Lifting Plan of One Free Water Separator: EBS-023-YOSC-HSE-002
Lifting Plan of One Free Water Separator: EBS-023-YOSC-HSE-002
Contents
1. PURPOSE ............................................................................................................................................................ 2
2. SCOPE ................................................................................................................................................................. 2
3. REFERENCES .................................................................................................................................................... 2
4. PREREQUISITES............................................................................................................................................... 2
6. DETAILS ............................................................................................................................................................. 4
6.3 TRANSPORTING FREE WATER SEPARATOR TO DESIGNATED PLACE AND UNLOADING ....................................... 4
8. APPENDIXES ..................................................................................................................................................... 7
Page 1 of 13
Lifting Plan of One Free Water Separator Installation
1. Purpose
This plan mainly describes the Lifting and installation of one free water separator in S1 in East
Baghdad oil field, define the construction process, quality and safety precautions of separator lifting,
and standardize the site construction.
2. Scope
This plan just applies to the lifting and installation of one free water stage separator in S1 at East
Baghdad Oil Field. Main construction activities include lifting, unloading, transportation,
equipment adjustment etc. of the separator.
3. References
API RECOMMENDED PRACTICE 686
SH/T 3536-2011
Lifting Construction Specification for Petrochemical Engineering
SH/T 3515-2003
Construction Standard for Large-size Equipment Hoisting Engineering
4. Prerequisites
4.1 Required Personnel
1) Construction staff shall pass the relevant training and the safety education;
2) Before construction, staff shall attend the construction safety and technical disclosure;
3) The staff involved in lifting work shall be familiar with lifting process, well know his job
responsibility, and obey the command;
4) Signal of lifting work is clear between lifting commander and crane driver.
4.2 Preparation of Tools and Machines
1) Tools and machines are complete, with required quantity;
2) Crane is with good working condition; its inspection is qualified;
3) Shackles, slings and other major tools and machines are inspected as qualified;
4) See appendix 5 for major equipment, tools and machines required for construction.
4.3 Technical Documents
1) Lifting plan and JSA of free water separator has been issued.
4.4 Site Condition
1) The ½” pipe affecting the entry and exit of crane and transportation trailer has been
removed;
2) Check the equipment transportation road along the equipment transportation route is
without any obstacle, the turning radius at turning area meets the requirement, the clear
Page 2 of 13
Lifting Plan of One Free Water Separator Installation
Total Max.
Rigging Crane Rated Load
Item to be Weight Lifting Working
No. Weight Working lifting Rate
Lifted (t) Weight Radius
(t) Condition weight(t) (%)
(t) (m)
Page 3 of 13
Lifting Plan of One Free Water Separator Installation
6. Details
6.1 Check Prerequisite
Check the Free water separator is ready for removal and lifting as per SECTION 4: Prerequisites.
Verify site condition before lifting, ensure travelling path of crane and trailer is clear.
6.2 Removal of Free Water Separator
1) The 100 T crane shall enter the designated location on the construction site, pay attention
that the front part of the crane does not collide with the access facilities on site.
2) By forklift or manual handling, place four road base plates under the crane outriggers.
3) Load the crane with all its own counterweights, adjust the main boom of the crane to 20.2M.
4) Connect the sling for equipment lifting as shown in appendix 4, protect slings with rubber
etc. to prevent slings to be damaged, and tie anti-swing ropes on both ends of the equipment.
After connecting the sling, raise the hook so that the sling is slightly stressed.
5) Tie anti-swing ropes on both ends of equipment to control the direction during lifting.
6) After sling is connected, remove the equipment connection bolt. Lift the equipment up 200-
300mm away from the platform for trial lifting. Check whether the equipment is balanced,
lifting device, slings, crane brakes and ground is normal or not.
7) After the trial lifting is qualified, the Free Water separator shall be lifted by operations such
as rotation, luffing etc. onto the transportation trailer for loading (should use the low bed
trailer).
6.3 Transporting Free Water Separator to designated place and Unloading
1) After the equipment is loaded, fix the equipment on truck by using 3 sets 5T chain blocks.
2) Special person shall be arranged to guide the truck, driving speed no more than 30km/h.
3) Ensure that the safety distance of the top of the device from the high voltage cable (if any)
is greater than 1.1m.
4) After the equipment is transported to designated place, unload the equipment as per the
steps in Section 7.2.
6.4 Loading of Free Water Separator and transporting
1) The 100 T crane shall enter the designated location on the lifting site.
2) By forklift or manual handling, place four road base plates under the crane outriggers.
3) Load the crane with all its own counterweights, adjust the main boom of the crane to 20.2M.
4) Connect the sling for equipment lifting as shown in appendix 4, protect slings with rubber
etc. to prevent slings to be damaged, and tie anti-swing ropes on both ends of the equipment.
After connecting the sling.
Page 4 of 13
Lifting Plan of One Free Water Separator Installation
5) Tie anti-swing ropes on both ends of equipment to control the direction during lifting.
6) After sling is connected, Lift the equipment up 200-300mm away for trial lifting. Check
whether the equipment is balanced, lifting device, slings, crane brakes and ground is normal
or not.
7) After the trial lifting is qualified, the Free Water separator shall be lifted by operations such
as rotation, luffing etc. onto the transportation trailer for loading
8) Pay attention to the nozzle orientation when loading.
9) Fix the equipment on truck by using 3 sets 5T chain blocks.
10) Before equipment transportation, check again whether the equipment transportation route
is without any obstacle.
11) Special person shall be arranged to guide the transportation trailer.
12) The vehicle driving speed shall be no more than 30km/h.
6.5 Lifting of Free Water Separator
1) The crane shall enter its standing location in construction area. Place four road base plates
under the outriggers and install the counterweights of the crane itself. Check if there are
obstacles at 4 meters from the center of the crane.
2) The transportation trailer shall enter the construction site.
3) Confirm again the orientation of equipment nozzle before equipment positioning.
4) Connect the sling for equipment lifting, protect slings with rubber etc. to prevent slings to
be damaged, and tie anti-swing ropes on both ends of the equipment. After connecting the
sling, raise the hook so that the sling is slightly stressed.
5) Remove the chain blocks that fix the equipment on the transportation trailer.
6) Working condition of crane: Main boom of the 100 T crane is 20.2m, with total
counterweight. Working radius shall be no more than 11m.
7) Lift the equipment up for 200-300mm away from the trailer for trial lifting. Check whether
the equipment is balanced, lifting device, slings, crane brakes and ground is normal or not.
8) If the trial lifting is qualified, drive the trailer away.
9) The crane shall lift the Free Water separator onto the platform by operations such as
rotation and luffing etc. Pay attention to keep the safe distance between the equipment and
crane body during lifting.
10) After equipment is positioned, remove the lifting device and slings.
6.6 Equipment Adjustment
1) Adjust the position, elevation and horizontal of equipment after it is positioned, ensure the
Page 5 of 13
Lifting Plan of One Free Water Separator Installation
Page 6 of 13
Lifting Plan of One Free Water Separator Installation
Page 7 of 13
Lifting Plan of One Free Water Separator Installation
Qj=(Q1+ Q2)*K1=(12T+1T)*1.1=14.3T
2) Take Free Water separator body for instance. See above figure for sling connection.
Page 8 of 13
Lifting Plan of One Free Water Separator Installation
Qj=K1*Q*g
Qj=K1*Q=1.1*12000*10=132000(N)
The lifting belts is 20T,the shackle is 25T and the wire rope is 11.4T, both more than 5.436T,
and meets requirement
Page 9 of 13
Lifting Plan One Free Water Separator Installation
Page 10 of 13
Lifting Plan One Free Water Separator Installation
Page 11 of 13
Lifting Plan One Free Water Separator Installation
Page 12 of 13
Lifting Plan One Free Water Separator Installation
现场负责人
Construction Commander
吊装指挥
Lifting Commander
吊车司机 起重工 钳工
Crane Driver Riggers Fitters
Page 13 of 13