MBA 641 Group Assignment Edited Getacher
MBA 641 Group Assignment Edited Getacher
June 2016
1
DBU
1. MOHA Soft Drink Company is distributing its products from its three factories
located at Bure, Dessie and Hawassa to four demanding centers: Addis Ababa,
Mekelle, Dire Dawa and Adama. The demand pattern for a product at four consumer
centers: Addis Ababa, Mekelle, Dire Dawa and Adama are 5000 bottles, 7000 bottles,
4000 bottles and 2000 bottles respectively. The supply for these centers is from
three factories Bure, Dessie and Hawassa. The capacities for the factories are 3000
bottles, 6000 bottles and 7000 bottles respectively. The unit transportation cost in
Birr from a factory to consumer center is given below in the matrix.
FROM TO
Addis Ababa Mekell Dire Dawa Adam
e a
Bure 8 9 12 8
Bessie 3 4 3 2
Hawassa 5 3 7 4
SOLUTION
Given
FROM TO supply
Addis Ababa Mekelle Dire Dawa Adama
Bure 8 9 12 8 3000
Bessie 3 4 3 2 6000
Hawass 5 3 7 4 7000
a
Demand 5000 7000 4000 2000 16000
18000
2
Sine total demand is greater than total supply by 2000 units, add a dummy row with 0
unit cost and 2000 units of supply. See the following table
FROM TO supply
Addis Ababa Mekelle Dire Dawa Adama
Bure 8 9 12 8 3000
Bessie 3 4 3 2 6000
Hawass 5 3 7 4 7000
a
Dummy 0 0 0 0 2000
Demand 5000 7000 4000 2000 18000
18000
Then the demand and supply are balanced.
To find initial feasible solution using North West Method.
FROM TO supply
Addis Ababa Mekelle Dire Dawa Adama
Bure 3000 8 9 12 8 3000
Bessie 2000 3 4000 4 3 2 6000
Hawass 5 3000 3 4000 7 4 7000
a
Dummy 0 0 0 2000 0 2000
Demand 5000 7000 4000 2000 18000
18000
m + n-1= 4+4-1 = 7 the number of occupied cells. But here the number of occupied
cells are 6 it is degenerate and impossible to
FROM TO supply
Addis Ababa Mekelle Dire Dawa Adama
Bure 8 9 3000 12 8 3000
Bessie 4000 3 4 3 2000 2 6000
Hawass 1000 5 5000 3 1000 7 4 7000
a
Dummy 0 2000 0 0 0 2000
Demand 5000 7000 4000 2000 18000
18000
3
m + n-1= 4+4-1 = 7 the number of occupied cells. But here the number of
occupied cells are 6
Total transportation cost =
TO suppl penality
Addis Ababa Mekelle Dire Dawa Adama y
Bure 8 3000 12 8 3000 1,1,1,1,1,1,1
9
Dessie 5000 3 1000 3 2 6000 1,1,1,2---
4
Hawassa 5 2000 3000 7 2000 4 7000 1,1,1,1,1,1--
3
Dummy 0 2000 0 0 2000 0-------
0
Demand 5000 7000 4000 2000 18000
18000
penality 3 1 3 2
3 1 3 2
3 1 3 2
3 1 5 2
- 1 - 2
1
m + n-1= 4+4-1 = 7 the number of occupied cells. But here the number of
occupied cells are 6
Total transportation cost =
2. GONZE Company has four factories that supply to five warehouses. The variable
cost of manufacturing and shipment of one ton of product from each factory to each
warehouse are shown in the matrix given below, Factory capacities and warehouse
requirements are shown in the margin.
4
X 13 6 11 11 12 45
Y 6 17 9 12 12 30
Z 15 20 11 14 6 50
Demand 40 20 50 30 40
Solution
Given :-
Since the above given problem is not balanced, we add a dummy column; i.e Sine
total supply is greater than total demand by 20 units, add a dummy column with 0 unit
cost and 20 units of demand. See the following table
To find the initial feasible solution using North West Method.
Supply
A B C D E Dummy
column
W 40 20 15 75
17 9 14 10 14 0
X 35 10 45
13 6 11 11 12 0
Y 20 10 30
6 17 9 12 12 0
Z 30 20 50
15 20 11 14 6 0
Demand 40 20 50 30 40 20 200
200
Total transportation cost = ( 40*17) + ( 20*9 ) +( 15*14 ) + ( 35*11) + ( 10*11)+ ( 20*12 )
+( 10*12) + ( 30*6) + ( 20*0)
= 680+ 180+ 385 + 110+ 240 + 120 + 180 + 0
= 2105
5
To find the initial feasible solution using Least Cost Method
Supply
A B C D E Dummy
column
W 10 15 30 14 20 75
17 9 14 10 0
X 20 25 11 45
13 6 11 12 0
Y 30 30
6 17 9 12 12 0
Z 10 40 50
15 20 11 14 6 0
Demand 40 20 50 30 40 20 200
200
6
Z 10 40 50 6,6,1,4,4,--
15 20 11 14 6 0
Demand 40 20 50 30 40 20 200
200
7 3 2 1 6 0
7 3 2 1 6 -
2 3 2 1 2 -
2 - 2 1 -
2 2 1
2 5 1
2 - 1
- 1
4. Consider the following information carefully and do as per the instruction given
7
ACTIVITY Immediate Optimistic Pessimistic Most Probable
A. Construct PERT network and calculate Earliest Start (ES), Earliest Finish
(EF), Latest Start (LS) and Latest Finish (LF) time of the project.
D. Can activity A be delayed without delaying the whole project? If so, how
many days?
E. Can activity B be delayed without delaying the whole project? If so, how
many days?
8 7 D 15
8 2 4
0
6 7
1
B F
3
5
8
5. Three strategies and three states of nature are given and payoffs represent profits.
State of nature
N1 N2 N3
Strategy
S1 47 49 33
S2 32 25 41
S3 51 30 14