commissioning and acceptance.
.2 Relate Detail Schedule activities to basic activities and milestones developed and
approved in Master Schedule.
.3 Clearly show sequence and interdependence of construction activities and
indicate:
.1 Start and completion of all items of Work, their major components, and
interim milestone completion dates.
.2 Activities for procurement, delivery, installation and completion of each
major piece of equipment, materials and other supplies, including:
.1 Time for submittals, resubmittals and review.
.2 Time for fabrication and delivery of manufactured products for
Work.
.3 Interdependence of procurement and construction activities.
.3 Include sufficient detail to assure adequate planning and execution of
Work. Activities should generally range in duration from 3 to 15 workdays
each.
.4 Provide level of detail for project activities such that sequence and
interdependency of Contract tasks are demonstrated and allow co-ordination and
control of project activities. Show continuous flow from left to right.
.5 Ensure activities with no float are calculated and clearly indicated on logical CPM
construction network system as being, whenever possible, continuous series of
activities throughout length of Project to form "Critical Path". Increased number
of critical activities is seen as indication of increased risk.
.6 Insert Change Orders in appropriate and logical location of Detail Schedule. After
analysis, clearly state and report to Consultant for review effects created by
insertion of new Change Order.
P a g e 7 | 8
Construction Progress Schedule – Critical Path Method (CPM) ‐ Section 01 32 16.06
Retail Store Renovation ‐ Construction
.3 Perform Detail Schedule update monthly with status dated (Data Date) on last
working day of month. Update to reflect activities completed to date, activities in
progress, logic and duration changes.
.4 Do not automatically update actual start and finish dates by using default
mechanisms found in project management software.
.5 Submit to Consultant copies of updated Detail Schedule.
.6 Requirements for monthly progress monitoring and reporting are basis for
progress payment request.
.7 Submit monthly written report based on Detail Schedule, showing Work to date
performed, comparing Work progress to planned, and presenting current
forecasts. Report must summarize progress, defining problem areas and
anticipated delays with respect to Work schedule, and critical paths. Explain
alternatives for possible schedule recovery to mitigate any potential delay.
Include in report:
.1 Description of progress made.
.2 Pending items and status of: shop drawings,.
.3 Status of Contract completion date and milestones.
.4 Current and anticipated problem areas, potential delays and corrective
measures.
.5 Review of progress and status of Critical Path activities.
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 8 | 8
Submittal Procedures ‐ Section 01 33 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 ADMINISTRATIVE
.1 Submit to Consultant submittals listed for review. Submit promptly and in orderly
sequence to not cause delay in Work. Failure to submit in ample time is not
considered sufficient reason for extension of Contract Time and no claim for
extension by reason of such default will be allowed.
.2 Do not proceed with Work affected by submittal until review is complete.
.3 Present shop drawings, product data, samples and mock-ups in SI Metric units.
.4 Where items or information is not produced in SI Metric units converted values
are acceptable.
.5 Review submittals prior to submission to Consultant. This review represents that
necessary requirements have been determined and verified, or will be, and that
each submittal has been checked and coordinated with requirements of Work
and Contract Documents. Submittals not stamped, signed, dated and identified
as to specific project will be returned without being examined and considered
rejected.
.6 Notify Consultant, in writing at time of submission, identifying deviations from
requirements of Contract Documents stating reasons for deviations.
.7 Verify field measurements and affected adjacent Work are coordinated.
.8 Contractor's responsibility for errors and omissions in submission is not relieved
by Consultant's review of submittals.
.9 Contractor's responsibility for deviations in submission from requirements of
Contract Documents is not relieved by Consultant review.
.10 Keep one reviewed copy of each submission on site.
P a g e 1 | 5
Submittal Procedures ‐ Section 01 33 00
Retail Store Renovation ‐ Construction
P a g e 2 | 5
Submittal Procedures ‐ Section 01 33 00
Retail Store Renovation ‐ Construction
P a g e 3 | 5
Submittal Procedures ‐ Section 01 33 00
Retail Store Renovation ‐ Construction
.1 This review shall not mean that Consultant approves detail design
inherent in shop drawings, responsibility for which shall remain with
Contractor submitting same, and such review shall not relieve Contractor
of responsibility for errors or omissions in shop drawings or of
responsibility for meeting requirements of construction and Contract
Documents.
.2 Without restricting generality of foregoing, Contractor is responsible for
dimensions to be confirmed and correlated at job site, for information that
pertains solely to fabrication processes or to techniques of construction
and installation and for co-ordination of Work of sub-trades.
1.3 SAMPLES
.1 Submit for review samples in duplicate as requested in respective specification
Sections. Label samples with origin and intended use.
.2 Deliver samples prepaid to Consultant's business address.
.3 Notify Consultant in writing, at time of submission of deviations in samples from
requirements of Contract Documents.
.4 Where colour, pattern or texture is criterion, submit full range of samples.
.5 Adjustments made on samples by Consultant are not intended to change
Contract Price. If adjustments affect value of Work, state such in writing to
Consultant prior to proceeding with Work.
.6 Make changes in samples which Consultant may require, consistent with
Contract Documents.
.7 Reviewed and accepted samples will become standard of workmanship and
material against which installed Work will be verified.
1.4 MOCK-UPS
.1 Erect mock-ups in accordance with 01 45 00 - Quality Control.
P a g e 4 | 5
Submittal Procedures ‐ Section 01 33 00
Retail Store Renovation ‐ Construction
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 5 | 5
Health and Safety Requirements ‐ Section 01 35 29.06
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Canada Labour Code, Part 2, Canada Occupational Safety and Health
Regulations
.2 Province of Ontario
.1 Occupational Health and Safety Act and Regulations for Construction
Projects, R.S.O. 1991, as amended by O. Reg. 252/142005
1.2 SUBMITTALS
.1 Submit in accordance with Section 01 33 00 - Submittal Procedures.
.2 Submit site-specific Health and Safety Plan: Within 7 days after date of contract
award and prior to commencement of Work. Health and Safety Plan must
include:
.1 Results of site specific safety hazard assessment.
.2 Results of safety and health risk or hazard analysis for site tasks and
operation found in work plan.
.3 Submit 2 copies of Contractor's authorized representative's work site health and
safety inspection reports to authority having jurisdiction.
.4 Submit copies of reports or directions issued by Federal, Provincial and
Territorial health and safety inspectors.
.5 Submit copies of incident and accident reports.
.6 Consultant will review Contractor's site-specific Health and Safety Plan and
provide comments to Contractor within 7 days after receipt of plan. Revise plan
as appropriate and resubmit plan to Consultant within 5 days after receipt of
comments from Consultant.
.7 Consultant's review of Contractor's final Health and Safety plan should not be
construed as approval and does not reduce the Contractor's overall responsibility
for construction Health and Safety.
.8 On-site Contingency and Emergency Response Plan: address standard
operating procedures to be implemented during emergency situations.
P a g e 1 | 4
Health and Safety Requirements ‐ Section 01 35 29.06
Retail Store Renovation ‐ Construction
1.6 MEETINGS
.1 Schedule and administer Health and Safety meeting with Consultant prior to
commencement of Work.
1.9 RESPONSIBILITY
.1 Be responsible for health and safety of persons on site, safety of property on site
and for protection of persons adjacent to site and environment to extent that they
may be affected by conduct of Work.
.2 Contractor will be responsible and assume the role Constructor as described in
the Ontario Occupational Health and Safety Act and Regulations for Construction
Projects.
.3 Comply with and enforce compliance by employees with safety requirements of
Contract Documents, applicable federal, provincial, territorial and local statutes,
regulations, and ordinances, and with site-specific Health and Safety Plan.
P a g e 2 | 4
Health and Safety Requirements ‐ Section 01 35 29.06
Retail Store Renovation ‐ Construction
1.14 BLASTING
.1 Blasting or other use of explosives is not permitted.
P a g e 3 | 4
Health and Safety Requirements ‐ Section 01 35 29.06
Retail Store Renovation ‐ Construction
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 4 | 4
Regulatory Requirements ‐ Section 01 41 00
Retail Store Renovation ‐ Construction
Part 1 General
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 1 | 1
Quality Control ‐ Section 01 45 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 INSPECTION
.1 Allow Consultant access to Work. If part of Work is in preparation at locations
other than Place of Work, allow access to such Work whenever it is in progress.
.2 Give timely notice requesting inspection if Work is designated for special tests,
inspections or approvals by Consultant, instructions or law of Place of Work.
.3 If Contractor covers or permits to be covered Work that has been designated for
special tests, inspections or approvals before such is made, uncover such Work,
have inspections or tests satisfactorily completed and make good such Work.
.4 Consultant will order part of Work to be examined if Work is suspected to be not
in accordance with Contract Documents. If, upon examination such work is found
not in accordance with Contract Documents, correct such Work and pay cost of
examination and correction.
1.3 PROCEDURES
.1 Notify appropriate agency and Consultant in advance of requirement for tests, in
order that attendance arrangements can be made.
.2 Submit samples and/or materials required for testing, as specifically requested in
specifications. Submit with reasonable promptness and in orderly sequence to
not cause delays in Work.
.3 Provide labour and facilities to obtain and handle samples and materials on site.
Provide sufficient space to store and cure test samples.
1.5 REPORTS
.1 Submit 4 copies of inspection and test reports to Consultant.
.2 Provide copies to manufacturer or fabricator of material being inspected or
tested.
P a g e 1 | 2
Quality Control ‐ Section 01 45 00
Retail Store Renovation ‐ Construction
1.6 TESTS AND MIX DESIGNS
.1 Furnish test results and mix designs as requested.
.2 Cost of tests and mix designs beyond those called for in Contract Documents or
beyond those required by law of Place of Work will be appraised by Consultant
and may be authorized as recoverable.
1.7 MOCK-UPS
.1 Prepare mock-ups for Work specifically requested in specifications. Include for
Work of Sections required to provide mock-ups.
.2 Construct in locations as specified in specific Section.
.3 Prepare mock-ups for Consultant review with reasonable promptness and in
orderly sequence, to not cause delays in Work.
.4 Failure to prepare mock-ups in ample time is not considered sufficient reason for
extension of Contract Time and no claim for extension by reason of such default
will be allowed.
.5 Specification section identifies whether mock-up may remain as part of Work or if
it is to be removed and when.
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 2 | 2
Temporary Utilities ‐ Section 01 51 00
Retail Store Renovation ‐ Construction
Part 1 General
P a g e 1 | 2
Temporary Utilities ‐ Section 01 51 00
Retail Store Renovation ‐ Construction
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 2 | 2
Construction Facilities ‐ Section 01 52 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 SUBMITTALS
.1 Provide submittals in accordance with Section 01 33 00 - Submittal Procedures.
P a g e 1 | 2
Construction Facilities ‐ Section 01 52 00
Retail Store Renovation ‐ Construction
.4 Contractor's traffic on roads selected for hauling material to and from site to
interfere as little as possible with regular traffic.
.5 Verify adequacy of existing roads and allowable load limit on these roads.
Contractor: responsible for repair of damage to roads caused by construction
operations.
.6 Provide necessary lighting, signs, barricades, and distinctive markings for safe
movement of traffic.
1.8 CLEAN-UP
.1 Remove construction debris, waste materials, packaging material from work site
daily.
.2 Clean dirt or mud tracked onto paved or surfaced roadways.
.3 Store materials resulting from demolition activities that are salvageable.
.4 Stack stored new or salvaged material not in construction facilities.
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 2 | 2
Temporary Barriers and Enclosures ‐ Section 01 56 00
Retail Store Renovation ‐ Construction
Part 1 General
1.2 HOARDING
.1 Erect temporary hoarding as indicated.
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 1 | 1
Common Product Requirements ‐ Section 01 61 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Conform to these reference standards, in whole or in part as specifically
requested in specifications.
1.2 QUALITY
.1 Products, materials, equipment and articles incorporated in Work shall be new,
not damaged or defective, and of best quality for purpose intended. If requested,
furnish evidence as to type, source and quality of products provided.
.2 Procurement policy is to acquire, in cost effective manner, items containing
highest percentage of recycled and recovered materials practicable consistent
with maintaining satisfactory levels of competition. Make reasonable efforts to
use recycled and recovered materials and in otherwise utilizing recycled and
recovered materials in execution of work.
.3 Defective products, whenever identified prior to completion of Work, will be
rejected, regardless of previous inspections. Inspection does not relieve
responsibility, but is precaution against oversight or error. Remove and replace
defective products at own expense and be responsible for delays and expenses
caused by rejection.
.4 Unless otherwise indicated in specifications, maintain uniformity of manufacture
for any particular or like item throughout building.
.5 Permanent labels, trademarks and nameplates on products are not acceptable in
prominent locations, except where required for operating instructions, or when
located in mechanical or electrical rooms.
1.3 AVAILABILITY
.1 Immediately upon signing Contract, review product delivery requirements and
anticipate foreseeable supply delays for items. If delays in supply of products are
foreseeable, notify Consultant of such, in order that substitutions or other
remedial action may be authorized in ample time to prevent delay in performance
of Work.
.2 In event of failure to notify Consultant at commencement of Work and should it
subsequently appear that Work may be delayed for such reason, Consultant
reserves right to substitute more readily available products of similar character, at
no increase in Contract Price or Contract Time.
1.5 TRANSPORTATION
.1 Pay costs of transportation of products required in performance of Work.
.2 Transportation cost of products supplied by Owner will be paid for by Owner.
Unload, handle and store such products.
P a g e 2 | 4
Common Product Requirements ‐ Section 01 61 00
Retail Store Renovation ‐ Construction
1.8 CO-ORDINATION
.1 Ensure co-operation of workers in laying out Work. Maintain efficient and
continuous supervision.
.2 Be responsible for coordination and placement of openings, sleeves and
accessories.
1.9 CONCEALMENT
.1 In finished areas conceal pipes, ducts and wiring in floors, walls and ceilings,
except where indicated otherwise.
.2 Before installation inform Consultant if there is interference. Install as directed by
Consultant.
1.12 FASTENINGS
.1 Provide metal fastenings and accessories in same texture, colour and finish as
adjacent materials, unless indicated otherwise.
.2 Prevent electrolytic action between dissimilar metals and materials.
.3 Use non-corrosive hot dip galvanized steel fasteners and anchors for securing
exterior work, unless stainless steel or other material is specifically requested in
affected specification Section.
.4 Space anchors within individual load limit or shear capacity and ensure they
provide positive permanent anchorage. Wood, or any other organic material
plugs are not acceptable.
.5 Keep exposed fastenings to a minimum, space evenly and install neatly.
P a g e 3 | 4
Common Product Requirements ‐ Section 01 61 00
Retail Store Renovation ‐ Construction
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 4 | 4
Execution ‐ Section 01 73 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 SUBMITTALS
.1 Submittals: in accordance with Section 01 33 00 - Submittal Procedures.
.2 Submit written request in advance of cutting or alteration which affects:
.1 Structural integrity of elements of project.
.2 Efficiency, maintenance, or safety of operational elements.
.3 Visual qualities of sight-exposed elements.
.4 Work of Owner or separate contractor.
.3 Include in request:
.1 Identification of project.
.2 Location and description of affected Work.
.3 Statement on necessity for cutting or alteration.
.4 Description of proposed Work, and products to be used.
.5 Alternatives to cutting and patching.
.6 Effect on Work of Owner or separate contractor.
.7 Written permission of affected separate contractor.
.8 Date and time work will be executed.
1.2 MATERIALS
.1 Required for original installation.
.2 Change in Materials: Submit request for substitution in accordance with Section
01 33 00 - Submittal Procedures.
1.3 PREPARATION
.1 Inspect existing conditions, including elements subject to damage or movement
during cutting and patching.
.2 After uncovering, inspect conditions affecting performance of Work.
.3 Beginning of cutting or patching means acceptance of existing conditions.
.4 Provide supports to assure structural integrity of surroundings; provide devices
and methods to protect other portions of project from damage.
.5 Provide protection from elements for areas which are to be exposed by
uncovering work; maintain excavations free of water.
1.4 EXECUTION
.1 Execute cutting, fitting, and patching to complete Work.
.2 Fit several parts together, to integrate with other Work.
P a g e 1 | 2
Execution ‐ Section 01 73 00
Retail Store Renovation ‐ Construction
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 2 | 2
Cleaning‐ Section 01 74 11
Retail Store Renovation ‐ Construction
Part 1 General
P a g e 1 | 2
Cleaning‐ Section 01 74 11
Retail Store Renovation ‐ Construction
.7 Clean and polish glass, mirrors, hardware, wall tile, stainless steel, chrome,
porcelain enamel, baked enamel, plastic laminate, and mechanical and electrical
fixtures. Replace broken, scratched or disfigured glass.
.8 Remove stains, spots, marks and dirt from decorative work, electrical and
mechanical fixtures, furniture fitments, walls, floors.
.9 Clean lighting reflectors, lenses, and other lighting surfaces.
.10 Vacuum clean and dust building interiors, behind grilles, louvres and screens.
.11 Wax, seal, shampoo or prepare floor finishes, as recommended by manufacturer.
.12 Inspect finishes, fitments and equipment and ensure specified workmanship and
operation.
.13 Clean equipment and fixtures to sanitary condition; clean or replace filters of
mechanical equipment.
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 2 | 2
Closeout Procedures ‐ Section 01 77 00
Retail Store Renovation ‐ Construction
Part 1 General
P a g e 1 | 2
Closeout Procedures ‐ Section 01 77 00
Retail Store Renovation ‐ Construction
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 2 | 2
Closeout Submittals ‐ Section 01 78 00
Retail Store Renovation ‐ Construction
Part 1 General
1.2 FORMAT
.1 Organize data as instructional manual.
.2 Binders: vinyl, hard covered, 3 'D' ring, loose leaf 219 x 279 mm with spine and
face pockets.
.3 When multiple binders are used correlate data into related consistent groupings.
.1 Identify contents of each binder on spine.
.4 Cover: identify each binder with type or printed title 'Project Record Documents';
list title of project and identify subject matter of contents.
.5 Arrange content by systems, under Section numbers and sequence of Table of
Contents.
.6 Provide tabbed fly leaf for each separate product and system, with typed
description of product and major component parts of equipment.
.7 Text: manufacturer's printed data, or typewritten data.
.8 Drawings: provide with reinforced punched binder tab.
.1 Bind in with text; fold larger drawings to size of text pages.
P a g e 1 | 7
Closeout Submittals ‐ Section 01 78 00
Retail Store Renovation ‐ Construction
P a g e 2 | 7
Closeout Submittals ‐ Section 01 78 00
Retail Store Renovation ‐ Construction
P a g e 3 | 7
Closeout Submittals ‐ Section 01 78 00
Retail Store Renovation ‐ Construction
Part 2 Products
Part 3 Execution
END OF SECTION
P a g e 7 | 7
Demolition ‐ Section 02 41 99
Retail Store Renovation ‐ Construction
Part 1 General
Part 2 Products
Part 3 Execution
3.1 EXAMINATION
.1 Inspect site with Consultant and verify extent and location of items designated for
removal, disposal, alternative disposal, recycling, salvage and items to remain.
.2 Locate and protect utilities. Preserve active utilities traversing site in operating
condition.
.3 Notify and obtain approval of utility companies before starting demolition.
.4 Disconnect, cap, plug or divert, as required, existing public utilities within the
property where they interfere with the execution of the work, in conformity with
the requirements of the authorities having jurisdiction. Mark the location of these
and previously capped or plugged services on the site and indicate location
(horizontal and vertical) on the record drawings. Support, shore up and maintain
pipes and conduits encountered.
.1 Immediately notify Consultant and utility company concerned in case of
damage to any utility or service
.2 Immediately notify the Consultant should uncharted utility or service be
encountered, and await instruction in writing regarding remedial action.
3.2 PREPARATION
.1 Protection of In-Place Conditions:
P a g e 1 | 2
Demolition ‐ Section 02 41 99
Retail Store Renovation ‐ Construction
3.3 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
END OF SECTION
P a g e 2 | 2
Metal Fabrications‐ Section 05 50 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Health Canada / Workplace Hazardous Materials Information System (WHMIS)
.1 Material Safety Data Sheets (MSDS).
Part 2 Products
2.1 MATERIALS
.1 Steel sections and plates: to CSA G40.20/G40.21, Grade 350W.
.2 Welding materials: to CSA W59.
.3 Welding electrodes: to CSA W48 Series.
.4 Bolts and anchor bolts: to ASTM A307.
P a g e 1 | 5
Metal Fabrications‐ Section 05 50 00
Retail Store Renovation ‐ Construction
.5 Stainless steel plate: to ASTM A480/A480M-15, Type 304. Brushed satin finish.
2.2 FABRICATION
.1 Fabricate work square, true, straight and accurate to required size, with joints
closely fitted and properly secured.
.2 Use self-tapping shake-proof flat headed screws on items requiring assembly by
screws or as indicated.
.3 Where possible, fit and shop assemble work, ready for erection.
.4 Ensure exposed welds are continuous for length of each joint. File or grind
exposed welds smooth and flush.
2.3 FINISHES
.1 Powder coat finish to all steel except stainless steel.
.2 Powder coat colours as indicated on drawings.
P a g e 2 | 5
Metal Fabrications‐ Section 05 50 00
Retail Store Renovation ‐ Construction
2.12 ACCESSORIES
.1 Standard, special, top display, box and postcard shelving: Folded metal, size and
thickness as detailed. Powder coated finish.
.2 Rear support bars, prongs and straight arms: Size and thickness as detailed.
Powder coated finish.
.3 Display tray: Folded stainless steel. Size and thickness as detailed. Brushed
satin finish.
.4 Pegboards: Folded metal panel. Size and thickness as detailed. Provide punched
holes and integrated brackets. Powder coated finish.
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously installed
under other Sections or Contracts are acceptable for metal fabrications
installation in accordance with manufacturer's written instructions.
P a g e 3 | 5
Metal Fabrications‐ Section 05 50 00
Retail Store Renovation ‐ Construction
3.2 ERECTION
.1 Do welding work in accordance with CSA W59 unless specified otherwise.
.2 Erect metalwork square, plumb, straight, and true, accurately fitted, with tight
joints and intersections.
.3 Provide suitable means of anchorage acceptable to Consultant such as dowels,
anchor clips, bar anchors, expansion bolts and shields, and toggles.
.4 Exposed fastening devices to match finish and be compatible with material
through which they pass.
.5 Supply components for work by other trades in accordance with shop drawings
and schedule.
.6 Deliver items over for casting into concrete and building into masonry together
with setting templates to appropriate location and construction personnel.
P a g e 4 | 5
Metal Fabrications‐ Section 05 50 00
Retail Store Renovation ‐ Construction
.2 Supply and install stainless steel, powder coated and black smoked metal at
table top display cases as detailed.
3.11 ACCESSORIES
.1 Supply and install standard, special, top display, box and postcard shelving c/w
brackets to fit into slotted uprights as detailed.
.2 Rear support bars, prongs and straight arms:
.1 Supply and install rear support bars, prongs and straight arms as
detailed. Rear support bars c/w brackets to fit into slotted uprights.
.3 Display trays:
.1 Supply and install metal display trays as detailed.
.4 Pegboards:
.1 Supply and install metal pegboards as detailed to fit into slotted uprights.
3.12 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and
equipment in accordance with Section 01 74 11 - Cleaning.
3.13 PROTECTION
.1 Protect installed products and components from damage during construction.
.2 Repair damage to adjacent materials caused by metal fabrications installation.
END OF SECTION
P a g e 5 | 5
Rough Carpentry for Minor Works ‐ Section 06 08 99
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 CSA International
.1 CSA B111-1974(R2003), Wire Nails, Spikes and Staples.
.2 CSA O121-08, Douglas Fir Plywood.
.3 CAN/CSA-Z809-08, Sustainable Forest Management.
.2 National Lumber Grades Authority (NLGA)
.1 Standard Grading Rules for Canadian Lumber 2010.
P a g e 1 | 3
Rough Carpentry for Minor Works ‐ Section 06 08 99
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Lumber: unless specified otherwise, softwood, S4S, moisture content 19% or
less in accordance with following standards:
.1 CAN/CSA-O141.
.2 NLGA Standard Grading Rules for Canadian Lumber.
.2 Furring, blocking, nailing strips:
.1 S2S is acceptable for blocking and accessories support.
.2 Board sizes: "Standard" or better grade.
.3 Dimension sizes: "Standard" light framing or better grade.
.3 Panel Materials:
.1 Douglas fir plywood (DFP): to CSA O121, standard construction.
.1 Urea-formaldehyde free.
2.2 ACCESSORIES
.1 Nails, spikes and staples: to CSA B111.
.2 Bolts: 12.5 mm diameter unless indicated otherwise, complete with nuts and
washers.
.3 Proprietary fasteners: toggle bolts, expansion shields and lag bolts, screws and
lead or inorganic fibre plugs, explosive actuated fastening devices,
recommended for purpose by manufacturer.
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously installed
under other Sections or Contracts are acceptable for rough carpentry installation
in accordance with manufacturer's written instructions.
.1 Visually inspect substrate in presence of Consultant.
.2 Inform Consultant of unacceptable conditions immediately upon
discovery.
.3 Proceed with installation only after unacceptable conditions have been
remedied .
3.2 INSTALLATION
.1 Comply with requirements of NBC, supplemented by the following paragraphs.
P a g e 2 | 3
Rough Carpentry for Minor Works ‐ Section 06 08 99
Retail Store Renovation ‐ Construction
3.3 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and
equipment in accordance with Section 01 74 11 - Cleaning.
END OF SECTION
P a g e 3 | 3
Finish Carpentry ‐ Section 06 20 00
Retail Store Renovation ‐ Construction
Part 1 General
1.2 REFERENCES
.1 American National Standards Institute (ANSI)
.1 ANSI A208.2-09, Medium Density Fibreboard (MDF) for Interior
Applications.
.2 ANSI/HPVA HP-1-10, American National Standard for Hardwood
and Decorative Plywood.
.2 Architectural Woodwork Manufacturers Association of Canada (AWMAC)
and Architectural Woodwork Institute (AWI)
.1 Architectural Woodwork Quality Standards, 1st edition, 2009.
.3 Canadian General Standards Board (CGSB)
.1 CAN/CGSB-11.3-M87, Hardboard.
.4 CSA International
.1 CSA B111-74(R2003), Wire Nails, Spikes and Staples.
.2 CSA O121-08, Douglas Fir Plywood.
.3 CSA O141-05(R2009), Softwood Lumber.
.5 National Lumber Grades Authority (NLGA)
.1 Standard Grading Rules for Canadian Lumber 2010.
P a g e 1 | 6
Finish Carpentry ‐ Section 06 20 00
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Softwood lumber: S4S, moisture content 19% or less in accordance with
following standards:
.1 CSA O141.
.2 NLGA Standard Grading Rules for Canadian Lumber.
.3 AWMAC premium grade, moisture content as specified.
.4 Hardwood lumber: moisture content 5 to 7%% or less in
accordance:
P a g e 2 | 6
Finish Carpentry ‐ Section 06 20 00
Retail Store Renovation ‐ Construction
2.2 ACCESSORIES
.1 Nails and staples: to CSA B111; galvanized to ASTM A123/A123M for
exterior work, interior humid areas and for treated lumber; plain finish
elsewhere.
.2 Wood screws: steel, type and size to suit application.
.3 Splines: wood.
.4 Adhesive and Sealants: in accordance with Section 07 92 00 - Joint
Sealants.
.1 VOC limit 30 g/L maximum to SCAQMD Rule 1168.
P a g e 3 | 6
Finish Carpentry ‐ Section 06 20 00
Retail Store Renovation ‐ Construction
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously
installed under other Sections or Contracts are acceptable for wood
products installation in accordance with manufacturer's written
instructions.
.1 Visually inspect substrate in presence of Consultant.
.2 Inform Consultant of unacceptable conditions immediately upon
discovery.
.3 Proceed with installation only after unacceptable conditions have
been remedied and after receipt of written approval to proceed from
Consultant .
3.2 INSTALLATION
.1 Do finish carpentry to Quality Standards of (AWMAC).
.2 Scribe and cut as required, fit to abutting walls, and surfaces, fit properly
into recesses and to accommodate piping, columns, fixtures, outlets, or
other projecting, intersecting or penetrating objects.
.3 Form joints to conceal shrinkage.
3.3 CONSTRUCTION
.1 Fastening:
.1 Position items of finished carpentry work accurately, level, plumb,
true and fasten or anchor securely.
.2 Design and select fasteners to suit size and nature of components
being joined. Use proprietary devices as recommended by
manufacturer.
.3 Set finishing nails to receive filler. Where screws are used to secure
members, countersink screw in round smooth cut hole and plug
with wood plug to match material being secured.
.4 Replace items of finish carpentry with damage to wood surfaces
including hammer and other bruises.
.2 Standing and running trim:
.1 Butt and cope internal joints of baseboards to make snug, tight,
joint. Cut right angle joints of casing and base with mitred joints.
.2 Fit backs of baseboards and casing snugly to wall surfaces to
eliminate cracks at junction of base and casing with walls.
P a g e 4 | 6
Finish Carpentry ‐ Section 06 20 00
Retail Store Renovation ‐ Construction
3.6 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools
and equipment in accordance with Section 01 74 11 - Cleaning.
P a g e 5 | 6
Finish Carpentry ‐ Section 06 20 00
Retail Store Renovation ‐ Construction
3.7 PROTECTION
.1 Protect installed products and components from damage during
construction.
.2 Repair damage to adjacent materials caused by finish carpentry
installation.
END OF SECTION
P a g e 6 | 6
Architectural Woodwork ‐ Section 06 40 00
Retail Store Renovation ‐ Construction
Part 1 General
1.2 REFERENCES
.1 American National Standards Institute (ANSI)
.1 ANSI A208.1-09, Particleboard.
.2 ANSI A208.2-09, Medium Density Fiberboard (MDF) for Interior
Applications.
.3 ANSI/HPVA HP-1-10, Standard for Hardwood and Decorative
Plywood.
.2 ASTM International
.1 ASTM D2832-92(R2011), Standard Guide for Determining Volatile
and Nonvolatile Content of Paint and Related Coatings.
.3 Architectural Woodwork Manufacturers Association of Canada (AWMAC)
and Architectural Woodwork Institute (AWI)
.1 Architectural Woodwork Quality Standards Illustrated, 8th edition,
Version 1.0 (2009).
.4 Canadian General Standards Board (CGSB)
.1 CAN/CGSB-71.20-M88, Adhesive, Contact, Brushable.
.5 CSA International
.1 CSA B111-74(R2003), Wire Nails, Spikes and Staples.
.2 CSA O121-08, Douglas Fir Plywood.
.3 CSA O141-05(R2009), Softwood Lumber.
.4 CSA O151-09, Canadian Softwood Plywood.
.6 Health Canada/Workplace Hazardous Materials Information System
(WHMIS)
.1 Material Safety Data Sheets (MSDS).
.7 National Hardwood Lumber Association (NHLA)
.1 Rules for the Measurement and Inspection of Hardwood and
Cypress 2011.
.8 National Lumber Grades Authority (NLGA)
P a g e 1 | 8
Architectural Woodwork ‐ Section 06 40 00
Retail Store Renovation ‐ Construction
P a g e 2 | 8
Architectural Woodwork ‐ Section 06 40 00
Retail Store Renovation ‐ Construction
P a g e 3 | 8
Architectural Woodwork ‐ Section 06 40 00
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Softwood lumber: unless specified otherwise, S4S, moisture content 15 %
or less in accordance with following standards:
.1 CSA O141.
.2 CAN/CSA-Z809 or FSC or SFI certified.
.3 NLGA Standard Grading Rules for Canadian Lumber.
.4 AWMAC custom grade, moisture content as specified.
.2 Machine stress-rated lumber is acceptable for all purposes.
.3 Hardwood lumber: moisture content 7 % or less in accordance with
following standards:
.1 National Hardwood Lumber Association (NHLA).
.2 CAN/CSA-Z809 or FSC or SFI certified.
.3 AWMAC premium grade, moisture content as specified.
.4 Hardwood plywood: to ANSI/HPVA HP-1, CAN/CSA-Z809 or FSC or SFI
certified.
.1 Plywood resin to contain no added urea-formaldehyde.
.5 Hardboard:
.1 To CAN/CGSB-11.3, CAN/CSA-Z809 or FSC or SFI certified.
.2 Hardboard resin to contain no added urea-formaldehyde.
.6 MDF (medium density fibreboard) core: to ANSI A208.2, Premium Grade,
13mm, 18mm, & 35mm thick, density 769 kg/m2, CAN/CSA-Z809 or FSC
or SFI certified.
.1 Medium density fibreboard performance requirements to: ANSI
A208.2.
.2 MDF resin to contain no added urea-formaldehyde.
.7 Nails and staples: to CSA B111.
.8 Wood screws: copper, type and size to suit application.
.9 Splines: wood.
.10 Sealant: in accordance with Section 07 92 00 - Joint Sealants.
.1 Sealants: VOC limit 250 g/L maximum to SCAQMD Rule 1168.
.11 Metal Veneer: 2mm thick folded metal with powder coat finish.
P a g e 4 | 8
Architectural Woodwork ‐ Section 06 40 00
Retail Store Renovation ‐ Construction
.12 Stainless Steel Veneer and Edging: 2mm thick stainless steel, formed to
shapes indicated and adhered to outer surfaces of shelves and cabinet
edges where indicated.
.13 Lighting: LED concealed lighting fixtures, length and profile to suit
conditions indicated.
P a g e 5 | 8
Architectural Woodwork ‐ Section 06 40 00
Retail Store Renovation ‐ Construction
.4 Fronts:
.1 MDF (medium density fibreboard), premium grade, square
edge, 18 mm thick.
.3 Casework Doors:
.1 Fabricate doors to AWMAC premium grade supplemented as
follows:
.2 MDF (medium density fibreboard), painted, premium grade, square
edge, 18 mm thick.
2.3 FABRICATION
.1 Set nails and countersink screws apply stained wood filler to indentations,
sand smooth and leave ready to receive finish.
.2 Shop install cabinet hardware for doors, shelves and drawers. Recess
shelf standards unless noted otherwise.
.3 Shelving to cabinetwork to be adjustable unless otherwise noted.
.4 Provide cutouts for plumbing fixtures, inserts, appliances, outlet boxes and
other fixtures.
.5 Shop assemble work for delivery to site in size easily handled and to
ensure passage through building openings.
.6 Obtain governing dimensions before fabricating items which are to
accommodate or abut appliances, equipment and other materials.
.7 Ensure adjacent parts of continuous laminate work match in colour and
pattern.
.8 Veneer laminated plastic to core material in accordance with adhesive
manufacturer's instructions and Section 06 47 00. Ensure core and
laminate profiles coincide to provide continuous support and bond over
entire surface. Use continuous lengths up to 3000 mm. Keep joints 600
mm from sink cutouts.
.9 Use straight self-edging laminate strip for flatwork to cover exposed edge
of core material. Chamfer exposed edges uniformly at approximately 20
degrees. Do not mitre laminate edges.
.10 Apply laminate backing sheet to reverse side of core of plastic laminate
work.
.11 Apply laminated plastic liner sheet where indicated.
.12 Apply metal veneer and stainless steel veneer and edging where
indicated, shaped to profiles indicated. Provide suitable adhesive for
application.
P a g e 6 | 8
Architectural Woodwork ‐ Section 06 40 00
Retail Store Renovation ‐ Construction
.13 Install concealed continuous LED lighting fixtures within the millwork units
where indicated, to CSA and all applicable Codes. Coordinate with the
electrical trade.
2.4 FINISHING
.1 Finish in accordance with Section 09 91 23 – Painting for Minor Works.
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously
installed under other Sections or Contracts are acceptable for architectural
woodwork installation in accordance with manufacturer's instructions.
.1 Visually inspect substrate in presence of Consultant.
.2 Inform Consultant of unacceptable conditions immediately upon
discovery.
.3 Proceed with installation only after unacceptable conditions have
been remedied and after receipt of written approval to proceed from
Consultant .
3.2 INSTALLATION
.1 Do architectural woodwork to Quality Standards of AWMAC.
.2 Install prefinished millwork at locations shown on drawings.
.1 Position accurately, level, plumb straight.
.3 Fasten and anchor millwork securely.
.1 Supply and install heavy duty fixture attachments for wall mounted
cabinets.
.4 Use draw bolts in countertop joints.
.5 Scribe and cut as required to fit abutting walls and to fit properly into
recesses and to accommodate piping, columns, fixtures, outlets or other
projecting, intersecting or penetrating objects.
.6 At junction of plastic laminate counter back splash and adjacent wall
finish, apply small bead of sealant in accordance with Section 07 92 00 -
Joint Sealants.
.7 Apply bituminous coating over wood framing members in contact with
masonry or cementitious construction.
.8 Fit hardware accurately and securely in accordance with manufacturer's
written instructions.
P a g e 7 | 8
Architectural Woodwork ‐ Section 06 40 00
Retail Store Renovation ‐ Construction
3.3 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools
and equipment in accordance with Section 01 74 11 - Cleaning.
.1 Clean millwork.
.2 Remove excess glue from surfaces.
3.4 PROTECTION
.1 Protect cabinet work from damage until final inspection.
.2 Protect installed products and components from damage during
construction.
.3 Repair damage to adjacent materials caused by architectural woodwork
installation.
END OF SECTION
P a g e 8 | 8
Plastic Laminate Finishing ‐ Section 06 47 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Canadian General Standards Board (CGSB)
.1 CAN/CGSB-71.20-M88, Adhesive, Contact, Brushable.
.2 CSA International
.1 CSA O121-08, Douglas Fir Plywood.
.3 Health Canada/Workplace Hazardous Materials Information System (WHMIS)
.1 Material Safety Data Sheets (MSDS).
P a g e 1 | 4
Plastic Laminate Finishing ‐ Section 06 47 00
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Laminated plastic for flatwork: to NEMA LD3.
.1 Type: general purpose.
.2 Grade: HGL.
.3 Size: 1.016 mm thick.
.4 Colour: P114 Poivre FA from Polyrey.
.5 Pattern: solid.
.6 Finish: satin.
.2 Laminated plastic for liner: to NEMA LD3.
.1 Type: cabinet liner.
.2 Grade: CLS.
.3 Size: 0.51 mm thick
.4 Colour: white.
.3 Plywood core: to CSA O121 solid two sides, Grade A, 19 mm thick.
.1 Ensure plywood core is urea-formaldehyde free.
.4 Laminated plastic adhesive: contact adhesive to CAN/CGSB-71.20.
.1 VOC limit 250 maximum.
2.2 FABRICATION
.1 Comply with NEMA LD3, Annex A.
.2 Obtain governing dimensions before fabricating items which are to accommodate
or abut appliances, equipment and other materials.
.3 Ensure adjacent parts of continuous laminate work match in colour and pattern.
P a g e 2 | 4
Plastic Laminate Finishing ‐ Section 06 47 00
Retail Store Renovation ‐ Construction
Part 3 Execution
3.2 INSTALLATION
.1 Install work plumb, true and square, neatly scribed to adjoining surfaces.
.2 Make allowances around perimeter where fixed objects pass through or project
into laminated plastic work to permit normal movement without restriction.
.3 Use draw bolts and splines in countertop joints. Maximum spacing 450 mm on
centre, 75 mm from edge. Make flush hairline joints.
.4 Provide cutouts for inserts, grilles, appliances, outlet boxes and other
penetrations. Round internal corners, chamfer edges and seal exposed core.
.5 For site application, offset joints in plastic laminate facing from joints in core.
3.3 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and
equipment in accordance with Section 01 74 11 - Cleaning.
.1 Clean to NEMA LD3, Annex B.
.2 Remove traces of primer, caulking, epoxy and filler materials and clean
doors and frames.
P a g e 3 | 4
Plastic Laminate Finishing ‐ Section 06 47 00
Retail Store Renovation ‐ Construction
3.4 PROTECTION
.1 Cover finished laminated plastic veneered surfaces with heavy kraft paper or put
in cartons during shipment.
.2 Protect installed laminated surfaces in accordance with manufacturer's written
recommendations.
.1 Remove protection only immediately before final inspection.
.3 Protect installed products and components from damage during construction.
.4 Repair damage to adjacent materials caused by laminate, adhesive, and core
materials installation.
END OF SECTION
P a g e 4 | 4
Quartz Surfacing Fabrications ‐ Section 06 61 19
Retail Store Renovation ‐ Construction
1 GENERAL
1.01 SUBMITTALS
.2 Shop drawings: Include layout, dimensions, materials, finishes, cutouts, and attachments.
.3 Samples:
.1 75 x 75 mm quartz samples in specified colour.
.4 Manufacturer's Instructions:
.1 Submit manufacturer's installation instructions.
.1 Deliver, handle, store and protect materials of this section in accordance with
manufacturer’s printed instructions.
.1 Maintain relative humidity between 25 and 60% at 22 degrees C during storage
and installation.
2 PRODUCTS
2.01 MATERIALS
3 EXECUTION
P a g e 1 | 2
Quartz Surfacing Fabrications ‐ Section 06 61 19
Retail Store Renovation ‐ Construction
3.02 INSTALLATION
.1 Install work plumb, true and square, neatly scribed to adjoining surfaces.
.2 Form field joints using manufacturer’s recommended adhesive, with joint widths no
greater than 3 mm in finished work.
.3 Tops: Flat and true to within 3 mm of a flat surface over a 3050 mm length.
.4 Provide cutouts for all penetrations. Round internal corners and round edges.
3.03 CLEANING
END OF SECTION
P a g e 2 | 2
Fire Stopping ‐ Section 07 84 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Underwriter's Laboratories of Canada (ULC)
.1 ULC-S115-1995, Fire Tests of Fire stop Systems.
1.2 DEFINITIONS
.1 Fire Stop Material: device intended to close off opening or penetration during fire
or materials that fill openings in wall or floor assembly where penetration is by
cables, cable trays, conduits, ducts and pipes and poke-through termination
devices, including electrical outlet boxes along with their means of support
through wall or floor openings.
.2 Single Component Fire Stop System: fire stop material that has Listed Systems
Design and is used individually without use of high temperature insulation or
other materials to create fire stop system.
.3 Multiple Component Fire Stop System: exact group of fire stop materials that are
identified within Listed Systems Design to create on site fire stop system.
.4 Tightly Fitted; (ref: NBC Part 3.1.9.1.1 and 9.10.9.6.1): penetrating items that are
cast in place in buildings of noncombustible construction or have "0" annular
space in buildings of combustible construction.
.1 Words "tightly fitted" should ensure that integrity of fire separation is such
that it prevents passage of smoke and hot gases to unexposed side of fire
separation.
P a g e 1 | 5
Fire Stopping ‐ Section 07 84 00
Retail Store Renovation ‐ Construction
P a g e 2 | 5
Fire Stopping ‐ Section 07 84 00
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Fire stopping and smoke seal systems: in accordance with CAN-ULC-S115.
.1 Asbestos-free materials and systems capable of maintaining effective
barrier against flame, smoke and gases in compliance with requirements
of CAN-ULC-S115 and not to exceed opening sizes for which they are
intended and conforming to specified special requirements described in
PART 3.
.2 Fire stop system rating: to meet or exceed fire resistance rating of
assembly.
.2 Service penetration assemblies: systems tested to CAN-ULC-S115.
.3 Service penetration fire stop components: certified by test laboratory to CAN-
ULC-S115.
.4 Fire-resistance rating of installed fire stopping assembly in accordance with NBC.
.5 Fire stopping and smoke seals at openings intended for ease of re-entry such as
cables: elastomeric seal.
.6 Fire stopping and smoke seals at openings around penetrations for pipes,
ductwork and other mechanical items requiring sound and vibration control:
elastomeric seal.
.7 Primers: to manufacturer's recommendation for specific material, substrate, and
end use.
.8 Water (if applicable): potable, clean and free from injurious amounts of
deleterious substances.
.9 Damming and backup materials, supports and anchoring devices: to
manufacturer's recommendations, and in accordance with tested assembly being
installed as acceptable to authorities having jurisdiction.
.10 Sealants for vertical joints: non-sagging.
Part 3 Execution
3.2 PREPARATION
.1 Examine sizes and conditions of voids to be filled to establish correct thicknesses
and installation of materials.
P a g e 3 | 5
Fire Stopping ‐ Section 07 84 00
Retail Store Renovation ‐ Construction
.1 Ensure that substrates and surfaces are clean, dry and frost free.
.2 Prepare surfaces in contact with fire stopping materials and smoke seals to
manufacturer's instructions.
.3 Maintain insulation around pipes and ducts penetrating fire separation.
.4 Mask where necessary to avoid spillage and over coating onto adjoining
surfaces; remove stains on adjacent surfaces.
3.3 INSTALLATION
.1 Install fire stopping and smoke seal material and components in accordance with
manufacturer's certified tested system listing.
.2 Seal holes or voids made by through penetrations, poke-through termination
devices, and unpenetrated openings or joints to ensure continuity and integrity of
fire separation are maintained.
.3 Provide temporary forming as required and remove forming only after materials
have gained sufficient strength and after initial curing.
.4 Tool or trowel exposed surfaces to neat finish.
.5 Remove excess compound promptly as work progresses and upon completion.
P a g e 4 | 5
Fire Stopping ‐ Section 07 84 00
Retail Store Renovation ‐ Construction
3.7 CLEANING
.1 Proceed in accordance with Section 01 74 11 - Cleaning.
.2 On completion and verification of performance of installation, remove surplus
materials, excess materials, rubbish, tools and equipment.
.3 Remove temporary dams after initial set of fire stopping and smoke seal
materials.
3.8 SCHEDULE
.1 Fire stop and smoke seal at:
.1 Penetrations through fire-resistance rated masonry, concrete, and
gypsum board partitions and walls.
.2 Top of fire-resistance rated masonry and gypsum board partitions.
.3 Intersection of fire-resistance rated masonry and gypsum board partitions.
.4 Control and sway joints in fire-resistance rated masonry and gypsum
board partitions and walls.
.5 Penetrations through fire-resistance rated floor slabs, ceilings and roofs.
.6 Openings and sleeves installed for future use through fire separations.
.7 Around mechanical and electrical assemblies penetrating fire separations.
.8 Rigid ducts: greater than 129 cm2
END OF SECTION
P a g e 5 | 5
Joint Sealants ‐ Section 07 92 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 ASTM International
.1 ASTM C919-08, Standard Practice for Use of Sealants in Acoustical
Applications.
.2 Canadian General Standards Board (CGSB)
.1 CAN/CGSB-19.13-M87, Sealing Compound, One-component,
Elastomeric, Chemical Curing.
.2 CAN/CGSB-19.17-M90, One-Component Acrylic Emulsion Base Sealing
Compound.
P a g e 1 | 5
Joint Sealants ‐ Section 07 92 00
Retail Store Renovation ‐ Construction
Part 2 Products
P a g e 2 | 5
Joint Sealants ‐ Section 07 92 00
Retail Store Renovation ‐ Construction
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify that conditions of substrate previously installed
under other Sections or Contracts are acceptable for joint sealants installation in
accordance with manufacturer's written instructions.
.1 Visually inspect substrate in presence of Consultant.
.2 Inform Consultant of unacceptable conditions immediately upon
discovery.
.3 Proceed with installation only after unacceptable conditions have been
remedied and after receipt of written approval to proceed from
Consultant .
P a g e 3 | 5
Joint Sealants ‐ Section 07 92 00
Retail Store Renovation ‐ Construction
3.3 PRIMING
.1 Where necessary to prevent staining, mask adjacent surfaces prior to priming
and caulking.
.2 Prime sides of joints in accordance with sealant manufacturer's instructions
immediately prior to caulking.
3.5 MIXING
.1 Mix materials in strict accordance with sealant manufacturer's instructions.
3.6 APPLICATION
.1 Sealant:
.1 Apply sealant in accordance with manufacturer's written instructions.
.2 Mask edges of joint where irregular surface or sensitive joint border exists
to provide neat joint.
.3 Apply sealant in continuous beads.
.4 Apply sealant using gun with proper size nozzle.
.5 Use sufficient pressure to fill voids and joints solid.
.6 Form surface of sealant with full bead, smooth, free from ridges, wrinkles,
sags, air pockets, embedded impurities.
.7 Tool exposed surfaces before skinning begins to give slightly concave
shape.
.8 Remove excess compound promptly as work progresses and upon
completion.
.2 Curing:
.1 Cure sealants in accordance with sealant manufacturer's instructions.
.2 Do not cover up sealants until proper curing has taken place.
3.7 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Clean adjacent surfaces immediately.
.3 Remove excess and droppings, using recommended cleaners as work
progresses.
P a g e 4 | 5
Joint Sealants ‐ Section 07 92 00
Retail Store Renovation ‐ Construction
3.8 PROTECTION
.1 Protect installed products and components from damage during construction.
.2 Repair damage to adjacent materials caused by joint sealants installation.
END OF SECTION
P a g e 5 | 5
Metal Doors and Frames ‐ Section 08 11 00
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 American Society for Testing and Materials International (ASTM)
.1 ASTM A653/A653M-06a, Specification for Steel Sheet, Zinc-Coated
(Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip
Process.
.2 Canadian General Standards Board (CGSB)
.1 CAN/CGSB-1.181-99, Ready-Mixed Organic Zinc-Rich Coating.
.3 Canadian Standards Association (CSA International)
.1 CSA-G40.20-04/G40.21-04, General Requirements for Rolled or Welded
Structural Quality Steel/Structural Quality Steel.
.2 CSA W59-03, Welded Steel Construction (Metal Arc Welding).
.4 Canadian Steel Door Manufacturers' Association (CSDMA)
.1 CSDMA, Recommended Specifications for Commercial Steel Doors and
Frames, 2000.
.2 CSDMA, Selection and Usage Guide for Commercial Steel Doors, 1990.
.5 National Fire Protection Association (NFPA)
.1 NFPA 80-99, Standard for Fire Doors and Fire Windows.
.2 NFPA 252-03, Standard Methods of Fire Tests of Door Assemblies.
.6 Underwriters' Laboratories of Canada (ULC)
.1 CAN4-S104-M80, Standard Method for Fire Tests of Door Assemblies.
P a g e 1 | 5
Metal Doors and Frames ‐ Section 08 11 00
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Hot dipped galvanized steel sheet: to ASTM A653M, ZF75, minimum base steel
thickness in accordance with CSDMA Table 1 - Thickness for Component Parts.
2.3 ADHESIVES
.1 Honeycomb cores and steel components: heat resistant, spray grade, resin
reinforced neoprene/rubber (polychloroprene) based, low viscosity, contact
cement.
.1 Adhesive: maximum VOC content 50 g/L .
.2 Lock-seam doors: fire resistant, resin reinforced polychloroprene, high viscosity,
sealant/adhesive.
2.4 PRIMER
.1 Touch-up prime CAN/CGSB-1.181.
.1 Maximum VOC limit 50 g/L .
P a g e 2 | 5
Metal Doors and Frames ‐ Section 08 11 00
Retail Store Renovation ‐ Construction
2.5 PAINT
.1 Field paint steel doors and frames in accordance with Sections, 09 91 99 -
Painting for Minor Works. Protect weatherstrips from paint. Provide final finish
free of scratches or other blemishes.
2.6 ACCESSORIES
.1 Door silencers: single stud rubber/neoprene type.
.2 Metallic paste filler: to manufacturer's standard.
.3 Fire labels: metal rivited.
P a g e 3 | 5
Metal Doors and Frames ‐ Section 08 11 00
Retail Store Renovation ‐ Construction
.3 Cope accurately and securely weld butt joints of mullions, transom bars, centre
rails and sills.
.4 Grind welded joints and corners to a flat plane, fill with metallic paste and sand to
uniform smooth finish.
.5 Securely attach floor anchors to inside of each jamb profile.
.6 Weld in 2 temporary jamb spreaders per frame to maintain proper alignment
during shipment.
P a g e 4 | 5
Metal Doors and Frames ‐ Section 08 11 00
Retail Store Renovation ‐ Construction
Part 3 Execution
END OF SECTION
P a g e 5 | 5
Flush Wood Doors ‐ Section 08 14 16
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Architectural Woodwork Manufacturers Association of Canada (AWMAC).
.1 Quality Standards for Architectural Woodwork 1998.
.2 Canadian Standards Association (CSA International).
.1 CAN/CSA O132.2 Series-90(R1998), Wood Flush Doors.
1.3 SAMPLES
.1 Submit samples in accordance with Section 01 33 00 - Submittal Procedures.
.2 Submit one 300 x 300 mm corner sample of each type wood door.
.3 Show door construction, core and faces.
.4 Manufacturer's Instructions:
.1 Submit manufacturer's installation instructions.
P a g e 1 | 4
Flush Wood Doors ‐ Section 08 14 16
Retail Store Renovation ‐ Construction
Part 2 Products
P a g e 2 | 4
Flush Wood Doors ‐ Section 08 14 16
Retail Store Renovation ‐ Construction
.2 Face Panels:
.1 Hardwood: Flat sliced, book matched select white maple for door
DR03 and white oak for door DR 06 to Architectural Woodwork
Quality Standards Section 200 (QSI 200), Grade A, edge-glued
joints. Hand select wood veneer from architectural grade flitches
of the specified species as required to provide a uniform grain
pattern and colour throughout. Veneer representative of low end
architectural grade quality will be unacceptable to the Consultant
and will be rejected.
.2 Hardboard face panel: hardboard for paint finish.
.3 Stain or paint finish: See Section 09 91 99 - Painting for Minor
Works
.4 Face Veneer: Apply veneer to the cross-banding in a hot press
using adhesive.
.3 Adhesive: Adhesive used to bond stiles, rails and layers of skins and
face sheets to core: Type II (water resistant) urea-free water resistant
adhesive conforming to the glue line requirements for wood doors under
CAN/CSA-O132.2 for interior use.
2.2 FABRICATION
.1 Vertical edge strips to match face veneer.
.2 Bevel vertical edges of single acting doors 3 mm in 50 mmon lock side and 1.5
mm in 50 mm on hinge side.
.3 Doors to be factory sealed at top , bottom and within all hardware cutouts.
Part 3 Execution
3.2 INSTALLATION
.1 Unwrap and protect doors in accordance with manufacturer's printed instructions.
.2 Install doors and hardware in accordance with manufacturer's printed
instructions.
.3 Adjust hardware for correct function.
P a g e 3 | 4
Flush Wood Doors ‐ Section 08 14 16
Retail Store Renovation ‐ Construction
3.3 ADJUSTMENT
.1 Re-adjust doors and hardware just prior to completion of building to function
freely and properly.
3.4 CLEANING
.1 Perform cleaning as soon as possible after installation to remove construction
and accumulated environmental dirt.
.2 Remove traces of primer, caulking; clean doors and frames.
.3 On completion of installation, remove surplus materials, rubbish, tools and
equipment barriers.
END OF SECTION
P a g e 4 | 4
Access Doors ‐ Section 08 31 00
Retail Store Renovation ‐ Construction
PART 1 General
1.1 SUBMITTALS
CLOSEOUT SUBMITTALS
.3 Provide maintenance data for cleaning and maintenance access doors for incorporation
into manual specified in Section 01 78 00 - Closeout Submittals.
PART 2 Products
PART 3 Execution
3.1 INSTALLATION
3.1 LOCATION
.1 Location: Ensure that equipment is within view and accessible for operating, inspecting,
adjusting, servicing without using special tools.
.3 As indicated on drawings.
END OF SECTION
P a g e 1 | 1
Side Coiling Grilles ‐ Section 08 33 36
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Aluminum Association (AA)
.1 AA DAF 45-03(R2009), Designation System for Aluminum Finishes.
.2 American Architectural Manufacturers Association (AAMA)
.1 AAMA 609/610-09, Cleaning and Maintenance Guide for Architecturally
Finished Aluminum.
P a g e 1 | 4
Side Coiling Grilles ‐ Section 08 33 36
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Anodized aluminum sheet metal: plain anodizing quality.
.2 Aluminum extrusions: Aluminum Association alloy AA6063-T5.
2.2 PRODUCT
.1 Cascade Coil Drapery Security System or approved equivalent:
.1 Drapery: stainless steel, 9.5 mm weave, 16 gauge.
.2 Vertical Channels: aluminum.
2.3 HARDWARE
.1 Top track: Secura Track System by Cascade Coil.
.1 Single track, stainless steel with stainless steel trolleys.
.2 Locking: centre opening lock operable from both sides.
.1 Include one cylinder lock and locking footbolts at 1500 mm intervals.
2.5 OPERATION
.1 Equip grille for operation by:
.1 Hand, install handles.
P a g e 2 | 4
Side Coiling Grilles ‐ Section 08 33 36
Retail Store Renovation ‐ Construction
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously installed
under other Sections or Contracts are acceptable for side coiling grilles
installation in accordance with manufacturer's written instructions.
.1 Visually inspect substrate in presence of Consultant.
.2 Inform Consultant of unacceptable conditions immediately upon
discovery.
.3 Proceed with installation only after unacceptable conditions have been
remedied .
3.2 INSTALLATION
.1 Manufacturer's Instructions: comply with manufacturer's written data, including
product technical bulletins, product catalogue installation instructions, product
carton installation instructions, and data sheets.
.2 Erect side coiling grilles and closures in accordance with manufacturers' printed
instructions.
.3 Install masterkeyed cylinder specified in Section 08 71 00 - Door Hardware.
.4 Adjust operating components to ensure smooth opening and closing of side
coiling grilles and closures.
3.3 CLEANING
.1 Perform cleaning of aluminum components in accordance with: AAMA 609.1 -
Voluntary Guide Specification for Cleaning and Maintenance of Architectural
Anodized Aluminum.
.2 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Perform cleaning of aluminum components in accordance with: AAMA
609.
.3 Clean aluminum and stainless steel with damp rag and approved non-
abrasive cleaner in accordance with manufacturer's instructions.
.4 Remove traces of primer, caulking; clean doors and frames.
.3 Final Cleaning: upon completion remove surplus materials, rubbish, tools and
equipment in accordance with Section 01 74 11 - Cleaning.
3.4 PROTECTION
.1 Protect installed products and components from damage during construction.
.2 Repair damage to adjacent materials caused by side coiling grille installation.
P a g e 3 | 4
Side Coiling Grilles ‐ Section 08 33 36
Retail Store Renovation ‐ Construction
END OF SECTION
P a g e 4 | 4
Cabinet and Miscellaneous Hardware ‐ Section 08 70 05
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 American National Standards Institute (ANSI) / Builders Hardware Manufacturers
Association (BHMA)
.1 ANSI/BHMA A156.9-2003, Cabinet Hardware.
.2 ANSI/BHMA A156.11- 2004, Cabinet Locks.
.3 ANSI/BHMA A156.18-2006, Materials and Finishes.
Part 2 Products
P a g e 2 | 4
Cabinet and Miscellaneous Hardware ‐ Section 08 70 05
Retail Store Renovation ‐ Construction
.1 Door or drawer locks: half mortised into back of door or drawer, nickel
plated finish.
.2 Cylinders: key into keying system as directed.
2.2 FASTENINGS
.1 Supply screws, bolts, expansion shields and other fastening devices required for
satisfactory installation and operation of hardware.
.2 Exposed fastening devices to match finish of hardware.
.3 Use fasteners compatible with material through which they pass.
2.3 KEYING
.1 Cabinet locks to be great grand master keyed. Submit keying schedule for
approval.
.2 Supply keys in duplicate for every lock in this Contract.
.3 Supply 3 master keys for each master key or grand master key group.
.4 Stamp keying code numbers on keys and cylinders.
.5 Install key cabinet where indicated.
Part 3 Execution
3.1 INSTALLATION
.1 Manufacturer's Instructions: comply with manufacturer's written
recommendations, including product technical bulletins, product catalogue
installation instructions, product carton installation instructions, and data sheets.
.2 Install hardware to standard hardware location dimensions in accordance with
manufacturer's recommendations and to project design requirements.
.3 Install key control cabinet and establish key control set-up.
3.2 ADJUSTING
.1 Adjust cabinet hardware for optimum, smooth operating condition.
.2 Lubricate hardware and other moving parts.
.3 Adjust cabinet door hardware to ensure tight fit at contact points with frames.
3.3 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Clean hardware with damp rag and approved non-abrasive cleaner, and
polish hardware in accordance with manufacturer's instructions.
.3 Remove protective material from hardware items where present.
P a g e 3 | 4
Cabinet and Miscellaneous Hardware ‐ Section 08 70 05
Retail Store Renovation ‐ Construction
3.4 DEMONSTRATION
.1 Keying System Setup and Cabinet:
.1 Set up key control system with file key tags, duplicate key tags, numerical
index, alphabetical index and key change index, label shields, control
book and key receipt cards.
.2 Place file keys and duplicate keys in key cabinet on their respective
hooks.
.3 Lock key cabinet and turn over key to Consultant.
.2 Maintenance Staff Briefing:
.1 Brief maintenance staff regarding:
.1 Proper care, cleaning, and general maintenance of projects
complete hardware.
.2 Description, use, handling, and storage of keys.
.3 Demonstrate operation, operating components, adjustment features, and
lubrication requirements.
3.5 PROTECTION
.1 Protect installed products and components from damage during construction.
.2 Repair damage to adjacent materials caused by cabinet and miscellaneous
hardware installation.
3.6 SCHEDULE
.1 Install recessed shelf standards in each millwork unit with doors where indicated
for full height of unit. Provide 2 standards per side.
.2 Install millwork doors with hinges.
.3 Install millwork drawers with slides.
.4 Install grommets at all penetrations as indicated.
.5 Install cabinet locks at each door and drawer as indicated.
.6 Installer lights as indicated.
.7 Install other items as indicated.
END OF SECTION
P a g e 4 | 4
Door Hardware ‐ Section 08 71 00
Retail Store Renovation ‐ Construction
Part 1 General
1.2 REFERENCES
.1 American National Standards Institute (ANSI) / Builders Hardware
Manufacturers Association (BHMA)
.1 ANSI/BHMA A156.1-2000, American National Standard for Butts
and Hinges.
.2 ANSI/BHMA A156.2-2003, Bored and Preassembled Locks and
Latches.
.3 ANSI/BHMA A156.3-2001, Exit Devices.
.4 ANSI/BHMA A156.4-2000, Door Controls - Closers.
.5 ANSI/BHMA A156.5-2001, Auxiliary Locks and Associated
Products.
.6 ANSI/BHMA A156.6-2005, Architectural Door Trim.
.7 ANSI/BHMA A156.8-2005, Door Controls - Overhead Stops and
Holders.
.8 ANSI/BHMA A156.13-2002, Mortise Locks and Latches Series
1000.
.9 ANSI/BHMA A156.16-2002, Auxiliary Hardware.
.10 ANSI/BHMA A156.18-2006, Materials and Finishes.
.2 Canadian Steel Door and Frame Manufacturers' Association (CSDMA)
.1 CSDMA Recommended Dimensional Standards for Commercial
Steel Doors and Frames - 2009.
P a g e 1 | 6
Door Hardware ‐ Section 08 71 00
Retail Store Renovation ‐ Construction
P a g e 2 | 6
Door Hardware ‐ Section 08 71 00
Retail Store Renovation ‐ Construction
Part 2 Products
.3 Concealed hinges:
.1 SOSS concealed hinges, bright nickel plated, complete with SOSS
concealed door closer kit. Acceptable product: Hafele 927.50.207.
Required for door DR-01.
P a g e 3 | 6
Door Hardware ‐ Section 08 71 00
Retail Store Renovation ‐ Construction
.4 Exit devices: to ANSI/BHMA A156.3, type Von Duprin “98” series flat bar
type.
.5 Door Closers and Accessories:
.1 Door controls (closers): to ANSI/BHMA A156.4, satin nickel plated
finish. Hafele Model 931.82.606
.6 Architectural door trim: to ANSI/BHMA A156.6.
.1 Door protection plates: kick plate type and mid rail plate, 1.27 mm
thick, 304 stainless steel, size: 700mm length. Hafele model
987.18.300
.2 Push plates: 300 x 75mm x 1.27 mm thick, 304 stainless steel push
plate. Hafele model 987.14.831
.3 Push/Pull units: 19 mm diameter pull handle, 225-425mm hole
centres, bolt through fixing. Hafele model 903.01.352
.4 Flush ring pull handle: 52 x 38mm flush ring pull handle, Hafele
model 901.03.804
.7 Privacy Set Release hardware: emergency release indicator and inside
turn, Hafele Model 902.53.870, required at washroom door.
2.3 FASTENINGS
.1 Use only fasteners provided by manufacturer. Failure to comply may void
warranties and applicable licensed labels.
.2 Supply screws, bolts, expansion shields and other fastening devices
required for satisfactory installation and operation of hardware.
.3 Exposed fastening devices to match finish of hardware.
.4 Where pull is scheduled on one side of door and push plate on other side,
supply fastening devices, and install so pull can be secured through door
from reverse side. Install push plate to cover fasteners.
.5 Use fasteners compatible with material through which they pass.
2.4 KEYING
.1 Doors, and cabinet locks to be as noted in Door Schedule and drawings.
Prepare detailed keying schedule in conjunction with Consultant.
.2 Supply keys in duplicate for every lock in this Contract.
.3 Supply 3 master keys for each master key or grand master key group.
.4 Stamp keying code numbers on keys and cylinders.
.5 Supply construction cores.
P a g e 4 | 6
Door Hardware ‐ Section 08 71 00
Retail Store Renovation ‐ Construction
Part 3 Execution
3.1 INSTALLATION
.1 Manufacturer's Instructions: comply with manufacturer's written
recommendations, including product technical bulletins, product catalogue
installation instructions, product carton installation instructions, and data
sheets.
.2 Supply metal door and frame manufacturers with complete instructions
and templates for preparation of their work to receive hardware.
.3 Supply manufacturers' instructions for proper installation of each hardware
component.
.4 Install hardware to standard hardware location dimensions in accordance
with CSDFMA Canadian Metric Guide for Steel Doors and Frames
(Modular Construction).
.5 Where door stop contacts door pulls, mount stop to strike bottom of pull.
.6 Use only manufacturer's supplied fasteners.
.1 Use of "quick" type fasteners, unless specifically supplied by
manufacturer, is unacceptable.
.7 Remove construction locks when directed by Consultant.
.1 Install permanent cores and ensure locks operate correctly.
3.2 ADJUSTING
.1 Adjust door hardware, operators, closures and controls for optimum,
smooth operating condition, safety and for weather tight closure.
.2 Lubricate hardware, operating equipment and other moving parts.
.3 Adjust door hardware to ensure tight fit at contact points with frames.
3.3 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Clean hardware with damp rag and approved non-abrasive cleaner,
and polish hardware in accordance with manufacturer's
instructions.
.3 Remove protective material from hardware items where present.
P a g e 5 | 6
Door Hardware ‐ Section 08 71 00
Retail Store Renovation ‐ Construction
3.4 DEMONSTRATION
.1 Keying System Setup and Cabinet:
.1 Set up key control system with file key tags, duplicate key tags,
numerical index, alphabetical index and key change index, label
shields, control book and key receipt cards.
.2 Place file keys and duplicate keys in key cabinet on their respective
hooks.
.3 Lock key cabinet and turn over key to DCC Representative.
.2 Maintenance Staff Briefing:
.1 Brief maintenance staff regarding:
.1 Proper care, cleaning, and general maintenance of projects
complete hardware.
.2 Description, use, handling, and storage of keys.
.3 Use, application and storage of wrenches for locksets.
.3 Demonstrate operation, operating components, adjustment features, and
lubrication requirements.
3.5 PROTECTION
.1 Protect installed products and components from damage during
construction.
.2 Repair damage to adjacent materials caused by door hardware
installation.
3.6 SCHEDULE
.1 Provide and install all hardware as noted in the Door & Hardware
Schedule listed on the drawings.
END OF SECTION
P a g e 6 | 6
Glazing ‐ Section 08 80 50
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Canadian General Standards Board (CGSB)
.1 CAN/CGSB-12.1-M90, Tempered or Laminated Safety Glass.
.2 Glass Association of North American (GANA)
.1 GANA Glazing Manual - 2008.
.2 GANA Laminated Glazing Reference Manual - 2009.
P a g e 1 | 3
Glazing ‐ Section 08 80 50
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Flat Glass:
.1 Safety glass: to CAN/CGSB-12.1, transparent, thickness as indictated on
drawings.
.1 Type 1-laminated and 2-tempered.
.1 Class B-float.
.2 Category 11.
.3 Edge treatment.
.2 Type 3-UV laminated.
.1 Class B-float.
.2 Category 1.
.3 Edge treatment.
.4 Plastic interlayer, clear, to block 99% of UV rays.
.3 Cast Acrylic:
.1 Cast acrylic sheet: Cell Cast Acrylic by Perspex.
.2 Thickness as indicated on drawings.
.3 Frosted.
.4 Colour to be selected from manufacturer's full colour
range.
.4 Plastic Film: in accordance with Section 08 87 53 - Architectural
Window Films.
.5 Sealant: in accordance with Section 07 92 00 - Joint Sealants.
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously installed
under other Sections or Contracts are acceptable for glazing installation in
accordance with manufacturer's written instructions.
.1 Verify that openings for glazing are correctly sized and within tolerance.
.2 Verify that surfaces of glazing channels or recesses are clean, free of
obstructions, and ready to receive glazing.
.3 Visually inspect substrate in presence of Consultant.
.4 Inform Consultant of unacceptable conditions immediately upon
discovery.
.5 Proceed with installation only after unacceptable conditions have been
remedied.
P a g e 2 | 3
Glazing ‐ Section 08 80 50
Retail Store Renovation ‐ Construction
3.2 PREPARATION
.1 Clean contact surfaces with solvent and wipe dry.
.2 Seal porous glazing channels or recesses with substrate compatible primer or
sealer.
.3 Prime surfaces scheduled to receive sealant.
3.3 INSTALLATION
.1 Shopfront aluminum glass channels:
.1 Comply with manufacturer's written installation instructions and approved
shop drawings.
.2 Fasten glass panel partition framing to building structure and supports as
indicated on approved shop drawings, utilizing approved fasteners and
spacing.
.3 Set frame in continuous bed of sealant.
3.4 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.1 Remove traces of primer, caulking.
.2 Remove glazing materials from finish surfaces.
.3 Remove labels.
.4 Clean glass using approved non-abrasive cleaner in accordance
with manufacturer's instructions.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools
and equipment in accordance with Section 01 74 11 - Cleaning.
3.5 PROTECTION
.1 Protect installed products and components from damage during construction.
.2 After installation, mark each light with an "X" by using removable plastic tape or
paste.
.3 Repair damage to adjacent materials caused by glazing installation.
END OF SECTION
P a g e 3 | 3
Architectural Window Films ‐ Section 08 87 53
Retail Store Renovation ‐ Construction
Part 1 General
P a g e 1 | 4
Architectural Window Films ‐ Section 08 87 53
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Architectural Window Film - General: Glass and plastic finishes field-applied
application to glass or plastic material as visual opaque or decorative film.
.1 Film: Polyester
.2 Product Family: Frost/Mat
.3 Adhesive Type: Pressure-sensitive
.4 Usage: Interior or exterior
.5 Shading Co-efficient (%): 0.40
.6 Visible Light Reflectance (%): 42
.7 Visible Light Transmittance (%): 19
.8 Acceptable Product: 3M Fasara Glass Finishes, Milky Crystal
(SH2MLCRX)
2.2 FABRICATION
.1 Shop installation of security film to glass panels:
.1 Ensure dust, grease, and chemical residue are removed from surface of
glass before installation of film.
.2 Examine glass under natural daylight and identify cracks, blisters,
bubbles, discolouration, edge defects or other anomalies that may cause
film to delaminate, or cause vision transparency or distortion problems.
.3 View glass from 2.0 m minimum. Report findings to Consultant.
.4 Proceed with Work only after receipt of written approval from Consultant
.1 Install film to glass panels ensuring no blisters, bubbles,
scratches, edge defects or distortions.
.2 Cut film edges straight and square to within 3 mm of edge of
panel.
.3 Deliver glass panels complete with security film installed and
labels intact and legible to site in accordance with section 01 61 00
- Common Product Requirements.
Part 3 Execution
3.1 PREPARATION
.1 Clean glass before beginning installation using neutral cleaning solution.
.2 Ensure no deleterious material adheres to glass by scraping surface of glass
using industrial razors.
.3 Ensure dust, grease, and chemical residue are removed from surface of glass
before installation of film.
P a g e 2 | 4
Architectural Window Films ‐ Section 08 87 53
Retail Store Renovation ‐ Construction
.4 Examine glass under natural daylight and identify cracks, blisters, bubbles,
discolouration, edge defects or other anomalies that may cause film to
delaminate or cause vision transparency or distortion problems. Report findings
to Consultant.
.5 Proceed with Work only after receipt of written approval from Consultant.
.6 Before beginning Work, place absorbent material on window sill to absorb
moisture accumulation generated by film application.
3.2 INSTALLATION
.1 Field Installation of Film to Glass Windows:
.1 Install film in the same manner as tested.
.2 Remove any window stops and window sealing device.
.3 Ensure no deleterious material adheres to glass by scraping surface of
glass using industrial razors.
.4 Ensure dust, grease, and chemical residue are removed from surface of
glass before installation of film.
.5 Examine glass under natural daylight and identify cracks, blisters,
bubbles, discolouration, edge defects or other anomalies that may cause
film to delaminate, or cause vision transparency or distortion problems.
Report findings to Consultant before starting Work.
.6 Proceed with Work only after receipt of written approval from Consultant.
.7 Install film to glass windows ensuring no blisters, bubbles, scratches or
distortions.
.2 Cut film edges straight and square.
.3 Ensure film is installed behind window stops.
.4 Cut edges in accordance with manufacturers written instructions.
.5 Apply and attach film to glass in accordance with manufacturer's written
instructions.
.6 Splicing:
.1 Splice film only when glass is greater in width than film.
.2 Splice film only after receipt of written approval from Consultant.
.3 Use butt factory edges only.
.4 Ensure maximum overlap of 3 mm.
.7 Use only water and film slip solution on glass to facilitate positioning of film.
.8 Ensure removal of excess water from between film and glass.
.9 Remove left over material form work area and return work area to original
condition.
P a g e 3 | 4
Architectural Window Films ‐ Section 08 87 53
Retail Store Renovation ‐ Construction
END OF SECTION
P a g e 4 | 4
Partitions for Minor Works ‐ Section 09 21 99
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 ASTM International
.1 ASTM C1396/C1396M-09a, Standard Specification for Gypsum
Wallboard.
.2 ASTM C475/C475M-02(2007), Standard Specification for Joint
Compound and Joint Tape for Finishing Gypsum Board.
.3 ASTM C645-09a, Standard Specification for Nonstructural Steel Framing
Members.
.4 ASTM C754-09a, Standard Specification for Installation of Steel Framing
Members to Receive Screw-Attached Gypsum Panel Products.
.5 ASTM C840-08, Standard Specification for Application and Finishing of
Gypsum Board.
.6 ASTM C1002-07, Standard Specification for Steel Self-Piercing Tapping
Screws for the Application of Gypsum Panel Products or Metal Plaster
Bases to Wood Studs or Steel Studs.
.7 ASTM C1047-10, Standard Specification for Accessories for Gypsum
Wallboard and Gypsum Veneer Base.
.2 South Coast Air Quality Management District (SCAQMD), California State,
Regulation XI. Source Specific Standards
.1 SCAQMD Rule 1168-A2005, Adhesives and Sealants Applications.
.3 Underwriters' Laboratories of Canada (ULC)
.1 CAN/ULC-S102-07, Standard Method of Test for Surface Burning
Characteristics of Building Materials and Assemblies.
P a g e 1 | 6
Partitions for Minor Works ‐ Section 09 21 99
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Performance / Design Criteria:
.1 Partition assembly to be non-combustible construction and fire resistance
rated.
.2 Minimum sound transmission class rating of installed panel partition to be
STC 30, tested to ASTM E90.
.2 Non-structural Metal Framing:
.1 Non-load bearing channel stud framing: to ASTM C645, 92 mm stud size,
roll formed from 0.53 mm thickness hot dipped galvanized steel sheet, for
screw attachment of gypsum board. Knock-out service holes at 460 mm
centres.
.2 Floor and ceiling tracks: to ASTM C645, in widths to suit stud sizes, 32
mm flange height.
.3 Metal channel stiffener: 19 x 1.4 mm thick cold rolled steel, coated with
rust inhibitive coating.
.3 Gypsum Board:
.1 Standard board: to ASTM C1396/C1396M, Type X, 16 mm thick, 1200
mm wide x maximum practical length, ends square cut, edges tapered.
.2 Metal furring runners, hangers, tie wires, inserts, anchors: to ASTM C645.
P a g e 2 | 6
Partitions for Minor Works ‐ Section 09 21 99
Retail Store Renovation ‐ Construction
2.2 ACCESSORIES
.1 Acoustical insulation: type recommended by manufacturer to achieve STC rating
specified.
.2 Sealants: in accordance with Section 07 92 00.
.3 Insulating strip: rubberized, moisture resistant, 3 mm thick closed cell neoprene
strip, 12 mm wide, with self sticking permanent adhesive on one face, lengths as
required.
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously installed
under other Sections or Contracts are acceptable for product installation in
accordance with manufacturer's written instructions prior to partition installation.
.1 Visually inspect substrate in presence of Consultant.
.2 Inform Consultant of unacceptable conditions immediately upon
discovery.
.3 Proceed with installation only after unacceptable conditions have been
remedied .
P a g e 3 | 6
Partitions for Minor Works ‐ Section 09 21 99
Retail Store Renovation ‐ Construction
P a g e 4 | 6
Partitions for Minor Works ‐ Section 09 21 99
Retail Store Renovation ‐ Construction
.10 Install gypsum boards in direction that will minimize number of end-butt joints.
Stagger end joints 250 mm minimum.
3.4 APPLICATION
.1 Apply gypsum board after bucks, anchors, blocking, sound attenuation, electrical
and mechanical work are approved.
.2 Apply gypsum board to metal furring or framing using screw fasteners. Maximum
spacing of screws 300 mm on centre.
3.5 INSTALLATION
.1 Erect accessories straight, plumb or level, rigid and at proper plane. Use full
length pieces where practical. Make joints tight, accurately aligned and rigidly
secured. Mitre and fit corners accurately, free from rough edges. Secure at 150
mm on centre.
.2 Install casing beads around perimeter of suspended ceilings.
.3 Install casing beads where gypsum board butts against surfaces having no trim
concealing junction and where indicated. Seal joints with sealant.
.4 Install access doors to electrical and mechanical fixtures specified in respective
sections.
.1 Rigidly secure frames to furring or framing systems.
.5 Finish face panel joints and internal angles with joint system consisting of joint
compound, joint tape and taping compound installed according to manufacturer's
directions and feathered out onto panel faces.
.6 Finish corner beads, control joints and trim as required with two coats of joint
compound and one coat of taping compound, feathered out onto panel faces.
.7 Fill screw head depressions with joint and taping compounds to bring flush with
adjacent surface of gypsum board so as to be invisible after surface finish is
completed.
.8 Completed installation to be smooth, level or plumb, free from waves and other
defects and ready for surface finish.
3.6 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and
equipment in accordance with Section 01 74 11 - Cleaning.
3.7 PROTECTION
.1 Protect installed products and components from damage during construction.
P a g e 5 | 6
Partitions for Minor Works ‐ Section 09 21 99
Retail Store Renovation ‐ Construction
END OF SECTION
P a g e 6 | 6
Gypsum Plastering (Honed Concrete) ‐ Section 09 23 00
Retail Store Renovation ‐ Construction
Part 1 General
1.2 REFERENCES
.1 ASTM International
.1 ASTM C28-00(2005), Standard Specification for Gypsum Plasters.
.2 ASTM C35-01(2009), Standard Specification for Inorganic
Aggregates for Use in Gypsum Plaster.
.3 ASTM C206-03, Standard Specification for Finishing Hydrated
Lime.
.4 ASTM C587-04, Standard Specification for Gypsum Veneer
Plaster.
.5 ASTM C631-09, Standard Specification for Bonding Compounds for
Interior Gypsum Plastering.
.6 ASTM C842-05, Standard Specification for Application of Interior
Gypsum Plaster.
.7 ASTM C843-99(2006), Standard Specification for Application of
Gypsum Veneer Plaster.
.8 ASTM C844-04, Standard Specification for Application of Gypsum
Base to Receive Gypsum Veneer Plaster.
.9 ASTM C1396/C1396M-09a, Standard Specification for Gypsum
Wallboard.
.2 Health Canada / Workplace Hazardous Materials Information System
(WHMIS)
.1 Material Safety Data Sheets (MSDS).
P a g e 1 | 6
Gypsum Plastering (Honed Concrete) ‐ Section 09 23 00
Retail Store Renovation ‐ Construction
.3 Samples:
.1 Submit for review and acceptance of each unit.
.2 Samples will be returned for inclusion into work.
.3 Submit duplicate 300 x 300 mm samples of polished plaster
concrete honed plaster finishes.
.4 Certificates: submit product certificates signed by manufacturer certifying
materials comply with specified performance characteristics and criteria
and physical requirements.
.5 Test Reports: certified test reports showing compliance with specified
performance characteristics and physical properties.
P a g e 2 | 6
Gypsum Plastering (Honed Concrete) ‐ Section 09 23 00
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Reinforcing Basecoat:
.1 Special reinforcing system that greatly reduces the risk of cracks
appearing from weak substrates. Acceptable product: Anti-Crack
System by Surfaceform or acceptable equivalent. Reinforcing coat
to be 1.25mm minimum.
.2 Polished plaster Concrete:
P a g e 3 | 6
Gypsum Plastering (Honed Concrete) ‐ Section 09 23 00
Retail Store Renovation ‐ Construction
2.2 MIXES
.1 Mix plasters to Manufacturer's written instructions..
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously
installed under other Sections or Contracts are acceptable for gypsum
plastering installation in accordance with manufacturer's written
instructions.
.1 Visually inspect substrate in presence of Consultant.
.2 Inform Consultant of unacceptable conditions immediately upon
discovery.
.3 Proceed with installation only after unacceptable conditions have
been remedied .
3.2 PREPARATION
.1 Prepare surfaces to receive plaster to ASTM C1396/C1396M.
.2 Ensure outlets are properly plugged, capped or covered before starting
work.
.3 Where plaster butts exposed masonry walls, insert 1 m wide strip of
polyethylene before applying plaster to protect masonry. Cut polyethylene
neatly at junction with plaster when plastering is completed.
P a g e 4 | 6
Gypsum Plastering (Honed Concrete) ‐ Section 09 23 00
Retail Store Renovation ‐ Construction
3.3 APPLICATION
.1 Manufacturer's Instructions: comply with manufacturer's written
recommendations, including product technical bulletins, product catalogue
installation instructions, product carton installation instructions, and data
sheets.
.2 Do plastering work to ASTM C587.
.3 Apply plaster finish level and plumb.
.4 Use 3 - 5 coats plaster in specify area depending on desired finish.
.5 Form small vee groove where plaster finish is flush with bases, window
frames, glazed wall tiles or similar construction.
.6 Reinforcing Basecoat Plaster:
.1 1.75 mm thick.
.2 Mix by hand, following manufacturer's directions.
.3 Apply initial reinforcing basecoat application (scratch coat) to
gypsum and/or concrete substrate, by hand using hand held tools
such as trowels, spatulas, brushes, and rollers with sufficient
material and pressure to form good bond to base and to cover well.
.4 Leave surface ready to receive the polished plaster concrete finish.
.7 Finishing Plaster/polished plaster concrete:
.1 Mix in accordance with applicable bag mixing instructions.
.2 Application:
.1 Apply 0.75 - 1.75 mm finish coat.
.2 Applied and finished using hand held tools, such as trowels,
spatulas, brushes and rollers. 3-5 coats to achieve dense,
hard, smooth surface with a honed finish to the colours
specified.
3.4 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish,
tools and equipment in accordance with Section 01 74 11 -
Cleaning.
P a g e 5 | 6
Gypsum Plastering (Honed Concrete) ‐ Section 09 23 00
Retail Store Renovation ‐ Construction
3.5 PROTECTION
.1 Protect installed products and components from damage during
construction.
.2 Repair damage to adjacent materials caused by gypsum plastering
installation.
END OF SECTION
P a g e 6 | 6
Ceramic Tiling ‐ Section 09 30 13
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 American National Standards Institute (ANSI)/Ceramic Tile Institute (CTI)
.1 ANSI A108.1-99, Specification for the Installation of Ceramic Tile
(Includes ANSI A108.1A-C, 108.4-.13, A118.1-.10, ANSI A136.1).
.2 CTI A118.4-92, Specification for Latex Cement Mortar (included in ANSI
A108.1).
.2 American Society for Testing and Materials International (ASTM)
.1 ASTM C144-04, Specification for Aggregate for Masonry Mortar.
.2 ASTM C979-05, Specification for Pigments for Integrally Coloured
Concrete.
.3 Canadian General Standards Board (CGSB)
.4 Canadian Standards Association (CSA International)
.1 CAN/CSA-A3000-03(R2006), Cementitious Materials Compendium
(Consists of A3001, A3002, A3003, A3004 and A3005).
.5 Terrazzo Tile and Marble Association of Canada (TTMAC)
.1 Tile Specification Guide 09 30 00 2012/2014, Tile Installation Manual.
.2 Tile Maintenance Guide 2000.
P a g e 1 | 4
Ceramic Tiling ‐ Section 09 30 13
Retail Store Renovation ‐ Construction
1.6 MAINTENANCE
.1 Extra Materials:
.1 Provide maintenance materials in accordance with Section 01 78 00 -
Closeout Submittals.
.2 Provide minimum 2% of each type and colour of tile required for project
for maintenance use. Store where directed.
.3 Maintenance material same production run as installed material.
Part 2 Products
P a g e 2 | 4
Ceramic Tiling ‐ Section 09 30 13
Retail Store Renovation ‐ Construction
.3 Latex additive: formulated for use in cement mortar and thin set bond coat.
.4 Water: potable and free of minerals and chemicals which are detrimental to
mortar and grout mixes.
2.4 GROUT
.1 Colouring Pigments:
.1 Pure mineral pigments, limeproof and nonfading, complying with ASTM
C979.
.2 Colouring pigments to be added to grout by manufacturer.
.3 Job coloured grout are not acceptable.
.4 Use in Commercial Cement Grout.
.2 Commercial Cement Grout: to ANSI A118.7.
2.5 ACCESSORIES
.1 Divider strips:
.1 Purpose made metal extrusion; anodized aluminum type.
.2 Transition Strips: purpose made metal extrusion; anodized aluminum type.
.3 Reducer Strips: purpose made metal extrusion; anodized aluminum type;
maximum slope of 1:2.
P a g e 3 | 4
Ceramic Tiling ‐ Section 09 30 13
Retail Store Renovation ‐ Construction
Part 3 Execution
3.2 WORKMANSHIP
.1 Do tile work in accordance with TTMAC Tile Installation Manual 2012/2014,
"Ceramic Tile", except where specified otherwise.
.2 Apply tile to clean and sound surfaces.
.3 Fit tile around corners, fitments, fixtures, drains and other built-in objects.
Maintain uniform joint appearance. Cut edges smooth and even. Do not split
tiles.
.4 Maximum surface tolerance 1:800.
.5 Make joints between tile uniform and approximately 1.5 mm wide, plumb,
straight, true, even and flush with adjacent tile. Ensure sheet layout not visible
after installation. Align patterns.
.6 Lay out tiles so perimeter tiles are minimum 1/2 size.
.7 Sound tiles after setting and replace hollow-sounding units to obtain full bond.
.8 Install divider strips at junction of tile flooring and dissimilar materials.
.9 Allow minimum 24 hours after installation of tiles, before grouting.
.10 Clean installed tile surfaces after installation and grouting cured.
3.4 CLEANING
.1 Proceed in accordance with Section 01 74 11 - Cleaning.
END OF SECTION
P a g e 4 | 4
Acoustical Ceilings for Minor Works ‐ Section 09 51 99
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 ASTM International
.1 ASTM C635/C635M-07, Standard Specifications for the Manufacture,
Performance and Testing of Metal Suspension Systems for Acoustical
Tile and Lay-In Panel Ceilings.
.2 ASTM C636/C636M-08, Standard Practice for Installation of Metal Ceiling
Suspension Systems for Acoustical Tile and Lay-In Panels.
.3 ASTM E580/E590M-09a, Standard Practice for Installation of Ceiling
Suspension Systems for Acoustical Tile and Lay-in Panels in Areas
Subject to Earthquake Ground Motions.
.2 Health Canada/Workplace Hazardous Materials Information System (WHMIS)
.1 Material Safety Data Sheets (MSDS).
P a g e 1 | 4
Acoustical Ceilings for Minor Works ‐ Section 09 51 99
Retail Store Renovation ‐ Construction
.2 Store materials inside, level, under cover. Protect from weather, damage
from construction operations and other causes, in accordance with
manufacturer's printed instructions.
.3 Handle materials to prevent damage to edges or surfaces. Protect metal
accessories and trim from being bent or damaged.
.4 Store and protect acoustic ceiling materials from nicks, scratches, and
blemishes.
.5 Replace defective or damaged materials with new.
Part 2 Products
2.1 COMPONENTS
.1 Acoustic units to: CAN/CGSB-92.1.
.1 Edge type square.
.2 Colour White.
.3 Size 610 x 610 x 16 mm thick.
.4 Shape flat.
.5 Acceptable products:
.1 Radar ClimaPlus by CGC.
.2 Vantage 10 by Certainteed.
.3 Fine Fissured by Armstrong.
.2 Acoustical Suspension:
.1 Intermediate duty system to ASTM C635.
.2 Basic materials for suspension system: commercial quality cold rolled
steel, zinc coated.
.3 Suspension system: non fire rated, two directional exposed tee bar grid.
.4 Exposed tee bar grid components: shop painted satin sheen, white
colour. Components die cut. Main tee with double web, rectangular bulb
and 25 mm rolled cap on exposed face. Cross tee with rectangular bulb;
web extended to form positive interlock with main tee webs; lower flange
extended and offset to provide flush intersection.
.5 Hanger wire: galvanized soft annealed steel wire, 3.6 mm diameter for
access tile ceilings.
.6 Hanger inserts: purpose made.
.7 Accessories: splices, clips, wire ties, retainers and wall moulding reveal,
to complement suspension system components, as recommended by
system manufacturer.
.3 Performance/Design Criteria:
.1 Maximum deflection: 1/360th of span to ASTM C635 deflection test.
P a g e 2 | 4
Acoustical Ceilings for Minor Works ‐ Section 09 51 99
Retail Store Renovation ‐ Construction
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously installed
under other Sections or Contracts are acceptable for product installation in
accordance with manufacturer's written instructions prior to acoustical ceiling
installation.
.1 Visually inspect substrate in presence of Consultant.
.2 Inform Consultant of unacceptable conditions immediately upon
discovery.
.3 Proceed with installation only after unacceptable conditions have been
remedied and after receipt of written approval to proceed from
Consultant .
3.2 INSTALLATION
.1 Installation: in accordance with ASTM C636 except where specified otherwise.
.2 Suspension System:
.1 Erect ceiling suspension system after work above ceiling has been
inspected by Consultant.
.2 Secure hangers to overhead structure using attachment methods suitable
to accommodate imposed dead and seismic loads..
.3 Install hangers spaced at maximum 1200 mm centres and within 150 mm
from ends of main tees.
.4 Lay out system according to reflected ceiling plan.
.5 Install wall moulding to provide correct ceiling height.
.6 Completed suspension system to support super-imposed loads, such as
diffusers, lighting fixtures and grilles..
.7 Support diffusers and light fixtures with additional ceiling suspension
hangers within 150 mm of each corner and at maximum 600 mm around
perimeter of fixture.
.8 Interlock cross member to main runner to provide rigid assembly.
.9 Ensure finished ceiling system is square with adjoining walls and level
within 1:1000.
.3 Acoustic Panels:
.1 Install acoustical panels and tiles in ceiling suspension system.
.2 Co-ordinate ceiling work with work of other sections such as interior
lighting, fire protection communication, and intrusion and detection
systems.
3.3 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
P a g e 3 | 4
Acoustical Ceilings for Minor Works ‐ Section 09 51 99
Retail Store Renovation ‐ Construction
3.4 PROTECTION
.1 Protect installed products and components from damage during construction.
.2 Repair damage to adjacent materials caused by acoustical ceiling installation.
END OF SECTION
P a g e 4 | 4
Wood Strip and Plank Flooring ‐ Section 09 64 29
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Health Canada/Workplace Hazardous Materials Information System (WHMIS)
.1 Material Safety Data Sheets (MSDS).
1.5 MOCK-UPS
.1 Construct mock-up in accordance with Section 01 45 00 - Quality Control.
.2 Construct mock-up 10 m2 minimum, of wood strip flooring including one inside
corner and one outside corner.
.3 Mock-up will be used:
.1 To judge quality of work, substrate preparation, operation of equipment
and material application.
P a g e 1 | 4
Wood Strip and Plank Flooring ‐ Section 09 64 29
Retail Store Renovation ‐ Construction
P a g e 2 | 4
Wood Strip and Plank Flooring ‐ Section 09 64 29
Retail Store Renovation ‐ Construction
.2 Temperature:
.1 Maintain ambient temperature minimum of 18 degrees C and
minimum of 21 degrees C from7 days before installation to at least
48 hours after completion of work and maintain relative humidity
not higher than 40% during same period.
.2 Maintain minimum temperature 10 degrees C within area of
installation until final acceptance of building.
.3 Ensure substrate is within moisture limits prescribed by flooring
manufacturer.
.4 Maintain heat and humidity levels near occupancy levels for 5
days prior to delivery and until sanding and finishing are complete
during winter months.
Part 2 Products
2.1 MATERIALS
.1 Nydree Acrylic Infused Flooring or approved equivalent.
.1 Acrylic Infused 2.54mm thick genuine hardwood.
.2 Plywood platform; 4" wide plank: 9 mm thick, 7 ply marine grade baltic
birch.
.3 Laminating adhesive to contain no formaldehyde.
.4 Length: 12” to 47” random.
.5 Nominal thickness: 3/8"
.6 Tongue and groove sides and ends with micro-bevelled edges.
.7 Series: Maple Bella Luna
.2 Adhesive: Lecol, Wakol PU 225 Parquet Adhesive or approved equivalent.
.1 2-Component reaction adhesive according to DIN EN 14293.
.2 Solvent-free.
.3 Water-free, no wood swelling.
.3 Floor finish; Infused Colour: Natural, Topical Stain, Ivory.
.4 Underlayment: as recommended by manufacturer.
Part 3 Execution
3.1 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously installed
under other Sections or Contracts are acceptable for wood strip and plank
flooring installation in accordance with manufacturer's written instructions.
P a g e 3 | 4
Wood Strip and Plank Flooring ‐ Section 09 64 29
Retail Store Renovation ‐ Construction
3.2 PREPARATION
.1 Check and record moisture content of both flooring and subflooring before
beginning installation.
.1 Ensure moisture content is within acceptable limits in accordance with
manufacturer's written recommendations.
.2 Underlayment: Install underlayment per manufacturer’s written instructions.
.3 Concrete Subfloor:
.1 Grind down high spots with 20 grit (no. 3 ½) paper.
.2 Fill low spots with proper levelling compound.
.3 Clean up grease, oil and other contaminants, and sweep slab clean.
3.3 INSTALLATION
.1 Manufacturer's Instructions: comply with manufacturer's written
recommendations, including product technical bulletins, product catalogue
installation instructions, product carton installation instructions, and data sheets.
.2 Install finish flooring, with adhesive as indicated, parallel to long dimension of
room.
.3 Maintain expansion space at perimeter of floor surface as recommended by
manufacturer.
3.4 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools
and equipment in accordance with Section 01 74 11 - Cleaning.
3.5 PROTECTION
.1 Protect new floors from time of final set of adhesive until final inspection.
.2 Prohibit traffic on floor for 48 hours after installation.
.3 Repair damage to adjacent materials caused by wood strip plank flooring
installation.
END OF SECTION
P a g e 4 | 4
Resilient Flooring for Minor Works ‐ Section 09 65 99
Retail Store Renovation ‐ Construction
Part 1 General
P a g e 1 | 3
Resilient Flooring for Minor Works ‐ Section 09 65 99
Retail Store Renovation ‐ Construction
Part 2 Products
2.2 ACCESSORIES
.1 Primers and adhesives: of types recommended by resilient flooring manufacturer
for specific material on applicable substrate, above, on or below grade.
.1 Adhesives: VOC limit 50 g/L maximum.
.2 Primer: in accordance with manufacturer's recommendations for surface
conditions:
.1 VOC limit: 100 g/L maximum.
.2 Sub-floor filler and leveller: white premix latex requiring water only to produce
cementitious paste as recommended by flooring manufacturer for use with their
product.
.3 Metal edge strips: extruded aluminum, smooth, mill finish with lip to extend under
floor finish, shoulder flush with top of adjacent floor finish.
Part 3 Execution
3.1 PREPARATION
.1 Prepare for installation in accordance with manufacturer's written
recommendations.
.2 Remove sub-floor ridges and bumps and fill low spots, cracks, joints, holes and
other defects with sub-floor filler.
.3 Clean floor and apply filler; trowel and float to leave smooth, flat hard surface.
.1 Prohibit traffic until filler is completely cured and dry.
.4 Remove or treat existing adhesives to prevent residual bleeding through to new
flooring or interfering with bonding of new adhesives.
P a g e 2 | 3
Resilient Flooring for Minor Works ‐ Section 09 65 99
Retail Store Renovation ‐ Construction
3.3 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and
equipment in accordance with Section 01 74 11 - Cleaning.
.1 Remove excess adhesive from floor, base and wall surfaces without
damage.
3.4 PROTECTION
.1 Protect installed products and components from damage during construction.
.2 Protect new floors in accordance with manufacturer's printed instructions.
.3 Repair damage to adjacent materials caused by resilient flooring installation.
END OF SECTION
P a g e 3 | 3
Sheet Carpeting ‐ Section 09 68 16
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 ASTM International
.1 ASTM E662-09, Standard Test Method for Specific Optical Density of
Smoke Generated by Solid Materials.
.2 Carpet and Rug Institute (CRI)
.1 CRI Carpet Installation Standard 2009.
P a g e 1 | 7
Sheet Carpeting ‐ Section 09 68 16
Retail Store Renovation ‐ Construction
P a g e 2 | 7
Sheet Carpeting ‐ Section 09 68 16
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Manufacturers:
.1 Ensure manufacturer has minimum 5 years experience in manufacturing
components similar to or exceeding requirements of project.
.2 Description:
.1 Sealants: VOC limit 150 g/L maximum.
.2 Primer: in accordance with manufacturer's recommendations for surface
conditions:
.1 VOC limit: 100 g/L maximum.
.3 Carpet and Accessories:
.1 Green Label Plus certified.
2.2 PERFORMANCE
.1 Flame Resistance: Passes (DOC FF-1-70).
.2 Radiant Panel: Class 1 (ASTM E-648).
.3 Smoke Development: 450 or less per ASTM E662.
.4 Wear: maximum 10% of pile face fiber by weight for 10 years.
.5 Edge Ravel: none for 10 years.
.6 Static Generation: less than 3.5 kV Step.
.7 Stain resistance: Commercial Stain Protection.
.8 Soil Resistance: Commercial Anti-Soil Protection.
.9 Indoor Air Quality Certification: certified to CRI Green Label IAQ requirements.
P a g e 3 | 7
Sheet Carpeting ‐ Section 09 68 16
Retail Store Renovation ‐ Construction
2.3 FABRICATION
.1 Acceptable Product: Bolyu Wynford III, 6258.
.2 Colour: Black Magic 2702.
.3 Face construction:
.1 Woven.
.4 Pile Surface Appearance:
.1 Level loop:textured.
.5 Pile fibre: to Avalar SD Nylon.
.6 Dyeing Method: solution dyed.
.7 Stitch Count: 10.0 S.P.I.
.8 Average Density: 6,933.
.9 Secondary Backing: woven polypropylene.
.10 Mill Width: 12 ft..
.11 Gauge: 1/10 in.
.12 Yarn Weight Tufted: 26 oz/yd2.
.13 Finished Pile Height: minimum 3.5 mm average.
2.4 ACCESSORIES
.1 Seaming Sealer Adhesive:
.1 Type in accordance with carpet manufacturer's written instructions for
purpose intended.
.1 VOC limit: 50 g/L maximum.
.2 Adhesive:
.1 Multi-purpose adhesive type: in accordance with carpet manufacturer's
written instructions for direct glue down installation.
.2 On site application VOC limit: 50 g/L maximum.
.3 Transition Mouldings:
.1 Carpet edge/reducer strip: mill finish aluminum.
.4 Carpet protection: non-staining heavy duty kraft paper.
.5 Subfloor patching compound: Portland cement base filler, mix with latex to form
cementitious paste.
P a g e 4 | 7
Sheet Carpeting ‐ Section 09 68 16
Retail Store Renovation ‐ Construction
Part 3 Execution
3.1 INSTALLERS
.1 Use experienced and qualified technicians to carry out assembly and installation
of sheet carpet.
3.2 EXAMINATION
.1 Verification of Conditions: verify conditions of substrates previously installed
under other Sections or Contracts are acceptable for sheet carpet installation in
accordance with manufacturer's written instructions.
.1 Inform Consultant of unacceptable conditions immediately upon
discovery.
.2 Proceed with installation only after unacceptable conditions have been
remedied.
3.3 PREPARATION
.1 Subfloor Preparation:
.1 Inspect concrete and determine special care required to make it suitable
for carpet.
.2 Remove dust, old adhesive, dirt, sealer and wax from existing surfaces.
.3 Remove ridges and bumps.
.4 Fill and level cracks 3 mm wide or protrusions over 0.8 mm with
appropriate and compatible latex patching compound. Apply sub-floor
filler to low spots and cracks to achieve floor level to a tolerance of 1:500.
Allow filler to cure.
.5 Comply with manufacturer's written recommendations for maximum patch
thickness.
.6 Prime large patch areas with compatible primer.
.7 Ensure concrete substrates are cured, clean and dry.
.8 Ensure concrete substrates are free of paint, dirt, grease, oil, curing or
parting agents, and other contaminates, including sealers, that interfere
with the bonding of adhesive.
.9 Where powdery or porous concrete surface is encountered, apply primer
compatible with adhesive to provide a suitable surface for glue-down
installation.
.2 Sheet Carpet Preparation:
.1 Pre-condition carpeting: following manufacturer's written instructions.
3.4 INSTALLATION
.1 Install sheet carpet in accordance with manufacturer's written instructions, and
CRI Carpet Installation Standard and co-ordinate with Section 01 73 00 -
Execution.
P a g e 5 | 7
Sheet Carpeting ‐ Section 09 68 16
Retail Store Renovation ‐ Construction
.2 Co-ordinate sheet carpet work with work of other trades, for proper time and
sequence to avoid construction delays.
.3 Install carpeting using minimum of pieces.
.4 Install carpet after finishing work is completed but before demountable office
partitions and telephone and electrical pedestal outlets are installed.
.5 Inspect finished installation for smooth wearing surface free from conspicuous
seams, burring and other faults.
.6 Use material from same dye lot.
.1 Ensure colour, pattern and texture match within visual areas.
.2 Maintain constant pile direction.
.7 Adhesive seams and cross-joints.
.1 Ensure seams are sealed.
.8 Fit around architectural, mechanical, electrical and telephone outlets, and
furniture fitments, around perimeter of rooms into recesses, and around
projections.
.9 Extend carpet into toe spaces, door reveals, closets, open-bottomed
obstructions, removable flanges, alcoves, and similar openings.
.10 Install carpet smooth and free from bubbles, puckers, and other defects.
3.7 SEAMS
.1 Seal edges of cut-outs with binding method.
.2 Ensure visibility of carpet seams and joints are acceptable industry standards.
3.8 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools
and equipment in accordance with Section 01 74 11 - Cleaning.
.1 Vacuum carpets clean immediately after completion of installation.
P a g e 6 | 7
Sheet Carpeting ‐ Section 09 68 16
Retail Store Renovation ‐ Construction
3.9 PROTECTION
.1 Protect installed products and components from damage during construction.
.2 Prohibit traffic on carpet for period of 24 hours minimum after installation and
until adhesive is completely cured.
.3 Install carpet protection to satisfaction of Consultant.
.4 Repair damage to adjacent materials caused by sheet carpeting installation.
END OF SECTION
P a g e 7 | 7
Painting for Minor Works ‐ Section 09 91 99
Retail Store Renovation ‐ Construction
Part 1 General
1.1 REFERENCES
.1 Health Canada/Workplace Hazardous Materials Information System (WHMIS)
.1 Material Safety Data Sheets (MSDS).
.2 The Master Painters Institute (MPI)
.1 Architectural Painting Specification Manual - current edition.
.2 Maintenance Repainting Manual - current edition.
P a g e 1 | 6
Painting for Minor Works ‐ Section 09 91 99
Retail Store Renovation ‐ Construction
Part 2 Products
2.1 MATERIALS
.1 Supply paint materials for paint systems from single manufacturer.
.2 Conform to latest MPI requirements for painting work including preparation and
priming.
P a g e 2 | 6
Painting for Minor Works ‐ Section 09 91 99
Retail Store Renovation ‐ Construction
P a g e 3 | 6
Painting for Minor Works ‐ Section 09 91 99
Retail Store Renovation ‐ Construction
Part 3 Execution
3.1 GENERAL
.1 Compliance: comply with manufacturer's written recommendations or
specifications, including product technical bulletins, handling, storage and
installation instructions, and data sheets.
.2 Perform preparation and operations for interior painting in accordance with MPI -
Architectural Painting Specifications Manual except where specified otherwise.
3.2 EXAMINATION
.1 Investigate existing substrates for problems related to proper and complete
preparation of surfaces to be painted. Report to Consultant damages, defects,
unsatisfactory or unfavourable conditions before proceeding with work.
.2 Conduct moisture testing of surfaces to be painted using properly calibrated
electronic moisture meter, except test concrete floors for moisture using simple
"cover patch test". Do not proceed with work until conditions fall within
acceptable range as recommended by manufacturer.
3.3 PREPARATION
.1 Protection of in-place conditions:
.1 Protect existing building surfaces and adjacent structures from paint
spatters, markings and other damage by suitable non-staining covers or
masking. If damaged, clean and restore surfaces as directed by
Consultant.
.2 Protect items that are permanently attached such as Fire Labels on doors
and frames.
.3 Protect factory finished products and equipment.
.2 Surface Preparation:
P a g e 4 | 6
Painting for Minor Works ‐ Section 09 91 99
Retail Store Renovation ‐ Construction
3.4 APPLICATION
.1 Paint only after prepared surfaces have been accepted by Consultant
.2 Use method of application approved by Consultant.
.1 Conform to manufacturer's application recommendations.
.3 Apply coats of paint in continuous film of uniform thickness.
.1 Repaint thin spots or bare areas before next coat of paint is applied.
.4 Allow surfaces to dry and properly cure after cleaning and between subsequent
coats for minimum time period as recommended by manufacturer.
.5 Sand and dust between coats to remove visible defects.
P a g e 5 | 6
Painting for Minor Works ‐ Section 09 91 99
Retail Store Renovation ‐ Construction
.6 Finish surfaces both above and below sight lines as specified for surrounding
surfaces, including such surfaces as tops of interior cupboards and cabinets and
projecting ledges.
.7 Finish top, bottom, edges and cutouts of doors after fitting as specified for door
surfaces.
.8 Mechanical/Electrical Equipment:
.1 Paint conduits, piping, hangers, ductwork and other mechanical and
electrical equipment exposed in finished areas, to match adjacent
surfaces, except as indicated.
.2 Do not paint over nameplates.
.3 Keep sprinkler heads free of paint.
.4 Paint fire protection piping red.
.5 Paint disconnect switches for fire alarm system and exit light systems in
red enamel.
.6 Paint natural gas piping yellow.
.7 Paint both sides and edges of backboards for telephone and electrical
equipment before installation.
.1 Leave equipment in original finish except for touch-up as required,
and paint conduits, mounting accessories and other unfinished
items.
3.5 CLEANING
.1 Progress Cleaning: clean in accordance with Section 01 74 11 - Cleaning.
.1 Leave Work area clean at end of each day.
.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and
equipment in accordance with Section 01 74 11 - Cleaning.
.3 Place stains and paint defined as hazardous or toxic waste, including tubes and
containers, in containers or areas designated for hazardous waste.
END OF SECTION