Damanganga-Pinjal Link Project EIA PDF
Damanganga-Pinjal Link Project EIA PDF
Damanganga-Pinjal Link Project EIA PDF
8.0 General
Owing to the fact, that the most of the commercial activities and job
opportunities are urban centric, the rural population continues to migrate
towards the urban centres. Owing to increase in urbanisation there is
continuous improvement in the living standards of the people, and the pace
of industrial and other development, many of the Metropolitan cities are
436
expected to face acute shortage of water for domestic and industrial
purposes. The rate of population growth of Metropolitan City of Greater
Mumbai over the decades is unprecedented. With population more than 18
million, it is one of the ten largest mega cities of the world. With the
present pace of development of Greater Mumbai, it is anticipated that there
would be acute shortage of domestic water in the year – 2050.
437
link project will augment about 895 Mm3: 579 Mm3 (1586 MLD) from
Damanganga basin; and 316 Mm3 (865 MLD) from Pinjal basin.
438
vii. A 545 m long Roller Compact Concrete Gravity dam across river
Pinjal (a tributary of Vaitarna river) proposed by Government of
Maharashtra and MCGM near village Khidse with FRL of 145.0 m
and corresponding gross storage capacity of 483.0 Mm3 and a saddle
dam of about 190 m long and 11.4 m high on the right flank. The
main dam is located at Latitude: 190 47’ 00” N and Longitude: 730
13’ 00” E.
viii. Conveyance system beyond Pinjal dam to carry water upto Mumbai
city to be planned by MCGM.
The study area considered for the environmental impact assessment studies
and preparation of environmental management plan comprise the following:
439
across river Vagh (a tributary of Damanganga river) near village Behadpada
in Jawhar taluka of Thane district in Maharashtra State.
Bhugad Dam Site: Based on the study of aerial photographs of the project
area two alternative dam alignments were selected for study. The dam axis
A - I is about 250 m upstream of Bhugad village while dam axis A - II is
located about 300 m downstream of Bhugad village. Detailed geotechnical
evaluation of alternative dam axis A –I and A –II was done. On comparative
evaluation, the dam axis A-II has been opted for (i) Shorter length of the
dam as compared to A-I axis, (ii) Shallow foundation in the central river and
on right bank, (iii) Retaining wall needed only on left bank as compared to
high retaining wall on either banks required for A-I axis and (iv) Suitable
conditions available to house spillway on central river bed with proper
location for stilling basin and flood routing.
440
8.2.2 No Project Option
441
for approval. The MoEF vide letter No. J-12011/56/2008-IA.I dated 3rd
December, 2008 (Annexure – 1.11 in Volume - II) indicated that the
Damanganga-Pinjal Link Project being drinking water supply project does
not cover under the provisions of EIA Notifications – 2006. As such,
Damanganga-Pinjal Link Project will not require clearance from the
Ministry of Environment & Forests. The Bhugad and Khargihill reservoirs
of Damanganga-Pinjal Link Project will involve the shifting of the families
residing in the villages likely to be affected by these reservoirs. This project
affected families are required to be resettled at the new locations. Therefore,
with a view to compensate the Project Affected Families (PAFs) ensuring
that the proper facilities in the re-settlement colonies are provided, a
Resettle & Rehabilitation Plan has been evolved. While formulating the
Resettlement & Rehabilitation Plan, the provisions of National Policy on
Resettlement & Rehabilitation (NPRR) - 2007 have been kept in view.
Various provisions of the Resettlement & Rehabilitation Policies of Gujarat
and Maharashtra States are compared with the provision of NPRR – 2007
and best of the provision have been adopted. The project is lying in the
tribal area as such the R&R plan required clearance from Ministry of Tribal
Affairs. The Damanganga-Pinjal Link Project is required about 1008 ha of
forest land, as such forest clearance under forest (Conservation) Act, 1980 is
required. A provision for afforestation in double the area in de-graded
forests has been kept as per the Forests (Conservation) Act, 1980. No Wild
Life Sanctuaries or National Parks are located in the project area. The
project will also require Techno-economic clearance from Central Water
Commission; investment clearance from Planning Commission; and
Consent to Establish from Maharashtra and Gujarat Pollution Control
Boards under Water (Prevention and Control of Pollution) Act 1974 and
The Air (Prevention and Control of Pollution) Act 1981.
The Geological Survey of India (GSI), Nagpur vide their letter No.
329/EG/GSI/2010 dated 26th July, 2010 (Annexure – 2.3 in Volume - II) had
indicated that the area of Damanganga-Pinjal Link Project is devoid of any
minerals of significant importance. Similarly, Archaeological Survey of
India, Aurangabad vide their letter No. 12/2009-10/Tech-3036 dated 17th
February, 2011 (Appendix – 2.1 in Volume – III(A)) have submitted the
brief report on archaeological exploration and informed that no monuments
or remains of archaeological Importance were noticed in the area of
442
Damanganga-Pinjal Link Project. As such, the No Objection Certificates
(NOCs) from Ministry of Coal & Mines and Archaeological Survey of India
are not required.
The sources of air pollution in the study area are vehicular traffic,
dust arising from unpaved village roads and domestic fuel burning. The
prime objective of the baseline air quality study was to establish the existing
ambient air quality of the area. The baseline status of the ambient air quality
has been established through a scientifically designed ambient air quality
monitoring network. The monitoring of ambient air quality has been done
for summer and winter seasons. The Ambient Air Quality in the project area
has been Monitoring at 19 locations. The list of ambient air quality
monitoring stations monitored is in Table - 8.1. The parameters such as
Suspended Particulate Matter (SPM), Respirable Suspended Particulate
Matter (PM10), Sulphur dioxide (SO2) and Oxides of Nitrogen (NOx) have
been monitored.
443
Table-8.1
Location of Ambient Air Quality (AAQ) Monitoring Stations
Stations Sampling Dam site Direction Distance
Location w.r.t site (Km)
A1 Toranmal Bhugad E 3
A2 Khadki Bhugad E 6
A3 Torangan Bhugad SE 1
A4 Harsul Bhugad S 2
A5 Kotambi Bhugad E 7
A6 Mulvad Khargihill N 2
A7 Ozarkhed Khargihill N 1
A8 Dhadhri Khargihill Catchment --
Area
A9 Mokhada Khargihill S 11
A10 Chas Khargihill SE 7
A11 Brahmanpada Khargihill E 6
A12 Peint Bhugad NE 6
A13 Ambai Khargihill NE 8
A14 Gavtha Khargihill E 2
A15 Pipalset Bhugad N 4
A16 Sarvartai Bhugad N 6
A17 Kaprada Bhugad NW 14
A18 Bapanvihir Link E 1
A19 Khadaohel Link E 1
The testing procedure adopted for monitoring of various ambient air quality
parameters is in Table – 8.2.
444
Table – 8.2
Testing Procedure Adopted for Various
Ambient Air Quality Parameters
Parameter Description IS Code Testing Procedure
445
Based on the findings of the ambient air quality survey, conducted for
the summer and winter seasons, it can be concluded that the ambient air
quality is quite good in the area. The values of these parameters were well
below the permissible limits specified for residential, rural and other areas.
The absence of industries and low vehicular traffic can be attributed for
good ambient air quality in the project area.
8.4.1.3 Meteorology
446
The average rainfall in the project area is 2245 mm. Most of the
rainfall is received during monsoon season i.e. from June to September.
There is wide variation in the occurrence of rainfall in the project area
ranging from 1657 mm annual at Harsul rain gauge station to 2983 mm
annual at Jawhar rain gauge station.
The water quality monitoring has been done in the study area for
three seasons: Summer Season (June, 2010); winter season (December,
2010); and Monsoon Season (August-September, 2011). The quality of
surface water has been ascertained from the chemical and physic-chemical
analysis of water samples collected from different river bodies. Grab
sampling method was used for collection of water samples. Ground water
samples were taken from the hand pumps. The methods adopted for water
testing are given in Table – 8.3 and the sampling locations are listed in
Table – 8.4
Table – 8.3
Protocols Adopted for Analysis of Various Water Quality Parameters
Testing
Parameters Unit Protocol
Procedure
IS :2488 Part – 1 Electrometric
pH @ 25 oC -
1966 Method
APHA (21st Edition)- Thermometry
Temperature (0C)
2550 B : Page 2 -61 Method
Dissolved Oxygen, IS – 3025 (Part–38): Wrinkler's
mg/l
DO 1989 Method
IS – 3025 (Part–44):
Modified
Biological Oxygen 1993
mg/l Wrinkler's
Demand ,BOD (Reaffirmed 1999)
Method
Edition 2.1 (2000 -
447
Testing
Parameters Unit Protocol
Procedure
10)
APHA (21st Edition)-
Chemical Oxygen Dichromate
mg/l Open Reflux Method
Demand, COD Reflux Technique
5220 B Page 5-15
IS: 3025 (Part-16) Water bath
Total Dissolved
mg/l 1984 (Reaffirmed Evaporation
Solids TDS
1996) Method
IS: 3025 (Part-17)
Total Suspended Filtration & Water
mg/l 1984 (Reaffirmed
Solids, TSS bath Evaporation
2002)
APHA (21st Edition)
Calcium as Ca+ mg/l – 3500 – Ca B : Page EDTA Method
3-65
APHA (21st Edition)
Calcium Hardness Calculation
mg/l – 3500 – Ca B : Page
as CaCO3 Method
3-65
APHA (21st Edition)
Magnesium as Calculation
mg/l – 3500 – Mg B : Page
Mg+ Method
3-84
Magnesium APHA (21st Edition)
Calculation
Hardness as mg/l – 3500 – Mg B : Page
Method
CaCO3 3-84
Total Hardness as APHA (21st Edition)
mg/l EDTA Method
CaCO3 – 2340 C Page 2 - 37
APHA (21st Edition) Flame
Sodium as Na mg/l – 3500 – Na B : PagePhotometric
3-98 Method
Flame
APHA (21st Edition)
Potassium as K mg/l Photometric
– 3500 – K B :
Method
Sodium
Calculation
Absorption Ration -- --
Method
(SAR)
Nitrogen APHA (21st Edition) Titrimetric
mg/l
Ammonia NH3-N – 4500 – NH3 C Method
448
Table – 8.4
List of Water Sampling Locations
Sr. Project River Village Sampling Location
No. component
Dam/tunnel
A Winter and Summer Seasons
1 Bhugad Damanganga Khadki Khadki
2 Bhugad Ras River Khadki 2 km Before
Khadki
3 Bhugad Kakad Jogmodi Jogmodi
4 Khargihill Chasna River Chas Chas
5 Bhugad Ground Water Torangan Hand Pump
6 Bhugad Ground Water Peint Restaurant
7 Bhugad Damanganga Savda Between Bila and
Savda
8 Link tunnel Tan River Khalachipada Khalachipada
9 Link tunnel Vagh river Ojerkhed 2 km From
Ojerkhed
10 Bhugad Damanganga Kotambi Kotambi
11 Bhugad Ground Water Harsul Villager’s House
12 Bhugad Ground Water Toranmal Hand Pump
13 Khargihill Lendi River Dhadhri Dhadhri
14 Khargihill Bet (Vagh) Mulvad Mulvad
River
15 Khargihill Vagh River Baldhapada Between Chas To
Ambai
16 Khargihill Ground Water Mokhada Villager’s House
17 Khargihill Lake Water Mokhada Near City Survey
Office
18 Khargihill Dhamni River Mokhada 2 km From
Mokhada
19 Khargihill Ground Water Ambai Hand Pump
20 Khargihill Ground Water Vavar Gram Panchayat
Office
21 Khargihill Ground Water Gavtha Hand Pump
22 Khargihill Vagh River Pehadpada Pehadpada
449
The result of Water Quality Monitoring indicates that:
ii. The TDS level in the study area ranged from 122 to 425 mg/l in
summer season; 68 to 400 mg/l in winter seasons; and 88 to 225 mg/l
in Monsoon seasons. The TDS level of various samples is well within
the permissible limit of 500 mg/l specified for drinking water and also
within the cause for rejection limit of 1500 mg/l.
iii. The hardness level ranged from 40 to 160 mg/l in summer season; 20
to 135 mg/l in winter seasons; and 76 to 120 mg/l in monsoon season
which indicates the soft nature of water. The hardness level is well
within the permissible limit of 200 mg/l specified for drinking water
iv. In monsoon season DO level ranged from 5.6 to 6.1 mg/l ; BOD
values are not detectable at many locations only at two or three
locations it is found in range of 1 to 3 mg/l well within the
permissible limits, which indicates that the organic pollution loading
entering the water bodies is well within the carrying capacity. The
low COD values also indicate the absence of chemical pollution
loading in the area. The marginal quantity of pollution load which
enters the water bodies gets diluted. The concentration of boron is in
range of 0.05 mg/l to 0.2 mg/l which is well within the permissible
limit ; concentration of Chloride is in range of 36 mg/l to 65 mg/l
which is well within the permissible limit of 200 mg/l for drinking
water quality; concentration of Sulphates is in range of 7 mg/l to 14
mg/l which is well within the permissible limit of 200 mg/l for
drinking water quality; concentration of Fluorides is in range of 0.4
mg/l to 0.55 mg/l use of water with fluoride level less than 1.0 mg/l
can lead to dental caries.
450
8.4.2.2 Ground Water Quality Monitoring
The Ground Water quality monitoring in the study area was done
during monsoon season at 8 sampling locations. The analysis of the
collected samples was carried out in the laboratory as per the standard
respective protocols. The summery of monsoon season ground water
monitoring is given below:
pH level in the study area ranged from 7.3 to 8.1 which indicates the
neutral nature of the water, and are within the permissible limit of 6.5 to 8.5
specified for meeting drinking water requirements; TDS level ranged from
136 to 197 mg/l which is well within the permissible limit of 500 mg/l
specified for drinking water and also within the cause for rejection limit of
1500 mg/l; hardness level ranged from 80 to 160 mg/l indicating soft nature.
The hardness level generally is well below the permissible limit of 200 mg/l
specified for drinking water.
The permissible limit for class E water (Irrigation use) as per IS: 2296
for Boron is 2.0 mg/l. The concentration of boron is in the range of 0.04
mg/l to 0.13mg/l which is well within the permissible limit.
The land use and land cover information of the catchment area of
Bhugad and Khargihill dams has been mapped using the satellite data of
dated 24th December, 2008; 16th February, 2008; and 10th February 2009
of IRS P6 LISS IV MX sensor of the IRS series of satellite having
resolution of 5.8 meters. Various major categories like Agricultural land,
451
Wasteland, Water body, etc. were identified and mapped. Area statistics is
calculated for different Land use/Land cover categories and furnished in
Table - 8.5 and 8.6 respectively for the catchment area of Bhugad and
Khargihill dam sites.
Table: 8.5
Catchment Area of Bhugad Dam - Land Use/Land Cover Statistics
S. No. Description % Area Area (Km2)
1 Built-up area (Residential
& Industrial) 1.07 7.56
2 Agricultural Land 9.98 70.69
3 Scrub 1.59 11.23
4 Dense Forest 33.38 236.31
5 Open Forest 50.84 359.94
6 River/ Water bodies 3.14 22.26
Total 100.00 708.00
Table: 8.6
Catchment Area of Khargihill Dam - Land Use/Land Cover Statistics
S. No. Description % Area Area (Km2)
1 Built-up area (Residential
& Industrial) 0.96 6.19
2 Agricultural Land 1.61 10.44
3 Scrub 1.16 7.46
4 Dense Forest 36.21 233.94
5 Open Forest 57.16 369.28
6 River/ Water bodies 2.90 18.71
Total 100.00 646.00
The catchment areas of Bhugad and Khargihill reservoirs are lying in Nasik
and Thane districts of Maharashtra state and Valsad district of Gujarat state.
The Engineering Geological Division of GSI, Nagpur vide Letter No.
329/EG/GSI/2010 dated 26th July, 2010 (Annexure – 2.3 in Volume - II)
informed that both the reservoirs are devoid of any mineral of economic
importance.
452
8.4.3.3 Historic/Archaeological Monuments
The Archaeological Survey of the project area has been carried out by
Archaeological Survey of India (ASI), Aurangabad Circle during May, 2009
and December, 2010. The Superintending Archaeologist, ASI, Aurangabad
Circle vide their F. .No.12/2009 -10/Tech-3036 dated 17-2-2011 (Appendix
– 2.1 in Volume – III(A)) submitted the brief report on the archaeological
survey and informed that no monuments or any remains of archaeological
importance were noticed at dam sites and in the submergence area of
Bhugad and Khargihill reservoirs proposed under Damanganga - Pinjal Link
Project.
8.4.3.4 Geology
The local geology of the link project area, which lies west of Trimbak in
northern part of Western Ghats is made up of a thick pile of Deccan lava
flows consisting of compound Pahoehoe; and simple flows that are grouped
as Salher and Ratangarh formations. The Bhugad reservoir lies in the
Deccan Volcanics. The rock assemblage exposed is classified as Salher
formation, which comprises of group Pahoehoe flows successions. No major
fault or shear zone was noticed in the area. The rock type encountered is
moderate to highly amygdular basalt, which is generally non-porphyritic in
nature with occasional thin bands of massive basalt occurring in it. The
Khargihill reservoir area is made of Pahoehoe and flows of Deccan
volcanics belonging to lower part of Salher Formation. The rocks are hard
massive, and devoid of any fault or shear zones. The rocks encountered are
massive basalt and amygdular basalt.
8.4.3.5 Soils
Damanganga – Pinjal link has been planned as drinking water supply project
which is devoid of any irrigation component, as such, the soil quality was
monitored at various locations in the catchment area only. The monitoring
has been conducted for three seasons, i.e. summer season (June, 2010),
winter season (December 2010) and Monsoon (Septmber-2011). The lists of
parameters monitored along with Protocols used for analysis are given in
453
Table – 8.7. The list of Sampling Locations is given in the Table – 8.8. As
per EIA manual, the soil sample has been collected once in a season.
Table: 8.7
Soil Quality Parameters Monitored and the List of Protocols
Table: 8.8
List of Soil Sampling Location
454
The season wise findings of soil monitoring are briefly described below:
455
between 0.074 gm/Kg to 0.38 gm/Kg; concentration of Sodium (Na)
is in the range between 0.092 gm/Kg to 0.97 gm/Kg; concentration of
Potassium (K) is in the range between 0.006 % to 0.279 %;
concentration of Total Phosphorus (P) is in the range between 0.16 %
to 0.23 %; and concentration of Total Nitrogen is in the range
between 0.07% to 0.26 %.
The study area falls in the South Indian Tropical Moist Deciduous
forests. Mainly two categories of the forest types are found in the study area
are: (i) Southern Indian Moist Deciduous Forests; and (ii) Southern Dry
Deciduous Forests. Detailed ecological survey in the area of Damanganga –
Pinjal link project was conducted for three seasons: (i) Winter season
(February, 2012); Summer season (April, 2012); and Post Monsoon season
(October, 2012). Status of flora was assessed using circular plot of various
sizes for trees, shrubs, herbs and grass species. Fifteen, ten and 2 m radius
plots were used to quantify trees, shrubs and herbaceous (herb and grass)
species respectively. Trees with > 25 cm GBH were considered as matured
trees and rest will be classified in the recruitment and regeneration classes.
Within the plots all the trees and shrubs were identified and enumerated. For
grass and herbs species list and cover availability were estimated visually.
Efforts were also made to identify the plants from the fresh material; those
that could not be satisfactorily identified in the field were brought to the
laboratory and identified by checking it with monographs, herbarium
specimens and other available literature on regional and state floras.
The forests of the study sites belong to the subgroup Southern moist
deciduous forest, and within this are more specifically classified as moist
teak forests. They are named as the Tectona-Terminalia-Adina-Anogeissus
series. The forests are known to be the richest in Maharashtra and contain
many invaluable timber species as well as medicinally important species.
Teak (Tectona grandis) is the most dominant species in study sites and
occurs throughout the area. Other dominating tree species are bamboo,
shisam (Dalbergia sisoo), khair (Acacia catectu), dhavdo (Anogeissus
latifolia) and kadam (Anthocaphalus sp.). The other indigenous tree species
456
available in the forest are Anogeissus sps. (dhav, dhavdo), Bauhinia
racemosa (asitro), Butea monosperma (khakharo, kesudo), Terminalia
crenulata (sadad), Lannea coromandelica (modad, golado), Boswellia
serrata (salai, halar, gugur), Diospyros melanoxylon (timaru, bidi patta),
Cassia fistula (garmaro), Syzygium cumini (jamu), Prosopis juliflora (gando
bavar), Eucalyptus sp (nilgiri)., Gmelina arborea (shevan), Termenelia
arjuna (arjun sadad), Cassia auriculata (avar), Emblica officinalis (amara)
etc.
Visible observation of study area, tree and shrub covers suggest that:
457
most suitable habitat for all floral components which was followed by
degraded-open lands. Teak is planted at some places as a part of
reforestation process.
458
carpio are also preferred fish catch of the local people. None of the fish
species observed till date show long migration pattern.
Table – 8.9
Village wise Medical Facilities in Bhugad Reservoir Area
Medical facilities (within range (km)
S.
Village Allopathic Maternity and Child Primary Health
No.
hospital welfare centre Centre
1 Bafanvihir > 10 > 10 > 10
2 Deodongara > 10 > 10 > 10
3 Goldari > 10 > 10 5
4 Dolmohal > 10 > 10 5
5 Kas > 10 > 10 > 10
6 Kharshet > 10 > 10 5
7 Kharpadi > 10 > 10 > 10
8 Borpada > 10 > 10 > 10
9 Khamshet > 10 > 10 > 10
10 Malghar > 10 > 10 > 10
11 Vadoli > 10 5 5
12 Aslona > 10 > 10 > 10
13 Shahuda > 10 > 10 > 10
14 Bilia > 10 > 10 > 10
459
Table – 8.10
Village wise Medical Facilities in Khargihill Reservoir Area
S. Village Health / Medical facilities (within range (in km)
No. Allopathic Maternity and Primary Health
hospital Child welfare centre Centre
1 Vavar >10 >10 >10
2 Vangani >10 >10 >10
3 Sawarpada >10 >10 >10
4 Karnijjali >10 >10 >10
5 Hateri >10 >10 within 5
6 Ase >10 >10 >10
7 Chas >10 >10 >10
8 Ghiwande >10 >10 >10
9 Vatakpada >10 >10 >10
10 Rayate >10 >10 >10
11 Dadhari >10 >10 >10
12 Sarsun >10 >10 >10
13 Suryanagar >10 >10 >10
14 Walan >10 >10 5 to 10
15 Mulwad >10 >10 >10
16 Chauripada within 5 >10 within 5
460
environmentally more compatible. Based on the project details and the
baseline environmental status, potential impacts as a result of the
construction and operation of the proposed Damanganga-Pinjal Link
Project have been identified. The Impact Assessment for quite a few
disciplines are subjective in nature and cannot be quantified. Wherever
possible, impacts have been quantified and otherwise, qualitative
assessment has been undertaken. The impacts on various aspects of
Environment have been assessed for construction as well as operation
phases of Environment.
461
anticipated due to increase in a vehicular movement during construction
phase.
(i) Construction Phase : The impacts on ambient noise levels are expected
during the project construction phase only, due to earth moving machinery,
increased vehicular movement, etc. The present Noise level was monitored
at 9 locations in the project area. No increase in noise levels is anticipated as
a result of various activities during the project construction phase. There
could be marginal impacts on the population residing in proximity to the
tunnel alignment during construction phase as a result of various activities.
However, based on past experience in similar projects, the impact however,
is not expected to be significant.
462
construction is likely to last for a period of 7 years. About 2,000 workers
and 500 technical staff are likely to migrate during project construction
phase. The employment opportunities in the area are limited. Thus,
during the project construction phase, many of the locals may get
employment. The construction phase also leads to mushrooming of
various allied activities to meet the demands of the immigrant labour
population in the project area. The increase in the population is expected
to be of the order of 6200. The total domestic water requirement of the
labour population (including families) is expected to be of the order of
0.434 MLD @ 70 LPCD. It is assumed that about 80% of the water
supplied will be generated as sewage. Thus, the total quantum of sewage
generated is expected to be of the order of 0.35 MLD. The total BOD
load contributed by various labour camps/colonies will be about 261
kg/day. Disposal of sewage without treatment could lead to adverse
impacts on land environment or water environment in which the
effluents are disposed. In this project the sewage generated from various
labour camps will be treated prior to its disposal.
(ii)Operation Phase
463
transfer to meet the domestic water requirement of Greater Mumbai city.
This is a beneficial impact to the population of Greater Mumbai by
overcoming the shortage in meeting the domestic water requirement.
Also, it is considered that before affecting the transfer of water to
Mumbai city the water requirement of the people in the vicinity of the
proposed reservoirs and in the downstream of dams will be met on
priority.
464
proposed Bhugad reservoir. To ensure that the functioning of Madhuban
reservoir is not affected by the proposed Bhugad reservoir, 91 Mm3 water
will be released from Bhugad reservoir which will compensate the quantity
of water that could have been generated from the Gujarat catchment area of
Madhuban dam intercepted by proposed Bhugad reservoir. As such no
adverse impacts on existing water bodies/lakes/reservoirs is anticipated.
465
(a)Environmental Degradation Due to Immigration of Labour
Population: The peak labour and technical staff congregation would be
of the order of 2,000 and 500 respectively. The population of
construction labour, technical and other work force for construction and
related activities and service providers including their families is
expected to be 6200. Separate accommodation and related facilities for
workers, service providers and technical staff are to be provided as a part
of the project. The congregation of labour force is likely to create
problems of sewage disposal, solid waste management and felling of
trees for meeting fuel requirements, etc.
466
conveyance of municipal wastes generated to the disposal site shall be
developed. At each labour camp, covered trailers to collect the solid waste
from the common collection point and transfer it to the disposal site needs to
be put to service.
(b) Water Logging and Salinisation: The project has been planned as
drinking water supply project to augment the domestic water supply of
467
Mumbai city. The transfer of water is through the lined tunnels, as such,
water logging is not expected due to this project.
TABLE – 8.13
Details of Forest Land to be Acquired for
Damanganga-Pinjal Project
Project Component Forest area (ha)
Bhugad dam 289.55
Khargihill dam 676.20
Bhugad to Khargihill 16.85
tunnel
Khargihill to Pinjal tunnel 25.70
Total 1008.3
468
8.5.4.1.2 Impacts on Wildlife
(a) Impact Due to Habitat Change Having Effect Like Corridor Loss
and Loss of Migratory Path for Wildlife Including Birds: The proposed
dams and reservoir do not lie on migratory path of any wildlife and also not
affecting the corridor of wildlife movement. Thus, no major adverse impact
of corridor loss is anticipated. Also, the project is not likely affect the
migratory path for wildlife.
(c) Impacts on Access of Animals to Food and Shelter: The total forest
area to be acquired for the project is 1008.3 ha. The acquisition of forest
land will lead to loss of major and minor forest produce. The animals in the
forest area to be acquired will migrate to other areas, leading to pressure on
existing forest resources. The loss of forest will not only lead to loss of
shelter but food resources as well. This can lead to animal to animal
conflict. In some cases, man-animal conflict as well. Thus, the project will
have an adverse impact on access of animals to food and shelter.
469
8.5.4.2 Impacts on Aquatic Ecology
(i) Construction phase
470
benthic biota is likely to be most severely affected as a result of the
proposed project.
471
Mumbai city and providing 10 Mm3 to the local public to meet various
requirements .Thus, the project will improve the water availability in the
project area and will provide an impetus for development.
472
(v) Impacts on Sensitive Locations like Archaeological Sites: As
indicated in Para 8.4.3.3 no monuments or any remains of archaeological
importance were noticed at dam sites, in the submergence area of Bhugad
and Khargihill reservoirs and both the tunnels proposed under Damanganga
- Pinjal Link Project. As such, project will not have any impact on
archaeological sites. However, a few village temples may be affected,
which shall be shifted/reconstructed at the resettlement sites.
473
Operation Phase: Improvement in availability of water for various uses,
increased agricultural production, availability of diversified food,
strengthening of educational and health facilities significantly improves
public health in the project area. On the other hand, water resources
development also has negative impacts, since, it could increase the habitat
of certain vectors like mosquitoes. Malaria is a common vector borne
disease in the project area. The project may create favourable conditions for
breeding of new pathogens or vectors such as mosquitoes, etc. Most of the
water borne diseases can largely be prevented by adequate hygiene. With
the increased water availability, quality of water being supplied is expected
to improve the incidence of water-borne diseases will reduce. However,
adequate measures in the form of strict public health measures are proposed.
The increase in surface area of water and Forest cover in the project
area may on a local level moderate the temperature, i.e. lead to reduction in
the number of days of high temperature, if not in the maximum temperature
itself. The higher humidity as a result of higher evapo-transpiration is likely
to raise the minimum temperature and increased occurrence of fogs during
the cooler months. The increased humidity level may also increase the
instances of fog due to increased moisture content in the atmosphere. At the
current level of knowledge a qualitative assessment on the above item is not
possible.
The major Green House Gases (GHGs) are carbon dioxide (CO2),
methane (CH4) and nitrous oxide (N2O). These gases are emitted from both
natural aquatic (lakes, rivers, estuaries, wetlands) and terrestrial ecosystems
(forest, soils) as well as from anthropogenic sources. In last few years GHG
emissions from freshwater reservoirs and their contribution to the increase
of GHGs in the atmosphere are also being considered as a source of
greenhouse gas emissions. In the case of reservoirs, it is known that the
amount of GHGs emitted at the air water interface varies over time. In fact,
there is an initial peak which occurs immediately after impoundment. The
increase of GHG emissions in reservoirs shortly after flooding is related to
474
the release of nutrients, enhanced bacterial activity and decomposition of
labile carbon. Magnitude of emissions for both reservoirs and natural
aquatic systems depend on physico-chemical characteristics of the water
body and on the incoming carbon from the watershed.
Table-8.14
Gas emissions from Reservoirs in Tropical Countries
S.No. Project Predicted gross* annual Predicted gross* annual
Name CO2 diffusive flux (mg C- CH4 diffusive flux (mg C-
CO2 m-2d-1) CH4 m-2d-1)
Predicted 67% Predicte 67%
value confidence d value confidence
interval interval
Lower Upper Lower Upper
limit limit limit limit
1 Sardar 1156 503 2659 238 67 846
Sarovar
2 Pong 361 157 829 55 15 195
3 Bhadra 354 154 815 62 17 220
4 Sabarigiri 361 157 830 56 16 200
5 Madhikhera 1115 485 2565 231 65 820
6 Doyang 744 324 1712 19 5 67
7 Hirakud 679 295 1561 75 21 266
Project
475
8.6 Environmental Management Plan
8.6.1 Pollution Control at Construction Sites
8.6.1.1 Air Pollution Control
476
An amount of Rs. 162.96 lakh is earmarked for air pollution control
(iii) Noise Due to Crusher: The exposure to labour operating with crushers
shall be restricted upto 30 minutes on a daily basis. Alternatively, the
477
workers need to be provided with ear muffs or plugs, so as to attenuate the
noise level near the crusher by atleast 15 dB(A). The exposure to noise
level in such a scenario to be limited upto 4 hours per day.
478
plantation will be done at the dumping sites for reclamation of the dumping
areas.
479
8.6.3.3 Restoration of Colony and Office Complex areas
The working area of dam site, Labour colony, Project Colony areas
have been selected for beautification of the project area after construction is
completed. The reservoirs created due to the construction of dams may be a
local point of tourist attraction. This could be used for sport fishing, so there
is a need to construct benches for sitting, development of resting sheds and
footpath. The beautification would be carried out by developing flowering
beds for plantation of Ornamental plants and flower gardens, creepers, and a
small park, construction of benches for sitting, resting sheds, walk way and
fountain. A provision of Rs.50 lakh has been earmarked for landscaping and
beautification of the area.
The total provisions of Rs. 381 lakh (Rs. 331 lakh + Rs. 50 lakh) has
been kept for Restoration of quarry and borrow areas, reclamation of
construction sites landscaping and beautification.
480
8.6.4.2 Biodiversity Management Plan
The workers who are well acquainted with the area will be engaged for
gathering information for anti-poaching and better vigilance. These
youth could be hired on a contractual basis.
Arrangement of an office for this purpose would be essential to monitor
all these activities.
Organizing public awareness programmes, conducting training camps,
etc.
Provision of fire lines within critical areas to protect the forest from
accidental fires.
For improvement of vigilance and measures to check poaching, check
posts and watch towers will be needed. Officers of State Forest/Wildlife
Department shall be provided with necessary equipment that would
increase their capability and efficiency.
Construction of bridges, road, and inspection paths for more effective
and meaningful patrolling of the staff shall be undertaken.
Improvement of vigilance by procurement of field vehicles and
motorbikes.
Creation of veterinary facilities and rescue camps for healthcare of wild
animals
(ii) Measures to Improve Habitat of Avi-fauna: Forests are vital for the
survival, foraging, breeding and nesting of avifauna. Natural forests provide
a variety of food materials to the birds not only in the form of nectar of
flowers, fruits, seeds etc. in the trees, shrubs, herbs and grasses but they
also contain a large number of insects eaten by birds. In the forests, food is
always available for the faunal component. Although most floral species
flower during spring through summer but fruit maturation and seed ripening
takes place in them throughout the year. Therefore, first strategy of
481
improvement of habitat for birds is avoiding nest predation or brood
parasitism through maintenance of large contiguous forest tract. These areas
have the ability to support the largest number of forest interior birds and will
also be more likely to provide habitat for area sensitive species. It is more
practicable to protect the existing forest area rather than creating new forest
area. Another measure for habitat improvement for avifauna is to be
installation of artificial nest boxes in the influence zone and catchment area
of the project after consultation with the forest department as well as local
NGOs. It is proposed to provide wooden boxes around water bodies in the
study area. About 400 nest boxes are proposed to be kept along the
periphery of Bhugad and Khargihill reservoirs. In addition about 400 nest
boxes are proposed to be provided along the periphery of various water
bodies namely, reservoirs, tanks, rivers, etc. It is proposed that one qualified
person be hired for a period of nine 7 years. An amount of Rs. 195.0 lakh
has been earmarked for habitat improvement of avi-fauna in the study area.
(iii) Wildlife Management Plan: An amount of Rs. 120 lakh has been
earmarked for implementation of Wildlife Management Plan.
(v) Eco-Tourism: The reservoir will have great tourism potential and it can
create many income generating resources to the local people in many ways
viz ; boating , angling competition , guide, creation of the paying guest
482
houses, travellers’ tour packages to the nearby sight seeing places,
development of camping sites, birds watching etc. As such, proposed
Bhugad and Khargihill reservoirs will be developed as Eco-tourist spot. A
provision of Rs. 70 lakh has been earmarked for development of eco-
tourism.
483
considering the fact that some of the labour will be staying along with their
families shall be about 6,200. Community kitchens will be provided to
worker families and the kerosene/LPG will be provided at subsidised rates.
All necessary safety appliances such as helmets, masks, ear plugs, etc.
shall be provided to the workers and staff. The regulations regarding
working platforms, excavations, trenches and safe means of entry and egress
shall be strictly complied. Efficient lighting and safety signs shall be
installed on temporary roads during construction and adequate traffic
regulations shall be adopted and implemented for temporary roads. All
facilities to be constructed shall be fully equipped with the fire protection
equipments as per IS standards. A provision of Rs. 3838.03 lakh is kept for
implementation of various environmental measures in labour camps.
484
breeding seasons of the anopheline mosquito (malaria vector) is sunshine or
moderate shade. Mosquito control and mosquito proofing measures have
been recommended to control malaria. The anti-malarial operations can be
coordinated by various Primary Health Centers located in villages close to
the submergence area of Bhugad and Khargihill dams.
(iii) Health Extension Activities: The health extension activities will have
to be carried out in the villages situated close to the dams being developed
as a part of the project. There would be possibility of the transmission of
communicable diseases due to migration of labour population from other
areas at the construction site. The doctors from the dispensary constructed
as a part of the project and other dispensaries in various villages in the
project area will make regular visits to the villages and organize health
promotional activities with the active participation of the local village
leaders, NGOs and available local health functionaries.
485
A detailed water quality monitoring programme be designed and
implemented. In areas showing incidence of water-borne diseases,
intensive water quality monitoring shall be done.
(vi) Cost Estimates: The total budget earmarked for Public Health delivery
system shall be Rs.1486 lakh.
486
The catchment area of Bhugad and Khargihill dam sites has been
divided in to 16 and 20 water sheds respectively. Based on SYI index these
water sheds have been categorised and are detailed in the Table - 8.15 and
8.16 respectively for Bhugad and Khargihill catchment area. The area under
different categories upto Bhugad and Khargihill dam catchments is
summarised in Table 8. 16
Table – 8.15
Erosion Intensity Categorization as per SYI
Classification in Bhugad Dam Catchment Area
Watershed Area SYI Category
number (ha) values
W1 3435 1110 Medium
W2 3232 1140 Medium
W3 4931 1220 High
W4 4604 1240 High
W5 3703 1210 High
W6 3739 1220 High
W7 4532 1190 Medium
W8 3755 1180 Medium
W9 4155 1160 Medium
W10 6202 1150 Medium
W11 4795 1230 High
W12 4984 1220 High
W13 5186 1210 High
W14 5386 1150 Medium
W15 3252 1050 Low
W16 4909 1080 Low
Total 70800
487
Table – 8.16
Erosion Intensity Categorization as per SYI
Classification in Khargihill Dam Catchment Area
Watershed Area SYI Category
number (ha) values
W1 3485 1330 Very High
W2 3409 1320 Very High
W3 4199 1150 Medium
W4 3161 1210 High
W5 3532 1220 High
W6 3840 1270 High
W7 1709 1150 Medium
W8 1384 1230 High
W9 3298 1170 Medium
W10 4734 1210 High
W11 3644 1180 Medium
W12 2173 1160 Medium
W13 2633 1090 Low
W14 2104 1050 Low
W15 4136 1210 High
W16 3328 1190 Medium
W17 4394 1140 Medium
W18 2537 1150 Medium
W19 3485 1310 Very High
W20 3415 1310 Very High
Total 64600
Table-8.16
Area under Different Erosion Categories
Category Bhugad dam (ha) Khargihill dam (ha)
Very low - -
Low 8161 (11.5%) 4737 (7.3%)
Medium 30697 (43.4%) 25282 (39.1%)
High 31942 (45.1%) 20787 (32.2%)
Very
High - 13794 (21.4%)
Total 70800 (100%) 64600 (100%)
488
The objective of the SYI method is to prioritize sub-watershed in a
catchment area for treatment. In Bhugad dam, area under high erosion
category is 31942 ha. In Khargihill dam, total area under very high and high
erosion categories is 13797 ha and 20787 ha respectively. Various
engineering and biological measures have been suggested for catchment
area treatment in the 7 watersheds categorised under high erosion category
in the catchment area upto Bhugad site and 10 watersheds categorised under
very high and high category in the catchment area upto Khargihill dam site.
Total cost of the CAT plan worked out as Rs. 2489 lakh.
The disaster Management Planning for dam break scenario consist of:
Identification/ construction of Evacuation path; setting up of alarms and
warning systems at appropriate locations; establishing communication
system; Dam safety and maintenance manual; Emergency Action Plan
(EAP); Administration and procedural aspects; Preventive action;
Evacuations plans; Evacuations team; Public awareness for disaster
mitigation; Notifications; Notification procedures; and Management after
receding of flood water.
In the event that the failure is imminent or the failure has occurred or
a potential emergency conditions is developing, the observer at the site is
required to report it to the Junior Engineer / Assistant Engineer who will
report to the Executive Engineer / Superintending Engineer for their
489
reporting to the Chief Engineer through a wireless system or by any
available fastest communication system. The Engineer-in-Charge is usually
responsible for making cognizant with the developing situation to the Civil
Administration viz. District Magistrate, Thane & Nasik and concerned sub-
divisional magistrates and tehsildars.
490
From the monitoring point of view, the important parameters are
water quality, air quality, noise, erosion and siltation, afforestation, fishery,
etc. An attempt will be made to establish early warning of indicators of
stress on the environment. Suggested environmental monitoring plans are
described in the following sections. The monitoring programme for
monitoring of various parameters in construction and operation phases is
summarised in Table - 8.17 and 8.18 respectively.
Table 8. 17
Environmental Monitoring Programme during Construction Phase
S. No. Particulars Parameters Frequency Location
1. Treated waste pH, BOD, COD, Once Before and after
water from TSS and Oil & every treatment from
STPs Grease month the STPs at
various labour
camps
2. Ambient Air SPM, RPM, SO2, Once At major
quality NOx and CO every construction sites
season
3. Noise Equivalent noise Every At major
level (Leq) month construction
sites.
4. Water-related Identification of Once Labour camps
diseases water related every and nearby
diseases, season settlements
adequacy of local
control and
curative measure,
etc.
491
Table – 8.18
Environmental Monitoring Programme during
Project Operation Phase
S. No. Particulars Parameters Frequency Location
1. Water pH, Turbidity, Total Pre Reservoirs.
Dissolved Solids, monsoon
Calcium, Season and
Magnesium, Post
Chlorides, Sulphate, monsoon
Nitrates, Iron, DO, season
BOD, COD etc.
2. Treated Waste pH, BOD, COD, Once every Before and
Water from TSS, and Oil & month after
STP Grease. treatment
from STP
3. Ecology Status of Once in 5 --
afforestation years
programmes
4. Fisheries Phytoplanktons, Twice a Reservoirs.
zooplanktons, year
benthic life, fish
composition
5. Incidence of Cause and control Once in a Settlements
water-related measures for various year around
diseases diseases. Reservoirs
and in
command
areas
6 Meteorological Temperature, Continuous At a location
Parameters rainfall, humidity, close to each
cloud cover, wind of the two
speed and direction, dam sites
Solar Insolation,
Evaporation Rate
492
The cost of Environmental Monitoring Programme will be Rs. 356.5
lakh for construction phase and Rs. 26.0 lakh per year during project
operation phase.
Table – 8.19
Details of cost for Implementation of Environmental Management Plan
S. Cost
Item
No. (Rs. lakh)
Compensatory Afforestation and Bio-
1 2801.0
diversity conservation
2 Greenbelt Development Plan 40.00
Environmental Management in labour
3 3838.03
camps
4 Public health delivery system 1486.0
Restoration and Landscaping of
5 381.0
construction sites
6 Muck Disposal plan 250.0
7 Water Pollution Control Measures 15.0
8 Air Pollution Control Measures 162.96
9 Energy Conservation measures 100.00
10 Catchment Area Treatment Plan 2489.0
11 Disaster Management Plan 200.00
Environmental Monitoring during
12 356.50
construction phase
13 Purchase of noise meter 1.50
14 Purchase of meteorological instruments 20.00
Total 12142 lakh
493