Method Statement For Flushing & Chemical Cleaning Procedure of Chilled Water System
Method Statement For Flushing & Chemical Cleaning Procedure of Chilled Water System
:
CLIENT ANME HERE
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 1 of 10
Project :
MEP Contractor :
Document No. :
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 2 of 10
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 3 of 10
TABLE OF CONTENTS
1. Scope ………………………………………………………………………………… 4
2. Responsibilities....………………………………………………………………….. 4.5
3. Equipment & Materials……......…………………………………………………… 5
4. Objective……………………………………………………………………………… 5
5. Flushing……………………………………..……………………………………….. 6.7
6. Chemical Cleaning.………………………………………………………………… 8.9
7. Health & Saftey……………………………..…….…………………………………. 9
8. Attachment…………………………………………………………………………… 9
1. SCOPE :
1.0 This method statement specify the detailed requirements and procedures for
Brought you by udistinguish.com Contact us [email protected]
Doc. No.:
CLIENT ANME HERE
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 4 of 10
Performing flushing & chemical of all above & under chilled water piping
system with in this project.
1.1 After completing this work of chilled water piping will be ready for the
commissioning and start up.
2. RESPOSIBILITIES:
2.0 The Construction Manager will ensure all preparations & installation works
are carried out according to Project Specification , the progress are carried
out according to the planned program, as per approved method statements
to cooperate with the Main Contractor regarding the implementation of any
comments raised by the company & to ensure all safety & quality
control are implemented.
2.1 The Site Engineer will ensure that the installation works are carried out
according to Project Specification ,Manufacturer data sheet , Approved
Method Statement , Safety Regulations & to distribute responsibilities
to his construction team & provide them with information for the installation
works.
2.2 To ensure the compliance of works with the related approved quality
control procedure & Company requirements & to coordinate with the Q.C.
Engineer to advise for the area raise for inspection.
2.3 To inspect & satisfy of the soundness completed works before requesting
Main Contractor to seek company approval & inspection.
2.4 To initiate inspection & test request from the Company approval through
the Main Contractor.
2.5 To advise the construction team of the specific requirements related to
work quality.
2.6 To maintain comprehensive inspection & test record any further reference
& documentation.
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 5 of 10
4. OBJECTIVE:
4.0 During construction of pipe work some contaminant will inevitably enter
in to the piping system like dust, welding slag, jointing compound, dirt &
debris. These contaminant if not removed form the system might affect the
performance of the system & shortening the life of the equipment with in
water system, block the cooling coils &wearing of pump blades.
4.1 The objective if flushing is to produce a clean water system free from all
these contaminants to obtain efficient operation.
4.2 However, flushing the system will not remove metal oxides, scales & other
deposits that adhered to the internal pipe surface.
4.3 Therefore, Chemical cleaning is initially required to remove all this deposits
from the pipe.
5. FLUSHING :
5.0.0 Visually check of all piping system must be ready for flushing, all
drain valves must be closed, all isolating valves & strainers are
accessible, and all temporary work must be removed.
5.0.1 Closed isolated valves serving fan coil unit and air handling unit &
bye pass chiller.
5.0.2 Chiller water system must be flushed with clean water as
follows:
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 6 of 10
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 7 of 10
5.1.0 The chilled water system shall be filled with water as described
In section 5.0.2.0 & 5.0.2.1 , air vented and circulated using
one primary pump in to 2 hours. ( Temporary pumps must be
used in initial flushing around the chilled bypass line if its
possible to start the permanent pump until the time of
flushing). Make up water shall be available to compensate
simultaneously.
5.1.1 Strainer screen within the system must be cleaned interval
regularly until the screen shows on dirt inside.
5.1.2 Drain valves for pumps & chillers on ground floor of each
building main entrance shaft must be open to drain one a time
to obtain maximum velocity. Circulation must b continuously
filling and drain.
5.1.3 Flushing this way ( Circulating & Draining ) must be continue
for at least a period of 24 hours.
5.1.4 Water sample must be clear from suspended matter and also
must be accept by the water treatment specialist prior to the
start of chemical cleaning.
6. CHEMICAL CLEANING
6.0.0 Chilled water system must be drain partially and fill with clear water.
Brought you by udistinguish.com Contact us [email protected]
Doc. No.:
CLIENT ANME HERE
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 8 of 10
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 9 of 10
7.0 All installation will in accordance with project safety plan and the
Main Contractor Safety Rules and Regulation.
7.1 Strictly follow manufacture Contractor Safety recommendation for handling
and use of the materials.
7.2 Ensure all involve personnel are aware of the same.
8. ATTACHMENT
REV.
PROJECT NAME HERE Date:
0
METHOD STATEMENT
Page No. : 10 of 10